Vous êtes sur la page 1sur 50

Adama Science and Technology

University

Chemical Engineering Program


Plant Design and Economics(ChEg5193)
lecture 7
Engineering Economics
Introduction 2

Economics ??

Economics is the study of how people and society choose to


employ scarce resources that could have alternative uses in
order to produce various commodities and to distribute them for
consumption, now or in the future”
WHAT IS ENGINEERING ECONOMICS?
The application of economic principles to engineering problems,

for example in comparing the comparative costs of two


alternative capital projects or in determining the optimum
engineering course from the cost aspect.
Chemical Engineering program, ASTU
3
Cost Estimation

A capital investment is required for any industrial

process, and determination of the necessary investment


is an important part of a plant-design project.
An acceptable plant design project must be profitable

Since net profit equals total income minus all expenses,

so chemical engineer be aware of the many different


types of costs involved in manufacturing processes.

Chemical Engineering program, ASTU


Cont’d 4

The total investment for any process consists of

 Fixed-capital investment for physical equipment and

facilities in the plant plus


Working capital which must be available to pay

salaries, keep raw materials and products on hand,


and handle other special items requiring a direct cash
outlay.
 Thus, in an analysis of costs in industrial processes,

capital-investment costs, manufacturing costs, and


Chemical Engineering program, ASTU
5
Cont’d

The total capital investment = Fixed capital +


Working
capital

Chemical Engineering program, ASTU


Fixed capital 6

The capital needed to supply the necessary manufacturing

and plant facilities is called the fixed-capital investment


Fixed capital is therefore the total cost of the plant ready for

star up
Fixed capital can be classified in to two major classes

 Manufacturing fixed-capital investment (Direct)

 Nonmanufacturing fixed-capital investment (Indirect)

Chemical Engineering program, ASTU


Cont’d 7

Manufacturing fixed-capital investment represents the capital

necessary for all items of equipment and their installation


with all auxiliaries that are needed for complete process
operation.
 Expenses for piping
 Instruments
 Insulation
 Foundations
Site preparation are typical examples of costs included
in the manufacturing fixed-capital investment.

Chemical Engineering program, ASTU


8
Cont’d
Nonmanufacturing fixed-capital investment: Fixed capital required

that are not directly related to the process operation is designated as

the nonmanufacturing fixed-capital investment. Includes;

Construction over head

 Supervision, engineering expenses, miscellaneous construction

costs, contractor’s fees, and contingencies.

 Cost for land, processing buildings, administrative and other

offices, warehouses, laboratories, transportation, waste-disposal

facilities, shops, and other permanent parts of the plant.

Chemical Engineering program, ASTU


9
Working Capital
The working capital for an industrial plant consists of

the total amount of money invested in


1. Raw materials and supplies carried in stock
2. Finished products in stock and semi-finished products
in the process of being manufactured
3. Accounts receivable

Chemical Engineering program, ASTU


10
Cont’d

4. Cash kept on hand for monthly payment of

operating expenses, such as


Salaries

Wages, and

 Raw-material purchases,

5. Accounts payable and


6. Taxes payable

Chemical Engineering program, ASTU


Cont’d 11

The raw-materials inventory included in working capital

usually amounts to a l-month supply of the raw materials


valued at delivered prices.
Because credit terms extended to customers are usually

based on an allowable 30-day payment period, the


working capital required for accounts receivable
ordinarily amounts to the production cost for 1 month of
operation.

Chemical Engineering program, ASTU


Cont’d 12

The ratio of working capital to total capital investment

varies with different companies,


Most chemical plants use an initial working capital

amounting to 10 to 20 % of the total capital investment.


This percentage may increase to as much as 50 % or

more for companies producing products of seasonal


demand because of the large inventories which must be
maintained for appreciable periods of time.

Chemical Engineering program, ASTU


13
14
15
16
Factors Affecting Investment and Production 17

Cost
When a chemical engineer determines costs for any type of

commercial process, these costs should be of sufficient


accuracy to provide reliable decisions.
To accomplish this, the engineer must have a complete

understanding of the many factors that can affect costs.


Therefore, engineer must keep up-to-date on price fluctuations,

company policies, governmental regulations, and other factors


affecting costs.

Chemical Engineering program, ASTU


1. Source of Equipment 18
One of the major costs involved in any chemical process is

for the equipment.


A substantial reduction in cost can be made by employing

idle equipment or by purchasing second-hand equipment.


During purchasing of new equipment, the chances for a

low cost estimate are increased if the engineer does not


place overly strict limitations on the design.

Chemical Engineering program, ASTU


2. Price Fluctuations 19

Prices may vary widely from one period to another, and this factor

must be considered when the costs for an industrial process are


determined.
It would obviously be ridiculous to assume that plant operators or

supervisors could be hired today at the same wage rate as in 1975.


The same is also true in comparing prices of equipment purchased

at different times.
Therefore, chemical engineer must keep up-to-date on price and

wage fluctuations.

Chemical Engineering program, ASTU


3. Operating Time and Rate of 20

Production
One of the factors that has an important effect on the costs is the

fraction of the total available time during which the process is in


operation.
Operating time, rate of production, and sales demand are closely

interrelated.
The ideal plant should operate under a time schedule which gives the

maximum production rate


If the production capacity of the process is greater than the Sales

demand, the operation can be carried on at reduced capacity


Chemical Engineering program, ASTU
21

Chemical Engineering program, ASTU


22
Cont’d
The point where the total product cost equals the total

income is known as the break-even point.


The effects of production rate and operating time on costs

should be recognized.
By considering sales demand along with the capacity and

operating characteristics of the equipment, the engineer


can recommend the production rate and operating
schedules that will give the best economic results.
Chemical Engineering program, ASTU
23
4. Governmental Policies
The national government has many regulations and

restrictions which have a direct effect on industrial costs.


Some examples of these are

 Import and export tariff regulations

 Restrictions on permissible depreciation rates

 Income-tax rules

 Environmental regulations

Chemical Engineering program, ASTU


Types of Capital Cost Estimates 24

An estimate of the capital investment for a process may

vary from a predesign estimate (based on little


information except the size of the proposed project) to a
detailed estimate prepared from complete drawings and
specifications.
There are five categories in capital cost estimate which

vary in accuracy range depending up on the stage of the


development of the project

Chemical Engineering program, ASTU


Cont’d 25

1. Order-of-magnitude estimate (ratio estimate) based


on similar previous cost data; probable accuracy of
estimate over ± 30 percent.

2. Study estimate (factored estimate) based on


knowledge of major items of equipment; probable
accuracy of estimate up to ± 30 percent.

Chemical Engineering program, ASTU


Cont’d 26

3. Preliminary estimate (Scope estimate) based on sufficient data


to permit the estimate to be budgeted; probable accuracy of
estimate within ± 20 percent.
4. Definitive estimate (project control estimate) based on almost
complete data but before completion of drawings and
specifications; probable accuracy of estimate within ± 10 percent.

5. Detailed estimate (contractor’s estimate) based on complete


engineering drawings, specifications, and site surveys; probable
accuracy of estimate within ± 5 percent.

Chemical Engineering program, ASTU


COST INDEXES 27

Most cost data which are available for immediate use

in a preliminary or predesign estimate are based on


conditions at some time in the past.
Because prices may change due to changes in

economic conditions, some method must be used for


updating cost data applicable at a past. This can be
done by the use of cost indexes.

Chemical Engineering program, ASTU


28
Cont’d
A cost index is merely an index value for a given point in

time showing the cost at that time relative to a certain base


time
If the cost at some time in the past is known, the

equivalent cost at the present time can be determined by


multiplying the original cost by the ratio of the present
index value to the index value applicable when the
original cost was obtained.

Chemical Engineering program, ASTU


Cont’d 29

The common indexes permit fairly accurate estimates


if the time period involved is less than 10 years.

Chemical Engineering program, ASTU


Cont’d 30

Many different types of cost indexes are published regularly.

Some of these can be used for estimating equipment costs,


labor, construction, materials, or other specialized fields.
The most common of these indexes are

 Marshall and Swif all-industry and process-industry equipment


indexes
 Engineering News-Record construction index

 Nelson-Farrar refinery construction index

 Chemical Engineering plant cost index

Chemical Engineering program, ASTU


Cost Factors in Capital Investment 31

Capital investment is the total amount of money needed to

supply the necessary plant and manufacturing facilities plus


the amount of money required as working capital
Let us consider now the proportional costs of each major

component of fixed-capital investment as outlined previously


The cost factors presented here are based on a careful study

by Bauman and associates (“Fundamentals of Cost


Engineering in the Chemical Industry”) plus additional data
and interpretations from other more recent sources.
Chemical Engineering program, ASTU
32
Cont’d
33
Purchased Equipment 34

• The cost of purchased equipment is the basis of several pre-

design methods for estimating capital investment.


• The three major essential items to the estimator in making

reliable cost estimates are


 Sources of equipment prices
 Methods of adjusting equipment prices for capacity
 Methods of estimating auxiliary process equipment

Chemical Engineering program, ASTU


35
Cont’d
The most accurate method for determining

process equipment costs is


 To obtain firm bids from fabricators or

suppliers.
 Second best in reliability are cost values

from the file of past purchase orders.

Chemical Engineering program, ASTU


36
Purchased Equipment Installation
The installation of equipment involves costs for labor,

foundations, supports, platforms, construction expenses,


and other factors directly related to the erection of
purchased equipment.
The next table presents the general range of installation

cost as a percentage of the purchased-equipment cost for


various types of equipment.

Chemical Engineering program, ASTU


37
38
Estimation of Total product Cost
Determination of the necessary capital investment is only

one part of a complete cost estimate.


Another equally important part is The Estimation of costs

for operating the plant and Selling the products.


 These costs can be grouped under the general heading of

Total Product Cost.

Chemical Engineering program, ASTU


39
Cont’d
Total product cost is generally divided into two categories

1. Manufacturing cost
Direct production cost
Fixed Charge
Plant overhead cost

2. General Expenses
 Administrative Expenses
Distribution and marketing expenses
 Research and development

Chemical Engineering program, ASTU


Direct Production Cost 40

 Direct production cost include expenses directly associated with the

manufacturing operation. This type of cost involves


 Raw Materials

 Operating Labor

 Direct Supervisory and Clerical Labor

 Utilities:such as steam, electricity, process and cooling water,

compressed air, natural gas, and fuel oil, …


 Plant maintenance and repairs

 Royalties

 Catalyst

Chemical Engineering program, ASTU


41
Fixed Charge
Fixed charges are expenses which remain practically

constant from year to year and do not vary widely


with changes in production rate.
 Property taxes
 Insurance
 Rent

Chemical Engineering program, ASTU


Plant Overhead Costs 42

 Plant overhead cost includes

 Costs for hospital and medical services

 Safety services

 Payroll overhead including pensions

 Vacation allowances

 Packaging, restaurant and recreation facilities

 Special employee benefits …

 These costs are similar to the basic fixed charges in that they do
not vary widely with changes in production rate.
Chemical Engineering program, ASTU
Administrative expenses 43

Administrative expenses include costs for

Office supplies

Engineering and legal expenses

Upkeep on office buildings

General communications.

Chemical Engineering program, ASTU


44
Distribution and marketing expenses
Are costs incurred in the process of selling and

distributing the various products.


These costs include

Expenditures for materials handling

Sales offices and salesmen costs

Technical sales service

Advertising cost

Chemical Engineering program, ASTU


45
Research and development expenses
Research and development expenses are incurred by

any progressive concern which wishes to remain in a


competitive industrial position.
Special equipment cost

 Research facilities

Consultant fees related to developing new ideas or

improved processes.

Chemical Engineering program, ASTU


Total product costs are commonly calculated on one

of three bases:
 Daily basis

 Unit-of-product basis

 Annual basis

The annual cost basis is probably the best choice for

estimation of total cost


SUMMARY 46
47
48
Thank You

Vous aimerez peut-être aussi