For a more realistic and practical planning, the Barangay Development Council may opt to prepare an action plan

in addition to the comprehensive development plan. This kind of plan is action-oriented, short-ranged and is meant to address the immediate problems of the locality. It highlights very specific activities and strategies, hence, it is expected that outputs desired will be accomplished.

OBJECTIVES
These are the immediate aims which the organization seeks to attain. These purposes should be aligned with the goals set in the comprehensive plan.

PROJECTS or ACTIVITES
To accomplish the objectives, projects or activities should be undertaken by the development workers. These projects or activities should likewise be supportive of the comprehensive plan for the barangay.

TARGET OUTPUTS
To ensure the attainment of the objective set, planners should categorically spell out the desired outputs. These are very specific aims expressed in quantitative terms. With the targets properly stated, it its easy to monitor and evaluate accomplishments.

STRATEGIES
These are the specific, more or less sure ways of facilitating the attainment of formulated objectives and targets. It is important that strategies be spelled out so that success in plan implementation can be realized. After all, it has been said that the world steps aside for the one who knows HOW TO GET THERE.

FUNDING REQUIREMENTS & SOURCES Hardly can there be a plan which does not involve

finances. Some materials and services cannot be procured without cash; therefore, it is imperative that planners provide funds for these, especially if such cannot be obtained thru self-help efforts. In this connection, planners should be able to identify the possible sources of funds.

PERSONS INVOLVED or RESPONSIBLE


It is important that at the inception of planning, planners are able to identify who should do what, otherwise, plan implementation will bog down. People involved in the performance of tasks/activities should be informed beforehand to ensure that these tasks are carried out later. With this part of the action plan, it is easy to pinpoint responsible/accountable people.

TIMETABLE
A plan should be time-bounded in order to avoid waste of time. Time is an irreplaceable resource: therefore, it should be effectively managed. A certain task should be monitored vis--vis the time allocated. To this effect a Gantt Chart may be used.

REMARKS
Under this column will be reflected certain statements or explanations which cannot be indicated elsewhere in the plan.

OBJECTIVES

PROJECTS ACTIVITIES

TARGETS

STRATEGIES

FUNDING REQS

FUNDING SOURCES

PERSONS INVOLVED

TIMETABLE

REMARKS

To generate awareness on the importance of cleanliness and beautification

CLEAN & GREEN PROJECT


2 big compost pits constructe d

Coordinate with BRGY. Council & SK for possible support.

Php.10,000

Barangay Fund

Barangay Residents

3rd week January

Self help

1. Excavation of compost pits

To make the place a model of cleanliness

2. Info drive on cleanliness & beautification

1 symposiu m on C & B conducted 60 Fruit trees planted

Launch a contest on The Cleanest Backyard

Brangay Council, BHWs. DOH staff

2nd week February

To develop self-reliance among the community residents

3. Treeplanting

Solicit donations for prizes Invite Resource Speakers From DTI

Php.20, 000

Barangay fund raising

Council Forester

March to April

Forester to coordinate with Dept. of Agriculture Secure Certified seeds from DA

4. Drainage construction

Roadside drainage constructe d Backyard space planted to vegetables

Barangy Council

May

5. Backyard gardening

Php.5, 000

Donations

BRGY. Capt. BRGY. Devt. Council

1st & 2nd weeks June

Solicit donations from business establishment s

6. Provision of trashcans.

20 big trashcans

July

OBJECTIVES

PROJECTS ACTIVITIES

TARGETS

STRATEGIES

FUNDING REQS

FUNDING SOURCES

PERSONS INVOLVED

TIMETABLE

REMARKS

SKILLS & LIVELIHOO D DEVT. PROJECT 1. Seminar on Food Processing 1 seminar to food processing conducted Residents to provide materials to be processed

Php.5, 000

BRGY. Training funds

BRGY Capt. DTI Staff

Prior to project implementation, students or other extension workers have to be oriented on social mobilization (SOCMOB) concepts. If they are familiar with SOCMOB concepts, they are better prepared to initiate and sustain service delivery in the community.

Is the act of making ready of calling for active involvement of participation.

SOCIAL MOBILIZATION
A process for engaging people in action and redirecting existing or creating new human and material resources for the achievement of a societys or communitys social goals.

To hasten the pace of change and development To enhance peoples awareness of the need to pursue a particular development program To fully utilize existing resources lying dormant in the community

To strengthen community participation for sustained commitment to development

ADVOCACY COMMUNITY ORGANIZING ACTIVE/ COORDINATED PARTICIPATION EMPOWERMENT

To generate collective action on identified community problems. To bring to the fore new ideas, attitudes and technologies. To generate commitment on providing resources

CAPACITY BUILDING
LINKAGING / NETWORKING PROGRAM SUSTAINABILITY

1-8parts

of a short-ranged action

plan 9. ___________ is the act of making ready of calling for active involvement or participation. 10. ___________ is a process of engaging people in action and redirecting existing or creating new human and material resources for the achievement of a societys goals.

11.

Meaning of SOCMOB

12-15.

give 4 elements of social mobilization