Académique Documents
Professionnel Documents
Culture Documents
WHAT IS A PROJECT?
A project can be defined as a set of large number of activities or jobs that are performed in a certain sequence determined logically and it has to be completed within a specified time or a specified cost or meeting the performance standards.
Copyright PCTI Group 2009
A network is a graphical representation of a project, depicting the flow as well as the sequence of well defined activities and events. There are two types of network techniques. 1. Critical path method ( CPM) 2. PERT
Copyright PCTI Group 2009
A B C D E F G H
CALCULATION OF START & FINISH TIMES ACTIVITY 1-2 2-3 2-4 4-5 4-6 3-5 5-6 3-6 DURATION 3 3 2 7 5 3 6 2
Copyright PCTI Group 2009
WHAT IS CRITICAL PATH? An activity is said to be critical if a delay in the start of the course makes a delay in the completion time of the entire project. A critical path is the longest path on the network. There is no flexibility in the activities on the critical path.
Copyright PCTI Group 2009
CALCULATIONS
ES= Ei EF= Ei+Tij LS= Lj- Tij LF= Lj TF= ( Lj-Ei)- Tij Te= To+4Tm+Tp 6 S.D= Tp-To 6
Copyright PCTI Group 2009
Break-Even Point
A ball bearing manufacturing company is planning to install an additional plant which will require leasing new equipment for a monthly payment of Rs.60,000. Variable cost be Rs.20 per item and each item will retail for Rs.70. 1) How many ball-bearing must be sold in order to break even? 2) What could be the profit (or loss) if 1000 items are made and sold in a month? 3) How any item must be sold to realize a profit of Rs.40000?
Break-Even Point
A small firm intends to increase the capacity of a bottleneck operation by adding a new machine. Two alternatives A and B have been identified, and the associated costs and revenues have been estimated. Annual fixed costs would be Rs.40,000 for A, and Rs.30,000 for B, variable costs per unit would be Rs.10 for A and Rs.12 for B; and revenue per unite would be Rs.15 for A and Rs.16 for B. Determine the break-even point in terms of units for each alternative. At what volume of output would the two alternatives yield the same profit? If expected annual demand is 12,000 units, which alternative would yield a higher profit?
Copyright PCTI Group 2009
i. ii. iii.
Break-Even Analysis
A manager has the option of purchasing one, two or three machines. Fixed costs and potential volumes are as follows:
Number of Machines 1 2 3
Variable cost is Rs.100 per unit, and revenue is Rs.400 per unit
i. ii.
Determine the break-even point for each range. If projected annual demand is between 580 and 660 units, how many machines should the manager purchase?
Copyright PCTI Group 2009
Break-Even Analysis
Paradise Airlines offers customers a vacation plan for Rs.5200. The airline estimates that the fixed costs associated with this plan are Rs.72,00,000 and at a volume of 3,000 passengers. Total variable costs would be Rs.48,00,000 and profits should be Rs.36,00,000. Find the break-even volume. If fixed costs remained constant, how many additional passengers (beyond break-even) would be required to increase profits to Rs.50,00,000?
Copyright PCTI Group 2009
i. ii.
Job Process 1 Sanding Time (hours) A B C D E 2.25 2.00 1.00 2.50 1.75
The following table contains information regarding jobs that are to be scheduled through one machine.
Job A B C D E F G Processing time (days) 6 12 2 11 10 3 6 Due date (days) 20 30 15 16 18 5 9
Sequence the jobs using i. Shortest processing Time (SPT) ii. Processing with Dates
Copyright PCTI Group 2009
The following table contains information concerning four jobs that are awaiting processing at a work centre. Job Job time (days) Due date (days)
20 16 15 17
ii. Processing with Due Dates Assume the list is by order of arrival For each of the methods, determine the average job flow time, average lateness and average number of jobs at the work centre. Is one method superior to the other? Explain.
Copyright PCTI Group 2009
Processing times (includes set-up times) and due dates for five jobs waiting to be processed at a work centre are given in the following table:
Job A B C D E
1) 2)
Determine the sequence of jobs, the average flow time, average job lateness and average number of jobs at the work centre at the work centre, for each of these rules: First Come First Serve (FCFS) Earliest Due Date (EDD)
Activit y A B C D E F G H I
Time (Weeks)
3 2 4 4 6 6 2 3 3
Copyright PCTI Group 2009
a) Draw the network diagram. b) What is the critical path? c) Suppose you want to shorten the completion time as much as possible, and have the option of shortening any of all of B,C,D and G each by two weeks. Which would you shorten? d) What is the new critical path and earliest completion time?
Activity A B C D E F G H
Time (Weeks) 6 2 5 7 1 2 3 6
a)Draw the network diagram b)Find the critical path c)Find the project completion d)Calculate the total float for each of the activities
Copyright PCTI Group 2009
A Project has been defined to contain the following list of activities along with their required times for completion:
Activity Time (Days) Immediate Predecessors
A B C D E F G H I
1 4 3 7 6 2 7 9 4
a)
b)
c)
d)
Draw the network diagram. Show the early start and early finish times. Find the critical path. What would happen if activity F was revised to take four Days instead of two?
Facility Location
A small manufacturing facility is being planned that will feed parts to three heavy manufacturing facilities. The location of the current plants with their coordinates and volume requirements is given in the following table.
Use the centre of gravity method to determine the best location for this new facility.
Copyright PCTI Group 2009
Facility Location
A small gear manufacturing facility is being planned that will feed parts to five heavy manufacturing facilities. The location of the current plants with their coordinates and volume requirements is given in the following table.
Plant location Location A Location B Location C Location D Location E Coordinates (X,Y) (325,75) (400,150) (450,350) (350,400) (25,450) Volume (parts per year) 1500 250 450 350 450
Use the centre of gravity method to determine the best location for this new facility.
Copyright PCTI Group 2009