Académique Documents
Professionnel Documents
Culture Documents
SCHEDULE
A schedule consists of a list of a project's terminal elements with intended start and finish dates. Terminal elements are the lowest element in a schedule, which is not further subdivided
Continued.
1. Both methods employed networks to schedule and display task sequences 2. Both methods identified activities a critical path of tasks that could not be delayed without delaying the projects;
3. Both methods identified activities with slack (float)that could be somewhat delayed without extending the project time; 4. Anything that could be done with PERT can also be determined through CPM
Network- a diagram of nodes connected by directional arcs; Path- a series of connected activities between any two
events in a network Critical path- the set of activities on a path from the projects start to finish event, that if delayed, will delay the completion date of the project. Marked by events having a zero slack.
Tasks a b c d e f g
c
f d S t a r t e
b
e
c
1 d
d
b 2 2 e 4 e
S S t t a a r r t t
I J
F G, H
6 4
Slack time
Slack/Float: It is the amount of time that an activity can be delayed without delaying the project; Slack= LST-EST = LFT-EFT
Problem
Activity Immediate Predecessor(s) Time Taken
A B C D E F G H I J K
A B B A C D A E,G,H F,I,J
12 9 10 10 24 10 35 40 15 4 6
Pessimistic time (Tp): the maximum possible time required to accomplish a task, assuming everything goes wrong;
Optimistic time (To): the minimal possible time required to accomplish a task, assuming everything is in your
favour
G H
I J
C, D F, G
E I
11 6
4 3
11 14
6 5
11 10
5 4
Slacks/Floats Types
Total float
extra
time available to complete an activity if its started as early as possible and finished as late as possible. (LF- ES)
time available to complete an activity when its started at EOT of its preceding activity and finished at EOT of its succeeding activity an activity is started at LOT of preceding activity and finished at EOT of succeeding
Free float
Extra
Independent float
When
PROJECT CRASHING
Project Crashing
Crashing
Crash time
Crash cost
cost of reducing activity time Activity Cost Slope: It indicates the additional cost incurred per unit of[Crash cos t NormalCost ] time saved in reducing the duration [ Normal Time Crash Time ] of an activity. Activity cost slope:
Goal
Project Cost
Direct costs
Consists
of labor, material, machine time, etc. and is associated with individual activities. If the time duration of the activities are reduced, the direct cost increases.
Indirect Costs
Associated
with the project not the activities If the duration of the project is reduced/ crashed, the indirect costs decrease. Administrative overhead, rent of equipment, etc.
Time-Cost Tradeoff
Minimum cost = optimal project time Total project cost Indirect cost Cost ($)
Problem on crashing
For a network shown below, normal time, crash time, normal cost and crash cost are given in the table. Construct the network by crashing it to the optimum level and find out the optimal project cost. Indirect cost is given as Rs 100per day.
Activity NORMAL Time (days) Cost(Rs) CRASH Time (days) Cost(Rs)
1-2
2-3 2-4 2-5 3-4 4-5
3
6 7 8 4 5
300
480 2100 400 320 500
2
4 5 6 3 4
400
520 2500 600 360 520
Resource Leveling
Resource leveling is a project management technique used to examine unbalanced use of resources (usually people or equipment) over time, and for resolving over-allocations or conflicts