Outline
Key Discussions from last week (Project Risks) Configuration Management Schedule & Cross Team Inspections Requirements Overview
General Specifics to look for in LOC Counter SRS

Reviews & Inspection Summary SRS Inspection Process Measurement Data Collection <SRS Inspection> Design Phase Overview

6/12/2007

2007_06_12_Rqmts.ppt

SRS & Test Plan


System Test manager participates in SRS inspection of other team** Reviews for clarity and completeness of requirements
Requirements provide basis for test plan

Test plan (baseline next week) inspected by other team**

6/12/2007

2007_06_12_Rqmts.ppt

Milestones
Requirements (SRS)
Initial Draft out for review Final draft for inspection Inspection Baselined June 10 June 12 June 12 June 15 June 17 June 19 June 22

System Test Plan


Draft out for review Inspection Baselined

High Level Design (SDS)


Inspected & Baselined June 19

6/12/2007

2007_06_12_Rqmts.ppt

Configuration Management Process


Three aspects: Change Tracking Version Control

Library
Objectives: Product content known & available at all times Product configuration is documented & provides known basis for changes

Products labeled & correlated w/ associated requirements, design & product info
Product functions traceable from requirements to delivery All product contents properly controlled & protected Proposed changes identified & evaluated for impact prior to go/no go decisions
6/12/2007 2007_06_12_Rqmts.ppt 5

Configuration Management
Types of product elements Maintained (e.g. software) Baselined & Maintained (e.g. SRS) Quality Records (e.g. meeting notes, action item list)

Key Functions
Latest Version of each product element (software, documents, quality records) Copies of prior versions of each product element Who changed from previous version

When changed
What changed Why changed
6/12/2007 2007_06_12_Rqmts.ppt 6

Configuration Management Plan


Configuration identification
Name Configuration items Owner Storage location

Configuration control procedure


Process for making changes, lock-out procedures (e.g. check-out, check-in procedures)

Configuration control board (CCB)


Reviews all change requests Determine if change is appropriate, well understood & resources available Approvals, commitments ? Defects: holding for CCB vs. urgency of change ?

Configuration change request form (CCR, aka CR) Baseline Process (see page 326) Backup procedures & facilities Configuration status reports (CSR) Software Change Management status reports @ weekly meeting
6/12/2007 2007_06_12_Rqmts.ppt 7

Baseline Considerations
Criteria
Defined in Configuration Management Plan Review / inspection completed & stakeholders recommend approve for baseline All major and blocking issues should be resolved CRs tracking any remaining (and unresolved) issues Update version # to reflect baselined document (e.g. 1.0) Place under change control

Actions

Project Baseline snapshot of CIs, baselined & current versions

6/12/2007

2007_06_12_Rqmts.ppt

Automated Configuration Mgmt


Lucent: Sablime / SBCS & SCCS Rational: DDTS / ClearCase Perforce Software: Perforce Microsoft: Visual SourceSafe MKS

6/12/2007

2007_06_12_Rqmts.ppt

Change Workflow
New / Proposed

Study

Assigned

NoChange Deferred Declined

Resolved

Integrated

Delivered

Verified

6/12/2007

2007_06_12_Rqmts.ppt

10

Requirements Phase
Outputs:
Completed & Inspected SRS document Completed Inspection form (INS) Time, defect & size data collected Configuration Management Plan* Updated project notebook

Note: On baselining SRS, the document should be placed under change control

6/12/2007

2007_06_12_Rqmts.ppt

11

Requirements Drivers

Functional Needs Statement

SW Requirements Specification

Development

Test

User Documentation

Customer

6/12/2007

2007_06_12_Rqmts.ppt

12

Software Requirements Specification (SRS)


Objective:
Provide information necessary for understanding the proposed product and to explain/justify the need for various product attributes (user code & documentation)

Standards:
IEEE610.12 1990, IEEE Standard Glossary of Software Engineering Terminology IEE830 1998, IEEE Recommended practice for Software Requirements Specifications IEEE 1220-1998 Application and Management of the Systems Engineering Process IEEE 1233-1998 Guide for Developing System Requirements Specifications

6/12/2007

2007_06_12_Rqmts.ppt

13

Software Requirements Statements


Unambiguous:
All involved (e.g. customers, developers, testers) interpret statement in same way Glossary defining each important term can help

Correctness:
describes a condition or attribute that is required of the final product & all agree this is the case Also, each rqmts statement must be compatible with prior information

Verifiable:
Requirement can be verified prior to delivery to customer by inspection or test To satisfy, use concrete terms and measurable quantities whenever possible

Consistency:
Assure individual requirements do not conflict with one another

Completeness:
All significant requirements for the product are provided (e.g. input: responses for both valid & invalid data)

6/12/2007

2007_06_12_Rqmts.ppt

14

Software Requirements Types


Functional:
Specific actions that program needs to perform in order to meet users needs Defined or quantified based upon customer expectations

Quality:
Various attributes including reliability, usability, efficiency, maintainability, portability, etc.

Performance: Regulatory:
Industry Standards (TL9000) Government/Regulatory (e.g. UL)

Security:
6/12/2007 2007_06_12_Rqmts.ppt 15

Security Requirements
Policy: what to secure, against what threats, by what means? Who is authorized? Confidentiality: preventing unauthorized reading or knowledge Integrity: preventing unauthorized modification or destruction Availability: accessible to authorized users Privileges: controlling access and actions based on authorizations Identification & authentication: challenging users to prove identity (e.g. passwords, codes) Correctness: mediation of access to prevent bypassing controls or tampering with system/data Audit: log to assist in identifying when a security attack has been attempted

6/12/2007

2007_06_12_Rqmts.ppt

16

Requirements Identification
Requirements should be numbered or labeled
e.g. Requirement XX Start Requirement XX End Requirement XX comment

Include release (e.g. cycle) number as part of label Traceable to functional need statement (see next slide)

6/12/2007

2007_06_12_Rqmts.ppt

17

Requirements Traceability
Backwards Traceability includes explicit information that identifies the higher level requirements that the lower level requirement derives from
Traceability should cover all phases (e.g. functional need requirements, requirements design, design code, requirements test) Ensures:
nothing is left out of product, change impact assessments

Trace Tables:
Backwards trace table showing link from lower level (e.g. SRS) to higher level (e.g. Strat form)
Part of lower level document

Forwards trace table shows lower level requirements derived from an upper level requirement

LOC Project generate a backwards trace table*


6/12/2007 2007_06_12_Rqmts.ppt 18

SRS Document Baseline/Change History


Tracks all versions and modifications Version numbering scheme documented in CM plan Change request information tracks to CRs
e.g.
Version 0.1 Pre-baseline version for review Version 1.0 Cycle 1 baseline version Version 1.1
CR 101 Clarify security requirements CR 102 delete support for VB files

Version 2.0 Cycle 2 baseline version Adds the following features . Version 2.1
6/12/2007 2007_06_12_Rqmts.ppt 19

SRS Characteristics Summary


Detailed, clearly delineated, concise, unambiguous & testable (quantifiable) Changes
Defects Clarifications Additions / Enhancements

Requirements should be numbered or labeled


e.g. Requirement XX Start Requirement XX End Requirement XX comment

Traceable to functional need statement Inspected & baselined Maintained under change control Document includes structural elements including:
Baseline/change history Approval page 6/12/2007 2007_06_12_Rqmts.ppt Customer documentation specifications

20

LOC Counter Requirements


(See also TSPi pp112-113 ) Overall description and framework of GUI (if provided) Input
File formats (ANSI text) & extensions (.c, .cc) supported Limits on file names (e.g. max characters) Additional features (e.g. browsing for input file) Error cases, one or both files empty, non-existent, unable to be opened

Results of Comparison Algorithm


Output if identical lines moved (e.g. Line A, B, C, D vs. Line A, C, B, D) Treatment of comments (in-line & alone), blank lines, braces (LOC counting) Multi-line statements / comments

Output
Format and location of output (e.g. screen, file, directory)

Errors
All errors including messages (invalid inputs, algorithm errors, etc.)

Other
Product installation & execution User documentation plan Response time Security Scalability (e.g. max file sizes supported) Concurrency HW requirements (e.g. processor, hard drive, display resolution, OS, peripherals such as mouse)
6/12/2007 2007_06_12_Rqmts.ppt 21

Why Do Reviews / Inspections?


Can identify defects early in the process more efficient (i.e. cheaper) defect removal Leverages knowledge of multiple engineers Leverages different viewpoints Improves defect detection odds Broadens understanding of product being inspected*

6/12/2007

2007_06_12_Rqmts.ppt

22

Inspections vs Reviews
Inspections
Formal, typically requires face to face meetings Measurement data collected Disposition of product agreed to Quality records available

Reviews
Informal Can be face to face, email exchange Measurement data and quality records optional Typically used for early product work & small code changes
6/12/2007 2007_06_12_Rqmts.ppt 23

Peer Reviews
Review Objectives:
Find defects Improve software element Consider alternatives Possibly, educate reviewers

Types:
Desk Check: informal, typically single peer, effectiveness? Walk-through: informal, several peers, notes taken, data collection optional Variant: test walk-through

6/12/2007

2007_06_12_Rqmts.ppt

24

Inspections
Inspection Objectives
Find defects at earliest possible point Verify to specification (e.g. design to requirements) Verify to standards Collect element and process data Set baseline point

Exit Criteria
All detected defects resolved Outstanding, non-blocking issues tracked

Techniques & Methods


Generic checklists & standards Inspectors prepared in advance Focus on problems, not on resolution Peers only Mandatory data collection

Roles: Moderator, reader, recorder, inspector, author


6/12/2007 2007_06_12_Rqmts.ppt 25

Inspection Logistics
Identify moderator (for TSPi, use process manager) Inspection briefing (identify inspection roles, set date/time for inspection) Review product
Individual reviews Record time spent reviewing Identify defects, but do not log on LOGD form
(defects recorded during inspection on INS & LOGD forms)

Typically want 3-5 days for an adequate review period

Inspection meeting

6/12/2007

Obtain & record preparation data Step through product one line or section at a time Raise defects or questions Defects recorded by moderator on INS form Defects recorded by producer on LOGD form (no need to use Change Requests) Peripheral issues & action items should be recorded in ITL log*
2007_06_12_Rqmts.ppt 26

Inspection Logistics (continued)


Estimate remaining defects
TBD (but, for each defect, record all members who identified it)

Conclude meeting
Agree on verification method for defects Agree on disposition (e.g. approved, approved with modification, reinspect)

Rework product & verify fixes (e.g. moderator) Obtain signatures of all inspectors on baseline sheet (file as quality record)

6/12/2007

2007_06_12_Rqmts.ppt

27

Measurement Data & Metrics


Base Metrics
# & Type of Defects found (major, minor) For each defect, who found # of pages inspected, preparation time (per inspector), inspection time

Measures
Preparation rate = # pages / average preparation time Inspection rate = # pages / inspection time Inspection defect rate = # major defects / inspection time Defect density = # estimated defects / # of pages Inspection yield = # defects / # estimated defects (individual & team)

SRS Phase Defect Containment (%) =


100% * # Defects removed @ step / ( Incoming defects + Injected defects)
6/12/2007 2007_06_12_Rqmts.ppt 28