Académique Documents
Professionnel Documents
Culture Documents
Capacity constraints Firm orders from known customers Aggregate Product Plan Forecast of demand from random customers Inventory levels
Inventory transactions
Reports
Dependent Demand
B(4)
C(2)
D(2)
E(1)
D(3)
F(2)
MRP designed to answer the following questions: y What is needed ? y How much is needed? y When is it needed ?
3 4
y Master schedule:
y states which end items are to be produced, when these are needed,
Master schedule
reports
Item/Week Drills
Inventory records
Inventory transaction
5
Saws
Subassembly
Wheels (2)
Frame (1)
10
Start production of D
1 week 2 weeks
D E
2 weeks to produce
Information about y Gross requirements y Scheduled receipts y Expected amount on hand Other details for each item such as y Supplier y Lead time y Lot size y Changes due to stock receipts and withdrawals y Canceled orders and similar events
B A E F
1 week 1 week 2 weeks
2 weeks
G
1 week
3 weeks
D 1 2 3 4 5 6 7 8
12
MRP Terminology
y Scheduled receipts
6
6 y
periods as their corresponding orders have been released in the past Planned order receipts become scheduled receipts at the time when they are released to suppliers
13
14
manufactured in order to be able to fully deliver independent demand requirements in a timely fashion
y Presence of positive net requirements signals
16
Lot-for-lot ordering The order or run size for each period is set equal to demand for that period. Lot size ordering
Net requirement quantities are subject to adjustments due to lot sizes considerations.
17
18
Example 1
A firm that produces wood shutter has received two orders. One for 100 shutters and one for 150 shutters. The 100 unit order is due for delivery at the start of week 4, and the 150 unit order is due for delivery at the start of week 8. Each shutter consists of four slatted wood sections and two frames. The wood sections are made by the firm, and fabrication takes 1 week. The frames are ordered, and lead time is 2 weeks. Assembly of the shutters requires 1 week. There is a scheduled receipt of 70 wood sections in (i,.e., at the beginning of week 1). Determine the size and timing of planned-order release necessary to meet delivery requirements under (1) lot for lot ordering, (2) Lot size ordering with a lot size of 320 for frames and 70 units for wood sections.
19 20
c. Develop MRP schedule with lot for lot ordering (order size equal to net requirements). Master schedule for Shutters:
Week number Quantity 1 2 3 4 100 5 6 7 8 150
100
150
4
100
8
150
150 150
21
22
100
150
d. Develop MRP schedule with lot size ordering 300 300 300 Master schedule for Shutters:
Week number Quantity 1 2 3 4 100 5 6 7 8 150
100
150
70 70
70
70 330 330
150 150
330
24
100
150
Another example
There is a beginning inventory of 110 units of D on hand, and all items have lead times of one week.
2 200 200 320 300 120 120 120 120 140 180 320 320 4 400 600 20 20 20 580 630 50 B
D (2)
70 70
70
70 20 330 350
350
630
25
80[ 50[c] A]
26
80
C: LT=1 weeks 1
Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases
5 50 50 50
A: LT=1 week
Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases
80 80 80 80
D: LT=1 week
Gross requirements Scheduled receipts Projected on hand 110 Net requirements Planned order receipts Planned order releases
27
80 110
50 times 2 100
110 30 70 70 70
28
Some orders get completed Other orders are nearing completion New orders will have been entered Existing orders will have been altered y Quantity changes y Delays y Missed deliveries
A schedule indicating the amount and timing of future orders Authorizing the execution of planned orders Revisions of the dates or quantities, or the cancellation of orders
y Order releases
y
y Changes
y
MRP in Services
y Food catering service
y End item
Evaluation of system operation, including deviations from plans and cost information
y
y Dependent demand
y Planning reports
y
bill of materials
y Hotel renovation
y Activities and materials
y Exception reports
y
E.g., late and overdue orders, excessive scrap rates, requirements for nonexistent parts
MRP Benefits
y Enables managers to easily
y determine the quantities of each component for a given
MRP Requirements
y To implement an effective MRP system requires: y A computer and the necessary software to handle computations and maintain records y Accurate and up-to-date y Master schedules
order size
y To know when to release orders for each component y To be alerted when items need attention
y Additional benefits
y Low levels of in-process inventories y The ability to track material requirements y The ability to evaluate capacity requirements y A means of allocating production time y The ability to easily determine inventory usage via
backflushing
MRP II
y Manufacturing resources planning (MRP II)
y Expanded approach to production resource planning, involving
Use MRP to simulate material requirements Convert material requirements to resource requirements Is shop capacity adequate? Revise tentative master production schedule
Can No capacity be changed to meet requirements
other areas of the firm in the planning process and enabling capacity requirements planning
y
Most MRP II systems have the capability of performing simulation to answer a variety of what if questions so they can gain a better appreciation of available options and their consequences
No
Yes
Firm up a portion of the MPS
Yes
Change capacity
36
1. The master production schedule states which end items are to be produced, in addition to when and how many. 2. Net requirements equal gross requirements minus safety stock.
3. The bill of materials indicates how much material will be needed to produce the quantities on a given master production schedule.
True or False?
4. The bill of materials contains information on lead times and current inventory position on every component required to produce the end item.
True or False?
6. The gross requirements at one level of an MRP plan determine the gross requirements at the next lower level.
5. The inventory records contain information on the status of each item by time period.
7. Lot-for-lot ordering in MRP eliminates the holding costs for parts that are carried over to other periods.