Académique Documents
Professionnel Documents
Culture Documents
Realistic
Yes
CRP is a process which determines the expected capacity requirements for each period at each work station, given the MRP production schedule. Production capacity per period is often limited.
New MRP schedules must be developed to obtain a feasible plan given the capacity constraints at all levels.
ADM 3301/Rim Jaber 3
The work loads of the work stations for all planning periods may need to be balanced:
use of overtime; selection of alternate work centers to perform tasks; use of external capacity (subcontracting); leveling of production: inventory vs. stockout; renegotiation of due dates, and re-scheduling.
ADM 3301/Rim Jaber 4
EXAMPLE 4
Going back to Example 4 of Aggregate Planning, the optimal production plan required (obtained from the Linear Programming optimal solution):
180 units manufactured during month 1, 284 units manufactured during month 2,
320 units manufactured during month 3, 352 units manufactured during month 4.
Demand for Product A for the next four months is 255, 294, 321, and 301 units; beg. Inv.= 85 5 units and end. Inv. = 50 units
Subcontracting (the work only: the company will provide the raw materials) is possible, but external capacity is limited to 12, 15, 15 and 17 units for the next four months respectively. Costs for this problem are: subcontracting: $650 per unit inventory holding: $125 per unit per month backlog: $250 per unit per month (one month maximum) hiring: $500 per worker laying off: $750 per worker raw materials: $500 per unit.
ADM 3301/Rim Jaber 7
x1 = 180, x2 = 280, x3 = 320, x4 = 352, y2 = 4, s1 = 10, s4 = 50, r3 = 1, v2 = 5, v3 = 5, v4 = 4. Manufacture at regular time 180, 280, 320 and 352 units in months 1, 2, 3, and 4, respectively, as well as 4 units at over-time in month 2. Keep in inventory 10 units at the end of month 1 and 50 units at the end of month 4. Backorder 1 unit in month 3. Hire 5 workers in month 2, 5 in month 3 and 4 in month 4.
ADM 3301/Rim Jaber 8
Product A is made up of 1 unit of component B, and 1 unit of part C. Component B is made up of 2 units of part C and 3 units of part D. Part C is made of 1 unit of raw material E and 1 unit of raw material F. Part D is made of 2 units of raw material E
C(1)
E(1) F(1)
10
Split Periods 1 to 4 (month) into Weeks 1 to 16 the production plan is split equally amongst the four weeks of each period (Due to a 1week lead time in the production process, there are only 15 production days left in month 1 3 production weeks for month 1).
= = = =
60 71 80 88
ADM 3301/Rim Jaber 12
13
For product A (end item) correspond to the weekly requirement quantities shown in the MPS. For B, C, D, E, and F (components) these quantities are derived from the Order releases of their immediate parents
ADM 3301/Rim Jaber 14
Net Requirements
Order Receipts(t) = Net Req.(t) Order releases = orders Receipts offset by lead time If Net Req.(1) >= 0 what does this implies?
Order Receipts(1) = 0 Net Req.(1) = 0 for item A, B, C, D, E, and F ADM 3301/Rim Jaber 15
Inputs
Order releases from MRP (Units Produced in Excel file) Job times, shop load Conversion of quantity requirements into labor and machine requirements. Compare these capacity requirements with available department capacity to determine the extent to which these product utilizes capacity.
Output
Underutilization unused capacity can be used for other jobs Overutilization available capacity is insufficient to handle ADM 3301/Rim Jaber 16 requirements
SYSTEM NERVOUSNESS
The term system nervousness describes the way a system might react to changes. Changes to the MPS in future periods cause a chain reaction of changes in material requirements in earlier periods. If the cascade of changes continues into past periods, shortages may result. This kind of chain reaction can be prevented by freezing the MPS.
ADM 3301/Rim Jaber 17
TIME FENCES
Time fences attempt to achieve a balance by requiring higher level authorization for changes to the MPS that are closer in time, but allowing changes further removed in time to be authorized by lower levels of management. Time fences is a series of time intervals during which order changes are allowed or restricted.
ADM 3301/Rim Jaber 18
TIME FENCES
Frozen
No schedule changes allowed within this window Specific changes allowed within product groups as long as parts are available
Moderately Firm
Flexible
Significant variation allowed as long as overall capacity requirements remain at the same levels
ADM 3301/Rim Jaber 19
MRP REQUIREMENTS
Computer system Mainly discrete products Accurate bill-of-material Accurate inventory status
20
Extensions of MRP
Closed-Loop MRP
MRP system provides input to the capacity plan, MPS, and production planning process
Capacity Planning
MRP system generates a load report which details capacity requirements This is used to drive the capacity planning process Changes pass back through the MRP system for rescheduling
2011 Pearson Education, Inc. publishing as Prentice Hall 21
B.
C.
23
Figure 14.8
24
No
Planning
Capacity requirements
(detailed)
Figure 14.8
25
Priority Control
Capacity Control
Input/output report
Execution
200
150
Lot 11
Available capacity
Lot 15
150
Lot 6
Available capacity
Lot 9 Lot 12 Lot 11
100
Lot 1
Lot 2
Lot 12
100
Lot 1
Lot 2
Lot 15
50
Lot 10
Lot 3
Lot 5
Lot 13
Lot 14
50
Lot 16
Lot 10
4 5 Period (a) 6 7 8 1
Lot 3
Lot 5
Lot 13
Lot 14
Lot 16
4 5 Period (b)
Figure 14.9
2011 Pearson Education, Inc. publishing as Prentice Hall 27
200
150
Lot 11
Available capacity
Lot 15
150
Lot 6
Available capacity
Lot 9 Lot 12 Lot 11
100
Lot 1
Lot 2
Lot 7 Lot 4
Lot 12
100
Lot 1
Lot 2
Lot 7 Lot 4
Lot 15
50
Lot Lot It is also possibleLot split lots 6 Lot 11 and Lot to and Lot moveLot 16 16 13 13 Lot Lot 8 8 Lot 3 3 them earlier in the schedule.This would avoid any 5 5 2 potential problems with late orders but5would 8 3 4 5 6 7 8 1 2 3 4 6 7 Period Period increase inventory holding cost.
Lot 10
Lot 14
50
Lot 10
Lot 14
(a)
(b)
Figure 14.9
2011 Pearson Education, Inc. publishing as Prentice Hall 28
Smoothing Tactics
1. Overlapping
Sends part of the work to following operations before the entire lot is complete
Reduces lead time
2. Operations splitting
Sends the lot to two different machines for the same operation Shorter throughput time but increased setup costs
MRP in Services
Some services or service items are directly linked to demand for other services
MRP in Services
(a) PRODUCT STRUCTURE TREE Veal picante #10001
Spinach #20004
Figure 14.10
Sauce #30006
Veal #30005
31
MRP in Services
(b) BILL OF MATERIALS
Description
Veal picante Cooked linguini Prepared veal and sauce Spinach Uncooked linguini Veal Sauce
Quantity
1 1 1 0.1 0.5 1 1
32
MRP in Services
(c) BILL OF LABOR FOR VEAL PICANTE
Labor Hours
Work Center
1 2 3
Operation
Cook linguini Cook veal and sauce
Labor Type
Helper one Assistant Chef
Setup Time
.0069 .0005 .0125
Run Time
.0041 .0022 .0500
33
34
Figure 14.11
38
Invoicing
Figure 14.11
ADM 3301/Rim Jaber 39
Inventory Management
Bills of Material
MRP
Work Orders
General Ledger
Accounts Payable
Payroll
Logistics
Electronic catalogs Quality management
43
44
Figure 14.12
Promote to Deliver
Covers front-end customer-oriented activities: Marketing Quote and order processing Transportation Documentation and labeling After sales service Warranty and guarantees
Design to Manufacture
Covers internal production activities: Design Shop floor engineering reporting Production Contract/project engineering management Plant Subcontractor maintenance management
Procure to Pay
Recruit to Hire
Covers all HR- and payroll-oriented activity: Time and attendance Payroll Travel and expenses
Covers sourcing activities: Vendor sourcing Purchase requisitioning Purchase ordering Purchase contracts Inbound logistics Supplier invoicing/ matching Supplier payment/ settlement Supplier performance
Dock to Dispatch
Covers internal inventory management: Warehousing Forecasting Distribution planning Replenishment planning 2011 Pearson Education, Inc. publishing as Prentice Hall
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America.
49