Académique Documents
Professionnel Documents
Culture Documents
Authors: Klaus-Peter Brand ABB Switzerland Ivan De Mesmaeker Outgoing Chairman of CIGRE B5 ABB Switzerland
8th Symposium on Power System Management Cavtat, November 9-12, 2008
Table of Contents - On-goings Level of integration Standardisation Typical bay and station level IEC 61850 - Use of IEC 61850 - Process bus - Communication between/outside substation - Conclusions
8th Symposium on Power System Management Cavtat, November 9-12, 2008
QB1
Line 1
Line 1
QB2 Line 2
QB2 Line 2
QB3
QB3
7 IEDs
2 IEDs
BPS 571
BCS 671
Bay Control Solution
Lessons learned from CIGRE: Specification functional oriented Away from box to box approach Functionality realised as near as possible to the primary process
Reference: CIGRE Brochure 329 Guidelines for specification and evaluation of Substation Automation Systems
8th Symposium on Power System Management Cavtat, November 9-12, 2008
Long term stability The standard shall be future proof, i.e. it must be able to follow the progress in communication technology as well as evolving system requirements. Free configuration The standard shall support different philosophies and allow a free allocation of functions e.g. it must work equally well for centralized (RTU like) or decentralized (SAS like) systems.
=QB1
=QB1
=QA1 =QC1
=S1CSWI1
=QA1 =QC1
=S1CSWI1
=QE1
=QE1
=XW1
Complete Single line 8 Symposium on Power System Management Cavtat, November 9-12, 2008
th
Communication Subnetwork
of initial investment
Switchyard
Exchangeable
Substation Automation System
Portable
IEC61850 Data Model of the Substation
ABB
2 5 LI NEA O O1 2 kV G B B
= 04 R 1 D +0
import
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16
ABB
P W R MO T I N U T O E NI OR G NI
=W 2 -Q 1 SE L -Q 2 SE L
Q - 0 SE L
LA E MP TE ST E
O U R R FE R V I MER
ABB
D TN E S I AC ESC EX E LO C
LO CA L C ONTR OL
A B B
A B N ew rkP art er B t o n R L 1 *4 E36
M ETERI NG
Specification
1 2 3 4 5 6 7 8
9 10 11 12 13 14 15 16
Supplier Knowhow
SAS capability
Station Topology
Long term
Short/medium term
Long term
Investments in engineering are save guarded because existing & tested SA design can be migrated to new technology of any manufacturer. 8th Symposium on Power System Management Cavtat, November 9-12, 2008
On-goings: Standardisation - IEC 61850 Engineering process based on SCL data exchange
Device capability IED Configuration Description (ICD) Device (IED) IED Configured IED Description file (CID)
Device specific tool
P2 Q J1 2
Q3 E 1
P2 Q J1 3
T1 /
P2 Q J1 4
Q E3
25 SPV
R SYN1 CILO 1 CSW I1
C 3ph B
XCBR1
Q1 C 1
CILO 2
CSW I2
XSWI1
1
C1 T / , ,
Q9
CILO 3
CSW I3
XSWI2
SW _ 3
CILO 4 CSW I4 XSWI3
SW _ 4
CILO 5 CSW I5 XSWI4
CT1 / , ,
Q1 E Q1 E
SW _ 5
CILO 6 CSW I6 XSWI5
Q0 ,
Q1 VT N
Q2
TVTR 1
21 Z1 <
PD IS1
21 Z2 <
PD IS2
21 Z3 <
PD IS3
21 Z<
PSCH1
ITT
PTR C1
51
I>
1 1
PTOC 1
Function spec
V1 T /
SW _ 2
SW _ 1
Q1 C
/ C T1 / , , / V1 T
/ / V T1
C T1 / , ,
Q1 A,
/
Q A1 , Q, A1
Q1 E
2 Q1 B Q1 B Q2 B Q2 B
Q B1
A S_P J1 1 A 2 W
5H 0z
W 1 B 15 V IL 0 0k
P W 2J1 2
5 z 0H W 1 B 150 IL 0 kV
Singl e line
1 Q1 A ,
Q B2
C B_1
P J1 6 2 Q
Q8
VT1 / Q5
Q2 B
Q1 B
Q2 5
Q1 5
Configure SA System
An al yz e
Co
Station Computer
Simulate
mp are
se ow Br
Client
IED
IED
IED
MultipleIEDs
Process Bus Process Interface Control & Protection Engineer Process Interface
Explore Ethernet
Explore IEDs
IED
Process Bus
IED
IED
IED
Process Interface
Process Interface
Process bus
Information exchange between the substation system (bay level) with the HV equipment: - Voltage and current samples IEC 61850-9-2 LE (80 s/cycles= 4 kHz) - Switch position - Commands
Control Center HMI, Station controller Router
Bay Controller
Relay X1
Relay X2
Bay Controller
Relay X1
Relay X2
Switchgear
CT/VT
Process bus
IEDs with LN instances without/with Process Bus
PDIS PDIS PDIS Protection IED PTOC PDIS PDIS PDIS Protection IED PTOC
PTRC
PTRC
TVTR
TCTR
hardwired
TVTR
TCTR
XCBR
Breaker IED
Process bus
Samples as values in SI units (SV) Logical Device Merging Unit LN PCTR LN PCTR LN TVTR LN PCTR LN PCTR LN TCTR
The Samples acc. to IEC 61850 Are independent from the instrument Transformer/Sensor Technology !!! 8 Symposium on Power System Management Cavtat, November 9-12, 2008
th
TRIP (GOOSE) Protection Device Logical Device Breaker IED LN PCTR LN PCTR LN XCBR Logical Device Breaker IED LN PCTR LN PCTR LN XCBR Process bus
Process bus
Phase T Protection Merging Unit Phase S Protection system X Control & Protection devices
Phase R
Protection system Y
Process bus
Ethernet ring Bay
Protection 1
Protection 2
Control
The process bus shall not jeopardize the requested independency of Main 1 and Main 2 !
Primary technology
For CITs a serial fiber optic link according to IEC 61950-9-2 is beneficial because of reduction of cabling complete galvanic decoupling enabling new applications (future paper)
Merging Units
Interface between any proprietary serial or non-conventional hard-wired link for analog values and IEC 61850 is the so-called Merging Unit (MU) typically used for NCITs. Interface between conventional, hardwired CITs is the so-called Stand-Alone Merging Unit (SAMU). The Merging Units deliver current and voltage as samples according to IEC 61850-9-2
Migration from CIT to NCIT Migration from CITs to NCITs requires the exchange of IEDs with conventional (analog) inputs by IEDs with non-conventional (serial) inputs IED : Intelligent Electronic Device In the examples IEDs are protection relays as transformer protection or line protection
Pxxx
Pxxx
Pxxx
SAMU
A/D A/D
MU
3I, 3U Pxxx
3I, 3U 3I, 3U
Mixed Mode in Protection IED
MU
MU
MU
3I, 3U
HV
HV
MV
MV
HV
HV
MU Protection SAMU
MU Protection MU
MV
MV
Principle: IEC 61850 (GOOSE, SV, etc.) in / IEC 61850 (GOOSE, SV) out Communication equipment: - Has to guarantee performance and data integrity - Has to support priorities, to provide quality attributes and health info. (IEC 61850-90-1 draft)
8th Symposium on Power System Management Cavtat, November 9-12, 2008
IEC 61850
IEC 61850
Line Protection
Line Protection
Line Bay
Line Bay
Frontend
IEC 61850
WAN transparent for IEC 61850 messages IEC 61850
Gateway Router
IEC 61850
Bay 1
Bay 2
Bay 3
Conclusions - Philosophy and spirit of IEC 61850 not only inside the Substation:
Use of the IEC 61850 concept (Logical nodes) in other domain
- Advantages: Better understanding (data model) Engineering and testing facilities (SCL) Openess for future extensions Openess for process bus:
Fully use of the advantages given by the new technology
Conclusions
IED Simulation (Tool) Simulation (Tool) Maintenance (Tool) System Integration/ Engineering (Tool) Switchyard Single Line Functions allocated Specification
F ICD
IED IED
SCD
SA T FA T
en an ce
File
SS D
Fil e
Upgrade (Tool) Test (Tool) Test (Tool) Ref.: PACWORLD Winter 2008 Brand
Ma in t
iles