SALIENT FEATURES & MAJOR COMPONENTS OF DDCMIS

24 May 2012

PMI Revision 00

SALIENT FEATURES OF DDCMIS


INTEGRATED PLANT CONTROL SYSTEM FOR SG, TG AND BALANCE OF PLANT. INTEGRATED PLANT OPERATION THROUGH FULLY INTERCHANGEABLE OPERTAOR WORK STATIONS (OWS) FOR SG, TG AND BALANCE OF PLANT IT MAY BE REMEMBERED THAT THE TERM DDCMIS USED TO BE REFERRED FOR THE SO-CALLED BOP-C&I , THE SG-C&I, i.e. FSSS, BOILER PROTECTION AND TG-C&I i.e. ATRS, TURBINE PROTECTION etc.
24 May 2012 PMI Revision 00 3

SALIENT FEATURES OF DDCMIS


PROVISION OF EXTENSIVE SELFDIAGNOSTICS USE OF LARGE VIDEO SCREENS FOR PROJECTIONS OF VARIOUS PLANT MIMICS AND PARAMETERS. PROVISION OF FAULT ALARM ANALYSIS TO GUIDE THE OPERATOR TO SEE THE MOST LIKELY EVENT. PROVISION OF TREND ALARMS FOR ANALYSIS AND HISTORICAL PURPOSE.

24 May 2012

PMI Revision 00

SALIENT FEATURES OF DDCMIS


PROVISION OF SAFETY HARDWARE FOR BURNER MANAGEMENT SYSTEMS. PROVISION OF FAIL-SAFE HARDWARE FOR TURBINE PROTECTION SYSTEM. PROVISION OF ADEQUATE RELIABILITY AND AVAILABILITY WITH PROPER REDUNDANCY IN SENSOR, INPUT/OUTPUT AND CONTROLLER.

24 May 2012

PMI Revision 00

DDCMIS CONFIGURATION

maxDNA SYSTEM
ENGG. STN FOR HMI HMI

PROCONTROL SYSTEM

MMI LAN

HMI REDUNDANT SERVERS ENGG.STN. FOR CONTROL SYS.

I.P. BUS Max. 4 nos. rdundant

Redundant F.G.Controllers

Measurement system / I/O subsystem

24 May 2012

PMI Revision 00

MAJOR COMPONENTS OF DDCMIS

24 May 2012

PMI Revision 00

MAJOR COMPONENTS OF DDCMIS


CONTROL SYSTEM MAN-MACHINE INFORMATION AND PLANT INFORMATION SYSTEM (MMIPIS) REDUNDANT DATA COMMUNICATION SYSTEM (DCS).

MASTER & SLAVE CLOCK SYSTEM.

24 May 2012

PMI Revision 00

MAJOR COMPONENTS OF DDCMIS


SEQUENCE OF EVENT (SOE ) AND ANNUNCIATION SYSTEM FUNCTIONS.
SYSTEM PROGRAMMING FACILITY:a) TUNING & CONFIGURATION FOR CONTROL SYSTEM. b) MODIFICATION & PROGRAM DEVELOPMENT FOR MMIPIS.

24 May 2012

PMI Revision 00

CONTROL SYSTEM PROCONTROL P-13/42

24 May 2012

PMI Revision 00

10

PROCONTROL P-13/42
PROCONTROL P13/42 CONTAINS A BUS SYSTEM: P-42 REPRESENTS INTRA PLANT BUS, IS RESPONSIBLE FOR SIGANL TRANSPORT. P-13 REPRESENTS LOCAL BUS, IS RESPONSIBLE FOR SIGANL CONVERSION AND SIGNAL PROCESSING.

24 May 2012

PMI Revision 00

11

PROCONTROL P-13/42 ARCHITECTURE

24 May 2012

PMI Revision 00

12

24 May 2012

PMI Revision 00

13

BASIC STRUCTURE OF PROCONTROL P13/42

24 May 2012

PMI Revision 00

14

24 May 2012

PMI Revision 00

15

24 May 2012

PMI Revision 00

16

24 May 2012

PMI Revision 00

17

CONTROL SYSTEM
PROGRAMMING & CONFIGURATION MMIPIS SYSTEM M&S CLOCK

DCS

SG- C&I SYSTEM


24 May 2012

BOP- C&I SYSTEM


PMI Revision 00

TG- C&I SYSTEM


18

SG-C&I SYSTEM
SG-C&I SYSTEM CONSISTS OF : 1. BURNER MANAGEMENT SYSTEM (BMS). 2. SOOT BLOWER CONTROL SYSTEM (SBC). 3. SECONDARY AIR DAMPER CONTROL SYSTEM (SADC). 4. AUXILIARY PRDS CONTROL SYSTEM (APRDS).

24 May 2012

PMI Revision 00

19

SG-C&I SYSTEM FEATURES


FOR BMS, SAFETY SYSTEM HARDWARE IS SPECIFIED (i.e. THE HARDWARE , WHICH MEETS THE REQUIREMENT OF NFPA AND VDE STANDARDS) TRIPLE REDUNDANT CONFIGURATION FOR THE FURNACE PROTECTION (MFT) PORTION OF BURNER MANAGEMENT SYSTEM (BMS). FOR SBC, SADC, APRDS, INTERLOCK AND PROTECTION, CONFIGURATION SIMILAR TO OLCS/CLCS IS USED. FOR MILL & OIL ELEVATIONS LOGICS, SAFETY SYSTEM HARDWARE SHALL BE USED.
24 May 2012 PMI Revision 00 20

TG-C&I SYSTEM
TG-C&I SYSTEM CONSISTS OF :
1. 2. 3. 4.
5. 6. 7. 8. 9.

TURBINE PROTECTION SYSTEM (TPS). AUTOMATIC TURBINE RUN-UP SYSTEM (ATRS). AUTOMATIC TURBINE TESTING SYSTEM (ATT). ELECTRO- HYDRAULIC TURBINE CONTROL SYSTEM (EHTC) FOR MAIN & BFP TURBINE. TURBINE STRESS CONTROL SYSTEM (TSCS). GLAND STEAM PRESSURE CONTROL SYSTEM. GENERATOR SEAL OIL SYSTEM. PRIMARY WATER SYSTEM. HYDROGEN CONTROL SYSTEM.
PMI Revision 00 21

24 May 2012

TG-C&I SYSTEM FEATURES


TRIPLE REDUNDANT OR 2 X 100 % REPEATED TWICE CONFIGURATION FOR THE TURBINE PROTECTION SYSTEM (TPS). FOR THIS, SAFETY SYSTEM HARDWARE OR FAIL-SAFE HARDWARE SHALL BE USED. FOR OTHERS, CONFIGURATION SIMILAR TO OLCS/CLCS TO BE USED.

24 May 2012

PMI Revision 00

22

BOP-C&I SYSTEM
BOP-C&I SYSTEM CONSISTS OF :
1. OPEN LOOP CONTROL SYSTEM (OLCS). 2. CLOSED LOOP CONTROL SYSTEM (CLCS). OLCS INCLUDES THE SEQUENCE CONTROL AND THE INTERLOCK OF ALL THE PLANT SYSTEMS WHICH ARE NOT COVERED IN SG-C&I AND TG-C&I. THIS INCLUDES MAJOR AUXILIARIES LIKE FD/ID/PA FANS, AIR-PREHEATER, BFP/CEP/CWP/ BCWP/ DMCWP/CLCWP AND ELECTRICAL BREAKERS.
24 May 2012 PMI Revision 00 23

BOP-C&I SYSTEM
(CLCS) INCLUDES THE MODULATING CONTROL FOR VARIOUS IMPORTANT PLANT PARAMETERS LIKE FW FLOW, DRUM LEVEL, FURNACE DRAFT, COMBUSTION CONTROL (FUEL FLOW AND AIR FLOW), PA HDR PRESSURE CONTROL, DEAERATOR /HOTWELL/ LP & HP HEATER LEVEL CONTROLS ETC.

24 May 2012

PMI Revision 00

24

MMIPIS

24 May 2012

PMI Revision 00

25

MAN-MACHINE INTERFACE AND PLANT INFORMATION SYSTEM


LATEST STATE-OF-THE-ART WORKSTATIONS /PCs AND SERVERS BASED ON OPENARCHITECTURE AND INDUSTRY STANDARD HARDWARE AND SOFTWARE TO ENSURE BETTER CONNECTIVITY. HARDWARE FROM COMPAQ/DIGITAL, HP, SUN MICRO-SYSTEM OR OTHER MAJOR SUPPLIERS OPERATING SYSTEM WINDOWS-2000, OPENVMS OR UNIX.
24 May 2012 PMI Revision 00 26

MAN-MACHINE INTERFACE AND PLANT INFORMATION SYSTEM


64/ 32-BIT SERVER/OWS WITH HIGH-SPEED AND LARGE MEMORY (256/512 MB RAM, 8 GB HDD FOR SERVER AND 128/256 MB RAM AND 4/6 GB HDD FOR OWS) TO ENSURE FAST RESPONSE. PROVISION OF LVS (LARGE VIDEO SCREEN). CONNECTION TO OTHER SYSTEM THROUGH STATIONWIDE WAN.

24 May 2012

PMI Revision 00

27

MMIPIS FUNCTIONALITIES
VPC OPERATION OTHER OPERATOR INFORMATIONS THROUGH VARIOUS DISPLAYS ALARMS, LOGS, HISTORICAL AND LONG TERM STORAGE. PERFORMANCE AND OTHER CALCULATIONS

24 May 2012

PMI Revision 00

28

24 May 2012

PMI Revision 00

29

24 May 2012

PMI Revision 00

30

SOE
A max of 256 important digital input points 1 Milli Second Resolution

Prints after 3 min. of last digital change


Later modified as 5 min. data

24 May 2012

PMI Revision 00

31

SEQUENCE OF EVENT (SOE ) AND ANNUNCIATION SYSTEM FUNCTIONS ORIGINALLY THESE USED TO BE STAND-ALONE SYSTEM (DIODE AUCTIONEERING, DBTC ETC REQUIRED) NOW INTEGRATED -THEREFORE THE DIODE AUCTIONEERING, DBTC ETC NOT REQUIRED. SOE - 1mS RESOLUTION, STORAGE OF REPOTS FOR LONG DURATION ANNUNCIATION LOGIC THROUGH OLCS/CLCS CONTROLLERS.
24 May 2012 PMI Revision 00 32

Post Trip Log


300 Important Analog Points Collected for 5min. Before and After TRIP

10 Sec. Resolution
Circular Buffer

24 May 2012

PMI Revision 00

33

LOGS
Event Activated logs SOE Post Trip Log Start-Up Log Time Activated Logs Daily Log Shift Log Maintenance Data Log On Demand Logs

24 May 2012

PMI Revision 00

34

Historical Storage
Plant data , alarms , SOEs , Post trip logs Previous Two Days Data on Hard Disk 15 Days Data on Magnetic Tape Latest Stage I : 60 days data on Servers

24 May 2012

PMI Revision 00

35

ALARM DISPLAY
Displays all the alarms in the order of their occurrence Useful for analysing the cause of the major failures. All digital DATA and Analog values crossing the limits will be displayed in this window in the order of their occurrence.

24 May 2012

PMI Revision 00

36

REAL TIME TREND


Operator can configure the required points for real time trending purpose and can see the real time trend and in case of any deviation (abnormal change) can react quickly.

OPERATOR GUIDANCE MESSAGES


Operator Guidance messages can be displayed on the DAS monitors when rolling or any important activity is going on.
24 May 2012 PMI Revision 00 37

HARDWARE
CPU I/O CARDS CRTS PRINTERS NETWORK

24 May 2012

PMI Revision 00

38

PANELS & CARDS BACKPLANE PROCESSORS Analog Input Modules

Digital Input Modules


Analog Output Modules

Digital Output Modules


Special Modules
24 May 2012 PMI Revision 00 39

Analog Input Module (mA input)

Accepts Current/Voltage Inputs 4 Channels are available Field input isolation is available Scanning time is 100 millisecond

15 Bit + 1 sign bit Accuracy

24 May 2012

PMI Revision 00

40

* Analog Input Module (RTD)


Used for 3 wire RTD inputs One card can take 04 inputs

Each channel can be programmed for RTD type.

* Analog Input Module (T/C)


Used for Thermocouple Inputs

One card can take 8 inputs


Each channel can be programmed for T/C type PMI Revision 00

24 May 2012

41

* Digital Input Module Process 16 Digital Inputs

24 May 2012

PMI Revision 00

42

* Analog Output Module


4 Outputs

Outputs are short circuit protected


Scan time 8 millisecond

Resolution 12 Bit

24 May 2012

PMI Revision 00

43

* Digital Output Module


16 Outputs are available Contact Rating 5 A 240 V AC 3A 30 V DC

0.3 A 110 V DC

24 May 2012

PMI Revision 00

44

Typical wiring for Digital Output Module

24 V DC

Fuse

Card

Field Device
PMI Revision 00 45

24 May 2012

SYSTEM PROGRAMMING FACILITY

24 May 2012

PMI Revision 00

46

SYSTEM PROGRAMMING FACILITY

LATEST TREND - COMBINED CONTROL


SYSTEM TUNING & MMIPIS PROGRAMMING SELF-DOCUMENTATION ENGINEERING WORKSTATIONS

24 May 2012

PMI Revision 00

47

Object-Oriented Configuration Graphical object-oriented configuration software tool. Includes self-documentation of configuration. True object-oriented features including encapsulation and inheritance. Library of standard algorithms or objects.
24 May 2012 PMI Revision 00 48

MASTER & SLAVE CLOCK SYSTEM

24 May 2012

PMI Revision 00

49

MASTER & SLAVE CLOCK SYSTEM RECEIVES TIME SYNCHRONISATION SIGNALS FROM THE GEO-POSITIONARY SATELLITE SIGNAL.

DISTRIBUTES THIS SIGNAL TO THE MMIPIS AND THE CONTROL SYSTEM.

24 May 2012

PMI Revision 00

50

OTHER RELATED TOPICS


POWER SUPPLY SYSTEM

CABLING & TERMINATION OF SG/TG C&I SYSTEM/


EQUIPMENT. OPERATION PHILOSOPHY , CONTROL AREA AND BACK-UP INSTRUMENTATION & GEOGRAPHICAL DISTRIBUTION - COMBINED CYCLE PLANTS.

REDUNDANCY
DESIGN CRITERIA
24 May 2012 PMI Revision 00 51

POWER SUPPLY SYSTEM


CONTROL SYSTEM POWER SUPPLY TWO SETS OF DC POWER SUPPLIES - ONE SET FOR SG/TG-C&I AND OTHER FOR BOP-C&I EACH WITH 2 X 100 % CHARGER AND 2 X 100 % BATTERY. OTHER IMPORTANT AC LOADS LIKE MMIPIS, PANEL INSTRUMENTS, ANALYSERS ETC. SHALL BE POWERED FROM UPS COMPRISING OF 2 X 100 % CHARGER, 2 X 100 % INVERTER AND 1 X 100 % BATTERY. HEAVY DUTY Ni-Cd BATTERIES HAVE BEEN ENVISAGED FOR LONGER LIFE & LESSER MAINTENANCE
24 May 2012 PMI Revision 00 52

CABLING & TERMINATION


EXTENSIVE GROUPING OF SIGNALS BY LARGE SCALE USE OF JBs AT STRATEGIC LOCATIONS.
USE OF CABLES WITH HIGHER NO OF PAIRS. USE OF CAGE-CLAMP CONNECTION FOR SYSTEM CABINETS, MARSHALLING PANELS & OUTGOING SIDE OF JBs, CJS BOXES etc. USE OF PLUG-IN SOCKET AND CONNECTORS FOR TRANSMITTERS, SWITCHES, LS/TS etc.

24 May 2012

PMI Revision 00

53

IMPORTANT SG / TG RELATED C&I SYSTEM


FLAME MONITORING SYSTEM COAL FEEDER C&I ELECTROMATIC SAFETY VALVES FURNACE TEMP PROBES ACCOUSTIC PYROMETER FOR FURNACE TEMP PROFILE BOILER FLAME ANALYSIS SYSTEM COAL BUNKER LEVEL MONITORING SYSTEM ELECTRONIC DRUM LEVEL MONITORING SYSTEM TURBINE SUPERVISORY SYSTEM TDBFP TURBINE SUPERVISORY SYSTEM

24 May 2012

PMI Revision 00

54

OPERATION PHILOSOPHY
CENTRALISED OPERATION OF MAIN PLANT THROUGH OWS / LVS. OFF-SITE PLANTS TO BE CONTROLLED FROM THEIR LOCAL STATIONS WITH STATION-WIDE LAN DATA LINK. MINIMUM BACKUP INSTRUMENTATION. GEOGRAPHICAL DISTRIBUTION - ALTHOUGH NOT VERY USEFUL FOR POWER PLANTS AS COMPARED TO PROCESS/INDUSTRIES, BEING ADOPTED FOR FEW AREAS WHERE SIGNALS ARE CONCENTRATED. REDUCTION OF CABLING, MUCH LESS ERECTION & COMMISSIONING TIME.
24 May 2012 PMI Revision 00 55

DESIGN CRITERIA
PROVENNESS
SUPPLIERS EXPERIENCE SYSTEM EXPERIENCE PROVENNESS VS OBSOLESCENCE

RELIABILITY AVAILABILITY
HARDWARE QUALITY (PUBLISHED MTBF etc.) CONFIGURATION REDUNDANCY FAULT TOLERANCE

STANDARDISATION AND UNIFORMITY OF H/W


SAME SERIES & FAMILY OF H/W AS FAR AS POSSIBLE DIFFICULTIES BECAUSE OF PACKAGING CONCEPTS & RESPOSIBILITY CENTRE & INTERFACES.
24 May 2012 PMI Revision 00 56

DESIGN CRITERIA
OPERATABILITY
DESIGN CONCEPT - FAIL SAFE ETC. FALSE TRIP VS SAFETY OPERATOR CONVENIENCE DURING NORMAL RUNNING & EMERGENCY MANAGEMENT REPORTING

MAINTAINBILITY
STANDARDISATION (AS INDICATED ABOVE) MODULAR DESIGN AND EXPANDABILITY DIAGNOSTIC, FAULT IDENTIFICATION AND FAULT TOLERANCE GUARD AGAINST OBSOLESCENCE AVAILABILTY OF SPARES

OTHER CRITERIA
UNIT OPERATION PHILOSOPHY MARKET TRENDS AND EVOLUTION OF INFORMATION TECHNOLOGY FEEDBACKS FROM EXISTING SYSTEMS
24 May 2012 PMI Revision 00 57

THANK YOU