Académique Documents
Professionnel Documents
Culture Documents
1.
2.
3.
1.
General
Planning Information:
Total load weight below hook
% of allowable load
Site/unit safety standards and procedures specific to this job have been reviewed
N/A
N/A
[ ] Hand Signals
Other
2.
Workers Responsibilities
PAGE 1 OF 5
Petron
CRITICAL LIFT CHECKLIST
a)
b)
c)
3.
Signal Person
Name
Head Rigger
Name
Will ensure adequate condition and rating of rigging equipment before lift
N/A
Hoisting Operator
Name
Has inspected the equipment and found it in acceptable condition for this lift
Hoisting Equipment:
Major hoisting equipment to be used:
PAGE 2 OF 5
Petron
CRITICAL LIFT CHECKLIST
N/A
N/A
N/A
N/A
N/A
Y
Y
Y
N
N/A
N/A
N/A
4.
Conditions
a)
lbs/kg
lbs/kg
lbs/kg
lbs/kg
lbs/kg
lbs/kg
lbs/kg
lbs/kg
lbs/kg
=
%
b)
Load exceeds 50% of max. allowable load and failure would endanger existing facilities
(If yes, complete this section and section 4a)
c)
Existing facilities
=
Facilities can be protected
Plan in place can be place for isolating facilities in case of failure
Occupied facilities beneath lift zone will be vacated
PAGE 3 OF 5
Y
Y
Y
Y
N/A
Petron
CRITICAL LIFT CHECKLIST
d)
e)
More than one crane required to make the lift and the verified lift exceed 50% of the max.
allowable load for any of the cranes
(If yes, complete this section)
A plan detailing the sequence of steps for the entire lift has been reviewed
All applicable conditions have been considered for each boom
Is the lift planned so that at no time any of the booms will have more than 80% of
their load capacity
A competent person has been selected to co-ordinate this lift
Name
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
f)
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
N/A
Additional Comments:
PAGE 4 OF 5
Petron
CRITICAL LIFT CHECKLIST
Safety plan/lift procedure reviewed by the following involved parties (Name in BLOCK letters, followed by signature):
Client Representative:
SNC-Lavalin:
Contractor:
PAGE 5 OF 5