Insulation resistance test
SIEMENS
42.4 Evaluation of the measurements
‘Cajeais ta be measured | Wessuring voages | — Winimam insulation values
fieference temperature 20°C) _|
[Soran Too - SOOO VOC.
[Rater wing 500-1000 VOC.
[insing tieemomates | 500 1000.7 06
[cold temometer 300 V8
[Stansby nesters "30006
index PL
(RO Sea See ‘R10 min Rt mi ‘Aesezament
S135" 32 “Goer sonst
=125 <2 Diagnosis reaured ——]
Coopyright@siemens AG 2012 / Energy Sector Power AcademyTesting of CT and VT
SIEMENS
Testing of the Current and Voltage Transformers
2.2
23
24
Task
The measuring circuits for protection, synchronisation, closed-loop control
and operational instrumentation are to be tested.
Preconditions
Work status
- Erection has been completed. (The Erection Clearance Certificate
[ECC] has been issued.)
Labelling of the equipment and designation of live enclosed plant
sections has been carried out.
Documentation
~ The circuit diagrams of the electrical equipment cabinets are available
Commissioning checklists CL-E21 and CL-E22
Personnel
= 1. Commissioning engineer: Engineer or technician with experience in
commissioning of types of the electrical equipment systems employed
in the plant.
1 Helper: skilled worker with adequate on-the-job training,
Measuring instruments and tools
Single-phase variable-voltage transformer (approx. 0 - 20 V
secondary voltage),
Single-phase test transformer (approx. 400 V secondary voltage),
4 Ammeter (AC),
1 Voltmeter (AC),
X Multimeter (A, V, Ohms).
Precautions
Observe the rules for handling electronic components sensitive to
electrostatic discharge (ESD measures).
- The VDE Regulations for "Erection and Operation of Electrical Power
Installations" are to be observed (VDE 0100/0101/0105).
~ Special safety arrangements shall be made for all areas which are not
explicitly designated as “electrical operating areas when performing
tests at voltages in excess of 50 V.
Scope
Testing of the plant side cable connections,
Checking that the mounting position is correct,
Checking of the phase and core assignment,
Checking of correct earthing,
Ocopyright@siomens AG 2012 | Energy Sector - Power Academy
pner-1Testing of CT and VT SIEMENS
= Checking of the function.
5. Execution
ual checks
Checking of the cables for damage and that they are connected
correctly,
Checking of the mounting position of the current transformers
(polarity)
~ Checking of the labelling of the individual cores, checking of the
phase/core assignment
- Inspection for cleanliness of voltage transformers, high voltage
connections and associated cable connections
- Inspection of isolators, support structures and earthing connections
5.2 Testing the current transformers,
= Secondary spare cores have to be short -circuited
- In the case of multi core type current transformers each winding must
be tested individually.
Enter the rating plate data in check list CL-E22 and compare the
current transformer data with the data contained in the circuit
documentation.
Testing of the current transformers: Apply a voltage of approx. 10 V
AC to the secondary winding of the current transformer with the
burden removed (at the input terminals of the first cabinet) and with
‘no short-circuit on the primary side. Depending on the type of current
transformer a current of between 10 and 50 mA should flow thus,
verifying the function of the current transformer. The test is to be
carried out individually for each core and phase. Where additional
tests have been specified in the contract for current transformers
which were not tested at the manufacturer's works, special testing
equipment is required.
- The burden in each core of each phase is determined by injection of a
current of 1 A (or 5 A as appropriate) in the direction of the load and.
measurement of the voltage with respect to earth. The voltage across
the burden must decrease on moving from burden to burden along
the current path.
- The measured burden should be compared with the rated data of the
current transformer. The residual current of the current transformer
can be neglected, i.e. there is no need to open the current transformer
terminals.
5.3 Testing of the voltage transformers
- Enter the rating plate data in check list CL-E21 and compare the
voltage transformer data with the data contained in the circuit
documentation.
~ Disconnect the primary-side connections at a suitable location and
apply a voltage of approx. 400 V AC to the primary side.
- Measure the primary and the secondary voltage at all connection
‘Scopyight@slemens AG 2012 / Eneray Sector~ Power Academy prict-2