FÉVRIER 2019 JUIN 2019 AOÛT 2019 SEPTEMBRE 2019 TOTAL FÉVRIER-SEPTEMBRE 2019

RUBRIQUE %TRAVAUX %TRAVAUX %TRAVAUX %TRAVAUX %TRAVAUX


Terrassements 78% 80% 85% 86% 8,10%
VRD Humide 37% 43% 44% 45% 7,94%
VRD Sec 33% 37% 38% 38% 5,12%
Bâtiment G-O 74% 75% 75% 75% 0,50%
Equipements 24% 32% 42% 43% 19,38%
CES 21,06% 21,69% 21,94% 21,94% 0,88%
Charpente 0% 6% 6% 6% 6,13%
TOTAL 73% 76% 77% 79% 6%

CMC 52,35% 53,99% 54,03% 54,03% 1,68%


ROTAHEM 63,94% 67,07% 70,90% 71,80% 7,86%
EQUIPEMENTS 24% 32% 42% 43% 19%