PERHITUNGAN LUAS PETAK

Diketahui :
a. 1 Hektar (Ha) = 100,000,000 Cm2 c.
b. Skala 1 : 6,000
e.

Panjang Lebar Luas


Tipe Pada
Pada Gambar Sebenarnya Pada Gambar Sebenarn
Gambar
(Cm) (Cm) (Cm) ya (Cm)
(Cm2)
K. I A1 6.22 37,320 6.22 37,320 38.69
A2 6.22 37,320 6.22 37,320 38.69
A3 6.22 37,320 6.22 37,320 38.69
A4 6.22 37,320 6.22 37,320 38.69
A5 6.22 37,320 6.22 37,320 38.69
A6 6.22 37,320 6.22 37,320 38.69
A7 6.22 37,320 6.22 37,320 38.69
Luas Tersier a 270.82
K. I B1 6.23 37,380 6.23 37,380 38.81
B2 6.23 37,380 6.23 37,380 38.81
B3 6.23 37,380 6.23 37,380 38.81
B4 6.23 37,380 6.23 37,380 38.81
B5 6.23 37,380 6.23 37,380 38.81
B6 6.23 37,380 6.23 37,380 38.81
B7 6.23 37,380 6.23 37,380 38.81
Luas Tersier b 271.69
K. I C1 6.23 37,380 6.23 37,380 38.81
C2 6.23 37,380 6.23 37,380 38.81
C3 6.23 37,380 6.23 37,380 38.81
C4 6.23 37,380 6.23 37,380 38.81
C5 6.23 37,380 6.23 37,380 38.81
C6 6.23 37,380 6.23 37,380 38.81
C7 6.23 37,380 6.23 37,380 38.81
Luas Tersier c 271.69
K. I D1 6.23 37,380 6.23 37,380 38.81
D2 6.23 37,380 6.23 37,380 38.81
D3 6.23 37,380 6.23 37,380 38.81
D4 6.23 37,380 6.23 37,380 38.81
D5 6.23 37,380 6.23 37,380 38.81
D6 6.23 37,380 6.23 37,380 38.81
D7 6.23 37,380 6.23 37,380 38.81
Luas Tersier d 271.69
K. I E1 6.23 37,380 6.23 37,380 38.81
E2 6.23 37,380 6.23 37,380 38.81
E3 6.23 37,380 6.23 37,380 38.81
E4 6.23 37,380 6.23 37,380 38.81
E5 6.23 37,380 6.23 37,380 38.81
E6 6.23 37,380 6.23 37,380 38.81
E7 6.23 37,380 6.23 37,380 38.81
Luas Tersier e 271.69
K. I F1 6.23 37,380 6.23 37,380 38.81
F2 6.23 37,380 6.23 37,380 38.81
F3 6.23 37,380 6.23 37,380 38.81
F4 6.23 37,380 6.23 37,380 38.81
F5 6.23 37,380 6.23 37,380 38.81
F6 6.23 37,380 6.23 37,380 38.81
F7 6.23 37,380 6.23 37,380 38.81
Luas Tersier f 271.69
K. I G1 6.23 37,380 6.23 37,380 38.81
G2 6.23 37,380 6.23 37,380 38.81
G3 6.23 37,380 6.23 37,380 38.81
G4 6.23 37,380 6.23 37,380 38.81
G5 6.23 37,380 6.23 37,380 38.81
G6 6.23 37,380 6.23 37,380 38.81
G7 6.23 37,380 6.23 37,380 38.81
Luas Tersier g 271.69
K. I H1 6.23 37,380 6.23 37,380 38.81
H2 6.23 37,380 6.23 37,380 38.81
H3 6.23 37,380 6.23 37,380 38.81
H4 6.23 37,380 6.23 37,380 38.81
H5 6.23 37,380 6.23 37,380 38.81
H6 6.23 37,380 6.23 37,380 38.81
H7 6.23 37,380 6.23 37,380 38.81
Luas Tersier h 271.69
K. I I1 6.23 37,380 6.23 37,380 38.81
I2 6.23 37,380 6.23 37,380 38.81
I3 6.23 37,380 6.23 37,380 38.81
I4 6.23 37,380 6.23 37,380 38.81
I5 6.23 37,380 6.23 37,380 38.81
I6 6.23 37,380 6.23 37,380 38.81
I7 6.23 37,380 6.23 37,380 38.81
Luas Tersier i 271.69
TOTAL LUAS 2,444.3
ETAK

NFR = 100,000,000
NFR = 100,000,000
NFR = 100,000,000

Luas 0.86

Sebenarnya Dalam Hektar Q


(Cm2) (Ha)

1,392,782,400 13.93 0.001 0.8 NFR


1,392,782,400 13.93 0.001
1,392,782,400 13.93 0.001
1,392,782,400 13.93 0.001
1,392,782,400 13.93 0.001
1,392,782,400 13.93 0.001 Maka,
1,392,782,400 13.93 0.001
97.49 0.014
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
1,397,264,400 13.97 0.002
97.81 0.011
880 0.098
880
A = Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90
C = 1

e
0.86 . 880
=
0.720

= 1051.111 Lt/dt
= 1.05111 M³/dt
= 0.720

. 1
Menentukan Luas Lahan yang Dilayani oleh Saluran

1. SALURAN PRIMER
Bendung - BB0 = R0 : L = 840.00 m
A = Ta +
= 97.49 +
= 880 Ha

2. SALURAN SEKUNDER
BB0 - BB1 = R1 : L = 372.00 m
A = Tb +
= 97.81 +
= 782.47 Ha

BB1 - BB2 = R2 : L = 372.00 m


A = Tc +
= 97.81 +
= 684.66 Ha

BB2 - BB3 = R3 : L = 372.00 m


A = Td +
= 97.81 +
= 586.85 Ha

BB3 - BB4 = R4 : L = 372.00


A = Te +
= 97.81
= 489.04 Ha

BB4 - BB5 = R5 : L = 372.00


A = Tf +
= 97.81
= 391.23 Ha

BB5- BB6 = R6 : L = 372.00


A = Tg +
= 97.81
= 293.43

BB6- BB7 = R7 : L = 372.00


A = Th +
= 97.81
195.62 Ha

BB7- BB8 = R8 : L = 372.00


A = Ti
= 97.81 Ha
3. SALURAN TERSIER
3.1 Saluran Tersier a
BKa1 - BKa2- BKa3- BKa4- BKa5-BKa6-BKa7 = RTa1 : L = 372.00 m
A = K.I A1 +
= 13.93 +
= 97.49 Ha

BKa2- BKa3- BKa4- BKa5- BKa6- BKa7 = RTa2 : L = 372.00 m


A = K.I A2 +
= 13.93 +
= 83.57 Ha

BKa3 - BKa4- BKa5- BKa6- BKa7 = RTa3 : L = 372.00 m


A = K.I A3 +
= 13.93 +
= 69.64 Ha

BKa4 - BKa5- BKa6- BKa7 = RTa4 : L = 372.00 m


A = K.I A4 +
= 13.93 +
= 55.71 Ha

BKa5- BKa6- BKa7 = RTa5 : L = 372.00 m


A = K.I A5 +
= 13.93
= 41.78 Ha

BKa6- BKa7 = RTa6 L = 372.00 m


A = K.I A6 +
= 13.93
= 27.86 Ha

BKa7 = RTa7 L = 372.00 m


A = K.I A7
= 13.93 Ha

3.2 Saluran Tersier b


BKb1 - BKb2 - BKb3- BKba4 - BKb5- BKb6- BKb7 = RTb1 : L = 372.00 m
A = K.I B1 +
= 13.97 +
= 97.81 Ha

BKb2 - BKb3- BKba4 - BKb5- BKb6- BKb7 = RTb2 : L = 372.0 m


A = K.I B2 +
= 13.97 +
= 83.84 Ha

BKb3- BKba4 - BKb5- BKb6- BKb7 = RTb3 : L = 372.00 m


A = K.I B3 +
= 13.97 +
= 69.86 Ha

BKb4 - BKb5- BKb6- BKb7 = RTb4 : L = 372.00 m


A = K.I B4 +
= 13.97 +
= 55.89 Ha

BKb5- BKb6- BKb7 = RTb5 : L = 372.00 m


A = K.I B5 +
= 13.97
= 41.92 Ha

BKb6- BKb7 = RTb6 : L = 372.00 m


A = K.I B5 +
= 13.97
= 27.95 Ha

BKb7 = RTb7 : L = 372.00 m


A = K.I B7
= 13.97
= 13.97 Ha
3.3 Saluran Tersier c
BKc1 - BKc2- BKc3 BKc4 - BKc5- BKc6- BKc7 = RTc1 : L = 372.00 m
A = K.I C1 +
= 13.97 +
= 97.81 Ha

BKc2- BKc3 BKc4 - BKc5- BKc6- BKc7 = RTc2 : L = 372.00 m


A = K.I C2 +
= 13.97 +
= 83.84 Ha

BKc3 - BKc4 - BKc5- BKc6- BKc7 = RTc3 : L = 372.00 m


A = K.I C3 +
= 13.97 +
= 69.86 Ha

BKc4 - BKc5-BKc6- BKc7 = RTc4 : L = 372.00 m


A = K.I C4 +
= 13.97 +
= 55.89 Ha

BKc5- BKc6- BKc7 = RTc5 L = 372.00 m


A = K.I C5 +
= 13.97
= 41.92 Ha

BKc6- BKc7 = RTc6 L = 372.00 m


A = KI. C6 +
= 13.97
= 27.95 Ha
BKc7 = RTc7 L = 372.00 m
A = KI. C7
= 13.97
= 13.97 Ha

3.4 Saluran Tersier d


BKd1 - BKd2 - BKd3 - BKda4 - BKd5- BKd6- BKd7 = RTd1 : L = 372.00 m
A = K.I D1 +
= 13.97 +
= 97.81 Ha

BKd2 - BKd3 - BKda4 - BKd5- BKd6- BKd7 = RTd2 : L = 372.00 m


A = K.I D2 +
= 13.97 +
= 83.84 Ha

BKd3 - BKda4 - BKd5- BKd6- BKd7 = RTd3 : L = 372.00 m


A = K.I D3 +
= 13.97 +
= 69.86 Ha

BKd4 - BKd5- BKd6- BKd7 = RTd4 : L = 372.00 m


A = K.I D4 +
= 13.97 +
= 55.89 Ha

BKd5- BKd6- BKd7 = RTd5 : L = 372.00 m


A = K.I D5 +
= 13.97
= 41.92 Ha

BKd6- BKd7 = RTd6 : L = 372.00 m


A = K.I D6 +
= 13.97
= 27.95 Ha

BKd7 = RTd7 : L = 372.00 m


A = K.I D7
= 13.97
= 13.97 Ha

3.5 Saluran Tersier e


BKe1 - BKe2 - BKe3 - BKe4 - BKe5- BKe6- BKe7 = RTe1 : L = 372.00 m
A = K.I E1 +
= 13.97 +
= 97.81 Ha

BKe2 - BKe3 - BKe4 - BKe5- BKe6- BKe7 = RTe2 : L = 372.00 m


A = K.I E2 +
= 13.97 +
= 83.84 Ha
BKe3 - BKe4 - BKe5- BKe6- BKe7 = RTe3 : L = 372.00 m
A = K.I D3 +
= 13.97 +
= 69.86 Ha

BKe4 - BKe5- BKe6- BKe7 = RTe4 : L = 372.00 m


A = K.I D4 +
= 13.97 +
= 55.89 Ha

BKe5- BKe6- BKe7 = RTe5 : L = 372.00 m


A = K.I D5 +
= 13.97
= 41.92 Ha

BKe6- BKe7 = RTe6 : L = 372.00 m


A = K.I E6 +
= 13.97
= 27.95 Ha

BKe7 = RTe7 : L = 372.00 m


A = K.I E7
= 13.97
= 13.97 Ha

3.6 Saluran Tersier f


BKf1 - BKf2 - BKf3 - BKf4 - BKf5- BKf6- BKf7 = RTf1 : L = 372.00 m
A = K.I F1 +
= 13.97 +
= 97.81 Ha

BKf2 - BKf3 - BKf4 - BKf5- BKf6- BKf7 = RTf2 : L = 372.00 m


A = K.I F2 +
= 13.97 +
= 83.84 Ha

BKf3 - BKf4 - BKf5- BKf6- BKf7 = RTf3 : L = 372.00 m


A = K.I D3 +
= 13.97 +
= 69.86 Ha

BKf4 - BKf5- BKf6- BKf7 = RTf4 : L = 372.00 m


A = K.I D4 +
= 13.97 +
= 55.89 Ha

BKf5- BKf6- BKf7 = RTf5 : L = 372.00 m


A = K.I D5 +
= 13.97
= 41.92 Ha
BKf6- BKf7 = RTf6 : L = 372.00 m
A = K.I F6 +
= 13.97
= 27.95 Ha

BKf7 = RTf7 : L = 372.00 m


A = K.I F7
= 13.97
= 13.97 Ha

3.7 Saluran Tersier g


BKg1 - BKg2 - BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg1 : L = 372.00 m
A = K.I G1 +
= 13.97 +
= 97.81 Ha

BKg2 - BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg2 : L = 372.00 m


A = K.I G2 +
= 13.97 +
= 83.84 Ha

BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg3 : L = 372.00 m


A = K.I D3 +
= 13.97 +
= 69.86 Ha

BKg4 - BKg5- BKg6- BKg7 = RTg4 : L = 372.00 m


A = K.I D4 +
= 13.97 +
= 55.89 Ha

BKg5- BKg6- BKg7 = RTg5 : L = 372.00 m


A = K.I D5 +
= 13.97
= 41.92 Ha

BKg6- BKg7 = RTg6 : L = 372.00 m


A = K.I G6 +
= 13.97
= 27.95 Ha

BKg7 = RTg7 : L = 372.00 m


A = K.I G7
= 13.97
= 13.97 Ha

3.7 Saluran Tersier h


BKg1 - BKg2 - BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg1 : L = 372.00 m
A = K.I H1 +
= 13.97 +
= 97.81 Ha

BKg2 - BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg2 : L = 372.00 m


A = K.I H2 +
= 13.97 +
= 83.84 Ha

BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg3 : L = 372.00 m


A = K.I H3 +
= 13.97 +
= 69.86 Ha

BKg4 - BKg5- BKg6- BKg7 = RTg4 : L = 372.00 m


A = K.I H4 +
= 13.97 +
= 55.89 Ha

BKg5- BKg6- BKg7 = RTg5 : L = 372.00 m


A = K.I D5 +
= 13.97
= 41.92 Ha

BKg6- BKg7 = RTg6 : L = 372.00 m


A = K.I H6 +
= 13.97
= 27.95 Ha

BKg7 = RTg7 : L = 372.00 m


A = K.I H7
= 13.97
= 13.97 Ha

3.7 Saluran Tersier i


BKg1 - BKg2 - BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg1 : L = 372.00 m
A = K.I I1 +
= 13.97 +
= 97.81 Ha

BKg2 - BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg2 : L = 372.00 m


A = K.I I2 +
= 13.97 +
= 83.84 Ha

BKg3 - BKg4 - BKg5- BKg6- BKg7 = RTg3 : L = 372.00 m


A = K.I I3 +
= 13.97 +
= 69.86 Ha

BKg4 - BKg5- BKg6- BKg7 = RTg4 : L = 372.00 m


A = K.I I4 +
= 13.97 +
= 55.89 Ha

BKg5- BKg6- BKg7 = RTg5 : L = 372.00 m


A = K.I D5 +
= 13.97
= 41.92 Ha

BKg6- BKg7 = RTg6 : L = 372.00 m


A = K.I I6 +
= 13.97
= 27.95 Ha

BKg7 = RTg7 : L = 372.00 m


A = K.I I7
= 13.97
= 13.97 Ha
eh Saluran

Tb + Tc + Td + Te + Tf + Tg + Th + Ti
97.49 + 97.81 + 97.81 97.81 97.81 97.81 97.81 97.81
Ha

Tc + Td + Te + Tf + Tg + Th + Ti
97.81 + 97.81 + 97.81 97.81 97.81 97.81 97.81
Ha

Td + Te + Tf + Tg + Th + Ti
97.81 97.81 97.81 97.81 97.81 97.81
Ha

Te + Tf + Tg + Th + Ti
97.81 97.81 97.81 97.81 97.81
Ha

Tf + Tg + Th + Ti
97.81 97.81 97.81 97.81
Ha

Tg + Th + Ti
97.81 97.81 97.81
Ha

Th + Ti
97.81 97.81

Ti
97.81
Ha

Ha
K.I A2 + K.I A3 + K.I A4 + K.I A5 + K.I A6 + K.I A7
13.93 + 13.93 + 13.93 + 13.93 13.93 13.93
Ha

K.I A3 + K.I A4 + K.I A5 + K.I A6 + K.I A7


13.93 + 13.93 + 13.93 13.93 13.93
Ha

K.I A4 + K.I A5 + K.I A6 + K.I A7


13.93 + 13.93 13.93 13.93
Ha

K.I A5 + K.I A6 + K.I A7


13.93 13.93 13.93
Ha

K.I A6 + K.I A7
13.93 13.93
Ha

K.I A7
13.93
Ha

Ha

K.I B2 + K.I B3 + K.I B4 + K.I B5 + K.I B6 + K.I B7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I B3 + K.I B4 + K.I B5 + K.I B6 + K.I B7


13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I B4 + K.I B5 + K.I B6 + K.I B7


13.97 + 13.97 13.97 13.97
Ha

K.I B5 + K.I B6 + K.I B7


13.97 13.97 13.97
Ha

K.I B6 + K.I B7
13.97 13.97
Ha

K.I B7
13.97
Ha

Ha

K.I C2 + K.I C3 + K.I C4 + K.I C5 + KI. C6 + KI. C7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I C3 + K.I C4 + K.I C5 + KI. C6 + KI. C7


13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I C4 + K.I C5 + KI. C6 + KI. C7


13.97 + 13.97 13.97 13.97
Ha

K.I C5 + KI. C6 + KI. C7


13.97 13.97 13.97
Ha

KI. C6 + KI. C7
13.97 13.97
Ha

KI. C7
13.97
Ha
Ha

K.I D2 + K.I D3 + K.I D4 + K.I D5 + K.I D6 + K.I D7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I D3 + K.I D4 + K.I D5 + K.I D6 + K.I D7


13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I D4 + K.I D5 + K.I D6 + K.I D7


13.97 + 13.97 13.97 13.97
Ha

K.I D5 + K.I D6 + K.I D7


13.97 13.97 13.97
Ha

K.I D6 + K.I D7
13.97 13.97
Ha

K.I D7
13.97
Ha

Ha

K.I E2 + K.I E3 + K.I E4 + K.I E5 + K.I E6 + K.I E7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I E3 + K.I E4 + K.I E5 + K.I E6 + K.I E7


13.97 + 13.97 + 13.97 13.97 13.97
Ha
K.I D4 + K.I D5 + K.I E6 + K.I E7
13.97 + 13.97 13.97 13.97
Ha

K.I D5 + K.I E6 + K.I E7


13.97 13.97 13.97
Ha

K.I E6 + K.I E7
13.97 13.97
Ha

K.I E7
13.97
Ha

Ha

K.I F2 + K.I F3 + K.I F4 + K.I F5 + K.I F6 + K.I F7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I F3 + K.I F4 + K.I F5 + K.I F6 + K.I F7


13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I D4 + K.I D5 + K.I F6 + K.I F7


13.97 + 13.97 13.97 13.97
Ha

K.I D5 + K.I F6 + K.I F7


13.97 13.97 13.97
Ha

K.I F6 + K.I F7
13.97 13.97
Ha
K.I F7
13.97
Ha

Ha

K.I G2 + K.I G3 + K.I G4 + K.I G5 + K.I G6 + K.I G7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I G3 + K.I G4 + K.I G5 + K.I G6 + K.I G7


13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I D4 + K.I D5 + K.I G6 + K.I G7


13.97 + 13.97 13.97 13.97
Ha

K.I D5 + K.I G6 + K.I G7


13.97 13.97 13.97
Ha

K.I G6 + K.I G7
13.97 13.97
Ha

K.I G7
13.97
Ha

Ha

K.I H2 + K.I H3 + K.I H4 + K.I H5 + K.I H6 + K.I H7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I H3 + K.I H4 + K.I H5 + K.I H6 + K.I H7


13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I H4 + K.I H5 + K.I H6 + K.I H7


13.97 + 13.97 13.97 13.97
Ha

K.I H5 + K.I H6 + K.I H7


13.97 13.97 13.97
Ha

K.I H6 + K.I H7
13.97 13.97
Ha

K.I H7
13.97
Ha

Ha

K.I I2 + K.I I3 + K.I I4 + K.I I5 + K.I I6 + K.I I7


13.97 + 13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I I3 + K.I I4 + K.I I5 + K.I I6 + K.I I7


13.97 + 13.97 + 13.97 13.97 13.97
Ha

K.I I5 + K.I I6 + K.I I6 + K.I I7


13.97 + 13.97 13.97 13.97
Ha

K.I I5 + K.I I6 + K.I I7


13.97 13.97 13.97
Ha

K.I I6 + K.I I7
13.97 13.97
Ha

K.I I7
13.97
Ha

Ha
REKAPITULASI PERENCANAAN JARINGAN SALURAN IRIGASI

NAMA RUAS PANJANG D. RENCANA DIMENSI SALURAN


SALURAN SALURAN SALURAN (m) M³/dt A V b h K I m W

INDUK B-BBO = R0 840.00 1.17 879.96 0.43 2.12 0.81 35.00 0.00035 1.00 0.50

BBO-BB1 = R1 372.00 0.93 782.47 0.41 2.20 0.76 35.00 0.00034 1.00 0.49

BB1-BB2 = R2 372.00 0.82 684.66 0.40 2.03 0.73 35.00 0.00034 1.00 0.48

BB2-BB3 = R3 372.00 0.70 586.85 0.39 1.84 0.70 35.00 0.00035 1.00 0.48
SEKUNDER

BB3-BB4 = R4 372.00 0.58 489.04 0.38 1.64 0.67 35.00 0.00036 1.00 0.47

BB4-BB5 = R5 372.00 0.47 391.23 0.37 1.42 0.63 35.00 0.00037 1.00 0.46

BB5-BB6 = R6 372.00 0.35 293.43 0.35 1.18 0.58 35.00 0.00038 1.00 0.44

BB6-BB7 = R7 372.00 0.23 195.62 0.32 0.90 0.51 35.00 0.00041 1.00 0.43
BB7-BB8 = R8 372.00 0.12 97.81 0.28 0.56 0.42 35.00 0.00045 1.00 0.41
Saluran Tersier b
BKa1 - BKa2 = RTa1 372.00 0.10 97.49 0.28 0.51 0.41 35.00 0.00046 1.00 0.40
BKa2 - BKa3 = RTa2 372.00 0.09 83.57 0.27 0.46 0.39 35.00 0.00047 1.00 0.40
BKa3 - BKa4 = RTa3 372.00 0.07 69.64 0.26 0.40 0.37 35.00 0.00049 1.00 0.39
BKa4 - BKa5 = RTa4 372.00 0.06 55.71 0.25 0.34 0.35 35.00 0.00051 1.00 0.39
TERSIER

BKa5 - BKa6 = RTa5 372.00 0.04 41.78 0.24 0.27 0.32 35.00 0.00053 1.00 0.38
TERSIER
BKa6 - BKa7 = RTa6 372.00 0.03 27.86 0.22 0.19 0.29 35.00 0.00058 1.00 0.37
Saluran Tersier b
BKb1 - BKb2 = RTb1 372.00 0.11 97.81 0.28 0.52 0.41 35.00 0.00046 1.00 0.40
BKb2 - BKb3 = RTb2 372.00 0.09 83.84 0.27 0.46 0.39 35.00 0.00047 1.00 0.40
BKb3 - BKb4 = RTb3 372.00 0.08 69.86 0.26 0.40 0.37 35.00 0.00049 1.00 0.39
BKb4 - BKb5 = RTb4 372.00 0.06 55.89 0.25 0.34 0.35 35.00 0.00051 1.00 0.39
BKb5 - BKb6 = RTb5 372.00 0.05 41.92 0.24 0.27 0.32 35.00 0.00053 1.00 0.38
BKb6 - BKb7 = RTb6 372.00 0.03 27.95 0.22 0.19 0.29 35.00 0.00058 1.00 0.37
PERHITUNGAN PETAK-PETAK TERSIER

1 TERSIER A 2 TERSIER B
K.I A1 = 13.93 Ha K.I B1 = 13.97
K.I A2 = 13.93 Ha K.I B2 = 13.97
K.I A3 = 13.93 Ha K.I B3 = 13.97
K.I A4 = 13.93 Ha K.I B4 = 13.97
K.I A5 = 13.93 Ha K.I B5 = 13.97
K.I A6 = 13.93 Ha K.I B6 = 13.97
K.I A7 = 13.93 Ha + K.I B7 = 13.97
K.I A = 97.49 Ha K.I B = 97.81

3 TERSIER C 4 TERSIER D
K.I C1 = 13.97 Ha K.I D1 = 13.97
K.I C2 = 13.97 Ha K.I D2 = 13.97
K.I C3 = 13.97 Ha K.I D3 = 13.97
K.I C4 = 13.97 Ha K.I D4 = 13.97
K.I C5 = 13.97 Ha K.I D5 = 13.97
K.I C6 = 13.97 Ha K.I D6 = 13.97
K.I C7 = 13.97 Ha + K.I D7 = 13.97
K. C = 97.81 Ha K.I D = 97.81

5 TERSIER E 6 TERSIER F
K.I E1 = 13.97 Ha K.I F1 = 13.97
K.I E2 = 13.97 Ha K.I F2 = 13.97
K.I E3 = 13.97 Ha K.I F3 = 13.97
K.I E4 = 13.97 Ha K.I F4 = 13.97
K.I E5 = 13.97 Ha K.I F5 = 13.97
K.I E6 = 13.97 Ha K.I F6 = 13.97
K.I E7 = 13.97 Ha + K.I F7 = 13.97
K.I E = 97.81 Ha K.I F = 97.81

7 TERSIER G TERSIER H
K.I G1 = 13.97 Ha K.I H1 = 13.97
K.I G2 = 13.97 Ha K.I H2 = 13.97
K.I G3 = 13.97 Ha K.I H3 = 13.97
K.I G4 = 13.97 Ha K.I H4 = 13.97
K.I G5 = 13.97 Ha K.I H5 = 13.97
K.I G6 = 13.97 Ha K.I H6 = 13.97
K.I G7 = 13.97 Ha + K.I H7 = 13.97
K.I G = 97.81 Ha K.I H = 97.81

TERSIER A = 97.49 Ha
TERSIER B = 97.81 Ha
TERSIER C = 97.81 Ha
TERSIER D = 97.81 Ha
TERSIER E = 97.81 Ha
TERSIER F = 97.81 Ha
TERSIER G = 97.81 Ha
TERSIER H = 97.81 Ha
TERSIER I = 97.81 Ha +
A Total = 880 Ha

PERHITUNGAN DIMENSI SALURAN PRIMER

1. Saluran Induk / Primer


1.1. Saluran Primer Bendung - BB0 = R0 :
Diketahui :
A = 880 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 . 0.90 = 0.648 (Saluran Primer)
C = 1 (Buku KP.03 Poin 2.2.4)
Maka,
Q = NFR . A . C
e
= 0.86 . 879.96 . 1
0.648

= 1167.852 Lt/dt
= 1.168 M³/dt
Dari Tabel Diperoleh Nilai :
m = 1.50 (Buku KP.03 Poin 3.3.5)
n = 1.30 (Buku KP.03 Lampiran 2)
K = 35.00 (Buku KP.03 Poin 3.2.2)

V = 0.42 . Q 0.182
= 0.42 . 1.168 0.182
= 0.432 m/dt

h = 0.775 . Q 0.282
= 0.775 . 1.168 0.282
= 0.810 m

n = 3.96 . Q 0.25 - m
= 3.96 . 1.168 0.25 - 1.50
= 2.617
b = n . h
= 2.617 . 0.810
= 2.119
= 2.12 m = 2.12 m

Kontrol h akibat pembulatan b = 2.12 m


F = Q
V
= 1.168
0.432
= 2.703 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
2.703 = 2.12 h + 1.50 h2
1.50 h2 + 2.12 h - 2.70 = 0

h.1.2 = -b± √ b2 - 4 . a. c
2.a
= -2.12 ± √ 4.49 -4 . 1.50 . -2.70
2 . 1.50
= -2.12 ± √ 4.49 + 16.22
3
= -2.12 ± √ 20.71
3
= -2.12 ± 4.55
3
h.1 = -2.12 + 4.55 h.2 = -2.12 - 4.55
3 3
h.1 = 0.811 m ( memenuhi ) h.2 = -2.223 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 2.12 + 2 . 0.811 √ 1.50 ² + 1
= 2.12 + 1.621 . 1.803
= 5.041 m
Jari-Jari Hidrolis ( R )
R = F
P
= 2.703
5.041
= 0.536 M
R²/³ = 0.660 M
Kemiringan Saluran ( I )
I =
{ V
K . R²/³
²
}
= { 0.432 ²
35.00 . 0.660 }
= 0.00035
Tinggi Jagaan (W)
W = 0.25 . h + 0.30
= 0.25 . 0.81 + 0.30
= 0.503 M
Kesimpulan
▪ Luas Areal Sawah (A) = 880 Ha
▪ Debit Rencana (Q) = 1.168 M³/dt
▪ Tinggi Air Saluran (h) = 0.811 M
▪ Lebar Dasar Saluran (b) = 2.119 M
▪ Keliling Basah (P) = 5.041 M
▪ Jari-Jari Hidrolis (R) = 0.536 M
▪ Kemiringan Saluran (I) = 0.00035 M
▪ Tinggi Jagaan (W) = 0.503 M
Sketsa

w = 0.503

h = 0.811

b= 2.12 M
PERHITUNGAN DIMENSI SALURAN SEKUNDER
1.2. Saluran Sekunder BB0- BB1 = R1 :
Diketahui :
A = 782.47 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.720 (Saluran Sekunder)
C = 1 (Buku KP.03 Poin 2.2.4)
Maka,
Q = NFR . A . C
e
= 0.86 . 782.5 . 1
0.720
= 934.615 Lt/dt
= 0.935 M³/dt
Dari Tabel Diperoleh Nilai :
n = 1.2 (Buku KP.03 Poin 3.3.5)
m = 1.00 (Buku KP.03 Lampiran 2)
K = 35.00 (Buku KP.03 Poin 3.2.2)

V = 0.42 . Q 0.182
= 0.42 . 0.935 0.182
= 0.415 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.935 0.282
= 0.760 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.935 0.25 - 1.00
= 2.894

b = n . h
= 2.894 . 0.760
= 2.200
= 2.20 m

Kontrol h akibat pembulatan b = 2.20 m

F = Q
V
= 0.935
0.415
= 2.253 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
2.253 = 2.20 h + 1.00 h2
1.00 h2 + 2.20 h - 2.25 = 0

h.1.2 = -b± √ b2 - 4 . a. c
2.a
= -2.20 ± √ 4.84 -4 . 1.00 . -2.25
2 . 1.00
= -2.20 ± √ 4.84 + 9.01
2
= -2.20 ± √ 13.85
2
= -2.20 ± 3.72
2

= -2.20 + 3.72 = -2.20 - 3.72


2 2
h.1 = 0.761 m ( memenuhi ) h.2 = -2.961 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 2.20 + 2 . 0.761 √ 1.00 ² + 1
= 2.200 + 1.522 . 1.414
= 4.352 M

Jari-Jari Hidrolis ( R )
R = F
P
= 2.253
4.352
= 0.518 m
R²/³ = 0.645 m
Kemiringan Saluran ( I )
I =
{ V
K . R²/³ } ²

=
{ 35.00
0.415
. 0.645 } ²

= 0.00034

Tinggi Jagaan (W)


W = 0.250 . h + 0.30
= 0.250 . 0.761 + 0.30
= 0.490 m
Kesimpulan
▪ Luas Areal Sawah (A) = 782.47 Ha
▪ Debit Rencana (Q) = 0.935 M³/dt
▪ Tinggi Air Saluran (h) = 0.761 m
▪ Lebar Dasar Saluran (b) = 2.200 m
▪ Keliling Basah (P) = 4.352 m
▪ Jari-Jari Hidrolis (R) = 0.518 m
▪ Kemiringan Saluran (I) = 0.00034 m
▪ Tinggi Jagaan (W) = 0.490 m
Sketsa

w =

h =
b = 2.200 M
1.3. Saluran Sekunder BB2- BB3 = R2 :

Diketahui :
A = 684.66 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.720 (Saluran Sekunder)
C = 1
Maka,
Q = NFR . A . C
e
= 0.86 . 684.66 . 1
0.720

= 817.788 Lt/dt
= 0.818 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.818 0.182
= 0.405 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.818 0.282
= 0.732 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.818 0.25 - 1.00
= 2.766

b = n . h
= 2.766 . 0.732
= 2.025
= 2.03 m

Kontrol h akibat pembulatan b = 2.03 m

F = Q
V
= 0.818
0.405
= 2.020 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
2.020 = 2.03 h + 1.00 h2
1.00 h2 + 2.03 h - 2.02 = 0
h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -2.03 ± √ 4.10 -4 . 1.00 . -2.02
2 . 1.00
= -2.03 ± √ 4.10 + 8.08
2
= -2.03 ± √ 12.18
2
= -2.03 ± 3.49
2
= -2.03 + 3.49 = -2.03 - 3.49
2 2
h.1 = 0.732 m ( memenuhi ) h.2 = -2.7577 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 2.03 + 2 . 0.732 √ 1.00 ² + 1
= 2.03 + 1.465 . 1.414
= 4.097 m

Jari-Jari Hidrolis ( R )
R = F
P
= 2.020
4.097
= 0.493 M
R²/³ = 0.624 M
Kemiringan Saluran ( I )
I =
{ V
K . R²/³
²
}
=
{ 35.00
0.405
. 0.624 }²
= 0.00034

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.732 + 0.30
= 0.483 M
Kesimpulan
▪ Luas Areal Sawah (A) = 684.660 Ha
▪ Debit Rencana (Q) = 0.818 M³/dt
▪ Tinggi Air Saluran (h) = 0.732 M
▪ Lebar Dasar Saluran (b) = 2.025 M
▪ Keliling Basah (P) = 4.097 M
▪ Jari-Jari Hidrolis (R) = 0.493 M
▪ Kemiringan Saluran (I) = 0.00034 M
▪ Tinggi Jagaan (W) = 0.483 M
Sketsa

w =

h =
b = 2.025 M
1.4. Saluran Sekunder BB2- BB3 = R3 :

Diketahui :
A = 586.85 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.72 (Saluran Sekunder)
C = 1
Maka,
Q = NFR . A . C
e
= 0.86 . 586.85 . 1
0.72
= 700.961 Lt/dt
= 0.701 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.701 0.182
= 0.394 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.701 0.282
= 0.701 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.701 0.25 - 1.00
= 2.623

b = n . h
= 2.623 . 0.70
= 1.839
= 1.84 m

Kontrol h akibat pembulatan b = 1.84 m


F = Q
V
= 0.701
0.394
= 1.780 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
1.780 = 1.84 h + 1.00 h2
1.00 h2 + 1.84 h - 1.78 = 0

h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -1.84 ± √ 3.38 -4 . 1.00 . -1.78
2 . 1.00
= -1.84 ± √ 3.38 + 7.12
2
= -1.84 ± √ 10.50
2
= -1.84 ± 3.24
2
= -1.84 + 3.24 = -1.84 - 3.24
2 2
h.1 = 0.701 m ( memenuhi ) h.2 = -2.540 m ( Tidak memenuhi )
Keliling Basah (P)
P = b + 2h √ M² + 1
= 1.84 + 2 . 0.701 √ 1.00 ² + 1
= 1.839 + 1.402 . 1.414
= 3.822 M

Jari-Jari Hidrolis ( R )
R = F
P
= 1.780
3.822
= 0.466 M
R²/³ = 0.601 M
Kemiringan Saluran ( I )
I =
{ V
K . R²/³
²
}
=
{ 35.00
0.394
. 0.601 } ²

= 0.00035

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.701 + 0.30
= 0.475 M
Kesimpulan
▪ Luas Areal Sawah (A) = 586.851 Ha
▪ Debit Rencana (Q) = 0.701 M³/dt
▪ Tinggi Air Saluran (h) = 0.701 M
▪ Lebar Dasar Saluran (b) = 1.839 M
▪ Keliling Basah (P) = 3.822 M
▪ Jari-Jari Hidrolis (R) = 0.466 M
▪ Kemiringan Saluran (I) = 0.00035 M
▪ Tinggi Jagaan (W) = 0.475 M
Sketsa

w =

h =
b = 1.839 M

1.5. Saluran Sekunder BB3- BB4 = R4 :

Diketahui :
A = 489.04 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.72 (Saluran Sekunder)
C = 1
Maka,

Q = NFR . A . C
e
= 0.86 . 489.04 . 1
0.72
= 584.134 Lt/dt
= 0.584 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.584 0.182
= 0.381 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.584 0.282
= 0.666 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.584 0.25 - 1.00
= 2.462

b = n . h
= 2.462 . 0.666
= 1.640
= 1.64 m

Kontrol h akibat pembulatan b = 1.64 m

F = Q
V
= 0.584
0.381
= 1.534 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
1.534 = 1.64 h + 1.00 h2
1.00 h2 + 1.64 h - 1.53 = 0

h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -1.64 ± √ 2.69 -4 . 1.00 . -1.53
2 . 1.00
= -1.64 ± √ 2.69 + 6.14
2
= -1.64 ± √ 8.82
2
= -1.64 ± 2.97
2
= -1.64 + 2.97 = -1.64 - 2.97
2 2
h.1 = 0.665 m ( memenuhi ) h.2 = -2.305 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 1.64 + 2 . 0.665 √ 1.00 ² + 1
= 1.640 + 1.331 . 1.414
= 3.522 M

Jari-Jari Hidrolis ( R )
R = F
P
= 1.534
3.522
= 0.436 M
R²/³ = 0.575 M
Kemiringan Saluran ( I )
I = V ²
{ K . R²/³ }
= 0.381 ²
{ 35.00 . 0.575 }
= 0.00036

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.67 + 0.30
= 0.466 M
Kesimpulan
▪ Luas Areal Sawah (A) = 489.043 Ha
▪ Debit Rencana (Q) = 0.584 M³/dt
▪ Tinggi Air Saluran (h) = 0.665 M
▪ Lebar Dasar Saluran (b) = 1.640 M
▪ Keliling Basah (P) = 3.522 M
▪ Jari-Jari Hidrolis (R) = 0.436 M
▪ Kemiringan Saluran (I) = 0.00036 M
▪ Tinggi Jagaan (W) = 0.466 M
Sketsa
w =

h =

b = 1.640 M

1.6. Saluran Sekunder BB4- BB5 = R5 :

Diketahui :
A = 391.23 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.72 (Saluran Sekunder)
C = 1
Maka,

Q = NFR . A . C
e
= 0.86 . 391.23 . 1
0.72
= 467.307 Lt/dt
= 0.467 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.467 0.182
= 0.366 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.467 0.282
= 0.625 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.467 0.25 - 1.00
= 2.274

b = n . h
= 2.274 . 0.625
= 1.422
= 1.42 m

Kontrol h akibat pembulatan b = 1.42 m

F = Q
V
= 0.467
0.366
= 1.278 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
1.278 = 1.42 h + 1.00 h2
1.00 h2 + 1.42 h - 1.28 = 0

h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -1.42 ± √ 2.02 -4 . 1.00 . -1.28
2 . 1.00
= -1.42 ± √ 2.02 + 5.11
2
= -1.42 ± √ 7.13
2
= -1.42 ± 2.67
2
= -1.42 + 2.67 = -1.42 - 2.67
2 2
h.1 = 0.624 m ( memenuhi ) h.2 = -2.0465 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 1.42 + 2 . 0.624 √ 1.00 ² + 1
= 1.42 + 1.249 . 1.414
= 3.188 M

Jari-Jari Hidrolis ( R )
R = F
P
= 1.278
3.188
= 0.401 M
R²/³ = 0.544 M
Kemiringan Saluran ( I )
I = V ²
{ K . R²/³ }
= 0.366 ²
{ 35.00 . 0.544 }
= 0.00037

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.62 + 0.30
= 0.456 M
Kesimpulan
▪ Luas Areal Sawah (A) = 391.234 Ha
▪ Debit Rencana (Q) = 0.467 M³/dt
▪ Tinggi Air Saluran (h) = 0.624 M
▪ Lebar Dasar Saluran (b) = 1.422 M
▪ Keliling Basah (P) = 3.188 M
▪ Jari-Jari Hidrolis (R) = 0.401 M
▪ Kemiringan Saluran (I) = 0.00037 M
▪ Tinggi Jagaan (W) = 0.456 M
Sketsa

w =

h =

b = 1.422 M

1.7. Saluran Sekunder BB5- BB6 = R6 :

Diketahui :
A = 293.43 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.72 (Saluran Sekunder)
C = 1
Maka,

Q = NFR . A . C
e
= 0.86 . 293.43 . 1
0.72
= 350.480 Lt/dt
= 0.350 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.350 0.182
= 0.347 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.350 0.282
= 0.577 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.350 0.25 - 1.00
= 2.047

b = n . h
= 2.047 . 0.58
= 1.180
= 1.18 m

Kontrol h akibat pembulatan b = 1.18 m

F = Q
V
= 0.350
0.347
= 1.010 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
1.010 = 1.18 h + 1.00 h2
1.00 h2 + 1.18 h - 1.01 = 0

h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -1.18 ± √ 1.39 -4 . 1.00 . -1.01
2 . 1.00
= -1.18 ± √ 1.39 + 4.04
2
= -1.18 ± √ 5.43
2
= -1.18 ± 2.33
2
= -1.18 + 2.33 = -1.18 - 2.33
2 2
h.1 = 0.575 m ( memenuhi ) h.2 = -1.7556 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 1.18 + 2 . 0.575 √ 1.00 ² + 1
= 1.180 + 1.151 . 1.414
= 2.807 M

Jari-Jari Hidrolis ( R )
R = F
P
= 1.010
2.807
= 0.360 M
R²/³ = 0.506 M
Kemiringan Saluran ( I )
I = V ²
{ K . R²/³ }
= 0.347 ²
{ 35.00 . 0.506 }
= 0.00038

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.58 + 0.30
= 0.444 M
Kesimpulan
▪ Luas Areal Sawah (A) = 293.43 Ha
▪ Debit Rencana (Q) = 0.350 M³/dt
▪ Tinggi Air Saluran (h) = 0.575 M
▪ Lebar Dasar Saluran (b) = 1.180 M
▪ Keliling Basah (P) = 2.807 M
▪ Jari-Jari Hidrolis (R) = 0.360 M
▪ Kemiringan Saluran (I) = 0.00038 M
▪ Tinggi Jagaan (W) = 0.444 M
Sketsa

w =

h =
b = 1.180 M
1.8. Saluran Sekunder BB6- BB7 = R7 :
Diketahui :
A = 195.62 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.720 (Saluran Sekunder)
C = 1 (Buku KP.03 Poin 2.2.4)
Maka,
Q = NFR . A . C
e
= 0.86 . 195.62 . 1
0.720
= 233.654 Lt/dt
= 0.234 M³/dt
Dari Tabel Diperoleh Nilai :
n = 1.2 (Buku KP.03 Poin 3.3.5)
m = 1.00 (Buku KP.03 Lampiran 2)
K = 35.00 (Buku KP.03 Poin 3.2.2)

V = 0.42 . Q 0.182
= 0.42 . 0.234 0.182
= 0.322 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.234 0.282
= 0.514 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.234 0.25 - 1.00
= 1.753

b = n . h
= 1.753 . 0.514
= 0.902
= 0.90 m

Kontrol h akibat pembulatan b = 0.90 m

F = Q
V
= 0.234
0.322
= 0.725 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.725 = 0.90 h + 1.00 h2
1.00 h2 + 0.90 h - 0.72 = 0

h.1.2 = -b± √ b2 - 4 . a. c
2.a
= -0.90 ± √ 0.81 -4 . 1.00 . -0.72
2 . 1.00
= -0.90 ± √ 0.81 + 2.90
2
= -0.90 ± √ 3.71
2
= -0.90 ± 1.93
2

= -0.90 + 1.93 = -0.90 - 1.93


2 2
h.1 = 0.513 m ( memenuhi ) h.2 = -1.4142 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 0.90 + 2 . 0.513 √ 1.00 ² + 1
= 0.902 + 1.025 . 1.414
= 2.351 M

Jari-Jari Hidrolis ( R )
R = F
P
= 0.725
2.351
= 0.308 m
R²/³ = 0.456 m
Kemiringan Saluran ( I )
I = V ²
{ K . R²/³ }
= 0.322 ²
{ 35.00 . 0.456 }
= 0.00041

Tinggi Jagaan (W)


W = 0.250 . h + 0.30
= 0.250 . 0.51 + 0.30
= 0.428 m
Kesimpulan
▪ Luas Areal Sawah (A) = 195.617 Ha
▪ Debit Rencana (Q) = 0.234 M³/dt
▪ Tinggi Air Saluran (h) = 0.513 m
▪ Lebar Dasar Saluran (b) = 0.902 m
▪ Keliling Basah (P) = 2.351 m
▪ Jari-Jari Hidrolis (R) = 0.308 m
▪ Kemiringan Saluran (I) = 0.00041 m
▪ Tinggi Jagaan (W) = 0.428 m
Sketsa

w =

h =
b = 0.902 M
1.2. Saluran Sekunder BB7- BB8 = R8 :
Diketahui :
A = 97.81 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 . 0.90 = 0.720 (Saluran Sekunder)
C = 1 (Buku KP.03 Poin 2.2.4)
Maka,
Q = NFR . A . C
e
= 0.86 . 97.81 . 1
0.720
= 116.827 Lt/dt
= 0.117 M³/dt
Dari Tabel Diperoleh Nilai :
n = 1.2 (Buku KP.03 Poin 3.3.5)
m = 1.00 (Buku KP.03 Lampiran 2)
K = 35.00 (Buku KP.03 Poin 3.2.2)

V = 0.42 . Q 0.182
= 0.42 . 0.117 0.182
= 0.284 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.117 0.282
= 0.423 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.117 0.25 - 1.00
= 1.315

b = n . h
= 1.315 . 0.423
= 0.556
= 0.56 m

Kontrol h akibat pembulatan b = 0.56 m

F = Q
V
= 0.117
0.284
= 0.411 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.411 = 0.56 h + 1.00 h2
1.00 h2 + 0.56 h - 0.41 = 0
h.1.2 = -b± √ b2 - 4 . a. c
2.a
= -0.56 ± √ 0.31 -4 . 1.00 . -0.41
2 . 1.00
= -0.56 ± √ 0.31 + 1.64
2
= -0.56 ± √ 1.95
2
= -0.56 ± 1.40
2

= -0.56 + 1.40 = -0.56 - 1.40


2 2
h.1 = 0.421 m ( memenuhi ) h.2 = -0.9771 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 0.56 + 2 . 0.421 √ 1.00 ² + 1
= 0.556 + 0.842 . 1.414
= 1.746 M

Jari-Jari Hidrolis ( R )
R = F
P
= 0.411
1.746
= 0.235 m
R²/³ = 0.381 m
Kemiringan Saluran ( I )
I =
{ V
K . R²/³
²
}
= 0.284 ²
{ 35.00 . 0.381 }
= 0.00045

Tinggi Jagaan (W)


W = 0.250 . h + 0.30
= 0.250 . 0.42 + 0.30
= 0.405 m
Kesimpulan
▪ Luas Areal Sawah (A) = 97.809 Ha
▪ Debit Rencana (Q) = 0.117 M³/dt
▪ Lebar Dasar Saluran (b) = 0.556 m
▪ Tinggi Air Saluran (h) = 0.421 m
▪ Keliling Basah (P) = 1.746 m
▪ Jari-Jari Hidrolis (R) = 0.235 m
▪ Kemiringan Saluran (I) = 0.00045 m
▪ Tinggi Jagaan (W) = 0.405 m
Sketsa

w =
h =

b = 0.556 M
2. Saluran Tersier
2.1 Saluran Tersier a
a BKa1 - BKa2- BKa3- BKa4- BKa5-BKa6-BKa7 = RTa1 :
Diketahui :
A = 97.49 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1
Maka,
Q = NFR . A . C
e
= 0.86 . 97.49 . 1
0.80
= 104.807 Lt/dt
= 0.105 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.105 0.182
= 0.279 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.105 0.282
= 0.410 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.105 0.25 - 1.00
= 1.253

b = n . h
= 1.253 . 0.41
= 0.514
= 0.51 m
Kontrol h akibat pembulatan b = 0.51 m
F = Q
V
= 0.105
0.279
= 0.376 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.376 = 0.51 h + 1.00 h2
1.00 h2 + 0.51 h - 0.38 = 0
= - b ± √ b - 4 . a. c
2
h.1.2
2.a
= -0.51 ± √ 0.26 -4 . 1.00 . -0.38
2 . 1.00

= -0.51 ± √ 0.26 + 1.50


2
= -0.51 ± √ 1.77
2
= -0.51 ± 1.33
2
= -0.51 + 1.33 = -0.51 - 1.33
2 2
h.1 = 0.408 m ( memenuhi ) h.2 = -0.922 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 0.51 + 2 . 0.408 √ 1.00 ² + 1
= 0.514 + 0.816 . 1.414
= 1.668 M

Jari-Jari Hidrolis ( R )
R = F
P
= 0.376
1.668
= 0.226 M
R²/³ = 0.371 M
Kemiringan Saluran ( I )
I =
{ V
K . R²/³
²
}
= 0.279 ²
{ 35.00 . 0.371 }
= 0.00046

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.41 + 0.30
= 0.402 M
Kesimpulan
▪ Luas Areal Sawah (A) = 97.495 Ha
▪ Debit Rencana (Q) = 0.105 M³/dt
▪ Tinggi Air Saluran (h) = 0.408 M
▪ Lebar Dasar Saluran (b) = 0.514 M
▪ Keliling Basah (P) = 1.668 M
▪ Jari-Jari Hidrolis (R) = 0.226 M
▪ Kemiringan Saluran (I) = 0.00046 M
▪ Tinggi Jagaan (W) = 0.402 M
Sketsa

w =

h =
b = 0.514 M
b BKa2- BKa3- BKa4- BKa5- BKa6- BKa7 = RTa2 :

Diketahui :
A = 83.57 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1
Maka,
Q = NFR . A . C
e
= 0.86 . 83.57 . 1
0.80
= 89.834 Lt/dt
= 0.090 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.090 0.182
= 0.271 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.090 0.282
= 0.393 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.090 0.25 - 1.00
= 1.168

b = n . h
= 1.168 . 0.393
= 0.459
= 0.46 m

Kontrol h akibat pembulatan b = 0.46 m


F = Q
V
= 0.090
0.271
= 0.332 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.332 = 0.46 h + 1.00 h2
1.00 h2 + 0.46 h - 0.33 = 0

= - b ± √ b - 4 . a. c
2
h.1.2
2.a
= -0.46 ± √ 0.21 -4 . 1.00 . -0.33
2 . 1.00
= -0.46 ± √ 0.21 + 1.33
2
= -0.46 ± √ 1.54
2
= -0.46 ± 1.24
2
= -0.46 + 1.24 = -0.46 - 1.24
2 2
h.1 = 0.390 m ( memenuhi ) h.2 = -0.849 m (Tidak memenuhi)

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.46 + 2 . 0.390 √ 1.00 ² + 1
= 0.459 + 0.781 . 1.414
= 1.563 M

Jari-Jari Hidrolis ( R )
R = F
P
= 0.332
1.563
= 0.212 M
R²/³ = 0.356 M
Kemiringan Saluran ( I )
I = { V } ²
K . R²/³
= { 0.271 } ²
35.00 . 0.356
= 0.00047

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.39 + 0.30
= 0.398 M
Kesimpulan
▪ Luas Areal Sawah (A) = 83.567 Ha
▪ Debit Rencana (Q) = 0.090 M³/dt
▪ Tinggi Air Saluran (h) = 0.390 M
▪ Lebar Dasar Saluran (b) = 0.459 M
▪ Keliling Basah (P) = 1.563 M
▪ Jari-Jari Hidrolis (R) = 0.212 M
▪ Kemiringan Saluran (I) = 0.00047 M
▪ Tinggi Jagaan (W) = 0.398 M

Sketsa
w =

h =

b = 0.459 M

c BKa3 - BKa4- BKa5- BKa6- BKa7 = RTa3 :

Diketahui :
A = 69.64 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1
Maka,
Q = NFR . A . C
e
= 0.86 . 69.64 . 1
0.80
= 74.862 Lt/dt
= 0.075 M³/dt

Dari Tabel Diperoleh Nilai :


m = 1.00
n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.075 0.182
= 0.262 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.075 0.282
= 0.373 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.075 0.25 - 1.00
= 1.071

b = n . h
= 1.071 . 0.373
= 0.400
= 0.40 m

Kontrol h akibat pembulatan b = 0.40 m

F = Q
V
= 0.075
0.262
= 0.286 M²

Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.286 = 0.40 h + 1.00 h2
1.00 h2 + 0.40 h - 0.29 = 0

h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.40 ± √ 0.16 -4 . 1.00 . -0.29
2 . 1.00
= -0.40 ± √ 0.16 + 1.14
2
= -0.40 ± √ 1.30
2
= -0.40 ± 1.14
2
= -0.40 + 1.14 = -0.40 - 1.14
2 2
h.1 = 0.371 m ( memenuhi ) h.2 = -0.771 m (Tidak memenuhi)
Keliling Basah (P)
P = b + 2h √ M² + 1
= 0.40 + 2 . 0.371 √ 1.00 ² + 1
= 0.400 + 0.742 . 1.414
= 1.448 M

Jari-Jari Hidrolis ( R )
R = F
P
= 0.286
1.448
= 0.197 M
R²/³ = 0.339 M
Kemiringan Saluran ( I )
I = V ²
{ K . R²/³ }
= 0.262 ²
{ 35.00 . 0.339 }
= 0.00049

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.37 + 0.30
= 0.393 M
Kesimpulan
▪ Luas Areal Sawah (A) = 69.639 Ha
▪ Debit Rencana (Q) = 0.075 M³/dt
▪ Tinggi Air Saluran (h) = 0.371 M
▪ Lebar Dasar Saluran (b) = 0.400 M
▪ Keliling Basah (P) = 1.448 M
▪ Jari-Jari Hidrolis (R) = 0.197 M
▪ Kemiringan Saluran (I) = 0.00049 M
▪ Tinggi Jagaan (W) = 0.393 M

Sketsa
w
=
h
=

b = 0.400 M

d. BKa4 - BKa5- BKa6- BKa7 = RTa4 :

DiketahA = 55.71 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 55.71 . 1
0.80
= 59.89 Lt/dt
= 0.060 M³/dt

Dari Tabel m = 1.00


n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.060 0.182
= 0.252 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.060 0.282
= 0.350 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.060 0.25 - 1.00
= 0.959

b = n . h
= 0.959 . 0.350
= 0.336
= 0.34 m

0.34 m
Kontrol h akibat pembulatan b =
F = Q
V
= 0.060
0.252
= 0.238 M²

Disubtitusi F = (b+m.h) h
F = bh + mh2
= 0.34 h + 1.00 h2
0.238 h2 + 0.34 h - 0.24 = 0
1.00
h.1.2 = - b ± √ b2 - 4 . a. c
2.a

= -0.34 ± √ 0.11 -4 . 1.00 . -0.24


2 . 1.00
= -0.34 ± √ 0.11 + 0.95
2
= -0.34 ± √ 1.06
2
= -0.34 ± 1.03
2
= -0.34 + 1.03 = -0.34 - ###
2 2
h.1 = 0.348 ( memenuhi ) h.2 = -0.684 ( Tidak memenuhi )

Keliling BaP = b + 2h √ M² + 1
= 0.34 + 2 . 0.348 √ 1.00 ² + 1
= 0.34 + 0.696 . 1.414
= 1.320 M

Jari-Jari Hi R = F
P
= 0.238
1.320
= 0.180 M
R²/³ = 0.319 M

KemiringanI = V ²
{ K . R²/³ }
= 0.252 ²
{ 35.00 . 0.319 }
= 0.00051
Tinggi Jag W = 0.25 . h + 0.30
= 0.25 . 0.35 + 0.30
= 0.387 M

Kesimp▪ Luas Areal Sawah (A) = 55.711 Ha


▪ Debit Rencana (Q) = 0.060 M³/dt
▪ Tinggi Air Saluran (h) = 0.348 M
▪ Lebar Dasar Saluran (b) = 0.336 M
▪ Keliling Basah (P) = 1.320 M
▪ Jari-Jari Hidrolis (R) = 0.180 M
▪ Kemiringan Saluran (I) = 0.00051 M
▪ Tinggi Jagaan (W) = 0.387 M

Sketsa w
=
h
=

b = 0.336 M

e. BKa5- BKa6- BKa7 = RTa5 :

DiketahA = 41.78 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 41.78 . 1
0.80
= 44.92 Lt/dt
= 0.045 M³/dt

Dari Tabel m = 1.00


n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.045 0.182
= 0.239 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.045 0.282
= 0.323 m
n = 3.96 . Q 0.25 - m
= 3.96 . 0.045 0.25 - 1.00
= 0.823

b = n . h
= 0.823 . 0.32
= 0.266
= 0.27 m

0.27 m
Kontrol h akibat pembulatan b =
F = Q
V
= 0.045
0.239
= 0.188 M²

Disubtitusi F = (b+m.h) h
F = bh + mh2
= 0.27 h + 1.00 h2
0.188 h2 + 0.27 h - 0.188 = 0
1.00
h.1.2 = - b ± √ b2 - 4 . a. c
2.a

= -0.27 ± √ 0.07 -4 . 1.00 . -0.19


2 . 1.00
= -0.27 ± √ 0.07 + 0.75
2
= -0.27 ± √ 0.82
2
= -0.27 ± 0.91
2
= -0.27 + 0.91 = -0.27 - 0.91
2 2
h.1 = 0.321 ( memenuhi ) h.2 = -0.5866 ( Tidak memenuhi )

Keliling BaP = b + 2h √ M² + 1
= 0.27 + 2 . 0.321 √ 1.00 ² + 1
= 0.266 + 0.641 . 1.414
= 1.173 M

Jari-Jari Hi R = F
P
= 0.188
1.173
= 0.160 M
R²/³ = 0.295 M
KemiringanI = V ²
{ K . R²/³ }
= { 0.239 }²
35.00 . 0.295
= 0.00053

Tinggi Jag W = 0.25 . h + 0.30


= 0.25 . 0.32 + 0.30
= 0.380 M

Kesimp▪ Luas Areal Sawah (A) = 41.783 Ha


▪ Debit Rencana (Q) = 0.045 M³/dt
▪ Tinggi Air Saluran (h) = 0.321 M
▪ Lebar Dasar Saluran (b) = 0.27 M
▪ Keliling Basah (P) = 1.173 M
▪ Jari-Jari Hidrolis (R) = 0.160 M
▪ Kemiringan Saluran (I) = 0.00053 M
▪ Tinggi Jagaan (W) = 0.380 M

Sketsa
w
=
h
=

b = 0.27 M

f. BKa6- BKa7 = RTa6

DiketahA = 27.86 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 27.86 . 1
0.80
= 29.94 Lt/dt
= 0.030 M³/dt

Dari Tabel m = 1.00


n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.030 0.182
= 0.222 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.030 0.282
= 0.288 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.030 0.25 - ###
= 0.647

b = n . h
= 0.647 . 0.29
= 0.187
= 0.19 m

0.19 m
Kontrol h akibat pembulatan b =
F = Q
V
= 0.030
0.222
= 0.135 M²

Disubtitusi F = (b+m.h) h
F = bh + mh2
= 0.19 h + 1.00 h2
0.135 h2 + 0.19 h - 0.135 = 0
1.00
h.1.2 = - b ± √ b - 4 . a. c
2

2.a

= -0.19 ± √ 0.03 -4 . 1.00 . -0.14


2 . 1.00
= -0.19 ± √ 0.03 + 0.54
2
= -0.19 ± √ 0.57
2
= -0.19 ± 0.76
2
= -0.19 + 0.76 = -0.19 - 0.76
2 2
h.1 = 0.286 ( memenuhi ) h.2 = -0.4724 ( Tidak memenuhi )

Keliling BaP = b + 2h √ M² + 1
= 0.19 + 2 . 0.286 √ 1.00 ² + 1
= 0.19 + 0.572 . 1.414
= 0.995 M

Jari-Jari Hi R = F
P
= 0.135
0.995
= 0.136 M
R²/³ = 0.264 M

KemiringanI = V ²
{ K . R²/³ }
= 0.222 ²
{ 35.00 . 0.264 }
= 0.00058

Tinggi Jag W = 0.25 . h + 0.30


= 0.25 . 0.29 + 0.30
= 0.371 M

Kesimp▪ Luas Areal Sawah (A) = 27.856 Ha


▪ Debit Rencana (Q) = 0.030 M³/dt
▪ Tinggi Air Saluran (h) = 0.286 M
▪ Lebar Dasar Saluran (b) = 0.19 M
▪ Keliling Basah (P) = 0.995 M
▪ Jari-Jari Hidrolis (R) = 0.136 M
▪ Kemiringan Saluran (I) = 0.00058 M
▪ Tinggi Jagaan (W) = 0.371 M

w
=
h
=

b = 0.19 M
g. BKa7 = RTa7
DiketahA = 13.93 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 13.93 . 1
0.80
= 14.97 Lt/dt
= 0.015 M³/dt

Dari Tabel m = 1.00


n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.015 0.182
= 0.196 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.015 0.282
= 0.237 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.015 0.25 - 1.00
= 0.385

b = n . h
= 0.385 . 0.24
= 0.091
= 0.09 m

0.09 m
Kontrol h akibat pembulatan b =
F = Q
V
= 0.015
0.196
= 0.077 M²

Disubtitusi F = (b+m.h) h
F = bh + mh2
= 0.09 h + 1.00 h2
0.077 h2 + 0.09 h - 0.077 = 0
1.00
h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.09 ± √ 0.01 -4 . 1.00 . -0.08
2 . 1.00
= -0.09 ± √ 0.01 + 0.31
2
= -0.09 ± √ 0.32
2
= -0.09 ± 0.57
2
= -0.09 + 0.57 = -0.09 - 0.57
2 2
h.1 = 0.237 ( memenuhi ) h.2 = -0.3285 ( Tidak memenuhi )

Keliling BaP = b + 2h √ M² + 1
= 0.09 + 2 . 0.237 √ 1.00 ² + 1
= 0.091 + 0.474 . 1.414
= 0.762 M

Jari-Jari Hi R = F
P
= 0.077
0.762
= 0.100 M
R²/³ = 0.216 M

KemiringanI = V ²
{ K . R²/³ }
= 0.196 ²
{ 35.00 . 0.216 }
= 0.00067

Tinggi Jag W = 0.25 . h + 0.30


= 0.25 . 0.24 + 0.30
= 0.359 M

Kesimp▪ Luas Areal Sawah (A) = 13.928 Ha


▪ Debit Rencana (Q) = 0.015 M³/dt
▪ Tinggi Air Saluran (h) = 0.237 M
▪ Lebar Dasar Saluran (b) = 0.09 M
▪ Keliling Basah (P) = 0.762 M
▪ Jari-Jari Hidrolis (R) = 0.100 M
▪ Kemiringan Saluran (I) = 0.00067 M
▪ Tinggi Jagaan (W) = 0.359 M

Sketsa w
=
h
=
b = 0.09 M

2.2 Saluran Tersier b


a. BKb1 - BKb2 - BKb3- BKba4 - BKb5- BKb6- BKb7 = RTb1 :
DiketahA = 97.81 Ha
NFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 97.81 . 1
0.80
= 105.144 Lt/dt
= 0.105 M³/dt

Dari Tabel m = 1.00


n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.105 0.182
= 0.279 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.105 0.282
= 0.411 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.105 0.25 - 1.00
= 1.255

b = n . h
= 1.255 . 0.41
= 0.515
= 0.52 m

Kontrol h akibat pembulatan b = 0.52 m

F = Q
V
= 0.105
0.279
= 0.377 M²
Disubtitusi F = (b+m.h) h
F = bh + mh2
= 0.52 h + 1.00 h2
0.377 h2 + 0.52 h - 0.38 = 0
1.00
h.1.2 = - b ± √ b - 4 . a. c
2

2.a
= -0.52 ± √ 0.27 -4 . 1.00 . -0.38
2 . 1.00

= -0.52 ± √ 0.27 + 1.51


2
= -0.52 ± √ 1.77
2
= -0.52 ± 1.33
2
= -0.52 + 1.33 = -0.52 - ###
2 2
h.1 = 0.408 m ( memenuhi ) h.2 = -0.924 m ( Tidak memenuhi )

Keliling Ba P = b + 2h √ M² + 1
= 0.52 + 2 . 0.408 √ 1.00 ² + 1
= 0.515 + 0.817 . 1.414
= 1.670 M

Jari-Jari Hi R = F
P
= 0.377
1.670
= 0.226 M
R²/³ = 0.371 M

KemiringanI = V ²
{ K . R²/³ }
= 0.279 ²
{ 35.00 . 0.371 }
= 0.00046

Tinggi Jag W = 0.25 . h + 0.30


= 0.25 . 0.41 + 0.30
= 0.402 M

Kesimp▪ Luas Areal Sawah (A) = 97.809 Ha


▪ Debit Rencana (Q) = 0.105 M³/dt
▪ Tinggi Air Saluran (h) = 0.408 M
▪ Lebar Dasar Saluran (b) = 0.515 M
▪ Keliling Basah (P) = 1.670 M
▪ Jari-Jari Hidrolis (R) = 0.226 M
▪ Kemiringan Saluran (I) = 0.00046 M
▪ Tinggi Jagaan (W) = 0.402 M

Sketsa w =

h = 0.402

0.408
b = 0.515 M
b. BKb2 - BKb3- BKba4 - BKb5- BKb6- BKb7 = RTb2 :
A = 83.84 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 83.84 . 1
0.80
= 90.124 Lt/dt
= 0.090 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.090 0.182
= 0.271 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.090 0.282
= 0.393 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.090 0.25 - 1.00
= 1.170

b = n . h
= 1.170 . 0.393
= 0.460
= 0.46 m

Kontrol h akibat pembulatan b = 0.46 m

F = Q
V
= 0.090
0.271
= 0.333 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.46 h + 1.00 h2
h2 + 0.46 h - 0.33 = 0
0.333
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.46 ± √ 0.21 -4 . 1.00 . -0.33
2 . 1.00
= -0.46 ± √ 0.21 + 1.33
2
= -0.46 ± √ 1.54
2
= -0.46 ± 1.24
2
= -0.46 + 1.24 = -0.46 - 1.24
2 2
h.1 = 0.391 m ( memenuhi ) h.2 = -0.851 m ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.46 + 2 . 0.391 √ 1.00 ² + 1
= 0.460 + 0.782 . 1.414
= 1.565 M

R = F
Jari-Jari Hidrolis ( P
= 0.333
1.565
= 0.212 M
R²/³ = 0.356 M

I = { V } ²
Kemiringan Saluran ( I ) K . R²/³
= { 0.271 } ²
35.00 . 0.356
= 0.00047

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.39 + 0.30
= 0.398 M

▪ Luas Areal Sawah (A) = 83.836 Ha


Kesimp▪ Debit Rencana (Q) = 0.090 M³/dt
▪ Tinggi Air Saluran (h) = 0.391 M
▪ Lebar Dasar Saluran (b) = 0.460 M
▪ Keliling Basah (P) = 1.565 M
▪ Jari-Jari Hidrolis (R) = 0.212 M
▪ Kemiringan Saluran (I) = 0.00047 M
▪ Tinggi Jagaan (W) = 0.398 M

Sketsa w

h =
=

b = 0.460 M

c. BKb3- BKba4 - BKb5- BKb6- BKb7 = RTb3 :


A = 69.86 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 69.86 . 1
0.80
= 75.103 Lt/dt
= 0.075 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.075 0.182
= 0.262 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.075 0.282
= 0.373 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.075 0.25 - 1.00
= 1.073

b = n . h
= 1.073 . 0.37
= 0.401
= 0.40 m
0.40 m

KonF = Q
V
= 0.075
0.262
= 0.286 M²
F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.40 h + 1.00 h2
h2 + 0.40 h - 0.29 = 0
0.286
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.40 ± √ 0.16 -4 . 1.00 . -0.29
2 . 1.00
= -0.40 ± √ 0.16 + 1.15
2
= -0.40 ± √ 1.31
2
= -0.40 ± 1.14
2
= -0.40 + 1.14 = -0.40 - 1.14
2 2
h.1 = 0.371 m ( memenuhi ) h.2 = -0.772 m (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.40 + 2 . 0.371 √ 1.00 ² + 1
= 0.401 + 0.742 . 1.414
= 1.450 M

R = F
Jari-Jari Hidrolis ( P
= 0.286
1.450
= 0.197 M
R²/³ = 0.339 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.262 ²
{ 35.00 . 0.339 }
= 0.00049

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.37 + 0.30
= 0.393 M

▪ Luas Areal Sawah (A) = 69.863 Ha


Kesimp▪ Debit Rencana (Q) = 0.075 M³/dt
▪ Tinggi Air Saluran (h) = 0.371 M
▪ Lebar Dasar Saluran (b) = 0.401 M
▪ Keliling Basah (P) = 1.450 M
▪ Jari-Jari Hidrolis (R) = 0.197 M
▪ Kemiringan Saluran (I) = 0.00049 M
▪ Tinggi Jagaan (W) = 0.393 M

Sketsa w

h =

b = 0.401 M

d. BKb4 - BKb5- BKb6- BKb7 = RTb4 :


A = 55.89 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 55.89 . 1
0.80
= 60.08 Lt/dt
= 0.060 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.060 0.182
= 0.252 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.060 0.282
= 0.351 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.060 0.25 - 1.00
= 0.961

b = n . h
= 0.961 . 0.351
= 0.337
= 0.34 m
0.34 m
KonF = Q
V
= 0.060
0.252
= 0.239 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.34 h + 1.00 h2
h2 + 0.34 h - 0.24 = 0
0.239
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.34 ± √ 0.11 -4 . 1.00 . -0.24
2 . 1.00
= -0.34 ± √ 0.11 + 0.95
2
= -0.34 ± √ 1.07
2
= -0.34 ± 1.03
2
= -0.34 + 1.03 = -0.34 - 1.03
2 2
h.1 = 0.348 ( memenuhi ) h.2 = -0.6852 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.34 + 2 . 0.348 √ 1.00 ² + 1
= 0.337 + 0.697 . 1.414
= 1.322 M

R = F
Jari-Jari Hidrolis ( P
= 0.239
1.322
= 0.181 M
R²/³ = 0.319 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.252 ²
{ 35.00 . 0.319 }
= 0.00051

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.35 + 0.30
= 0.387 M
▪ Luas Areal Sawah (A) = 55.891 Ha
Kesimp▪ Debit Rencana (Q) = 0.060 M³/dt
▪ Tinggi Air Saluran (h) = 0.348 M
▪ Lebar Dasar Saluran (b) = 0.337 M
▪ Keliling Basah (P) = 1.322 M
▪ Jari-Jari Hidrolis (R) = 0.181 M
▪ Kemiringan Saluran (I) = 0.00051 M
▪ Tinggi Jagaan (W) = 0.387 M

Sketsa w

h =

b = 0.337 M

e. BKb5- BKb6- BKb7 = RTb5 :


A = 41.92 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 41.92 . 1
0.80
= 45.06 Lt/dt
= 0.045 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.045 0.182
= 0.239 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.045 0.282
= 0.323 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.045 0.25 - 1.00
= 0.825

b= n . h
= 0.825 . 0.32
= 0.267
= 0.27 m
Kontrol h akibat pembulatan b = 0.27 m

F = Q
V
= 0.045
0.239
= 0.189 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.27 h + 1.00 h2
h2 + 0.27 h - 0.19 = 0
0.189
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.27 ± √ 0.07 -4 . 1.00 . -0.19
2 . 1.00
= -0.27 ± √ 0.07 + 0.75
2
= -0.27 ± √ 0.83
2
= -0.27 ± 0.91
2
= -0.27 + 0.91 = -0.27 - 0.91
2 2
h.1 = 0.321 ( memenuhi ) h.2 = -0.5876 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.27 + 2 . 0.321 √ 1.00 ² + 1
= 0.267 + 0.642 . 1.414
= 1.174 M

R = F
Jari-Jari Hidrolis ( P
= 0.189
1.174
= 0.161 M
R²/³ = 0.295 M

I = { V }²
Kemiringan Saluran ( I ) K . R²/³
= { 0.239 }²
35.00 . 0.295
= 0.00053

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.32 + 0.30
= 0.380 M

▪ Luas Areal Sawah (A) = 41.918 Ha


Kesimp▪ Debit Rencana (Q) = 0.045 M³/dt
▪ Tinggi Air Saluran (h) = 0.321 M
▪ Lebar Dasar Saluran (b) = 0.267 M
▪ Keliling Basah (P) = 1.174 M
▪ Jari-Jari Hidrolis (R) = 0.161 M
▪ Kemiringan Saluran (I) = 0.00053 M
▪ Tinggi Jagaan (W) = 0.380 M

Sketsa w

h =

b = 0.267 M

f. BKb6- BKb7 = RTb6 :


A = 27.95 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 27.95 . 1
0.80
= 30.04 Lt/dt
= 0.030 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.030 0.182
= 0.222 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.030 0.282
= 0.288 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.030 0.25 - 1.00
= 0.649

b = n . h
= 0.649 . 0.29
= 0.187
= 0.19 m
Kontrol h akibat pembulatan b = 0.19 m

F = Q
V
= 0.030
0.222
= 0.135 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.19 h + 1.00 h2
h2 + 0.19 h - 0.14 = 0
0.135
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.19 ± √ 0.03 -4 . 1.00 . -0.14
2 . 1.00
= -0.19 ± √ 0.03 + 0.54
2
= -0.19 ± √ 0.58
2
= -0.19 ± 0.76
2
= -0.19 + 0.76 = -0.19 - 0.76
2 2
h.1 = 0.286 ( memenuhi ) h.2 = -0.4732 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.19 + 2 . 0.286 √ 1.00 ² + 1
= 0.187 + 0.572 . 1.414
= 0.996 M

R = F
Jari-Jari Hidrolis ( P
= 0.135
0.996
= 0.136 M
R²/³ = 0.264 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.222 ²
{ 35.00 . 0.264 }
= 0.00058

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.29 + 0.30
= 0.372 M

▪ Luas Areal Sawah (A) = 27.945 Ha


Kesimp▪ Debit Rencana (Q) = 0.030 M³/dt
▪ Tinggi Air Saluran (h) = 0.286 M
▪ Lebar Dasar Saluran (b) = 0.187 M
▪ Keliling Basah (P) = 0.996 M
▪ Jari-Jari Hidrolis (R) = 0.136 M
▪ Kemiringan Saluran (I) = 0.00058 M
▪ Tinggi Jagaan (W) = 0.372 M

w
Sketsa
h =

b = 0.187 M

g. BKb7 = RTb7 :
A = 13.97 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 13.97 . 1
0.80
= 15.02 Lt/dt
= 0.015 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.2
= 0.42 . 0.015 0
= 0.196 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.015 0.282
= 0.237 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.015 0.25 - 1.00
= 0.386

b = n . h
= 0.386 . 0.237
= 0.092
= 0.09 m
Kontrol h akibat pembulatan b = 0.09 m

F = Q
V
= 0.015
0.196
= 0.077 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.09 h + 1.00 h2
h2 + 0.09 h - 0.08 = 0
0.077
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.09 ± √ 0.01 -4 . 1.00 . -0.08
2 . 1.00
= -0.09 ± √ 0.01 + 0.31
2
= -0.09 ± √ 0.32
2
= -0.09 ± 0.57
2
= -0.09 + 0.57 = -0.09 - 0.57
2 2
h.1 = 0.237 ( memenuhi ) h.2 = -0.3287 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.09 + 2 . 0.237 √ 1.00 ² + 1
= 0.092 + 0.474 . 1.414
= 0.762 M

R = F
Jari-Jari Hidrolis ( P
= 0.077
0.762
= 0.101 M
R²/³ = 0.217 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.196 ²
{ 35.00 . 0.217 }
= 0.00067

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.24 + 0.30
= 0.359 M

▪ Luas Areal Sawah (A) = 13.973 Ha


Kesimp▪ Debit Rencana (Q) = 0.015 M³/dt
▪ Tinggi Air Saluran (h) = 0.237 M
▪ Lebar Dasar Saluran (b) = 0.092 M
▪ Keliling Basah (P) = 0.762 M
▪ Jari-Jari Hidrolis (R) = 0.101 M
▪ Kemiringan Saluran (I) = 0.00067 M
▪ Tinggi Jagaan (W) = 0.359 M

Sketsa w

h =

=
b = 0.092 M
2.3 Saluran Tersier C
a. BKc1 -A = 97.81 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 97.81 . 1
0.80
= 105.144 Lt/dt
= 0.105 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.105 0.182
= 0.279 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.105 0.282
= 0.411 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.105 0.25 - 1.00
= 1.255

b = n . h
= 1.255 . 0.41
= 0.515
= 0.52 m

Kontrol h akibat pembulatan b = 0.52 m


F = Q
V
= 0.105
0.279
= 0.377 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.52 h + 1.00 h2
h2 + 0.52 h - 0.38 = 0
###
### h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.52 ± √ 0.27 -4 . 1.00 . -0.38
2 . 1.00
= -0.52 ± √ 0.27 + 1.51
2
= -0.52 ± √ 1.77
2
= -0.52 ± 1.33
2
= -0.52 + 1.33 = -0.52 - ###
2 2
h.1 = 0.408 m ( memenuhi ) h.2 = -0.924 m ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.52 + 2 . 0.408 √ 1.00 ² + 1
= 0.515 + 0.817 . 1.414
= 1.670 M

R = F
Jari-Jari Hidrolis ( P
= 0.377
1.670
= 0.226 M
R²/³ = 0.371 M

I = { V } ²
Kemiringan Saluran ( I ) K . R²/³
= { 0.279 } ²
35.00 . 0.371
= 0.00046

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.41 + 0.30
= 0.402 M

▪ Luas Areal Sawah (A) = 97.809 Ha


Kesimp▪ Debit Rencana (Q) = 0.105 M³/dt
▪ Tinggi Air Saluran (h) = 0.408 M
▪ Lebar Dasar Saluran (b) = ### M
▪ Lebar Dasar Saluran (b) = 0.515 M
▪ Jari-Jari Hidrolis (R) = 0.226 M
▪ Kemiringan Saluran (I) = 0.00046 M
▪ Tinggi Jagaan (W) = 0.402 M

Sketsa w

h =

=
b = 0.52 M
b. BKc2- BKc3 BKc4 - BKc5- BKc6- BKc7 = RTc2 :
A = 83.84 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 83.84 . 1
0.80
= 90.124 Lt/dt
= 0.090 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.090 0.182
= 0.271 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.090 0.282
= 0.393 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.090 0.25 - 1.00
= 1.170

b = n . h
= 1.170 . 0.39
= 0.460
= 0.46 m

Kontrol h akibat pembulatan b = 0.46 m


F = Q
V
= 0.090
0.271
= 0.333 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.46 h + 1.00 h2
h2 + 0.46 h - 0.33 = 0
0.333
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.46 ± √ 0.21 -4 . 1.00 . -0.33
2 . 1.00
= -0.46 ± √ 0.21 + 1.33
2
= -0.46 ± √ 1.54
2
= -0.46 ± 1.24
2
= -0.46 + 1.24 = -0.46 - ###
2 2
h.1 = 0.391 m ( memenuhi ) h.2 = -0.851 m ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.46 + 2 . 0.391 √ 1.00 ² + 1
= 0.460 + 0.782 . 1.414
= 1.565 M

R = F
Jari-Jari Hidrolis ( P
= 0.333
1.565
= 0.212 M
R²/³ = 0.356 M

I = V ²
Kemiringan Saluran { K . R²/³ }
=
{ 35.00
0.271
. 0.356 } ²

= 0.00047

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.39 + 0.30
= 0.398 M

▪ Luas Areal Sawah (A) = 83.836 Ha


Kesimp▪ Debit Rencana (Q) = 0.090 M³/dt
▪ Tinggi Air Saluran (h) = 0.391 M
▪ Lebar Dasar Saluran (b) = 0.46 M
▪ Jari-Jari Hidrolis (R) = 0.212 M
▪ Keliling Basah (P) = 1.565 M
▪ Kemiringan Saluran (I) = 0.00047 M
▪ Tinggi Jagaan (W) = 0.398 M

Sketsa w

h =
=

b = 0.46 M

c. BKc3 - BKc4 - BKc5- BKc6- BKc7 = RTc3 :


A = 69.86 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 69.86 . 1
0.80
= 75.103 Lt/dt
= 0.075 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.075 0.182
= 0.262 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.075 0.282
= 0.373 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.075 0.25 - 1.00
= 1.073

b = n . h
= 1.073 . 0.37
= 0.401
= 0.40 m

Kontrol h akibat pembulatan b = 0.40 m


F = Q
V
= 0.075
0.262
= 0.286 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.40 h + 1.00 h2
h2 + 0.40 h - 0.29 = 0
0.286
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.40 ± √ 0.16 -4 . 1.00 . -0.29
2 . 1.00
= -0.40 ± √ 0.16 + 1.15
2
= -0.40 ± √ 1.31
2
= -0.40 ± 1.14
2
= -0.40 + 1.14 = -0.40 - 1.14
2 2
h.1 = 0.371 m ( memenuhi ) h.2 = -0.772 m ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.40 + 2 . 0.371 √ 1.00 ² + 1
= 0.401 + 0.742 . 1.414
= 1.450 M

R = F
Jari-Jari Hidrolis ( P
= 0.286
1.450
= 0.197 M
R²/³ = 0.339 M

I = { V } ²
Kemiringan Saluran ( I ) K . R²/³
= { 0.262 } ²
35.00 . 0.339
= 0.00049

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.37 + 0.30
= 0.393 M

▪ Luas Areal Sawah (A) = 69.863 Ha


Kesimp▪ Debit Rencana (Q) = 0.075 M³/dt
▪ Tinggi Air Saluran (h) = 0.371 M
▪ Lebar Dasar Saluran (b) = 0.40 M
▪ Keliling Basah (P) = 1.450 M
▪ Jari-Jari Hidrolis (R) = 0.197 M
▪ Kemiringan Saluran (I) = 0.00049 M
▪ Tinggi Jagaan (W) = 0.393 M
Sketsa w

h =

b = 0.40 M

d. BKc4 - BKc5-BKc6- BKc7 = RTc4 :


A = 55.89 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 55.89 . 1
0.80
= 60.08 Lt/dt
= 0.060 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.060 0.182
= 0.252 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.060 0.282
= 0.351 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.060 0.25 - 1.00
= 0.961

b = n . h
= 0.961 . 0.35
= 0.337
= 0.34 m

Kontrol h akibat pembulatan b = 0.34 m


F = Q
V
= 0.060
0.252
= 0.239 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.34 h + 1.00 h2
h2 + 0.34 h - 0.24 = 0
###
### h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.34 ± √ 0.11 -4 . 1.00 . -0.24
2 . 1.00
= -0.34 ± √ 0.11 + 0.95
2
= -0.34 ± √ 1.07
2
= -0.34 ± 1.03
2
= -0.34 + 1.03 = -0.34 - ###
2 2
h.1 = 0.348 ( memenuhi ) h.2 = -0.6852 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.34 + 2 . 0.348 √ 1.00 ² + 1
= 0.337 + 0.697 . 1.414
= 1.322 M

R = F
Jari-Jari Hidrolis ( P
= 0.239
1.322
= 0.181 M
R²/³ = 0.319 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.252 ²
{ 35.00 . 0.319 }
= 0.00051

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.35 + 0.30
= 0.387 M

▪ Luas Areal Sawah (A) = 55.891 Ha


Kesimp▪ Debit Rencana (Q) = 0.060 M³/dt
▪ Tinggi Air Saluran (h) = 0.348 M
▪ Lebar Dasar Saluran (b) = 0.34 M
▪ Keliling Basah (P) = 1.322 M
▪ Jari-Jari Hidrolis (R) = 0.181 M
▪ Kemiringan Saluran (I) = 0.00051 M
▪ Tinggi Jagaan (W) = 0.387 M

Sketsa w

h =

=
b = 0.34 M

e. BKc5- BKc6- BKc7 = RTc5


A = 41.92 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 41.92 . 1
0.80
= 45.06 Lt/dt
= 0.045 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.045 0.182
= 0.239 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.045 0.282
= 0.323 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.045 0.25 - 1.00
= 0.825

b = n . h
= 0.825 . 0.32
= 0.267
= 0.27 m

Kontrol h akibat pembulatan b = 0.27 m


F = Q
V
= 0.045
0.239
= 0.189 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.27 h + 1.00 h2
h2 + 0.27 h - 0.19 = 0
0.189
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.27 ± √ 0.07 -4 . 1.00 . -0.19
2 . 1.00
= -0.27 ± √ 0.07 + 0.75
2
= -0.27 ± √ 0.83
2
= -0.27 ± 0.91
2
= -0.27 + 0.91 = -0.27 - 0.91
2 2
h.1 = 0.321 ( memenuhi ) h.2 = -0.5876 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.27 + 2 . 0.321 √ 1.00 ² + 1
= 0.267 + 0.642 . 1.414
= 1.174 M

R = F
Jari-Jari Hidrolis ( P
= 0.189
1.174
= 0.161 M
R²/³ = 0.295 M

I = { V }²
Kemiringan Saluran ( I ) K . R²/³
= { 0.239 }²
35.00 . 0.295
= 0.00053
W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.32 + 0.30
= 0.380 M

▪ Luas Areal Sawah (A) = 41.918 Ha


Kesimp▪ Debit Rencana (Q) = 0.045 M³/dt
▪ Tinggi Air Saluran (h) = 0.321 M
▪ Lebar Dasar Saluran (b) = 0.267 M
▪ Keliling Basah (P) = 1.174 M
▪ Jari-Jari Hidrolis (R) = 0.161 M
▪ Kemiringan Saluran (I) = 0.00053 M
▪ Tinggi Jagaan (W) = 0.380 M

Sketsa w

h =

=
b = 0.27 M

f. BKc6- BKc7 = RTc6


A = 27.95 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 27.95 . 1
0.80
= 30.04 Lt/dt
= 0.030 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.030 0.182
= 0.222 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.030 0.282
= 0.288 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.030 0.25 - 1.00
= 0.649

b = n . h
= 0.649 . 0.29
= 0.187
= 0.19 m

Kontrol h akibat pembulatan b = 0.19 m


F = Q
V
= 0.030
0.222
= 0.135 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.19 h + 1.00 h2
h + 0.19 h -
2
0.14 = 0
0.135
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.19 ± √ 0.03 -4 . 1.00 . -0.14
2 . 1.00
= -0.19 ± √ 0.03 + 0.54
2
= -0.19 ± √ 0.58
2
= -0.19 ± 0.76
2
= -0.19 + 0.76 = -0.19 - 0.76
2 2
h.1 = 0.286 ( memenuhi ) h.2 = -0.4732 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.19 + 2 . 0.286 √ 1.00 ² + 1
= 0.187 + 0.572 . 1.414
= 0.996 M

R = F
Jari-Jari Hidrolis ( P
= 0.135
0.996
= 0.136 M
R²/³ = 0.264 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.222 ²
{ 35.00 . 0.264 }
= 0.00058

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.29 + 0.30
= 0.372 M

▪ Luas Areal Sawah (A) = 27.945 Ha


▪ Tinggi Air Saluran (h) = 0.286 M
▪ Lebar Dasar Saluran (b) = 0.187 M
▪ Keliling Basah (P) = 0.996 M
▪ Jari-Jari Hidrolis (R) = 0.136 M
▪ Kemiringan Saluran (I) = 0.00058 M
▪ Tinggi Jagaan (W) = 0.372 M
Sketsa w =

h =

b = 0.19 M
g. BKc7 =A = 13.97 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 13.97 . 1
0.80
= 15.02 Lt/dt
= 0.015 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.015 0.182
= 0.196 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.015 0.282
= 0.237 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.015 0.25 - 1.00
= 0.386

b = n . h
= 0.386 . 0.24
= 0.092
= 0.09 m

Kontrol h akibat pembulatan b = 0.09 m


F = Q
V
= 0.015
0.196
= 0.077 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.09 h + 1.00 h2
h2 + 0.09 h - 0.08 = 0
0.077
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.09 ± √ 0.01 -4 . 1.00 . -0.08
2 . 1.00
= -0.09 ± √ 0.01 + 0.31
2
= -0.09 ± √ 0.32
2
= -0.09 ± 0.56
2
= -0.09 + 0.56 = -0.09 - 0.56
2 2
h.1 = 0.235 ( memenuhi ) h.2 = -0.3267 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.09 + 2 . 0.235 √ 1.00 ² + 1
= 0.092 + 0.470 . 1.414
= 0.756 M

R = F
Jari-Jari Hidrolis ( P
= 0.077
0.756
= 0.102 M
R²/³ = 0.218 M

I = V ²
Kemiringan Saluran { K . R²/³ }
0.196
=
{ 35.00 . 0.218 }²
= 0.00066

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.24 + 0.30
= 0.359 M

▪ Luas Areal Sawah (A) = 13.973 Ha


Kesimp▪ Debit Rencana (Q) = 0.015 M³/dt
▪ Tinggi Air Saluran (h) = 0.235 M
▪ Lebar Dasar Saluran (b) = 0.09 M
▪ Keliling Basah (P) = 0.756 M
▪ Jari-Jari Hidrolis (R) = ### M
▪ Jari-Jari Hidrolis (R) = 0.102 M
▪ Tinggi Jagaan (W) = 0.359 M

Sketsa w

h =

=
b = 0.09 M

2.4 Saluran Tersier D


a. BKd1 -A = 97.81 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Maka, Q = NFR . A . C
e
= 0.86 . 97.81 . 1
0.80
= 105.144 Lt/dt
= 0.105 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = ###

V = 0.42 . Q 0.182
= 0.42 . 0.105 0.182
= 0.279 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.105 0.282
= 0.411 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.105 0.25 - 1.00
= 1.255

b = n . h
= 1.255 . 0.41
= 0.515
= 0.52 m

Kontrol h akibat pembulatan b = 0.52 m


F = Q
V
= 0.105
0.279
= 0.377 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.52 h + 1.00 h2
h2 + 0.52 h - 0.38 = 0
0.377
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.52 ± √ 0.27 -4 . 1.00 . -0.38
2 . 1.00
= -0.52 ± √ 0.27 + 1.51
2
= -0.52 ± √ 1.77
2
= -0.52 ± 1.33
2
= -0.52 + 1.33 = -0.52 - 1.33
2 2
h.1 = 0.408 m ( memenuhi ) h.2 = -0.924 m ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.52 + 2 . 0.408 √ 1.00 ² + 1
= 0.515 + 0.817 . 1.414
= 1.670 M

R = F
Jari-Jari Hidrolis ( P
= 0.377
1.670
= 0.226 M
R²/³ = 0.371 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.279 ²
{ 35.00 . 0.371 }
= 0.00046

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.41 + 0.30
= 0.402 M

▪ Luas Areal Sawah (A) = 97.809 Ha


Kesimp▪ Debit Rencana (Q) = 0.105 M³/dt
▪ Tinggi Air Saluran (h) = 0.408 M
▪ Lebar Dasar Saluran (b) = 0.52 M
▪ Keliling Basah (P) = 1.670 M
▪ Jari-Jari Hidrolis (R) = 0.226 M
▪ Kemiringan Saluran (I) = 0.00046 M
▪ Tinggi Jagaan (W) = 0.402 M
Sketsa w

h =

b = 0.52 M

b. BKd2 - BKd3 - BKda4 - BKd5- BKd6- BKd7 = RTd2 :


A = 83.84 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 83.84 . 1
0.80
= 90.124 Lt/dt
= 0.090 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.090 0.182
= 0.271 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.090 0.282
= 0.393 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.090 0.25 - 1.00
= 1.170

b = n . h
= 1.170 . 0.39
= 0.460
= 0.46 m

Kontrol h akibat pembulatan b = 0.46 m

F = Q
V
= 0.090
0.271
= 0.333 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.46 h + 1.00 h2
h2 + 0.46 h - 0.33 = 0
0.333
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.46 ± √ 0.21 -4 . 1.00 . -0.33
2 . 1.00
= -0.46 ± √ 0.21 + 1.33
2
= -0.46 ± √ 1.54
2
= -0.46 ± 1.24
2
= -0.46 + 1.24 = -0.46 - 1.24
2 2
h.1 = 0.391 m ( memenuhi ) h.2 = -0.851 m (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.46 + 2 . 0.391 √ 1.00 ² + 1
= 0.460 + 0.782 . 1.414
= 1.565 M

R = F
Jari-Jari Hidrolis ( P
= 0.333
1.565
= 0.212 M
R²/³ = 0.356 M

I =
Kemiringan Saluran { V
K . R²/³ } ²

=
{ 35.00
0.271
. 0.356 } ²

= 0.00047

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.39 + 0.30
= 0.398 M

▪ Luas Areal Sawah (A) = 83.836 Ha


Kesimp▪ Debit Rencana (Q) = 0.090 M³/dt
▪ Tinggi Air Saluran (h) = 0.391 M
▪ Lebar Dasar Saluran (b) = 0.46 M
▪ Keliling Basah (P) = 1.565 M
▪ Jari-Jari Hidrolis (R) = 0.212 M
▪ Kemiringan Saluran (I) = 0.00047 M
▪ Tinggi Jagaan (W) = 0.398 M

Sketsa w =

h =

b = 0.46 M

c. BKd3 -A = 69.86 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 69.86 . 1
0.80
= 75.103 Lt/dt
= 0.075 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.075 0.182
= 0.262 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.075 0.282
= 0.373 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.075 0.25 - 1.00
= 1.073

b = n . h
= 1.073 . 0.37
= 0.401
= 0.40 m
Kontrol h akibat pembulatan b = 0.40 m
F = Q
V
= 0.075
0.262
= 0.286 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.40 h + 1.00 h2
h2 + 0.40 h - 0.29 = 0
0.286
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.40 ± √ 0.16 -4 . 1.00 . -0.29
2 . 1.00
= -0.40 ± √ 0.16 + 1.15
2
= -0.40 ± √ 1.31
2
= -0.40 ± 1.14
2
= -0.40 + 1.14 = -0.40 - 1.14
2 2
h.1 = 0.371 m ( memenuhi ) h.2 = -0.772 m (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.40 + 2 . 0.371 √ 1.00 ² + 1
= 0.401 + 0.742 . 2.000
= 1.885 M

R = F
Jari-Jari Hidrolis ( P
= 0.286
1.885
= 0.152 M
R²/³ = 0.285 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.262 ²
{ 35.00 . 0.285 }
= 0.00069

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.37 + 0.30
= 0.393 M
▪ Luas Areal Sawah (A) = 69.863 Ha
Kesimp▪ Debit Rencana (Q) = 0.075 M³/dt
▪ Tinggi Air Saluran (h) = 0.371 M
▪ Lebar Dasar Saluran (b) = 0.40 M
▪ Keliling Basah (P) = 1.885 M
▪ Jari-Jari Hidrolis (R) = 0.152 M
▪ Kemiringan Saluran (I) = 0.00069 M
▪ Tinggi Jagaan (W) = 0.393 M

Sketsa w =

h =

b = 0.40 M

d. BKd4 -A = 55.89 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 55.89 . 1
0.80
= 60.08 Lt/dt
= 0.060 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.060 0.182
= 0.252 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.060 0.282
= 0.351 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.060 0.25 - 1.00
= 0.961

b = n . h
= 0.961 . 0.35
= 0.337
= 0.34 m

Kontrol h akibat pembulatan b = 0.34 m

F = Q
V
= 0.060
0.252
= 0.239 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.34 h + 1.00 h2
h2 + 0.34 h - 0.24 = 0
0.239
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.34 ± √ 0.11 -4 . 1.00 . -0.24
2 . 1.00
= -0.34 ± √ 0.11 + 0.95
2
= -0.34 ± √ 1.07
2
= -0.34 ± 1.03
2
= -0.34 + 1.03 = -0.34 - 1.03
2 2
h.1 = 0.348 ( memenuhi ) h.2 = -0.6852 (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.34 + 2 . 0.348 √ 1.00 ² + 1
= 0.337 + 0.697 . 2.000
= 1.730 M

R = F
Jari-Jari Hidrolis ( P
= 0.239
1.730
= 0.138 M
R²/³ = 0.267 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.252 ²
{ 35.00 . 0.267 }
= 0.00073

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.35 + 0.30
= 0.387 M

▪ Luas Areal Sawah (A) = 55.891 Ha


Kesimp▪ Debit Rencana (Q) = 0.060 M³/dt
▪ Tinggi Air Saluran (h) = 0.348 M
▪ Lebar Dasar Saluran (b) = 0.34 M
▪ Keliling Basah (P) = 1.730 M
▪ Jari-Jari Hidrolis (R) = 0.138 M
▪ Kemiringan Saluran (I) = 0.00073 M
▪ Tinggi Jagaan (W) = 0.387 M

Sketsa w =

h =

b = 0.34 M

e. BKd5- A = 41.92 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 41.92 . 1
0.80
= 45.06 Lt/dt
= 0.045 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.045 0.182
= 0.239 m/dt
h = 0.775 . Q 0.282
= 0.775 . 0.045 0.282
= 0.323 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.045 0.25 - 1.00
= 0.825

b = n . h
= 0.825 . 0.32
= 0.267
= 0.27 m

Kontrol h akibat pembulatan b = 0.27 m

F = Q
V
= 0.045
0.239
= 0.189 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.27 h + 1.00 h2
h2 + 0.27 h - 0.19 = 0
0.189
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.27 ± √ 0.07 -4 . 1.00 . -0.19
2 . 1.00
= -0.27 ± √ 0.07 + 0.75
2
= -0.27 ± √ 0.83
2
= -0.27 ± 0.91
2
= -0.27 + 0.91 = -0.27 - 0.91
2 2
h.1 = 0.321 ( memenuhi ) h.2 = -0.5876 (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.27 + 2 . 0.321 √ 1.00 ² + 1
= 0.267 + 0.642 . 2.000
= 1.551 M

R = F
Jari-Jari Hidrolis ( P
= 0.189
1.551
= 0.122 M
R²/³ = 0.246 M

I = V ²
Kemiringan Saluran { K . R²/³ }
= 0.239 ²
{ 35.00 . 0.246 }
= 0.00077

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.32 + 0.30
= ### M

▪ Luas Areal Sawah (A) = 41.918 Ha


Kesimp▪ Debit Rencana (Q) = 0.045 M³/dt
▪ Tinggi Air Saluran (h) = 0.321 M
▪ Lebar Dasar Saluran (b) = 0.27 M
▪ Keliling Basah (P) = 1.551 M
▪ Jari-Jari Hidrolis (R) = 0.122 M
▪ Kemiringan Saluran (I) = 0.00077 M
▪ Tinggi Jagaan (W) = 0.380 M

Sketsa w

h =

=
b = 0.27 M

f. BKd6- BKd7 = RTd6 :


A = 27.95 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 27.95 . 1
0.80
= 30.04 Lt/dt
= 0.030 M³/dt
m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.030 0.182
= 0.222 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.030 0.282
= 0.288 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.030 0.25 - 1.00
= 0.649

b = n . h
= 0.649 . 0.29
= 0.187
= 0.19 m

Kontrol h akibat pembulatan b = 0.19 m

F = Q
V
= 0.030
0.222
= 0.135 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.19 h + 1.00 h2
h2 + 0.19 h - 0.14 = 0
0.135
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.19 ± √ 0.03 -4 . 1.00 . -0.14
2 . 1.00
= -0.19 ± √ 0.03 + 0.54
2
= -0.19 ± √ 0.58
2
= -0.19 ± 0.76
2
= -0.19 + 0.76 = -0.19 - 0.76
2 2
h.1 = 0.286 ( memenuhi ) h.2 = -0.4732 (Tidak memenuhi)
P = b + 2h √ M² + 1
Keliling Basah = 0.19 + 2 . 0.286 √ 1.00 ² + 1
= 0.187 + 0.572 . 1.414
= 0.996 M

R = F
Jari-Jari Hidrolis ( P
= 0.135
0.996
= 0.136 M
R²/³ = 0.264 M

I = V ²
Kemiringan Saluran { K . R²/³ }
=
{ 35.00
0.222
. 0.264 }²
= 0.00058

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.29 + 0.30
= 0.372 M

▪ Luas Areal Sawah (A) = 27.945 Ha


Kesimp▪ Debit Rencana (Q) = 0.030 M³/dt
▪ Tinggi Air Saluran (h) = 0.286 M
▪ Lebar Dasar Saluran (b) = 0.19 M
▪ Keliling Basah (P) = 0.996 M
▪ Jari-Jari Hidrolis (R) = 0.136 M
▪ Kemiringan Saluran (I) = 0.00058 M
▪ Tinggi Jagaan (W) = 0.372 M

Sketsa w

h =

=
b = 0.19 M

g. BKd7 =A = 13.97 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 13.97 . 1
0.80
= 15.02 Lt/dt
= 0.015 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.015 0.182
= 0.196 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.015 0.282
= 0.237 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.015 0.25 - 1.00
= 0.386

b = n . h
= 0.386 . 0.24
= 0.092
= 0.09 m

Kontrol h akibat pembulatan b = 0.09 m

F = Q
V
= 0.015
0.196
= 0.077 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.09 h + 1.00 h2
h2 + 0.09 h - 0.08 = 0
0.077
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.09 ± √ 0.01 -4 . 1.00 . -0.08
2 . 1.00
= -0.09 ± √ 0.01 + 0.31
2
= -0.09 ± √ 0.32
2
= -0.09 ± 0.56
2
= -0.09 + 0.56 = -0.09 - 0.56
2 2
h.1 = 0.235 ( memenuhi ) h.2 = -0.3267 (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.09 + 2 . 0.235 √ 1.00 ² + 1
= 0.092 + 0.470 . 1.414
= 0.756 M

R = F
Jari-Jari Hidrolis ( P
= 0.077
0.756
= 0.102 M
R²/³ = 0.218 M

I = V ²
Kemiringan Saluran { K . R²/³ }
=
{ 35.00
0.196
. 0.218 }²
= 0.00066

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.24 + 0.30
= 0.359 M

▪ Luas Areal Sawah (A) = 13.973 Ha


Kesimp▪ Debit Rencana (Q) = 0.015 M³/dt
▪ Tinggi Air Saluran (h) = 0.235 M
▪ Lebar Dasar Saluran (b) = 0.09 M
▪ Keliling Basah (P) = 0.756 M
▪ Jari-Jari Hidrolis (R) = 0.102 M
▪ Kemiringan Saluran (I) = 0.00066 M
▪ Tinggi Jagaan (W) = 0.359 M

Sketsa w =

h =

b = 0.09 M

2.5 Saluran Tersier E


a. BKe1 -A = 97.81 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 97.81 . 1
0.80
= 105.144 Lt/dt
= 0.105 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.105 0.182
= 0.279 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.105 0.282
= 0.411 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.105 0.25 - 1.00
= 1.255

b = n . h
= 1.255 . 0.41
= 0.515
= 0.52 m

Kontrol h akibat pembulatan b = 0.52 m

F = Q
V
= 0.105
0.279
= 0.377 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.52 h + 1.00 h2
h2 + 0.52 h - 0.38 = 0
0.377
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.52 ± √ 0.27 -4 . 1.00 . -0.38
2 . 1.00
= -0.52 ± √ 0.27 + 1.51
2
= -0.52 ± √ 1.77
2
= -0.52 ± 1.33
2
= -0.52 + 1.33 = -0.52 - 1.33
2 2
h.1 = 0.408 m ( memenuhi ) h.2 = -0.924 m (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.52 + 2 . 0.408 √ 1.00 ² + 1
= 0.515 + 0.817 . 1.414
= 1.670 M

R = F
Jari-Jari Hidrolis ( P
= 0.377
1.670
= 0.226 M
R²/³ = 0.371 M

I = { V } ²
Kemiringan Saluran ( I ) K . R²/³
= { 0.279 } ²
35.00 . 0.371
= 0.00046

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.41 + 0.30
= 0.402 M

▪ Luas Areal Sawah (A) = 97.809 Ha


Kesimp▪ Debit Rencana (Q) = 0.105 M³/dt
▪ Tinggi Air Saluran (h) = 0.408 M
▪ Lebar Dasar Saluran (b) = 0.515 M
▪ Keliling Basah (P) = 1.670 M
▪ Jari-Jari Hidrolis (R) = 0.226 M
▪ Kemiringan Saluran (I) = 0.00046 M
▪ Tinggi Jagaan (W) = 0.402 M

Sketsa w =

h =

b = 0.52 M
b. BKe2 - BKe3 - BKe4 - BKe5- BKe6- BKe7 = RTe2 :
A = 83.84 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 83.84 . 1
0.80
= 90.124 Lt/dt
= 0.090 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.090 0.182
= 0.271 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.090 0.282
= 0.393 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.090 0.25 - 1.00
= 1.170

b = n . h
= 1.170 . 0.39
= 0.460
= 0.46 m

Kontrol h akibat pembulatan b = 0.46 m

F = Q
V
= 0.090
0.271
= 0.333 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.46 h + 1.00 h2
h2 + 0.46 h - 0.33 = 0
0.333
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.46 ± √ 0.21 -4 . 1.00 . -0.33
2 . 1.00
= -0.46 ± √ 0.21 + 1.33
2
= -0.46 ± √ 1.54
2
= -0.46 ± 1.24
2
= -0.46 + 1.24 = -0.46 - 1.24
2 2
h.1 = 0.391 m ( memenuhi ) h.2 = -0.851 m (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.46 + 2 . 0.391 √ 1.00 ² + 1
= 0.460 + 0.782 . 1.414
= 1.565 M

R = F
Jari-Jari Hidrolis ( P
= 0.333
1.565
= 0.212 M
R²/³ = 0.356 M

I = { V } ²
Kemiringan Saluran ( I ) K . R²/³
= { 0.271 } ²
35.00 . 0.356
= 0.00047

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.39 + 0.30
= 0.398 M

▪ Luas Areal Sawah (A) = 83.836 Ha


Kesimp▪ Debit Rencana (Q) = 0.090 M³/dt
▪ Tinggi Air Saluran (h) = 0.391 M
▪ Lebar Dasar Saluran (b) = 0.46 M
▪ Keliling Basah (P) = 1.565 M
▪ Jari-Jari Hidrolis (R) = 0.212 M
▪ Kemiringan Saluran (I) = 0.00047 M
▪ Tinggi Jagaan (W) = 0.398 M

Sketsa w =
h =

b = 0.46 M

c. BKe3 - BKe4 - BKe5- BKe6- BKe7 = RTe3 :


A = 69.86 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 69.86 . 1
0.80
= 75.103 Lt/dt
= 0.075 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.075 0.182
= 0.262 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.075 0.282
= 0.373 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.075 0.25 - 1.00
= 1.073

b = n . h
= 1.073 . 0.37
= 0.401
= 0.40 m

Kontrol h akibat pembulatan b = 0.40 m


F = Q
V
= 0.075
0.262
= 0.286 M²
F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.40 h + 1.00 h2
h2 + 0.40 h - 0.29 = 0
0.286
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.40 ± √ 0.16 -4 . 1.00 . -0.29
2 . 1.00
= -0.40 ± √ 0.16 + 1.15
2
= -0.40 ± √ 1.31
2
= -0.40 ± 1.14
2
= -0.40 + 1.14 = -0.40 - 1.14
2 2
h.1 = 0.371 m ( memenuhi ) h.2 = -0.772 m (Tidak memenuhi)

P = b + 2h √ M² + 1
Keliling Basah = 0.40 + 2 . 0.371 √ 1.00 ² + 1
= 0.401 + 0.742 . 1.414
= 1.450 M

R = F
Jari-Jari Hidrolis ( P
= 0.286
1.450
= 0.197 M
R²/³ = 0.339 M

I = { V } ²
Kemiringan Saluran ( I ) K . R²/³
= { 0.262 } ²
35.00 . 0.339
= 0.00049

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.37 + 0.30
= 0.393 M

▪ Luas Areal Sawah (A) = 69.863 Ha


Kesimp▪ Debit Rencana (Q) = 0.075 M³/dt
▪ Tinggi Air Saluran (h) = 0.371 M
▪ Lebar Dasar Saluran (b) = 0.40 M
▪ Keliling Basah (P) = 1.450 M
▪ Jari-Jari Hidrolis (R) = 0.197 M
▪ Kemiringan Saluran (I) = 0.00049 M
▪ Tinggi Jagaan (W) = 0.393 M

Sketsa w =

h =

b = 0.40 M

d. BKe4 - BKe5- BKe6- BKe7 = RTe4 :


A = 55.89 Ha
DiketahNFR = 0.86 Lt/dt/Ha
e = 0.80 (Saluran Tersier)
C = 1

Q = NFR . A . C
Maka, e
= 0.86 . 55.89 . 1
0.80
= 60.08 Lt/dt
= 0.060 M³/dt

m = 1.00
Dari Tabel n = 1.00
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.060 0.182
= 0.252 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.060 0.282
= 0.351 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.060 0.25 - 1.00
= 0.961

b = n . h
= 0.961 . 0.35
= 0.337
= 0.34 m
Kontrol h akibat pembulatan b = 0.34 m

F = Q
V
= 0.060
0.252
= 0.239 M²

F = (b+m.h) h
Disubtitusi F = bh + mh2
= 0.34 h + 1.00 h2
h2 + 0.34 h - 0.24 = 0
0.239
1.00 h.1.2 = - b ± √ b2 - 4 . a. c
2.a
= -0.34 ± √ 0.11 -4 . 1.00 . -0.24
2 . 1.00
= -0.34 ± √ 0.11 + 0.95
2
= -0.34 ± √ 1.07
2
= -0.34 ± 1.03
2
= -0.34 + 1.03 = -0.34 - 1.03
2 2
h.1 = 0.348 ( memenuhi ) h.2 = -0.6852 ( Tidak memenuhi )

P = b + 2h √ M² + 1
Keliling Basah = 0.34 + 2 . 0.348 √ 1.00 ² + 1
= 0.337 + 0.697 . 1.414
= 1.322 M

R = F
Jari-Jari Hidrolis ( P
= 0.239
1.322
= 0.181 M
R²/³ = 0.319 M

I = { V } ²
Kemiringan Saluran ( I ) K . R²/³
= { 0.252 } ²
35.00 . 0.319
= 0.00051

W = 0.25 . h + 0.30
Tinggi Jagaan = 0.25 . 0.35 + 0.30
= 0.387 M

▪ Luas Areal Sawah (A) = 55.891 Ha


Kesimp▪ Debit Rencana (Q) = 0.060 M³/dt
▪ Tinggi Air Saluran (h) = 0.348 M
▪ Lebar Dasar Saluran (b) = 0.34 M
▪ Keliling Basah (P) = 1.322 M
▪ Jari-Jari Hidrolis (R) = 0.181 M
▪ Kemiringan Saluran (I) = 0.00051 M
▪ Tinggi Jagaan (W) = 0.387 M

Sketsa w =

h =

b = 0.34 M
RSIER

Ha
Ha
Ha
Ha
Ha
Ha
Ha
Ha

Ha
Ha
Ha
Ha
Ha
Ha
Ha +
Ha

13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
97.81 Ha

13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
13.97 Ha
97.81 Ha
(Tidak memenuhi)
0.503 M

0.811 M
(Saluran Sekunder)
(Tidak memenuhi)

0.490 m

0.761 m
(Saluran Sekunder)
(Tidak memenuhi)

0.483 M

0.732 M
(Saluran Sekunder)
( Tidak memenuhi )

M³/dt

0.475 M

0.701 M
(Saluran Sekunder)
(Tidak memenuhi)

M³/dt
0.466 M

0.665 M

(Saluran Sekunder)
(Tidak memenuhi)

M³/dt
0.456 M

0.624 M

(Saluran Sekunder)
(Tidak memenuhi)

M³/dt

0.444 M

0.575 M
(Saluran Sekunder)
(Tidak memenuhi)

0.428 m

0.513 m
(Saluran Sekunder)
(Tidak memenuhi)

0.405 m
0.421 m
(Tidak memenuhi)

0.402 M

0.408 M
(Tidak memenuhi)
0.398 M

0.390 M
(Tidak memenuhi)
0.393 M

0.371 M
( Tidak memenuhi )
0.387 M

0.348 M
( Tidak memenuhi )
0.380 M

0.321 M
( Tidak memenuhi )
0.371 M

0.286 M
( Tidak memenuhi )

0.359 M

0.237 M
( Tidak memenuhi )

0.402 M

0.408 M
( Tidak memenuhi )

0.398 M
0.391 M
(Tidak memenuhi)
0.393 M

0.371 M
( Tidak memenuhi )
0.387 M

0.348 M
( Tidak memenuhi )
0.380 M

0.321 M
( Tidak memenuhi )
0.372 M

0.286 M
( Tidak memenuhi )

0.359 M

0.237 M
( Tidak memenuhi )

0.402 M

0.408 M
( Tidak memenuhi )

0.398 M
0.391 M
( Tidak memenuhi )
0.393 M

0.371 M
( Tidak memenuhi )
0.387 M

0.348 M
( Tidak memenuhi )
0.380 M

0.321 M
( Tidak memenuhi )
0.372 M

0.286 M
( Tidak memenuhi )

0.359 M

0.235 M
( Tidak memenuhi )
0.402 M

0.408 M
(Tidak memenuhi)
0.398 M

0.391 M
(Tidak memenuhi)
0.393 M

0.371 M
(Tidak memenuhi)
0.387 M

0.348 M
(Tidak memenuhi)
0.380 M

0.321 M
(Tidak memenuhi)
0.372 M

0.286 M
(Tidak memenuhi)

0.359 M

0.235 M
(Tidak memenuhi)

0.402 M

0.408 M
(Tidak memenuhi)

0.398 M
0.391 M
(Tidak memenuhi)
0.393 M

0.371 M
( Tidak memenuhi )
0.387 M

0.348 M
PERHITUNGAN DIMENSI SALURAN PEMBUANG
A. SALURAN PEMBUANG INDUK (SP.I)
Diketahui :
A = 880 Ha
Q = 0.098 M³/dt

D
DM =
3 . 8.64 `
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 880 0.9
= 95.920 Lt/dt
= 0.959 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.959 0.182
= 0.417 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.959 0.282
= 0.766 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.959 0.25 - 1.00
= 2.919 m

b = n . h
= 2.919 . 0.766
= 2.236
= 2.24 m

Kontrol h akibat pembulatan b = 2.24 m


Q
F =
V
= 0.959
0.417
= 2.301 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
2.301 = 2.24 h + 1.00 h2
1 h2 + 2.24 h - 2.30 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -2.24 ± √ 5.00 -4 . 1 . -2.30
2 . 1
= -2.24 ± √ 5.00 + 9.20
2
= -2.24 ± √ 14.20
2
= -2.24 ± 3.77
2
= -2.24 + 3.77 = -2.24 - 3.77
2 2
h.1 = 0.766 ( memenuhi ) h.2 = -3.002268 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 2.24 + 2 . 0.766 √ 1 ² + 1
= 2.236 + 1.533 . 1.414
= 4.404 M

Jari-Jari Hidrolis ( R )
F
R =
P
2.301
=
4.404
= 0.523 M
R²/³ = 0.649 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.417 ²
=
{ 35.00 . 0.649 }
= 0.00034

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.77 + 0.30
= 0.492 M

Kesimpulan
▪ Luas Areal Sawah (A) = 880
▪ Debit Rencana (Q) = 0.098
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.959
▪ Kecepatan Aliran (V) = 0.417
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 2.919
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.766
▪ Lebar Dasar Saluran (b) = 2.24
▪ Keliling Basah (P) = 4.404
▪ Jari-Jari Hidrolis (R) = 0.523
▪ Kemiringan Saluran (I) = 0.00034
▪ Tinggi Jagaan (W) = 0.492
Sketsa

W = 0.492 m

h = 0.766 m

b = 2.236 m

B. SALURAN PEMBUANG Ta (SP 1)


Diketahui :
A = 97.49 Ha
Q = 0.014 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.49 0.92
= 12.673 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.288 m/dt
h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.433 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1.00
= 1.363 m

b = n . h
= 1.363 . 0.43
= 0.590
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.288
= 0.439 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.439 = 0.59 h + 1.00 h2
1 h 2
+ 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.35 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.35 + 1.76
2
= -0.59 ± √ 2.11
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.431 ( memenuhi ) h.2 = -1.020 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1.00 ² + 1
= 0.590 + 0.861 . 1.414
= 1.808 M

Jari-Jari Hidrolis ( R )
F
R =
R =
P
0.439
=
1.808
= 0.243 M
R²/³ = 0.389 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.288 ²
=
{ 35.00 . 0.389 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan
▪ Luas Areal Sawah (A) = 97.49
▪ Debit Rencana (Q) = 0.014
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.288
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.363
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.808
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa

W = 0.408 m

h = 0.431 m

b = 0.590 m

C. SALURAN PEMBUANG Tb (SP 2)


Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.433 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1.00
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h 2
+ 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.35 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.35 + 1.76
2
= -0.59 ± √ 2.11
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.431 ( memenuhi ) h.2 = -1.022 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.4077 M

Kesimpulan
▪ Luas Areal Sawah (A) = 97.81
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa

W = 0.408 m

h = 0.431 m

b = 0.591 m

D. SALURAN PEMBUANG Tc (SP 3)


Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.43 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1.00
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h2 + 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.3 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.3 + 1.76
2
= -0.59 ± √ 2.1
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.43 ( memenuhi ) h.2 = -1.022054 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ }
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan
▪ Luas Areal Sawah (A) = 97.809
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa

W = 0.408 m

h = 0.431 m

b = 0.591 m

E. SALURAN PEMBUANG Td (SP 4)


Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.43 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h2 + 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.3 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.3 + 1.76
2
= -0.59 ± √ 2.1
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.43 ( memenuhi ) h.2 = -1.022054 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan
▪ Luas Areal Sawah (A) = 97.81
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa
W = 0.408 m

h = 0.431 m

b = 0.591 m

F. SALURAN PEMBUANG Te (SP 5)


Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.43 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h2 + 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.3 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.3 + 1.76
2
= -0.59 ± √ 2.1
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.43 ( memenuhi ) h.2 = -1.022054 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan :
▪ Luas Areal Sawah (A) = 97.81
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa

W = 0.408 m

h = 0.431 m

b = 0.591 m

G. SALURAN PEMBUANG Te (SP 6)


Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.43 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h2 + 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.3 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.3 + 1.76
2
= -0.59 ± √ 2.1
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.43 ( memenuhi ) h.2 = -1.022054 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan :
▪ Luas Areal Sawah (A) = 97.81
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa

W = 0.408 m

h = 0.431 m

b = 0.591 m
H. SALURAN PEMBUANG Te (SP 7)
Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.43 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h2 + 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.3 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.3 + 1.76
2
= -0.59 ± √ 2.1
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.43 ( memenuhi ) h.2 = -1.022054 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan :
▪ Luas Areal Sawah (A) = 97.81
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa

W = 0.408 m

h = 0.431 m

b = 0.591 m
I. SALURAN PEMBUANG Te (SP 8)
Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.43 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h2 + 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.3 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.3 + 1.76
2
= -0.59 ± √ 2.1
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.43 ( memenuhi ) h.2 = -1.022054 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan :
▪ Luas Areal Sawah (A) = 97.81
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408

Sketsa

W = 0.408 m

h = 0.431 m

b = 0.591 m
J. SALURAN PEMBUANG Te (SP 9)
Diketahui :
A = 97.81 Ha
Q = 0.011 M³/dt

D
DM =
3 . 8.64
3
=
3 . 0.12
= 0.116 Lt/dt/Ha
Catatan:
- Untuk Lapisan Pembuang Permukaan di ambil selama 3 Hari mm D = 3
- Untuk 1 mm/hari = 1/8,64 Lt/dt/Ha
Maka debit pembuangan rencana dari sawah dihitung :
QD = 1.62 . DM . A 0.9 (Buku KP 03 hal 66-67)
= 1.62 . 0.116 . 97.81 0.92
= 12.710 Lt/dt
= 0.127 M³/dt
Untuk Harga Nilai :
m = 1.00
n = 1.20
K = 35.00

V = 0.42 . Q 0.182
= 0.42 . 0.127 0.182
= 0.289 m/dt

h = 0.775 . Q 0.282
= 0.775 . 0.127 0.282
= 0.43 m

n = 3.96 . Q 0.25 - m
= 3.96 . 0.127 0.25 - 1
= 1.364 m

b = n . h
= 1.364 . 0.43
= 0.591
= 0.59 m

Kontrol h akibat pembulatan b = 0.59 m


Q
F =
V
= 0.127
0.289
= 0.440 M²
Disubtitusi :
F = (b+m.h) h
F = bh + mh2
0.440 = 0.59 h + 1.00 h2
1 h 2
+ 0.59 h - 0.44 = 0

-b± √ b2 - 4 . a. c
h.1.2 =
2.a
= -0.59 ± √ 0.3 -4 . 1 . -0.4
2 . 1
= -0.59 ± √ 0.3 + 1.76
2
= -0.59 ± √ 2.1
2
= -0.59 ± 1.45
2
= -0.59 + 1.45 = -0.59 - 1.45
2 2
h.1 = 0.43 ( memenuhi ) h.2 = -1.022054 ( Tidak memenuhi )

Keliling Basah (P)


P = b + 2h √ M² + 1
= 0.59 + 2 . 0.431 √ 1 ² + 1
= 0.591 + 0.862 . 1.414
= 1.810 M

Jari-Jari Hidrolis ( R )
F
R =
P
0.440
=
1.810
= 0.243 M
R²/³ = 0.390 M
Kemiringan Saluran ( I )
V ²
I =
{ K . R²/³ }
0.289 ²
=
{ 35.00 . 0.390 }
= 0.00045

Tinggi Jagaan (W)


W = 0.25 . h + 0.30
= 0.25 . 0.43 + 0.30
= 0.408 M

Kesimpulan :
▪ Luas Areal Sawah (A) = 97.81
▪ Debit Rencana (Q) = 0.011
▪ Modulus pembuang (DM) = 0.116
▪ Debit pembuang rencana (QD) = 0.127
▪ Kecepatan Aliran (V) = 0.289
▪ koefisien Kekasaran sticler (K) = 35.000
▪ Perbandingan Lebar Dasar Saluran Dengan Kadar Air (n) = 1.36
▪ Kemiringan Talud (M) = 1.000
▪ Tinggi Air Saluran (h) = 0.431
▪ Lebar Dasar Saluran (b) = 0.59
▪ Keliling Basah (P) = 1.810
▪ Jari-Jari Hidrolis (R) = 0.243
▪ Kemiringan Saluran (I) = 0.00045
▪ Tinggi Jagaan (W) = 0.408
Sketsa

W = 0.408 m

h = 0.431 m

b = 0.591 m
KP 03 hal 66-67)
k memenuhi )

Ha 880
M³/dt 0.098
Lt/dt/Ha 0.116
M³/dt 0.959
M/dt 0.417
M 35.000
M 2.919
1.000
M 0.766
M 2.236
M 4.404
M 0.523
M 0.000
M 0.492
k memenuhi )
Ha 97.49
M³/dt 0.014
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.288
M 35.000
M 1.363
1.000
M 0.431
M 0.590
M 1.808
M 0.243
M 0.000
M 0.408
k memenuhi )

Ha 97.81
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
dak memenuhi )
Ha 97.809
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
k memenuhi )

Ha 97.81
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
k memenuhi )
Ha 97.81
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
k memenuhi )
Ha 97.81
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
k memenuhi )

Ha 97.81
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
k memenuhi )
Ha 97.81
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
k memenuhi )

Ha 97.81
M³/dt 0.011
Lt/dt/Ha 0.116
M³/dt 0.127
M/dt 0.289
M 35.000
M 1.364
1.000
M 0.431
M 0.591
M 1.810
M 0.243
M 0.000
M 0.408
REKAPITULASI PERENCANAAN JARINGAN SALURAN PEMBUANG

NAMA PANJANG QD DIMENSI SALURAN


SALURAN SALURAN (m) M³/dt A V h n b p
SALURAN PEMBUANG
2035.00 0.96 879.96 0.42 0.77 2.92 2.24 4.40
INDUK (S.I)

SALURAN PEMBUANG
2010.00 0.13 97.49 0.29 0.43 1.36 0.59 1.81
Tersier a ( Ta ) / S1

SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier b ( Tb ) / S2
SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier c ( Tc ) / S3
SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier d ( Td ) / S4
SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier e ( Te ) / S5
SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier f ( Tf ) / S6
SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier g ( Tg ) / S7
SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier h ( Tf ) / S8
SALURAN PEMBUANG
2010.00 0.13 97.81 0.29 0.43 1.36 0.59 1.81
Tersier i ( Tg ) / S9
AN PEMBUANG

MENSI SALURAN
R I W K M

0.52 0.00034 0.49 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00

0.24 0.00045 0.41 35.00 1.00


Menentukan Luas Lahan yang Dilayani oleh Saluran Pembuang

A. SALURAN PEMBUANG INDUK (SP.I)

L = 2,035.00 m
A = Ta + Tb + Tc + Td + Te
= 97.49 + 97.81 + 97.81 + 97.81 97.81
= 880 Ha

B. SALURAN PEMBUANG Ta (SP 1)

L = 2,010.00 m
A = Ta
= 97.49 Ha

C. SALURAN PEMBUANG Tb (SP 2)

L = 2,010.00 m
A = Tb
= 97.81 Ha

D. SALURAN PEMBUANG Tc (SP 3)

L = 2,010.00 m
A = Tc
= 97.81 Ha

E. SALURAN PEMBUANG Td (SP 4)

L = 2,010.00 m
A = Td
= 97.81 Ha

F. SALURAN PEMBUANG Te (SP 5)

L = 2,010.00 m
A = Te
= 97.81 Ha

G. SALURAN PEMBUANG Te (SP 6)

L = 2,010.00 m
A = Tf
= 97.81 Ha

H. SALURAN PEMBUANG Te (SP 7)

L = 2,010.00 m
A = Tg
= 97.81 Ha

I. SALURAN PEMBUANG Te (SP 8)

L = 2,010.00 m
A = Th
= 97.81 Ha

J. SALURAN PEMBUANG Te (SP 9)

L = 2,010.00 m
A = Ti
= 97.81 Ha
+ Tf + Tg + Th + Ti
97.81 97.81 97.81 97.81