Vous êtes sur la page 1sur 3

CUADRO DE CAUDALES PERFIL DE CALLE 28 DE JULIO

Q
LONGITUD Q PROPIO Q LATERAL Q TOTAL
TRAMO CD ANTERIOR
TRAMO(M) (LT/SG.) (LT/SG.) (LT/SG.)
(LT/SG.)
BP34.-BP35 0.00256 21.30 0.05 0.00 0.00 0.05
BP35.-BP36 0.00256 48.90 0.13 0.05 0.00 0.18
BP36.-BP37 0.00256 31.11 0.08 0.18 0.00 0.26
BP37.-BP39 0.00256 31.11 0.08 0.26 0.00 0.34
BP39.-BP40 0.00256 40.00 0.10 0.34 0.00 0.44
BP40.-BP42 0.00256 40.60 0.10 0.44 0.00 0.55
BP42.-BP43 0.00256 52.91 0.14 0.55 0.00 0.68
BP43.-BP44 0.00256 39.29 0.10 0.68 0.00 0.78
BP44.-BP45 0.00256 20.13 0.05 0.78 0.00 0.83
BP45.-BP46 0.00256 50.92 0.13 0.83 0.00 0.96
BP46.-BP47 0.00256 48.06 0.12 0.96 0.00 1.09
BP47.-BP48 0.00256 38.19 0.10 1.09 0.00 1.19
BP48.-BP49 0.00256 57.11 0.15 1.19 0.00 1.33

LONG.TOTAL SISTEMA N° 01 519.63

CUADRO DE CAUDALES PERFIL DE CALLE 28 DE JULIO

TRAMO BUZON LONGITUD COTA TAPA COTA FONDO BUZON PENDIENTE Qreal DIAMETRO DIAMETRO Qtll Descar Prop. Vtll Hproporc. Veloc.Propr. Vreal Hr H trabajo Alt. Buz. Alt. Buz. Vol. Entre
DEL AL ENTRE BUZONES INICIAL FINAL INICIAL FINAL m/m (lt/sg) (pulgadas) (pulgadas) (lt/sg) Qreal/Qtll (m/sg) (m/sg) (m/sg) cm. % Inicial(m) Final(m) Buz.(m3)
BP34.-BP35 34 35 21.30 3269.69 3268.50 3268.49 3267.30 0.06 0.05 0.47 8 105.212 0.001 3.242 0.076 0.27 0.86 1.553 7.64 1.200 1.200 20.45
BP35.-BP36 35 36 48.90 3268.50 3265.15 3267.30 3263.95 0.07 0.18 0.71 8 89.621 0.002 3.590 0.080 0.27 0.99 1.617 7.96 1.200 1.200 46.94
BP36.-BP37 36 37 31.11 3265.15 3261.27 3263.95 3260.07 0.12 0.26 0.72 8 120.923 0.002 4.844 0.080 0.28 1.34 1.623 7.99 1.200 1.200 29.87
BP37.-BP39 37 39 31.11 3261.27 3257.25 3260.07 3256.05 0.13 0.34 0.80 8 123.085 0.003 4.931 0.081 0.28 1.38 1.650 8.12 1.200 1.200 29.87
BP39.-BP40 39 40 40.00 3257.25 3246.57 3256.05 3244.57 0.29 0.44 0.76 8 183.436 0.002 7.348 0.080 0.28 2.04 1.635 8.04 1.200 2.000 51.20
BP40.-BP42 40 42 40.60 3246.57 3244.00 3244.57 3242.80 0.04 0.55 1.17 8 71.493 0.008 2.864 0.091 0.31 0.88 1.856 9.13 2.000 1.200 51.97
BP42.-BP43 42 43 52.91 3244.00 3239.78 3242.80 3238.58 0.08 0.68 1.13 8 96.701 0.007 3.874 0.090 0.30 1.18 1.832 9.01 1.200 1.200 50.79
BP43.-BP44 43 44 39.29 3239.78 3236.86 3238.58 3235.66 0.07 0.78 1.21 8 93.345 0.008 3.739 0.093 0.31 1.17 1.887 9.29 1.200 1.200 37.72
BP44.-BP45 44 45 20.13 3236.86 3235.10 3235.66 3233.90 0.09 0.83 1.20 8 101.246 0.008 4.056 0.093 0.31 1.26 1.881 9.26 1.200 1.200 19.32
BP45.-BP46 45 46 50.92 3235.10 3228.00 3233.90 3226.80 0.14 0.96 1.16 8 127.858 0.008 5.122 0.091 0.31 1.58 1.852 9.12 1.200 1.200 48.88
BP46.-BP47 46 47 48.06 3228.00 3227.71 3226.80 3226.51 0.01 1.09 2.19 8 26.598 0.041 1.065 0.153 0.46 0.49 3.106 15.29 1.200 1.200 46.14
BP47.-BP48 47 48 38.19 3227.71 3227.48 3226.51 3225.48 0.03 1.19 1.71 8 56.232 0.021 2.253 0.118 0.38 0.85 2.393 11.78 1.200 2.000 48.88
BP48.-BP49 48 49 57.11 3227.48 3224.50 3225.48 3223.30 0.04 1.33 1.67 8 66.898 0.020 2.680 0.116 0.37 1.00 2.348 11.56 2.000 1.200 73.10

Volumen a excavar: 555.13

CUADRO DE CAUDALES PERFIL DE CALLE SAN MARTIN

Q
LONGITUD Q PROPIO Q LATERAL Q TOTAL
TRAMO CD TRAMO(M) ANTERIOR
(LT/SG.) (LT/SG.) (LT/SG.)
(LT/SG.)
BP11.-BP12 0.00256 20.00 0.05 0.00 0.00 0.05
BP12.-BP13 0.00256 39.11 0.10 0.05 0.00 0.15
BP13.-BP14 0.00256 14.43 0.04 0.15 0.00 0.19
BP14.-BP15 0.00256 20.75 0.05 0.19 0.00 0.24
BP15.-BP16 0.00256 47.00 0.12 0.24 0.00 0.36
BP16.-BP17 0.00256 26.92 0.07 0.36 0.00 0.43
BP17.-BP18 0.00256 31.79 0.08 0.43 0.00 0.51
BP18.-BP20 0.00256 15.68 0.04 0.51 0.00 0.55
BP20.-BP21 0.00256 19.15 0.05 0.55 0.00 0.60
BP21.-BP22 0.00256 26.68 0.07 0.60 0.00 0.67
BP22.-BP23 0.00256 30.38 0.08 0.67 0.00 0.75
BP23.-BP30 0.00256 17.88 0.05 0.75 0.00 0.79
BP30.-BP31 0.00256 42.41 0.11 0.79 1.00 0.90
BP31.-BP32 0.00256 46.91 0.12 0.90 2.00 1.02
BP32.-BP33 0.00256 18.47 0.05 1.02 3.00 1.07
BP33.-BP45 0.00256 17.29 0.04 1.07 4.00 1.11
LONG.TOTAL SISTEMA N° 01 434.85

CUADRO DE CAUDALES PERFIL DE CALLE SAN MARTIN

TRAMO BUZON LONGITUD COTA TAPA COTA FONDO BUZON PENDIENTE Qreal DIAMETRO DIAMETRO Qtll Descar Prop. Vtll Hproporc. Veloc.Propr. Vreal Hr H trabajo Alt. Buz. Alt. Buz. Vol. Entre
DEL AL ENTRE BUZONES INICIAL FINAL INICIAL FINAL m/m (lt/sg) (pulgadas) (pulgadas) (lt/sg) Qreal/Qtll (m/sg) (m/sg) (m/sg) cm. % Inicial(m) Final(m) Buz.(m3)
BP11.-BP12 11 12 20.00 3283.59 3281.69 3282.39 3280.49 0.10 0.05 0.41 8 137.196 0.000 4.228 0.076 0.26 1.12 1.546 7.61 1.200 1.200 19.20
BP12.-BP13 12 13 39.11 3281.69 3272.47 3280.49 3271.27 0.24 0.15 0.53 8 216.124 0.001 6.660 0.077 0.27 1.78 1.561 7.68 1.200 1.200 37.55
BP13.-BP14 13 14 14.43 3272.47 3272.34 3271.27 3271.14 0.01 0.19 1.05 8 42.249 0.004 1.302 0.085 0.29 0.38 1.722 8.48 1.200 1.200 13.85
BP14.-BP15 14 15 20.75 3272.34 3273.78 3271.14 3270.98 0.01 0.24 1.19 8 39.087 0.006 1.204 0.088 0.30 0.36 1.795 8.84 1.200 2.800 33.20
BP15.-BP16 15 16 47.00 3273.78 3267.07 3270.98 3265.87 0.11 0.36 0.84 8 146.772 0.002 4.523 0.081 0.28 1.26 1.637 8.06 2.800 1.200 75.20
BP16.-BP17 16 17 26.92 3267.07 3263.36 3265.87 3262.16 0.14 0.43 0.86 8 165.246 0.003 5.092 0.081 0.28 1.42 1.643 8.09 1.200 1.200 25.84
BP17.-BP18 17 18 31.79 3263.36 3262.12 3262.16 3260.92 0.04 0.51 1.16 8 87.912 0.006 2.709 0.088 0.30 0.81 1.780 8.76 1.200 1.200 30.52
BP18.-BP20 18 20 15.68 3262.12 3260.00 3260.92 3258.80 0.14 0.55 0.95 8 163.672 0.003 5.044 0.082 0.28 1.43 1.676 8.25 1.200 1.200 15.05
BP20.-BP21 20 21 19.15 3260.00 3259.81 3258.80 3258.61 0.01 0.60 1.60 8 44.338 0.014 1.366 0.103 0.34 0.47 2.099 10.33 1.200 1.200 18.38
BP21.-BP22 21 22 26.68 3259.81 3257.63 3258.61 3256.43 0.08 0.67 1.12 8 127.238 0.005 3.921 0.086 0.29 1.16 1.757 8.65 1.200 1.200 25.61
BP22.-BP23 22 23 30.38 3257.63 3253.81 3256.43 3252.61 0.13 0.75 1.08 8 157.841 0.005 4.864 0.085 0.29 1.42 1.734 8.53 1.200 1.200 29.16
BP23.-BP30 23 30 17.88 3253.81 3250.94 3252.61 3249.74 0.16 0.79 1.05 8 178.336 0.004 5.495 0.085 0.29 1.59 1.722 8.47 1.200 1.200 17.16
BP30.-BP31 30 31 42.41 3250.94 3246.87 3249.74 3245.67 0.10 0.90 1.21 8 137.894 0.007 4.249 0.089 0.30 1.28 1.811 8.91 1.200 1.200 40.71
BP31.-BP32 31 32 46.91 3246.87 3241.29 3245.67 3240.09 0.12 1.02 1.22 8 153.520 0.007 4.731 0.089 0.30 1.43 1.815 8.93 1.200 1.200 45.03
BP32.-BP33 32 33 18.47 3241.29 3240.24 3240.09 3239.04 0.06 1.07 1.43 8 106.131 0.010 3.270 0.096 0.32 1.05 1.957 9.63 1.200 1.200 17.73
BP33.-BP45 33 45 17.29 3240.24 3235.10 3239.04 3233.90 0.30 1.11 1.06 8 242.697 0.005 7.479 0.085 0.29 2.17 1.728 8.50 1.200 1.200 16.60

Volumen a excavar: 460.82

CUADRO DE CAUDALES PERFIL DE CALLE PRINCIPAL

Q
LONGITUD Q PROPIO Q LATERAL Q TOTAL
TRAMO CD TRAMO(M) ANTERIOR
(LT/SG.) (LT/SG.) (LT/SG.)
(LT/SG.)
BP01.-BP02 0.00256 80.36 0.21 0.00 0.00 0.21
BP02.-BP03 0.00256 79.95 0.20 0.21 0.00 0.41
BP03.-BP04 0.00256 32.94 0.08 0.41 0.00 0.50
BP04.-BP05 0.00256 25.00 0.06 0.50 0.00 0.56
BP05.-BP06 0.00256 25.00 0.06 0.56 0.00 0.62
BP06.-BP15 0.00256 25.00 0.06 0.62 0.00 0.69

LONG.TOTAL SISTEMA N° 01 268.25

CUADRO DE CAUDALES PERFIL DE CALLE PRINCIPAL

TRAMO BUZON LONGITUD COTA TAPA COTA FONDO BUZON PENDIENTE Qreal DIAMETRO DIAMETRO Qtll Descar Prop. Vtll Hproporc. Veloc.Propr. Vreal Hr H trabajo Alt. Buz. Alt. Buz. Vol. Entre
DEL AL ENTRE BUZONES INICIAL FINAL INICIAL FINAL m/m (lt/sg) (pulgadas) (pulgadas) (lt/sg) Qreal/Qtll (m/sg) (m/sg) (m/sg) cm. % Inicial(m) Final(m) Buz.(m3)
BP01.-BP02 1 2 80.36 3305.81 3299.12 3304.61 3297.92 0.08 0.21 0.72 8 128.432 0.002 3.958 0.079 0.27 1.08 1.600 7.87 1.200 1.200 77.15
BP02.-BP03 2 3 79.95 3299.12 3291.45 3297.92 3290.25 0.10 0.41 0.90 8 137.870 0.003 4.248 0.082 0.28 1.19 1.659 8.17 1.200 1.200 76.75
BP03.-BP04 3 4 32.94 3291.45 3291.07 3290.25 3289.77 0.01 0.50 1.38 8 53.733 0.009 1.656 0.095 0.32 0.53 1.922 9.46 1.200 1.300 32.94
BP04.-BP05 4 5 25.00 3291.07 3287.95 3289.77 3286.75 0.12 0.56 0.97 8 154.709 0.004 4.767 0.083 0.28 1.36 1.686 8.30 1.300 1.200 25.00
BP05.-BP06 5 6 25.00 3287.95 3282.84 3286.75 3281.64 0.20 0.62 0.92 8 201.243 0.003 6.201 0.082 0.28 1.75 1.664 8.19 1.200 1.200 24.00
BP06.-BP15 6 15 25.00 3282.84 3273.78 3281.64 3272.58 0.36 0.69 0.85 8 267.963 0.003 8.257 0.081 0.28 2.30 1.641 8.08 1.200 1.200 24.00

Volumen a excavar: 259.84


CUADRO DE CAUDALES PERFIL DE CALLE N° 2

Q
LONGITUD Q PROPIO Q LATERAL Q TOTAL
TRAMO CD ANTERIOR
TRAMO(M) (LT/SG.) (LT/SG.) (LT/SG.)
(LT/SG.)
BE07.-BE08 0.00256 35.19 0.09 0.00 0.00 0.09
BE08.-BE09 0.00256 44.23 0.11 0.09 0.00 0.20
BE09.-BE10 0.00256 33.69 0.09 0.20 0.00 0.29
BE10.-BE13 0.00256 4.29 0.01 0.29 0.00 0.30

LONG.TOTAL SISTEMA N° 01 117.4

CUADRO DE CAUDALES PERFIL DE CALLE N° 2

TRAMO BUZON LONGITUD COTA TAPA COTA FONDO BUZON PENDIENTE Qreal DIAMETRO DIAMETRO Qtll Descar Prop. Vtll Hproporc. Veloc.Propr. Vreal Hr H trabajo Alt. Buz. Alt. Buz. Vol. Entre
DEL AL ENTRE BUZONES INICIAL FINAL INICIAL FINAL m/m (lt/sg) (pulgadas) (pulgadas) (lt/sg) Qreal/Qtll (m/sg) (m/sg) (m/sg) cm. % Inicial(m) Final(m) Buz.(m3)
BE07.-BE08 7 8 35.19 3250.88 3249.71 3249.78 3248.51 0.04 0.09 0.61 8 84.562 0.001 2.606 0.078 0.27 0.70 1.577 7.76 1.100 1.200 32.37
BE08.-BE09 8 9 44.23 3249.71 3243.87 3248.51 3242.67 0.13 0.20 0.65 8 124.420 0.002 4.984 0.079 0.27 1.36 1.601 7.88 1.200 1.200 42.46
BE09.-BE10 9 10 33.69 3243.87 3239.34 3242.67 3238.24 0.13 0.29 0.75 9 169.988 0.002 5.380 0.079 0.27 1.47 1.805 7.90 1.200 1.100 30.99
BE10.-BE13 10 13 4.29 3239.34 3235.47 3238.24 3234.47 0.88 0.30 0.53 10 582.027 0.001 14.921 0.076 0.27 3.96 1.941 7.64 1.100 1.000 3.60

Volumen a excavar: 109.43