Capacity Table of Priyadarshini Jurala Project

(as per Hydrographic survey 2012; implemented from 01.06.2016)


Sl Elevation Elevation Area Capacity Capacity Live Capacity
Remarks
No in mts in Ft in M Sqm in MCFt (TMC) (TMC)

1 297.479 975.981 0.000 0 0.000 0.000


2 299.009 981.001 0.000 0 0.000 0.000
3 300.533 986.001 0.004 0 0.000 0.000
4 300.838 987.001 0.006 0 0.000 0.000
5 301.447 988.999 0.015 0 0.000 0.000
6 301.752 990.000 0.020 1 0.001 0.000
7 302.057 991.001 0.026 1 0.001 0.000
8 303.000 994.094 0.054 2 0.002 0.000
9 304.000 997.375 0.124 5 0.005 0.000
10 305.000 1,000.656 0.271 12 0.012 0.000
11 305.500 1,002.297 0.392 17 0.017 0.000
12 306.000 1,003.937 0.603 27 0.027 0.000
13 306.500 1,005.577 0.847 39 0.039 0.000
14 307.000 1,007.218 1.187 57 0.057 0.000
15 307.500 1,008.858 1.783 83 0.083 0.000
16 308.000 1,010.499 2.908 124 0.124 0.000
17 308.500 1,012.139 4.275 187 0.187 0.000
18 309.000 1,013.780 5.822 276 0.276 0.000
19 309.500 1,015.420 7.280 392 0.392 0.000
20 309.982 1,017.001 8.820 527 0.527 0.000 Spillway Crest
21 310.000 1,017.060 8.884 533 0.533 0.000
22 310.050 1,017.224 9.062 550 0.550 0.000
23 310.100 1,017.388 9.239 566 0.566 0.000
24 310.150 1,017.552 9.417 583 0.583 0.000
25 310.200 1,017.717 9.594 599 0.599 0.000
26 310.250 1,017.881 9.772 616 0.616 0.000
27 310.286 1,017.999 9.900 628 0.628 0.000
28 310.300 1,018.045 9.952 633 0.633 0.000
29 310.350 1,018.209 10.135 652 0.652 0.000
30 310.400 1,018.373 10.319 670 0.670 0.000
31 310.450 1,018.537 10.503 688 0.688 0.000
32 310.500 1,018.701 10.687 707 0.707 0.000
33 310.550 1,018.865 10.871 725 0.725 0.000
34 310.591 1,018.999 11.022 740 0.740 0.000
35 310.600 1,019.029 11.057 744 0.744 0.000
36 310.650 1,019.193 11.254 764 0.764 0.000
37 310.700 1,019.357 11.450 785 0.785 0.000
38 310.750 1,019.521 11.647 806 0.806 0.000
39 310.800 1,019.685 11.844 826 0.826 0.000
40 310.850 1,019.849 12.040 847 0.847 0.000
41 310.896 1,020.000 12.221 866 0.866 0.000
42 310.900 1,020.013 12.236 868 0.868 0.000
43 310.950 1,020.177 12.426 890 0.890 0.000
44 311.000 1,020.341 12.616 913 0.913 0.000
45 311.050 1,020.505 12.805 935 0.935 0.000
46 311.100 1,020.669 12.995 958 0.958 0.000
47 311.150 1,020.833 13.185 980 0.980 0.000
48 311.200 1,020.997 13.374 1003 1.003 0.000
49 311.201 1,021.001 13.378 1003 1.003 0.000
50 311.250 1,021.161 13.558 1027 1.027 0.000
51 311.300 1,021.325 13.742 1052 1.052 0.000
52 311.350 1,021.490 13.925 1076 1.076 0.000
53 311.400 1,021.654 14.109 1101 1.101 0.000
54 311.450 1,021.818 14.292 1125 1.125 0.000
55 311.500 1,021.982 14.476 1150 1.150 0.000
Capacity Table of Priyadarshini Jurala Project
(as per Hydrographic survey 2012; implemented from 01.06.2016)
Sl Elevation Elevation Area Capacity Capacity Live Capacity
Remarks
No in mts in Ft in M Sqm in MCFt (TMC) (TMC)

56 311.506 1,022.001 14.498 1153 1.153 0.000


57 311.550 1,022.146 14.664 1176 1.176 0.000
58 311.600 1,022.310 14.853 1203 1.203 0.000
59 311.650 1,022.474 15.041 1230 1.230 0.000
60 311.700 1,022.638 15.230 1256 1.256 0.000
61 311.750 1,022.802 15.419 1283 1.283 0.000
62 311.800 1,022.966 15.607 1310 1.310 0.000
63 311.810 1,022.999 15.645 1315 1.315 0.000
64 311.850 1,023.130 15.789 1338 1.338 0.000
65 311.900 1,023.294 15.970 1367 1.367 0.000
66 311.950 1,023.458 16.150 1395 1.395 0.000
67 312.000 1,023.622 16.330 1424 1.424 0.000
68 312.050 1,023.786 16.511 1453 1.453 0.000
69 312.100 1,023.950 16.691 1481 1.481 0.000
70 312.115 1,023.999 16.745 1490 1.490 0.000
71 312.150 1,024.114 16.880 1511 1.511 0.000
72 312.200 1,024.278 17.072 1542 1.542 0.000
73 312.250 1,024.442 17.265 1572 1.572 0.000
74 312.300 1,024.606 17.458 1603 1.603 0.000
75 312.350 1,024.770 17.650 1633 1.633 0.000
76 312.400 1,024.934 17.843 1664 1.664 0.000
77 312.420 1,025.000 17.920 1676 1.676 0.000 Sill of Canals
78 312.450 1,025.098 18.050 1696 1.696 0.000
79 312.500 1,025.262 18.266 1728 1.728 0.000
80 312.550 1,025.427 18.483 1761 1.761 0.000
81 312.600 1,025.591 18.700 1794 1.794 0.000
82 312.650 1,025.755 18.916 1827 1.827 0.000
83 312.700 1,025.919 19.133 1860 1.860 0.000
84 312.725 1,026.001 19.241 1876 1.876 0.000
85 312.750 1,026.083 19.357 1894 1.894 0.000
86 312.800 1,026.247 19.589 1929 1.929 0.000
87 312.850 1,026.411 19.821 1964 1.964 0.000
88 312.900 1,026.575 20.053 1999 1.999 0.000
89 312.950 1,026.739 20.286 2035 2.035 0.000
90 313.000 1,026.903 20.518 2070 2.070 0.000
91 313.030 1,027.001 20.657 2091 2.091 0.000
92 313.050 1,027.067 20.756 2106 2.106 0.000
93 313.100 1,027.231 21.004 2144 2.144 0.000
94 313.150 1,027.395 21.252 2182 2.182 0.000
95 313.200 1,027.559 21.500 2220 2.220 0.000
96 313.250 1,027.723 21.748 2257 2.257 0.000
97 313.300 1,027.887 21.995 2295 2.295 0.000
98 313.334 1,027.999 22.164 2321 2.321 0.000
99 313.350 1,028.051 22.241 2334 2.334 0.000
100 313.400 1,028.215 22.481 2374 2.374 0.000
101 313.450 1,028.379 22.721 2415 2.415 0.000
102 313.500 1,028.543 22.961 2455 2.455 0.000
103 313.550 1,028.707 23.202 2496 2.496 0.000
104 313.600 1,028.871 23.442 2536 2.536 0.000
105 313.639 1,028.999 23.629 2568 2.568 0.000
Capacity Table of Priyadarshini Jurala Project
(as per Hydrographic survey 2012; implemented from 01.06.2016)
Sl Elevation Elevation Area Capacity Capacity Live Capacity
Remarks
No in mts in Ft in M Sqm in MCFt (TMC) (TMC)

106 313.650 1,029.035 23.677 2577 2.577 0.000


107 313.700 1,029.199 23.897 2620 2.620 0.000
108 313.750 1,029.364 24.117 2663 2.663 0.000
109 313.800 1,029.528 24.337 2706 2.706 0.000
110 313.850 1,029.692 24.557 2749 2.749 0.000
111 313.900 1,029.856 24.777 2791 2.791 0.000
112 313.944 1,030.000 24.970 2829 2.829 0.000
113 313.950 1,030.020 24.998 2834 2.834 0.000
114 314.000 1,030.184 25.236 2880 2.880 0.000
115 314.050 1,030.348 25.473 2925 2.925 0.000
116 314.100 1,030.512 25.711 2971 2.971 0.000
117 314.150 1,030.676 25.948 3016 3.016 0.000
118 314.200 1,030.840 26.185 3061 3.061 0.000
119 314.249 1,031.001 26.418 3106 3.106 0.000
120 314.250 1,031.004 26.423 3107 3.107 0.000
121 314.300 1,031.168 26.663 3155 3.155 0.000
122 314.350 1,031.332 26.904 3203 3.203 0.000
123 314.400 1,031.496 27.144 3251 3.251 0.000
124 314.450 1,031.660 27.385 3298 3.298 0.000
125 314.500 1,031.824 27.625 3346 3.346 0.000
126 314.550 1,031.988 27.866 3394 3.394 0.000
127 314.554 1,032.001 27.885 3398 3.398 0.000
128 314.600 1,032.152 28.128 3445 3.445 0.000
129 314.650 1,032.316 28.391 3496 3.496 0.000
130 314.700 1,032.480 28.655 3546 3.546 0.000
131 314.750 1,032.644 28.919 3597 3.597 0.000
132 314.800 1,032.808 29.182 3648 3.648 0.000
133 314.850 1,032.972 29.446 3699 3.699 0.000
134 314.858 1,032.999 29.488 3707 3.707 0.000 MDDL
135 314.900 1,033.136 30.244 3755 3.755 0.048
136 314.950 1,033.301 31.143 3811 3.811 0.104
137 315.000 1,033.465 32.043 3868 3.868 0.161
138 315.050 1,033.629 32.942 3925 3.925 0.218
139 315.100 1,033.793 33.842 3982 3.982 0.275
140 315.150 1,033.957 34.741 4038 4.038 0.331
141 315.163 1,033.999 34.975 4053 4.053 0.346
142 315.200 1,034.121 35.088 4099 4.099 0.392
143 315.250 1,034.285 35.242 4162 4.162 0.455
144 315.300 1,034.449 35.395 4225 4.225 0.518
145 315.350 1,034.613 35.548 4287 4.287 0.580
146 315.400 1,034.777 35.702 4350 4.350 0.643
147 315.450 1,034.941 35.855 4412 4.412 0.705
148 315.468 1,035.000 35.910 4435 4.435 0.728
149 315.500 1,035.105 36.053 4476 4.476 0.769
150 315.550 1,035.269 36.278 4541 4.541 0.834
151 315.600 1,035.433 36.502 4605 4.605 0.898
152 315.650 1,035.597 36.726 4670 4.670 0.963
153 315.700 1,035.761 36.950 4734 4.734 1.027
154 315.750 1,035.925 37.175 4799 4.799 1.092
155 315.751 1,035.928 37.179 4800 4.800 1.093
Capacity Table of Priyadarshini Jurala Project
(as per Hydrographic survey 2012; implemented from 01.06.2016)
Sl Elevation Elevation Area Capacity Capacity Live Capacity
Remarks
No in mts in Ft in M Sqm in MCFt (TMC) (TMC)

156 315.800 1,036.089 37.700 4875 4.875 1.168


157 315.850 1,036.253 38.231 4951 4.951 1.244
158 315.900 1,036.417 38.762 5027 5.027 1.320
159 315.950 1,036.581 39.294 5104 5.104 1.397
160 316.000 1,036.745 39.825 5180 5.180 1.473
161 316.050 1,036.909 40.357 5256 5.256 1.549
162 316.100 1,037.073 40.888 5333 5.333 1.626
163 316.150 1,037.238 41.419 5409 5.409 1.702
164 316.200 1,037.402 41.951 5485 5.485 1.778
165 316.250 1,037.566 42.482 5562 5.562 1.855
166 316.300 1,037.730 43.013 5638 5.638 1.931
167 316.350 1,037.894 43.545 5714 5.714 2.007
168 316.400 1,038.058 44.076 5790 5.790 2.083
169 316.450 1,038.222 44.608 5867 5.867 2.160
170 316.500 1,038.386 45.139 5943 5.943 2.236
171 316.550 1,038.550 45.670 6019 6.019 2.312
172 316.600 1,038.714 46.202 6096 6.096 2.389
173 316.650 1,038.878 46.733 6172 6.172 2.465
174 316.700 1,039.042 47.264 6248 6.248 2.541
175 316.750 1,039.206 47.796 6325 6.325 2.618
176 316.800 1,039.370 48.327 6401 6.401 2.694
177 316.850 1,039.534 48.859 6477 6.477 2.770
178 316.900 1,039.698 49.390 6554 6.554 2.847
179 316.916 1,039.751 49.560 6578 6.578 2.871
180 316.950 1,039.862 49.808 6640 6.640 2.933
181 317.000 1,040.026 50.172 6731 6.731 3.024
182 317.050 1,040.190 50.536 6823 6.823 3.116
183 317.100 1,040.354 50.900 6914 6.914 3.207
184 317.150 1,040.518 51.264 7005 7.005 3.298
185 317.200 1,040.682 51.628 7097 7.097 3.390
186 317.250 1,040.846 51.993 7188 7.188 3.481
187 317.300 1,041.010 52.357 7279 7.279 3.572
188 317.350 1,041.175 52.721 7371 7.371 3.664
189 317.400 1,041.339 53.085 7462 7.462 3.755
190 317.450 1,041.503 53.449 7553 7.553 3.846
191 317.500 1,041.667 53.813 7645 7.645 3.938
192 317.516 1,041.719 53.930 7674 7.674 3.967
193 317.550 1,041.831 54.044 7740 7.740 4.033
194 317.600 1,041.995 54.211 7836 7.836 4.129
195 317.650 1,042.159 54.379 7933 7.933 4.226
196 317.700 1,042.323 54.546 8029 8.029 4.322
197 317.750 1,042.487 54.713 8126 8.126 4.419
198 317.800 1,042.651 54.881 8222 8.222 4.515
199 317.850 1,042.815 55.048 8319 8.319 4.612
200 317.900 1,042.979 55.216 8415 8.415 4.708
201 317.950 1,043.143 55.383 8512 8.512 4.805
202 317.964 1,043.189 55.430 8539 8.539 4.832
203 318.000 1,043.307 55.716 8611 8.611 4.904
204 318.050 1,043.471 56.114 8710 8.710 5.003
205 318.100 1,043.635 56.512 8810 8.810 5.103
Capacity Table of Priyadarshini Jurala Project
(as per Hydrographic survey 2012; implemented from 01.06.2016)
Sl Elevation Elevation Area Capacity Capacity Live Capacity
Remarks
No in mts in Ft in M Sqm in MCFt (TMC) (TMC)

206 318.150 1,043.799 56.910 8909 8.909 5.202


207 318.199 1,043.960 57.300 9007 9.007 5.300
208 318.200 1,043.963 57.304 9009 9.009 5.302
209 318.250 1,044.127 57.528 9111 9.111 5.404
210 318.300 1,044.291 57.751 9214 9.214 5.507
211 318.350 1,044.455 57.974 9316 9.316 5.609
212 318.400 1,044.619 58.197 9418 9.418 5.711
213 318.450 1,044.783 58.421 9521 9.521 5.814
214 318.479 1,044.879 58.550 9580 9.580 5.873
215 318.500 1,044.948 58.618 9624 9.624 5.917
216 318.516 1,045.000 58.670 9657 9.657 5.950 FRL
Evaporation in cusecs = 0.40874 x Area in M Sqm x Evaporation in mm