Excavation & Filling Quantity 28.02.2018 Estimated
Excavation & Filling Quantity 28.02.2018 Estimated
Quantity (m3) [According to Construction Drawings] Already Completed Quantity (m3) Balance Quantity (m3)
8 19+670 - 20+360 1,449,062.11 - 12,688.53 71,797.97 606,732.54 - 12,688.53 1,861.50 842,329.57 - - 69,936.47
26 25+370 - 25+770 357,973.90 - 5,220.45 104,303.35 280,381.47 - 4,872.70 - 77,592.43 - 347.75 104,303.35
28 25+950 - 26+230 285,673.93 - 3,157.03 40,959.09 23,539.83 - 562.68 - 262,134.10 - 2,594.35 40,959.09
Total 2,979,810.19 1,656,337.94 206,611.45 73,555.04 248,556.46 1,443,825.75 617,541.29 181,991.02 66,611.87 1,861.50 1,535,984.44 1,245,408.10 6,943.17 246,694.96