Matériaux Unité Distance de

provenance
Prix Usine Transport

(Dh/U) (Dh/Km) (Km)


T.V.O M3 120.00 2.00 30
Sable de mer M3 140.00 2.00 40
Sable Lavé M3 90.00 2.00 40
Gravier G1/G2 M3 50.00 3.00 20
Ciment en sac de 50 kg CPJ 45 Tn 1100.00 5.00 22
Ciment en sac de 50 kg CPJ 35 Tn 1040.00 5.00 22
Bois du coffrage (fardeau) F 3000.00 5.00 22
Acier kg 8.50 0.02 10
Point clous kg 11.00 0.02 10
Huille de couffrage Li 2.00 0.11 10
File d'attaches kg 10.00 0.02 10
BPE M3 800.00 0.03 10
Pierre séches M3 60.00 3.00 20
Treilles soudés R=13.2 M2 R 92.00 0.28 10
Polystyréne 4cm M2 27.00 0.41 10
Couvre joint de dilaltaion en bois ML 35.00 0.23 10
Agglos 20 * 20 * 20 U 5.00 0.08 10
Brique 6 trous U 2.00 0.01 10
Brique creuse 12 U 3.00 0.02 10
Brique creuse 8 U 3.00 0.01 10
Platre en sac de 50 kg Tn 560.00 5.00 22
Baguette d'angle ML 5.00 0.02 10
Feutres 36s M2 25.00 0.02 10
Bitume Kg 16.00 0.00 10
Gargouilles U 320.00 1.00 10
Tuyeau en P.V.C 110 HP ML 50.00 0.08 10
Tuyeau en P.V.C 200 HP ML 65.00 0.08 10
Grillage de signalisation ML 10.00 0.15 10
Plancher hourdis 25+5 M2 87.00 1.00 20
plancher hourdis 16+4 M2 82.00 1.00 20
plancher hourdis 12+4 M 79.00 1.00 20
Prix d'usine Manutensio n Prix ouvrier
+ Nbre ouvrier
transport TU Manutention Taux Perte

(Dh) (Dh) H (Dh) %


180.00 0 17.27 0.000 0.000 3%
220.00 0 17.27 0.000 0.000 3%
170.00 0 17.27 0.000 0.000 3%
110.00 0 17.27 0.000 0.000 3%
1210.00 2 17.27 1.200 41.448 3%
1150.00 2 17.27 1.200 41.448 3%
3110.00 1 818.00 0.160 130.880 0%
8.65 3 17.27 0.009 0.466 0%
11.16 1 17.27 0.010 0.173 5%
3.10 1 17.27 0.040 0.691 0%
10.16 1 17.27 0.010 0.173 5%
800.30 2 17.27 0.005 0.173 3%
120.00 0 17.27 0.000 0.000 3%
94.75 2 17.27 0.091 3.143 0%
31.05 0 17.27 0.000 0.000 0%
37.25 1 17.27 0.006 0.104 5%
5.80 4 17.27 0.006 0.414 5%
2.12 2 17.27 0.006 0.207 5%
3.20 4 17.27 0.006 0.414 5%
3.12 4 17.27 0.005 0.345 5%
670.00 2 17.27 1.200 41.448 3%
5.15 2 17.27 0.020 0.691 2%
25.15 3 17.27 0.020 1.036 2%
16.03 4 17.27 0.015 1.036 3%
330.00 0 17.27 0.000 0.000 0%
50.75 2 17.27 0.015 0.518 2%
65.75 2 17.27 0.015 0.518 2%
11.50 0 17.27 0.000 0.000 0%
107.00 4 17.27 0.006 0.414 5%
102.00 4 17.27 0.006 0.414 5%
99.00 4 17.27 0.006 0.414 5%
Prix perte TOTAL

(Dh) VRC
5.40 185.40
6.60 226.60
5.10 175.10
3.30 113.30
37.54 1288.99
35.74 1227.19
0.00 3240.88
0.00 9.12
0.57 11.90
0.00 3.79
0.52 10.85
24.01 824.49
3.60 123.60
0.00 97.89
0.00 31.05
1.87 39.22
0.31 6.53
0.12 2.44
0.18 3.80
0.17 3.64
21.34 732.79
0.12 5.96
0.52 26.71
0.51 17.58
0.00 330.00
1.03 52.29
1.33 67.59
0.00 11.50
5.37 112.79
5.12 107.54
4.97 104.39