DAYATAKA PRATAMA
MONITORING PEK. PINTU KAYU
PROYEK RUSUNAWA DAANMOGOT
PERIODE =
Lantai - Dasar ( )
Nomor
Type P1A P1A P2 P2 TANGGA
Pintu
P1 P2 P2 PJ2A PJ2A
PJ1B
Type P1 P1 P2 PJ2A P2 P2 P2
Pintu
TANGGA
Nomor P2B
PINTU TERPASANG
PENANDA NOMER UNIT TOTAL PINTU TERPASANG
PINTU BELUM TERPASANG P1A : 130
P2 : 284
P5 : 149
TOTAL 563
PEMASANGAN PINTU TOWER A
LANTAI UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5 UNIT 6 UNIT 7 UNIT 8 UNIT 9
2 4 4 4 4 4 4 4 4 4
3 4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4 4
5 4 4 4 4 4 4 4 4 4
6 4 4 4 4 4 4 4 4 4
7 3 3 4 4 3 4 4 4 4
8 4 4 4 4 4 4 4 3 3
9 4 4 4 4 4 3 4 4 4
10 1 1 1 2 3 2 2 3 3
11
12
13
14
15
16
UNIT KOMPLIT
UNIT BELUM KOMPLIT
UNIT 10 UNIT 11 UNIT 12 UNIT 13 UNIT 14 UNIT 15 UNIT 16 UNIT 17 UNIT 18 TOTAL PINTU
4 4 4 4 4 4 4 4 68
4 4 4 4 4 4 3 4 4 71
4 4 4 4 4 4 4 4 68
4 4 4 4 4 4 1 4 4 69
4 4 4 4 4 4 4 4 68
4 4 4 4 4 4 4 3 64
4 3 4 4 4 4 4 4 65
4 4 4 4 4 3 2 3 63
2 1 2 1 1 1 1 27
0
0
0
0
0
0
TOTAL PEMASANGAN 563