CONCRETE

Rb Rbt Rb,ser Rbt,ser Eb fctm


NAME
(daN/cm2) (daN/cm2) (daN/cm2) (daN/cm2) (daN/cm2) (N/mm2)
B3,5 21 2.6 27 3.9 9.50E+04 -
B5 28 3.7 35 5.5 1.30E+05 -
B7,5 45 4.8 55 7 1.60E+05 -
B10 60 5.6 75 8.5 1.90E+05 -
B12,5 75 6.6 95 10 2.15E+05 1.4
B15 85 7.5 110 11 2.40E+05 1.6
B20 115 9 150 13.5 2.75E+05 1.9
B22,5 130 9.5 165 14.5 2.85E+05 2.05
B25 145 10.5 185 15.5 3.00E+05 2.2
B30 170 11.5 220 17.5 3.25E+05 2.6
B35 195 13 255 19.5 3.45E+05 2.9
B40 220 14 290 21 3.60E+05 3.02
B45 250 15 320 22.5 3.70E+05 3.2
B50 275 16 360 24.5 3.80E+05 3.5
B55 300 17 395 26 3.90E+05 3.8
B60 330 18 430 27.5 3.95E+05 4.1
B65 350 18.5 465 28.5 4.00E+05 4.2
B70 370 19 500 30 4.10E+05 4.4
B80 410 21 570 33 4.20E+05 4.6
B90 440 21.5 640 36 4.25E+05 4.8
B100 475 22 710 38 4.30E+05 5.0
M75 28 3.7 35 5.5 1.30E+05 -
M100 45 4.8 55 7 1.60E+05 -
M125 60 5.6 75 8.5 1.90E+05 -
M150 75 6.6 95 10 2.15E+05 1.4
M200 85 7.5 110 11 2.40E+05 1.6
M250 115 9 150 13.5 2.75E+05 1.9
M300 130 9.5 165 14.5 2.85E+05 2.05
M350 145 10.5 185 15.5 3.00E+05 2.2
M400 170 11.5 220 17.5 3.25E+05 2.6
M450 195 13 255 19.5 3.45E+05 2.9
M500 220 14 290 21 3.60E+05 3.02
M600 250 15 320 22.5 3.70E+05 3.2
M650 275 16 360 24.5 3.80E+05 3.5
M700 300 17 395 26 3.90E+05 3.8
M800 330 18 430 27.5 3.95E+05 4.1
B100 Concrete Bê tông
Rb = 475 (daN/cm ) 2

Rbt = 22 (daN/cm2)
Rb,ser = 710 (daN/cm2)
Rbt,ser = 38 (daN/cm2)
Eb = 430000 (daN/cm2)
fctm = 5 (N/mm2)

Eurocode
fctm
TCVN fck
N/mm2 N/mm2
B12.5 C8/10 1.4
B15 C12/15 1.6
B20 C16/20 1.9
B22.5 C18/22 2.05
B25 C20/25 2.2
B30 C25/30 2.6
B35 C30/37 2.9
B40 C32/40 3.02
B45 C35/45 3.2
B50 C40/50 3.5
B55 C45/55 3.8
B60 C50/60 4.1
B65 C55/67 4.2
B70 C60/75 4.4
B80 C70/85 4.6
B90 C80/95 4.8
B100 C90/105 5