P10 P7 Esquema Comp. Total CA-50 Esquema Comp.

Total CA-50
Elemento Pos. Diam. Q. Elemento Pos. Diam. Q.
(cm) (cm) (cm) (kg) (cm) (cm) (cm) (kg)
Pos. Diam. Q. Comp. Total Pos. Diam. Q. Comp. Total P13 1 Ø16 16 272 16 107 395 6320 99.8 P1=P28=P29=P30 1 Ø12.5 4 285 285 1140 11.0
(cm) (cm) (cm) (cm) P53

95

25
5
2 Ø6.3 19 229 4351 10.7 2 Ø6.3 21 77 1617 4.0
1 Ø12.5 10 330 3300 1 Ø12.5 8 330 2640

5
15 9
5
3 Ø12.5 4 110 440 4.2

30
3 Ø6.3 38 27 1026 2.5 80
2 Ø6.3 19 229 4351 2 Ø6.3 19 189 3591 15

23
4 Ø16 16 205 3280 51.8

30
4 Ø6.3 3 70 210 0.5

5
175

3 Ø6.3 19 136 2584 3 Ø6.3 19 92 1748 7

92
5 Ø6.3 3 216 648 1.6 Total+10%: 21.7

5
4 Ø6.3 19 27 513 +2.880 4 Ø12.5 8 140 1120 6 Ø6.3 6
5
12

24 144 0.4
(x5): 108.5
P2 1 Ø12.5 4 285 285 1140 11.0
5 Ø12.5 10 140 1400 1º PAVIMENTO 5 Ø6.3 3 179 537 12

Total+10%: 183.5

25
2 Ø6.3 21 77 1617 4.0

5
6 Ø6.3 3 219 657 P14 1 Ø16 4 272 16 77 365 1460 23.0 9

3 Ø12.5 4 110 440 4.2

30
+2.880
7 Ø6.3 3 24 72 8N1 2 Ø12.5 6 365 365 2190 21.1 80

23
95
3 Ø6.3 19 229 4351 10.7 4 Ø6.3 3 70 210 0.5

5
8N1Ø12.5 C=330

5
1º PAVIMENTO 15 7

Total+10%: 21.7
10N1

49
4 Ø6.3 19 136 2584 6.3
P6

5
+2.220 1 Ø12.5 4 285 1140 11.0

330
15 285

N2+N3 c/15
8N1 8N1 5 Ø6.3 19
5
27 513 1.3

19Ø6.3

25
2 Ø6.3 21 5 77 1617 4.0
8N1Ø12.5

75

27
15

10N1Ø12.5 C=330
80

5 6 Ø16 4 160 640 10.1 9

30
B B 130
3 Ø12.5 4 110 440 4.2

30
+2.420 7 Ø12.5 6 145 870 8.4 80

30
115

N2+N3+N4 c/15
15

23
4 Ø6.3 3 70 210 0.5

330

5
92
5 8 Ø6.3 3 219 657 1.6
10N1 10N1 N3Ø6.3c/15 C=92
7

5
19Ø6.3
12

10N1Ø12.5 8N4 Total+10%: 21.7

8N4Ø12.5 C=140
5

95

49

5
9 Ø6.3 3 24 72 0.2
15
100

B B 15 20
12

Total+10%: 91.0
P47=P50=P51=P52 1 Ø12.5 4 285 285 1140 11.0
+0.000
N2Ø6.3c/15 C=189

5
N4Ø6.3c/15 C=27

25
P15 2 Ø6.3 21 77 1617 4.0

5
1 Ø16 4 272 16 72 360 1440 22.7
10N5 Corte B-B 9
15 Térreo 2 Ø12.5 10 360 360 3600 34.7

110
3 Ø12.5 4 110 440 4.2

30
10N5Ø12.5 C=140
5

N3Ø6.3c/15 C=136 8N4 80

75
3 Ø6.3 19 189 3591 8.8

23
4 Ø6.3 3 70 210 0.5

72
8N4 8N4Ø12.5

5
5
80

15
+0.000 15 7
20

A A 30 Total+10%: 21.7

27
4 Ø6.3 19 92 1748 4.3
N2Ø6.3c/15 C=229

5
15 (x4): 86.8
Térreo

110
5

10N5 5 5
P54
Corte B-B 5 Ø6.3 57 27 1539 3.8 1 Ø12.5 4 285 285 1140 11.0
Vista XX Vista YY 15

10N5 10N5Ø12.5 6 Ø16 4 150 600 9.5

92

25
30
2 Ø6.3 21 5 77 1617 4.0
12 120

100
A A 12 7 Ø12.5 10 140 1400 13.5 9

30
30
20

110

N5Ø6.3c/16 C=179 3 Ø12.5 4 110 440 4.2

30
80
N7Ø6.3c/16 C=24

72
8 Ø6.3 3 5 179 537 1.3
Corte A-A

23
12 4 Ø6.3 3 70 210 0.5

5
Vista XX Vista YY 9 Ø6.3 3
5
24 72 0.2
7

5
12 Total+10%: 21.7
Total+10%: 108.7
20
12 Aço: CA-50 (42.4 kg). Taxa: 83.56 kg/m3 Planta: 1º PAVIMENTO P17 1 Ø16 4 272 16 57 345 1380 21.8
P3 1 Ø12.5 4 285 285 1140 11.0

N6Ø6.3c/16 C=219

25
2 Ø12.5 4 330 1320 12.7 2 Ø6.3 21 77 1617 4.0

5
276 1342

Corte A-A Concreto: C30, em geral (0.46 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50 3 Ø12.5 4
9

110 440 4.2

30
80
3 Ø6.3 19 199 3781 9.3 80

5
15

23
4 Ø6.3 3 70 210 0.5
Fôrmas: 5.76 m2 Cobrimento: 2.5 cm Escala vertical 1:100

5
28
4 Ø6.3 19 95 1805 4.4 7

Aço: CA-50 (55.0 kg). Taxa: 86.85 kg/m3 Planta: 1º PAVIMENTO

5
15 Total+10%: 21.7
5 Ø16 4 155 620 9.8

30
125 P31=P33=P34=P35 1 Ø12.5 4 285 285 1140 11.0
6 Ø12.5 4 140 560 5.4 P36
Concreto: C30, em geral (0.58 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50

30
110

25
2 Ø6.3 21 5 77 1617 4.0

77
7 Ø6.3 3 189 567 1.4 9

5
12

Fôrmas: 6.91 m2 Cobrimento: 2.5 cm Escala vertical 1:100 3 Ø12.5 4 110 440 4.2

30
80
Total+10%: 71.3

23
P18 4 Ø6.3 3 70 210 0.5

5
1 Ø12.5 4 276 1342 330 1320 12.7
7
2 Ø12.5 12 330 330 3960 38.1
Total+10%: 21.7
(x5): 108.5

40
3 Ø6.3 38 119 4522 11.1

5
15
P37=P38=P39=P40 1 Ø12.5 4 285 285 1140 11.0
4 Ø12.5 16 140 2240 21.6

30
110

25
5
2 Ø6.3 21 77 1617 4.0
P20

52
9
5 Ø6.3 3 139 417 1.0

5
3 Ø12.5 4 110 440 4.2

30
P17 5
12
80

Pos. Diam. Q. Comp. Total 6 Ø6.3 6 24 144 0.4

23
4 Ø6.3 3 70 210 0.5

5
12

(cm) (cm) Pos. Diam. Q. Comp. Total Total+10%: 93.4 7

Total+10%: 21.7
P20 1 Ø12.5 10 330 3300 31.8
1 Ø12.5 10 330 3300 (cm) (cm) 276 1342
(x4): 86.8
P41

85
2 Ø6.3 19 209 3971 9.7 1 Ø12.5 4 285 285 1140 11.0
2 Ø6.3 19 209 3971 1 Ø16 4 345 1380

5
15

25
2 Ø6.3 21 77 1617 4.0

5
2 Ø12.5 4 330 1320

44
3 Ø6.3 19 126 2394 5.9
3 Ø6.3 19 126 2394 5
15
3 Ø12.5 4
9

110 440 4.2

30
4 Ø6.3 19 27 513 3 Ø6.3 19 199 3781 4 Ø6.3 19
5
27 513 1.3
80

23
15
4 Ø6.3 3 70 210 0.5

5
+2.880 4 Ø6.3 19 95 1805 5 Ø12.5 10 140 1400 13.5

30
5 Ø12.5 10 140 1400 110 7

Total+10%: 21.7

82
6 Ø6.3 3 199 597 1.5
6 Ø6.3 3 199 597 1º PAVIMENTO 5 Ø16 4 155 620 5
12 P42=P43=P44=P45 1 Ø12.5 4 285 285 1140 11.0
+2.880 5 P46

7 Ø6.3 3 24 72 6 Ø12.5 4 140 560 7 Ø6.3 3 24 72 0.2

25
2 Ø6.3 21 5 77 1617 4.0
12

Total+10%: 70.3 9
1º PAVIMENTO 7 Ø6.3 3 189 567 3 Ø12.5 4 110 440 4.2

30
P21 1 Ø12.5 4 276 1342 330 1320 12.7 80

4N2Ø12.5 C=330
10N1 2 Ø12.5 8 330 2640 25.4

23
330 4 Ø6.3 3 70 210 0.5

4N1Ø16 C=345
4N2

5
+2.420 4N1 N1 7

55
345
3 Ø6.3 19 147 2793 6.8 Total+10%: 21.7
10N1Ø12.5 C=330

330
4N1
85

5
N3+N4 c/15
4N2 80 28 5
14
(x5): 108.5

19Ø6.3
+2.420 4 Ø6.3 76 26 1976 4.8 P32 1 Ø12.5 4 285 285 1140 11.0

15

15
4N1Ø16 14
N2+N3+N4 c/15

20

5
5
B B 5 Ø12.5 12 140 1680 16.2

30
330

110

25
10N1 10N1 4N2Ø12.5 2 Ø6.3 21 77 1617 4.0

5
N3Ø6.3c/15 C=199 N4Ø6.3c/15 C=95
19Ø6.3

52
9
6 Ø6.3 3 137 411 1.0
10N1Ø12.5

85

44

5
3 Ø12.5 4 120 480 4.6
N2

30
11

90
90
B B 15 7 Ø6.3 6
5
23 138 0.3

23
4N6Ø12.5 C=140
4N5Ø16 C=155
4 Ø6.3 3 70 210 0.5

5
11

N4Ø6.3c/15 C=27 Corte B-B Total+10%: 73.9 7

15 +0.000 Total+10%: 22.1


10N5 4N5
P22 1 Ø16 4 272 16 57 345 1380 21.8
10N5Ø12.5 C=140

5
P4 1 Ø12.5 10 330 3300 31.8
N3Ø6.3c/15 C=126 N5 2 Ø12.5 4 276 1342 330 1320 12.7
276 1342

125
15 Térreo 4N6 4N5

110
85

95
5

2 Ø6.3 19 229 4351 10.7

85
+0.000 20

77 3 Ø6.3 19 209 3971 9.7

5
5
15
N2Ø6.3c/15 C=209 4N6
15

12
4N5Ø16

49
3 Ø6.3 19 136 2584 6.3
20

Térreo A A 5

30
Corte B-B

5
4 Ø6.3 19 5 99 1881 4.6
110

10N5 30 30 4N6Ø12.5 15
5
15

N7Ø6.3c/16 C=189 5 Ø16 4 155 620 9.8 4 Ø6.3 19 27 513 1.3

30
10N5 10N5Ø12.5
82

125 15

A A
90

N6 6 Ø12.5 4 140 560 5.4

30
5 Ø12.5 10 140 1400 13.5

30
12 Vista XX Vista YY 110 110
30

82

92
N7Ø6.3c/16 C=24 Corte A-A 7 Ø6.3 3 5 199 597 1.5 6 Ø6.3 3 219 657 1.6

5
12 12
5

Vista XX Vista YY Total+10%: 72.1 7 Ø6.3 3 24 72 0.2


5

12
P23

20
12 Aço: CA-50 (53.0 kg). Taxa: 98.41 kg/m3 Planta: 1º PAVIMENTO 1
2
Ø16
Ø12.5
4
4
272

276
16 57

1342
345
330
1380 21.8
1320 12.7
P5 1 Ø12.5 8 276 1342
Total+10%: 71.9
330 2640 25.4
N6Ø6.3c/16 C=199
Concreto: C30, em geral (0.49 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50

75
3 Ø6.3 19 189 3591 8.8

75
2 Ø6.3 19 193 3667 9.0

5
Corte A-A 15

5
17

27
4 Ø6.3 19 92 1748 4.3
Fôrmas: 6.05 m2 Cobrimento: 2.5 cm Escala vertical 1:100

27
3 Ø6.3 19 96 1824 4.5

5
15
17

Aço: CA-50 (53.5 kg). Taxa: 93.81 kg/m3 Planta: 1º PAVIMENTO 5 Ø16 4 155 620 9.8

30
125
4 Ø12.5 8 140 1120 10.8

30
110
6 Ø12.5 4 140 560 5.4

30
110

72
5 Ø6.3 3 183 549 1.3
Concreto: C30, em geral (0.52 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50

72
7 Ø6.3 3 179 537 1.3

5
14

5
12
Total+10%: 56.1
Total+10%: 70.5
P7
Fôrmas: 6.34 m2 Cobrimento: 2.5 cm Escala vertical 1:100 P25 1 Ø16 4 272 16 57 345 1380 21.8
1 Ø12.5 8 276 1342 330 2640 25.4

75
2 Ø12.5 4 276 1342 330 1320 12.7 2 Ø6.3 19 189 3591 8.8

5
P24 15

75
3 Ø6.3 19 189 3591 8.8

27
3 Ø6.3 19 92 1748 4.3

5
15

Pos. Diam. Q. Comp. Total 15

27
4 Ø6.3 19 92 1748 4.3 4 Ø12.5 8 140 1120 10.8

30
5
P15 (cm) (cm) 15
110

72
5 Ø16 4 155 620 9.8 5 Ø6.3 3 179 537 1.3

30
125

5
Pos. Diam. Q. Comp. Total 1 Ø12.5 6 330 1980 6 Ø12.5 4 140 560 5.4
12

30
110
Total+10%: 55.7
(cm) (cm) 2 Ø6.3 19 149 2831

72
7 Ø6.3 3 5 179 537 1.3 P10 1 Ø12.5 10 276 1342 330 3300 31.8
12

1 Ø16 4 360 1440 3 Ø6.3 19 27 513

95
Total+10%: 70.5 2 Ø6.3 19 229 4351 10.7
+2.880

5
P27 15
1 Ø16 4 272 16 57 345 1380 21.8
2 Ø12.5 10 360 3600 4 Ø12.5 6 275 1650

49
2 Ø12.5 4 276 1342 330 1320 12.7 3 Ø6.3 19 5 136 2584 6.3

3 Ø6.3 19 189 3591 1º PAVIMENTO 5 Ø6.3 3 139 417 15

75
5
3 Ø6.3 19 189 3591 8.8 4 Ø6.3 19 27 513 1.3

5
15
4 Ø6.3 19 92 1748
15

5 Ø12.5 10 140 1400 13.5

30
110

27
4 Ø6.3 19 92 1748 4.3
6N1

5
5 Ø6.3 57 27 1539

92
15
6 Ø6.3 3 219 657 1.6

6N1Ø12.5 C=330

5
5 Ø16 4 155 620 9.8

30
12
125
6 Ø16 4 150 600 +2.420 5
6 Ø12.5 4 140 560 5.4

30
110
7 Ø6.3 3 24 72 0.2

330
12

N2+N3 c/15
7 Ø12.5 10 140 1400 6N1 6N1 Total+10%: 71.9

72
7 Ø6.3 3 5 179 537 1.3

19Ø6.3
6N1Ø12.5 12 P11 1 Ø12.5 4 330 1320 12.7

55

5
276 1342
+2.880 8 Ø6.3 3 179 537 B B
60

15
Total+10%: 70.5
2 Ø12.5 8 330 330 2640 25.4
P24 1 Ø12.5 6 330 1980 19.1
1º PAVIMENTO 9 Ø6.3 3 24 72 N3Ø6.3c/15 C=27
276 1342

95
3 Ø6.3 19 229 4351 10.7

5
55
2 Ø6.3 19 149 2831 6.9 15
10N2Ø12.5 C=360

5
15 15

21
4 Ø6.3 38 81 3078 7.5
N1 5

5
20

3 Ø6.3 19 27 513 1.3


N2Ø6.3c/15 C=149 15
5 Ø12.5 12
15

140 1680 16.2

30
+0.000 4 Ø12.5 6 275 1650 15.9

30
245 110

10N2 Corte B-B


4N1Ø16 C=360

92
6 Ø6.3 3 219 657 1.6

52
5 Ø6.3 3 139 417 1.0
360
N3+N4+3N5 c/15

Térreo

5
5
6N4Ø12.5 C=275
4N1 +2.220 10N2 12 12
5

6N4 Total+10%: 48.6

21
7 Ø6.3 3 75 225 0.6

5
19Ø6.3

4N1 5 P26 1 Ø12.5 8 330 2640 25.4


4N1Ø16
75

27

80

276 1342 12

B B N2 5
15
Total+10%: 82.2
10N2Ø12.5

65
2 Ø6.3 19 169 3211 7.9 P12

245
1 Ø12.5 4 330 1320 12.7

5
276 1342

15 N5Ø6.3c/15 C=27 6N4 15


2 Ø16 8 345 345 2760 43.6
5

23
6N4 6N4Ø12.5 3 Ø6.3 19 85 1615 4.0

52
N4Ø6.3c/15 C=92

5
3 Ø16 2 272 16 57 345 690 10.9
10N7Ø12.5 C=140

60

N6 A A 15
4N6Ø16 C=150

4 Ø12.5 8 275 2200 21.2


15

30
245

85
20
4 Ø6.3 19 209 3971 9.7

5
15
+0.000
N3Ø6.3c/15 C=189

62
5 Ø6.3 3 159 477 1.2
4N6 5

5
5 Ø6.3 19 27 513 1.3
12 12

Térreo Corte B-B Total+10%: 65.7


15
120

20

6 Ø12.5 4 140 560 5.4

30
10N7 4N6
110

30 N5Ø6.3c/49 C=139
5

110
P48 1 Ø16 4
285
330 1320 20.8

22
7 Ø16 10 155 1550 24.5

30
5 23 125

10N7 Corte A-A 283


72

4N6Ø16 2 Ø16 2 315 630 9.9

6
80

N7 26

82
8 Ø6.3 3 196 588 1.4
A A 30 30 10N7Ø12.5 12 Vista XX Vista YY 5

25
3 Ø6.3 21 77 1617 4.0 12

5
5

5
N9Ø6.3c/16 C=24 4 Ø16 6
9

140 840 13.3


9 Ø6.3 3
12
24 72 0.2

30
110

Vista XX Vista YY Aço: CA-50 (30.0 kg). Taxa: 78.88 kg/m3 Planta: 1º PAVIMENTO Total+10%: 120.7

22
5 Ø6.3 3 64 192 0.5 Ø6.3: 481.2

5
20
12 6 Ø12.5: 1233.2

N8Ø6.3c/16 C=179 Concreto: C30, em geral (0.35 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50 Esquema
Total+10%: 53.4
Comp. Total CA-50
Ø16: 547.9
Total: 2262.3

Corte A-A Elemento Pos. Diam. Q.


(cm) (cm) (cm) (kg)
Fôrmas: 4.61 m2 Cobrimento: 2.5 cm Escala vertical 1:100 P49 1 Ø12.5 6 285 285 1710 16.5

Aço: CA-50 (81.7 kg). Taxa: 161.14 kg/m3 Planta: 1º PAVIMENTO

25
2 Ø6.3 21 5 77 1617 4.0
9

3 Ø12.5 6 120 720 6.9

30
Concreto: C30, em geral (0.46 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50 90

22
4 Ø6.3 3 67 201 0.5

5
6

Fôrmas: 5.76 m2 Cobrimento: 2.5 cm Escala vertical 1:100 P18 Total+10%: 30.7

Pos. Diam. Q. Comp. Total


(cm) (cm)
1 Ø12.5 4 330 1320
P12 2 Ø12.5 12 330 3960
Pos. Diam. Q. Comp. Total +2.880
3 Ø6.3 38 119 4522
(cm) (cm) 4 Ø12.5 16 140 2240
1 Ø12.5 4 330 1320 1º PAVIMENTO 5 Ø6.3 3 139 417
2 Ø16 8 345 2760 6 Ø6.3 6 24 144

12N2Ø12.5 C=330
3 Ø16 2 345 690

4N1Ø12.5 C=330
4 Ø6.3 19 209 3971 4N1 +2.420
N1 60

5 Ø6.3 19 27 513

330
12N2 12N2 40

2N3 c/15
19Ø6.3
6 Ø12.5 4 140 560 4N1Ø12.5

15
4N1

20

5
B B 12N2Ø12.5
7 Ø16 10 155 1550 N3Ø6.3c/15 C=119
+2.880 8 Ø6.3 3 196 588 N2

16N4Ø12.5 C=140
9 Ø6.3 3 24 72 Corte B-B
1º PAVIMENTO +0.000
N1 16N4
Térreo
8N2Ø16 C=345

110
5

16N4
60

8N2 16N4Ø12.5 52
4N1Ø12.5 C=330

5
16N4

12

12
2N3Ø16 C=345

4N1
20

2N3 A A

5
30
345

2N3 +2.220
8N2 N2 N5Ø6.3c/16 C=139 N6Ø6.3c/16 C=24
330
N4+N5 c/15

2N1 2N3Ø16 Corte A-A


19Ø6.3

5
4N1Ø12.5
85

2N1 N3
90

Vista XX Vista YY
B B 8N2Ø16 15
N5Ø6.3c/15 C=27
N6
N2
5
Aço: CA-50 (68.1 kg). Taxa: 179.20 kg/m3 Planta: 1º PAVIMENTO
10N7Ø16 C=155
4N6Ø12.5 C=140

+0.000
20
15 Concreto: C30, em geral (0.35 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50 00 18/04/2022 INICIAL Yvens Bolsoni

4N6 N4Ø6.3c/15 C=209 N° REV. DATA DESCRIÇÃO DESENHISTA


Fôrmas: 4.61 m2 Cobrimento: 2.5 cm Escala vertical 1:100
125

Térreo 10N7 4N6 Corte B-B


110

5
10N7
82

N7
90

4N6Ø12.5 PROJETISTA CLIENTE

A A 30 30 10N7Ø16 12
N9Ø6.3c/16 C=24 1º PAVIMENTO
5
Vista XX Vista YY
12 Planta: 1º PAVIMENTO Fôrmas Superfície Volume Barras MALLMANN ENGENHARIA
20

Elemento (m2) (m2) (m3) (kg) engenharia


N8Ø6.3c/16 C=196
Corte A-A Concreto: C30, em geral Pilares 161.83 - 10.830 2262.3 EMPREENDIMENTO E LOCAL
DIREITOS AUTORAIS RESERVADOS. PROIBIDA SUA REPRODUÇÃO, TRANSFERÊNCIA TOTAL OU PARCIAL SEM PREVIA AUTORIZAÇÃO.

FOLHA Nº:

Aço das barras: CA-50


Aço: CA-50 (86.0 kg). Taxa: 150.77 kg/m3 Planta: 1º PAVIMENTO
Concreto: C30, em geral (0.52 m3) Tamanho máximo do agregado: 15 mm Escala horizontal 1:50 Aço dos estribos: CA-50
PRÉDIO RESIDENCIAL
Rua Camomila Romana, Lote 49 - Quadra 48 - Parque Savoy City - São Paulo – SP 006
FASE:
TÍTULO REVISÃO:

Fôrmas: 6.34 m2 Cobrimento: 2.5 cm Escala vertical 1:100 PROJETO ESTRUTURAL


PLANTA DE PILARES DO TÉRREO AO 1° PAVIMENTO
ARMADURAS E SESSÃO DOS PILARES
PE 00
DISCIPLINA DESENHISTA VERIFICADOR APROVADO CONTRATO DATA ESCALA

ESTRUTURAL Eng. Yvens Bolsoni Eng. Yvens Bolsoni Eng. Yvens Bolsoni ------ 11.04.2021 1:50