Madrasha Estimate
Madrasha Estimate
1 earthwork
F1 1 8 8 6.33 405.12 cf
F2 1 10 10 6.67 667.00
F3 1 11 11 6.75 816.75
F4 3 11 11 6.83 2479.29
Total 11001.28 Cf
2 Sand filling
F1 1 8 8 6.33 405.12 cf
F2 1 10 10 6.67 667.00
F3 1 11 11 6.75 816.75
F4 3 11 11 6.83 2479.29
3 RCC work
foundation
F1 1 8 8 1.33 85.12 cf
F2 1 10 10 1.67 167.00
F3 1 11 11 1.75 211.75
F4 3 11 11 1.67 606.21
Total 3089.54 Cf
Grade beam
Total 700.67 Cf
Slab
S1 1 21.375 14.125 0.25 75.48 Cf
Total 812.89 Cf
4 Rebar work
foundation
16mm dia
F1 1 2 14 9.33 261.24 Rf
F2 1 1 20 11.33 226.60
1 1 24 11.33 271.92
F3 1 2 22 12.33 542.52
F4 3 2 22 12.33 1627.56
CF1 1 1 18 18 324.00
1 1 29 8.87 257.23
1 1 8 18 144.00
1 1 50 8.87 443.50
CF2 1 2 7 14.66 205.24
1 2 23 8.34 383.64
CF3 1 1 24 18 432.00
1 1 50 9.53 476.50
1 1 8 18 144.00
1 1 50 9.53 476.50
Total 7532.08