Vous êtes sur la page 1sur 20

50

1 2 3 4 5 Seam
A 217.46 223.88 239.89 261.79 295.35 1
B 216.87 224.64 241.57 263.26 294.59 2
C 214.50 258.53 243.26 267.20 297.44 3
D 199.99 177.49 200.47 244.07 260.34 4
E 152.36 155.49 196.93 235.75 257.11 5
F 105.24 144.67 195.70 230.06 260.66
G 66.10 103.31 155.78 181.08 215.10
H 0.00 34.35 99.35 114.80 144.96
I 0.00 22.45 73.30 100.49 139.36 luas
31007.68
LUAS 1 2 3 4 5 39200.27
A-A' 65.24 179.10 239.89 104.72 738.38 1327.32 48770.25
B-B' 65.06 179.71 241.57 105.30 736.46 1328.10 57210.88
C-C' 64.35 206.82 243.26 106.88 743.60 1364.90 64505.59
D-D' 60.00 141.99 200.47 97.63 650.84 1150.92
E-E' 45.71 124.39 196.93 94.30 642.78 1104.12
F-F' 31.57 115.73 195.70 92.02 651.65 1086.68
G-G' 19.83 82.64 155.78 72.43 537.74 868.43
H-H' 0.00 27.48 99.35 45.92 362.41 535.16
I-I' 0.00 17.96 73.30 40.20 348.40 479.86
9245.49
SEAM STRIKE
1 226
2 211 23
3 253 21
4 225 21
5 255 29
Data Singkapan
Strike (N...o E) Dip (o) Tebal Semu (m) Tebal Sebenarnya (m)
226 32 0.5 0.3
211 23 2.2 0.8
253 21 2.9 1.0
255 21 1.1 0.4
255 29 5.1 2.5

volume tonase
8215.78 10680.51990906
32931.04 42810.35585867
50685.31 65890.90147701
22552.80 29318.63992045
159491.95 207339.5298227
273876.88 356039.9469879
Seam Cross SectionSolid (ton)
1 12761.40 10680.52
2 41206.75 42810.36
3 62891.71 65890.90
4 29115.99 29318.64
5 205114.16 207339.53
TOTAL 351090.01 356039.95
4949.94
SAYATAN LUAS VOLUME
50 1 2 3 4 5 JARAK 1 2
A-A' 65.96 182.13 241.56 105.40 736.01 50.00 3094.41 9152.38
B-B' 57.81 183.97 241.57 107.49 748.26 50.00 2471.08 7705.06
C-C' 41.03 124.24 196.22 94.17 643.07 50.00 1813.87 5983.36
D-D' 31.53 115.10 195.85 92.90 651.73 50.00 1174.49 3598.44
E-E' 15.45 28.84 42.83 51.59 60.98 50.00
TOTAL 211.79 634.27 918.04 451.55 2840.04 8553.86 26439.24
214515.59

SAYATAN LUAS VOLUME


75 1 2 3 4 5 JARAK 1 2
A-A' 64.77 179.67 241.60 105.42 738.72 50.00 2842.90 7924.98
B-B' 48.94 137.33 200.05 97.71 651.01 50.00 2007.60 6311.74
C-C' 31.36 115.14 195.70 91.36 655.00 50.00 907.45 4035.42
D-D' 4.94 46.28 106.55 53.22 415.72 50.00
TOTAL 150.01 478.42 743.89 347.72 2460.45 5757.95 18272.14
160102.22

LUAS VOLUME
SECTION 1 2 3 4 5 JARAK 1 2
A-A' 65.16 179.73 241.77 105.03 736.02 50.00 2646.38 7576.72
B-B' 40.70 123.34 196.23 94.92 643.86 50.00 1405.87 4979.86
C-C' 15.54 75.86 143.59 68.94 515.17 50.00 0.00 0.00
TOTAL 121.39 378.93 581.59 268.89 1895.04 4052.25 12556.58
108622.21

SAYATAN LUAS VOLUME


60 1 2 3 4 5 JARAK 1 2
A-A' 55.93 155.00 210.82 93.12 659.20 59.50 3018.44 8749.36
B-B' 45.53 139.10 196.47 89.54 678.43 59.50 2158.69 7154.04
C-C' 27.04 101.38 166.03 82.50 325.70 59.50 1129.55 5056.79
D-D' 10.93 68.60 135.49 65.61 327.53 59.50 325.23 2242.73
E-E' 0.00 6.79 22.42 30.80 39.72 59.50
TOTAL 139.43 470.86 731.23 361.57 2030.57 6631.90 23202.92
184257.02

SAYATAN LUAS VOLUME


JARAK
60 1 2 3 4 5 1 2
A-A' 47.991 131.7 152.12 65.92 463.9 11.00 571.06 1577.77
B-B' 55.839 155.168 210.88 93.024 659.875 35.00 1944.83 5466.15
C-C' 55.2939 157.1832 213.087 96.5608 668.27 35.00 1703.12 4814.87
D-D' 42.027 117.952 170.56 85.652 423.55 38.00 1331.32 4157.66
E-E' 28.0425 100.872 167.603 82.6132 325.3925 38.00 962.19 3660.92
F-F' 22.599 91.808 165.81 80.06 327.6 46.00 645.77 3377.50
G-G' 5.478 55.04 119.81 59.768 323.05 46.00 0.00 1659.13
H-H' 0 17.096 71.38 38.652 300.2 6.00 0.00 76.92
I-I' 0 8.544 42.17 18.24 288.2
TOTAL 257.27 835.36 1313.42 620.49 3780.04 7158.29 24790.91
TOTAL
197696.84

200204.34 2507.50
VOLUME TONNASE
3 4 5 DENSITAS 1 2 3 4 5
12078.28 5322.29 37106.56 1.30 4022.73 11898.09 15701.76 6918.98 48238.53
10944.90 5041.54 34783.19 1.30 3212.41 10016.58 14228.37 6554.00 45218.14
9801.95 4676.83 32369.94 1.30 2358.04 7778.37 12742.54 6079.88 42080.92
5967.19 3612.22 17817.62 1.30 1526.83 4677.97 7757.34 4695.89 23162.91

38792.31 18652.88 122077.31 11120.01 34371.01 50430.00 24248.75 158700.50


TOTAL
278870.27

VOLUME
3 4 5 DENSITAS 1 2 3 4 5
11041.18 5078.40 34743.06 1.30 3695.77 10302.47 14353.53 6601.92 45165.98
9893.50 4726.88 32650.19 1.30 2609.88 8205.26 12861.55 6144.94 42445.24
7556.08 3614.66 26768.19 1.30 1179.69 5246.05 9822.90 4699.06 34798.64
1.30 0.00 0.00 0.00 0.00 0.00
28490.75 13419.94 94161.44 7485.34 23753.78 37037.98 17445.92 122409.87
TOTAL
208132.89

VOLUME TONNASE
3 4 5 DENSITAS 1 2 3 4 5
10950.05 4998.84 34496.94 1.30 3440.30 9849.74 14235.07 6498.49 44846.02
8495.38 4096.49 28975.69 1.30 1827.63 6473.82 11043.99 5325.44 37668.39
0.00 0.00 0.00 1.30 0.00 0.00 0.00 0.00 0.00
19445.43 9095.33 63472.63 5267.93 16323.55 25279.05 11823.93 82514.41
TOTAL
141208.87

VOLUME TONNASE
3 4 5 DENSITAS 1 2 3 4 5
12116.88 5434.02 39794.34 1.30 3923.97 11374.16 15751.94 7064.22 51732.65
10784.38 5118.23 29872.72 1.30 2806.30 9300.25 14019.69 6653.69 38834.53
8970.22 4406.37 19433.44 1.30 1468.41 6573.82 11661.29 5728.28 25263.48
4697.70 2868.29 10925.63 1.30 422.80 2915.55 6107.01 3728.77 14203.32

36569.18 17826.90 100026.13 8621.47 30163.79 47539.93 23174.96 130033.97


TOTAL
184257.02 239534.13

VOLUME TONNASE
DENSITAS
3 4 5 1 2 3 4 5
1996.50 874.19 6180.76 1.30 742.38 2051.11 2595.45 1136.45 8034.99
7419.42 3317.73 23242.54 1.30 2528.27 7105.99 9645.25 4313.05 30215.30
6713.82 3188.72 19106.85 1.30 2214.05 6259.33 8727.97 4145.34 24838.91
6425.10 3197.04 14229.91 1.30 1730.72 5404.95 8352.63 4156.15 18498.88
6334.85 3090.79 12406.86 1.30 1250.85 4759.20 8235.30 4018.03 16128.91
6569.26 3216.04 14964.95 1.30 839.50 4390.76 8540.04 4180.86 19454.43
4397.37 2263.66 14334.75 1.30 0.00 2156.87 5716.58 2942.76 18635.18
340.65 170.68 1765.20 1.30 0.00 100.00 442.84 221.88 2294.76
40196.97 19318.86 106231.81 9305.77 32228.19 52256.06 25114.52 138101.36
TOTAL
197696.84 257005.90

260265.64 3259.74
NO SAYATAN
TOTAL SUMBERDAYA BATUBARA (ton)
1 JARAK 50 M 278870.27
2 JARAK 75 M 208132.89
3 JARAK 100 M 141208.87
TOTAL 628212.03

TOTAL SUMBERDAYA
Seam Volume Densitas Tonnase
1 7158.29 1.30 9305.77
2 24790.91 1.30 32228.19
3 40196.97 1.30 52256.06
4 19318.86 1.30 25114.52
5 106231.81 1.30 138101.36
TOTAL 197696.84 257005.90
PERHITUNGAN SEAM 1 (Tebal 0.3 meter)
Sayatan Panjang (m) Luas (m2) Jarak (m) Volume (m3) Densitas (ton/m3) Tonase
A-A' 217.46 65.24
11 716.64 1.3 931.64
B-B' 216.87 65.06
B-B' 216.87 65.06
35 2264.68 1.3 2944.09
C-C' 214.50 64.35
C-C' 214.50 64.35
35 2176.06 1.3 2828.88
D-D' 199.99 60.00
D-D' 199.99 60.00
38 2008.40 1.3 2610.91
E-E' 152.36 45.71
E-E' 152.36 45.71
38 1468.33 1.3 1908.83
F-F' 105.24 31.57
F-F' 105.24 31.57
46 1182.20 1.3 1536.86
G-G' 66.10 19.83
TOTAL 9816.31 12761.20

PERHITUNGAN SEAM 3 (Tebal 1 meter)


Sayatan Panjang (m) Luas (m2) Jarak (m) Volume (m3) Densitas (ton/m3) Tonase
A-A' 239.89 239.89
11 2647.98 1.30 3442.37
B-B' 241.57 241.57
B-B' 241.57 241.57
35 8484.35 1.30 11029.66
C-C' 243.26 243.26
C-C' 243.26 243.26
35 7765.17 1.30 10094.72
D-D' 200.47 200.47
D-D' 200.47 200.47
38 7550.60 1.30 9815.78
E-E' 196.93 196.93
E-E' 196.93 196.93
38 7460.03 1.30 9698.04
F-F' 195.70 195.70
F-F' 195.70 195.70
46 8084.13 1.30 10509.37
G-G' 155.78 155.78
G-G' 155.78 155.78
46 5868.04 1.30 7628.45
H-H' 99.35 99.35
H-H' 99.35 99.35
6 517.95 1.30 673.33
I-I' 73.30 73.30
TOTAL 48378.24 62891.71
PERHITUNGAN SEAM 2 (Tebal 0.8 meter)
Sayatan Panjang (m) Luas (m2) Jarak (m) Volume (m3) Densitas (ton/m3) Tonase
A-A' 223.88 179.10
11 1973.47 1.30 2565.52
B-B' 224.64 179.71
B-B' 224.64 179.71
35 6764.32 1.30 8793.62
C-C' 258.53 206.82
C-C' 258.53 206.82
35 6104.18 1.30 7935.44
D-D' 177.49 141.99
D-D' 177.49 141.99
38 5061.30 1.30 6579.68
E-E' 155.49 124.39
E-E' 155.49 124.39
38 4562.40 1.30 5931.12
F-F' 144.67 115.73
F-F' 144.67 115.73
46 4562.65 1.30 5931.44
G-G' 103.31 82.64
G-G' 103.31 82.64
46 2532.85 1.30 3292.71
H-H' 34.35 27.48
H-H' 34.35 27.48
6 136.32 1.30 177.22
I-I' 22.45 17.96
TOTAL 31697.50 41206.75

PERHITUNGAN SEAM 4 (Tebal 0.4 meter)


Sayatan Panjang (m) Luas (m2) Jarak (m) Volume (m3) Densitas (ton/m3) Tonase
A-A' 261.79 104.72
11 1155.10 1.30 1501.63
B-B' 263.26 105.30
B-B' 263.26 105.30
35 3713.21 1.30 4827.18
C-C' 267.20 106.88
C-C' 267.20 106.88
35 3578.89 1.30 4652.56
D-D' 244.07 97.63
D-D' 244.07 97.63
38 3646.63 1.30 4740.62
E-E' 235.75 94.30
E-E' 235.75 94.30
38 3540.12 1.30 4602.15
F-F' 230.06 92.02
F-F' 230.06 92.02
46 3782.48 1.30 4917.22
G-G' 181.08 72.43
G-G' 181.08 72.43
46 2722.13 1.30 3538.77
H-H' 114.80 45.92
H-H' 114.80 45.92
6 258.35 1.30 335.85
I-I' 100.49 40.20
TOTAL 22396.92 29115.99
PERHITUNGAN SEAM 5 (Tebal 2.5 meter)
Sayatan Panjang (m) Luas (m2) Jarak (m) Volume (m3) Densitas (ton/m3) Tonase
A-A' 295.35 738.38
11 8111.63 1.30 10545.12
B-B' 294.59 736.46
B-B' 294.59 736.46
35 25901.05 1.30 33671.37
C-C' 297.44 743.60
C-C' 297.44 743.60
35 24402.66 1.30 31723.45
D-D' 260.34 650.84
D-D' 260.34 650.84
38 24578.83 1.30 31952.48
E-E' 257.11 642.78
E-E' 257.11 642.78
38 24594.22 1.30 31972.48
F-F' 260.66 651.65
F-F' 260.66 651.65
46 27355.91 1.30 35562.69
G-G' 215.10 537.74
G-G' 215.10 537.74
46 20703.39 1.30 26914.41
H-H' 144.96 362.41
H-H' 144.96 362.41
6 2132.43 1.30 2772.16
I-I' 139.36 348.40
TOTAL 157780.12 205114.16
TOTAL SUMBERDAYA
Seam Volume Densitas Tonnase
1 9816.31 1.30 12761.20
2 31697.50 1.30 41206.75
3 48378.24 1.30 62891.71
4 22396.92 1.30 29115.99
5 157780.12 1.30 205114.16
TOTAL 270069.09 351089.81

273581.09 355655.42
3512.00 4565.60
HASIL SAYATAN SU
LUASAN (M2) VOLUME M3 DENSITAS TONASE LUASAN (M2)
SAYATAN 50 JARAK (M) SAYATAN 75
LS1 1331.06 1335.08 50.00 66753.92 1.30 86780.09 LS1 1330.19
LS2 1339.10 1218.92 50.00 60945.77 1.30 79229.50 LS2 1135.03
LS3 1098.73 1092.92 50.00 54645.95 1.30 71039.74 LS3 1088.56
LS4 1087.10 643.40 50.00 32169.83 1.30 41820.78 LS4 626.71
LS5 199.69 50.00 9984.50 1.30 12979.85
TOTAL 5055.68 4290.31 224499.98 291849.97 TOTAL 4180.49
9345.99 224499.98 7382.54

50 5055.68
75 4180.49
100 287156.6
HASIL SAYATAN SUMBERDAYA TERUKUR
VOLUME M DENSITAS TONASE LUASAN (M2) JARAK (M)
JARAK (M) SAYATAN 100
1232.61 75.00 92445.77 1.30 120179.50 LS1 1327.71 1213.38 100.00
1111.80 75.00 83384.86 1.30 108400.32 LS2 1099.05 959.07 100.00
857.64 75.00 64322.70 1.30 83619.51 LS3 819.08 100.00
75.00 47003.27 1.30 61104.24

3202.04 287156.60 373303.57 TOTAL 3245.84 2172.44


287156.60 5418.28
VOLUME M3 TONASE PERHITUNGAN SUMBRDAYA BATUBARA
DENSITAS
NO SAYATAN
121337.86 1.30 157739.22 1 JARAK 50 M
95906.56 1.30 124678.53 2 JARAK 75 M
81908.23 1.30 106480.70 3 JARAK 100 M
TOTAL

299152.65 388898.45
299152.65 SAYATAN
50 75

0.00
ERHITUNGAN SUMBRDAYA BATUBARA
TOTAL SUMBERDAYA BATUBARA (ton)
291849.97
373303.57
388898.45
1054051.99

SAYATAN
100

0.00
Searah Dengan Strike Searah Dengan Dip
titik bor jarak (m) titik bor jarak titik bor jarak titik bor jarak
1-2 91 7-8 76 1-9 96 5-6 99
2-3 76 8-9 88 2-8 100 7-11 94
3-4 70 6-11 65 3-7 102 8-10 100
5-7 74 11-10 84 4-5 100
LUAS 1 2 3 4 5
A-A' 65.24 179.10 239.89 104.72 1327.32 A-A' 726.354
B-B' 65.06 179.71 241.57 105.30 1328.10 B-B' 735.689
C-C' 64.35 206.82 243.26 106.88 1364.90 C-C' 738.977
D-D' 60.00 141.99 200.47 97.63 1150.92 D-D' 663.038
E-E' 45.71 124.39 196.93 94.30 1104.12 E-E' 650.59
F-F' 31.57 115.73 195.70 92.02 1086.68 F-F' 653.854
G-G' 19.83 82.64 155.78 72.43 868.43 G-G' 537.807
H-H' 0.00 27.48 99.35 45.92 535.16 H-H' 353.872
I-I' 0.00 17.96 73.30 40.20 479.86 I-I' 331.486
352.75 1077.83 1649.24 763.40 9245.49
0.3 0.8 1 0.4
137.57414 1120.9478 2144.0107 396.96738 3799.5

0.3 9816.4642 45810.30 158099.42


0.8 31697.498 41.610585
1 48378.24 0.4079674
0.4 22396.917
112289.12
Sayatan Luas (m2) Jarak (m) Volume (m3)
137.41 A-A' 137.41
11 1548.04
144.05 B-B' 144.05
117.67 B-B' 144.05
35 4580.09
162.96 C-C' 117.67
189.26 C-C' 117.67
35 4910.96
218.83 D-D' 162.96
207.12 D-D' 162.96
38 6692.01
181.12 E-E' 189.26
200.03 E-E' 189.26
38 7753.56
F-F' 218.83
F-F' 218.83
46 9796.75
G-G' 207.12
G-G' 207.12
46 8929.54
H-H' 181.12
H-H' 181.12
6 1143.45
I-I' 200.03
TOTAL 45354.39

Sayatan Luas (m2) Jarak (m) Volume (m3)


726.354 A-A' 726.35
11 8041.24
735.689 B-B' 735.69
738.977 B-B' 735.69
35 25806.66
663.038 C-C' 738.98
650.59 C-C' 738.98
35 24535.26
653.854 D-D' 663.04
537.807 D-D' 663.04
38 24958.93
353.872 E-E' 650.59 112745.02
331.486 E-E' 650.59
38 24784.44
F-F' 653.85
F-F' 653.85
46 27408.20
G-G' 537.81
G-G' 537.81
46 20508.62
H-H' 353.87
H-H' 353.87
6 2056.07
I-I' 331.49
TOTAL 158099.42