RENCANA PROGRAM KONSTRUKSI S/D TGL 20 DESEMBER 2023

PROYEK SPAM JATILUHUR 1

Realisasi Rencana

Item Pekerjaan Sat 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Ket


Jumat Sabtu Minggu Total Bobot (%) Total Bobot (%)
Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot % Vol Bobot %

Trase Sentra Timur 0.164 0.042 0.042 0.042 0.042 0.042 0.042 0.053 0.095 0.095 0.095 0.095 0.095 0.095 0.053 0.095 0.095 0.095 1.375

MTBM 0.084 0.042 0.042 0.042 0.042 0.042 0.042 - 0.042 0.042 0.042 0.042 0.042 0.042 - 0.042 0.042 0.042 0.710

Pengadaan Pipa m 7.5 7.5 - 15.0 0.030 7.50 0.015 7.50 0.015 7.50 0.015 7.50 0.015 7.50 0.015 7.50 0.015 - 7.50 0.015 7.50 0.015 7.50 0.015 7.50 0.015 7.50 0.015 7.50 0.015 - 7.50 0.015 7.50 0.015 7.50 0.015 112.5 0.251

Progress Pipa m 7.5 7.5 - 15.0 0.054 7.50 0.027 7.50 0.027 7.50 0.027 7.50 0.027 7.50 0.027 7.50 0.027 - 7.50 0.027 7.50 0.027 7.50 0.027 7.50 0.027 7.50 0.027 7.50 0.027 - 7.50 0.027 7.50 0.027 7.50 0.027 112.5 0.459
-
Open Cut 0.080 - - - - - - 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.053 0.665

Pengadaan Pipa m 24.6 24.6 0.025 - - - - - - - - - - 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 24.60 0.025 270.6 0.300

Progress Pipa m 24.6 24.6 0.014 - - - - - - 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 270.6 0.173

Reinstatement m 24.6 24.6 24.6 73.8 0.041 - - - - - - 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 24.60 0.014 270.6 0.192
-
IPA Bekasi 0.032 - 0.117 0.028 0.024 - 0.095 - 0.242 - - 0.080 - 0.073 - 0.232 0.043 0.222 1.186

Hidrofill 0.032 - - - 0.024 - 0.024 - - - - 0.024 - 0.024 - 0.194 - - 0.320

Pengecoran Slab Lt.2 m3 49.0 49.0 0.009 - - - - - - - - - - - - - - 313.00 0.060 - - 313.0 0.069 Target kurva s closed utk pengecoran slab lt.2 (aktual tgl 1 closed utk slab lt.2)

Pembesian Slab Lt.2 kg 10,780.0 10,780.0 0.015 - - - - - - - - - - - - - - 68,860.00 0.095 - - 68,860.0 0.110 Target kurva s closed utk pengecoran slab lt.2 (aktual tgl 1 closed utk slab lt.2)

Pengecoran wall Lt.2 m3 - 14.0 14.0 0.003 - - - 22.50 0.005 - 22.50 0.005 - - - - 22.50 0.005 - 22.50 0.005 - - - - 90.0 0.023

Pembesian wall Lt.2 kg - 3,080.0 3,080.0 0.004 - - - 4,950.00 0.007 - 4,950.00 0.007 - - - - 4,950.00 0.007 - 4,950.00 0.007 - - - - 19,800.0 0.031

Pengecoran kolom Lt.2 m3 - - - 20.00 0.006 - 20.00 0.006 - - - - 20.00 0.006 - 20.00 0.006 - - - - 80.0 0.023

Pembesian kolom Lt.2 kg - - - 4,400.00 0.006 - 4,400.00 0.006 - - - - 4,400.00 0.006 - 4,400.00 0.006 - - - - 17,600.0 0.024

Pengecoran balok Lt.2 m3 - - - - - - - - - - - - - - 72.00 0.018 - - 72.0 0.018

Pembesian balok Lt.2 kg - - - - - - - - - - - - - - 15,840.00 0.022 - - 15,840.0 0.022

Hidropaq - - - 0.028 - - 0.071 - 0.201 - - - - 0.041 - - - - 0.341

Pengecoran Slab Lt.2 m3 - - - - - - - 337.00 0.067 - - - - - - - - - 337.0 0.067 Pekerjaan dinding lt. dasar sdh closed (0.040%)

Pembesian Slab Lt.2 kg - - - - - - - 74,140.00 0.102 - - - - - - - - - 74,140.0 0.102

Pengecoran wall Lt.2 m3 - - 33.00 0.009 - - 84.00 0.022 - - - - - - 49.000 0.013 - - - - 166.0 0.043

Pembesian wall Lt.2 kg - - 7,260.00 0.010 - - 18,480.00 0.025 - - - - - - 10,780.000 0.015 - - - - 36,520.0 0.050

Pengecoran kolom Lt.2 m3 - - 16.50 0.004 - - 42.00 0.011 - - - - - - 24.500 0.006 - - - - 83.0 0.022

Pembesian kolom Lt.2 kg - - 3,630.00 0.005 - - 9,240.00 0.013 - - - - - - 5,390.000 0.007 - - - - 18,260.0 0.025

Pengecoran balok Lt.2 m3 - - - - - - - 62.00 0.013 - - - - - - - - - 62.0 0.013

Pembesian balok Lt.2 kg - - - - - - - 13,640.00 0.019 - - - - - - - - - 13,640.0 0.019

Intake - - - - - - - - 0.042 - - - - - - - 0.043 - 0.084

Pengecoran Top Slab m3 - - - - - - - - - - - - - - - 73.13 0.021 - 73.1 0.021 Utk kurva S pengecoran kolom sudah closed

Pembesian Top Slab kg - - - - - - - - - - - - - - - 16,088.60 0.022 - 16,088.6 0.022

Pengecoran wall m3 - - - - - - - 80.00 0.018 - - - - - - - - - 80.0 0.018

Pembesian wall kg - - - - - - - 17,600.00 0.024 - - - - - - - - - 17,600.0 0.024

Reservoir - - 0.117 - - - - - - - - 0.056 - 0.007 - 0.038 - 0.046 0.264

Pengecoran wall m3 - 150.00 0.034 - - - - - - - - 70.00 0.016 - - - - - 70.00 0.016 290.0 0.066

Pembesian wall kg - 33,000.00 0.045 - - - - - - - - 15,400.00 0.021 - - - - - 15,400.00 0.021 63,800.0 0.088

Pengecoran kolom m3 - 70.00 0.016 - - - - - - - - 35.00 0.008 - - - 70.00 0.016 - - 175.0 0.041

Pembesian kolom kg - 15,400.00 0.021 - - - - - - - - 7,700.00 0.011 - - - 15,400.00 0.021 - - 38,500.0 0.053

Pengecoran pile cap saluran m3 - - - - - - - - - - - - - - - - 14.27 0.004 14.3 0.004

Pembesian pile cap saluran kg - - - - - - - - - - - - - - - - 3,139.13 0.004 3,139.1 0.004

Pengecoran pondasi mesin m3 - - - - - - - - - - - - 17.89 0.002 - - - - 17.9 0.002

Pembesian pondasi mesin kg - - - - - - - - - - - - 3,936.19 0.005 - - - - 3,936.2 0.005

Sludge Building - - - - - - - - - - - - - - - - 0.057 0.057

Pekerjaan Struktur Modul Sludge Holding Tank Ls - - - - - - - - - - - - - - - - 0.200 0.015 0.2 0.015

Pekerjaan Struktur Modul Sludge Building Ls - - - - - - - - - - - - - - - - 0.600 0.042 0.6 0.042

Pekerjaan Bangunan Penunjang - - - - - - - - - - - - - - - - 0.120 0.120

Kantor Manajemen IPA Bekasi Unit - - - - - - - - - - - - - - - - 0.170 0.039 0.2 0.039

Chemical Room IPA Bekasi Unit - - - - - - - - - - - - - - - - 0.200 0.036 0.2 0.036

Workshop & Warehouse IPA Bekasi Unit - - - - - - - - - - - - - - - - 0.200 0.027 0.2 0.027

Kantor Operasional dan Laboratorium IPA Bekasi Unit - - - - - - - - - - - - - - - - 0.100 0.018 0.1 0.018

IPA Cibeet - - - - - - - - - - - - - - - - 0.281 0.281

Intake - - - - - - - - - - - - - - - - 0.013 0.013

Pekerjaan Dinding Bata Ls - - - - - - - - - - - - - - - - 1.000 0.010 1.0 0.010

Hand Railink m - - - - - - - - - - - - - - - - 54.000 0.003 54.0 0.003

Pekerjaan Saluran Baku - - - - - - - - - - - - - - - - 2.000 0.008 2.000 0.008

Pekerjaan Struktur Beton Bangunan Sadap Ls - - - - - - - - - - - - - - - - 1.000 0.005 1.0 0.005

Entrance Ring Joint Diameter Inside 800 mm Unit - - - - - - - - - - - - - - - - 1.000 0.003 1.0 0.003

Hidropaq 0.017 0.017

Pekerjaan Struktur Saluran Beton m3 - - - - - - - - - - - - - - - - 34.535 0.010 34.5 0.010

Pekerjaan Struktur Tangga Beton m3 - - - - - - - - - - - - - - - - 4.875 0.002 4.9 0.002

Hand Railink m - - - - - - - - - - - - - - - - 97.400 0.006 97.4 0.006

Hidrofill 0.082 0.082

Pekerjaan Struktur Beton Nozzle Plate & Support Pipam3 - - - - - - - - - - - - - - - - 4.000 0.034 4.0 0.034

Pekerjaan Struktur Tangga Beton m3 - - - - - - - - - - - - - - - - 19.599 0.005 19.6 0.005

Pekerjaan penutup ata zincalum m2 - - - - - - - - - - - - - - - - 364.000 0.008 364.0 0.008

Hand Railink m - - - - - - - - - - - - - - - - 595.350 0.036 595.4 0.036

Sludge Building 0.022 0.022

Pekerjaan Struktur Modul Sludge Building Ls - - - - - - - - - - - - - - - - 0.084 0.004 0.1 0.004

Pekerjaan Arsitektur Pendukung Sludge Building Ls - - - - - - - - - - - - - - - - 0.170 0.018 0.2 0.018

Reservoir 0.002 0.002

Hand Railink m - - - - - - - - - - - - - - - - 39.200 0.002 39.2 0.002

Pekerjaan Bangunan Penunjang 0.136 0.136

Pekerjaan Saluran Utilitas m - - - - - - - - - - - - - - - - 26.900 0.046 26.9 0.046

Pekerjaan Struktur PLN dan MCC Room Ls - - - - - - - - - - - - - - - - 0.197 0.011 0.2 0.011

Rumah Pompa Hidran IPA Cibeet Unit - - - - - - - - - - - - - - - - 0.683 0.023 0.7 0.023

Chemical Room IPA Cibeet Unit - - - - - - - - - - - - - - - - 0.145 0.026 0.1 0.026

Workshop & Warehouse IPA Cibeet Unit - - - - - - - - - - - - - - - - 0.095 0.008 0.1 0.008

Pos Jaga IPA Cibeet Unit - - - - - - - - - - - - - - - - 1.000 0.012 1.0 0.012

Bangunan Pengolah Limbah IPA Cibeet Unit - - - - - - - - - - - - - - - - 0.500 0.004 0.5 0.004

Menara Air IPA Cibeet Unit - - - - - - - - - - - - - - - - 0.250 0.006 0.3 0.006

Trase Cibeet 0.047 0.047

Reinstatement m 793.250 0.040 793.3 0.040

Manhole Unit 4.000 0.006 4.0 0.006

TOTAL 0.196 0.042 0.159 0.070 0.065 0.042 0.137 0.053 0.337 0.095 0.095 0.175 0.095 0.167 0.053 0.327 0.138 0.646 2.890