Poteau (P5)

Niveau G(t) Q(t) S (m²) PPpoutres(t) G'(t) Q'(t) Pu(t) Ps(t)


PH Etage (P5) 1.40 0.10 10.98 2.32 17.64 1.10 25.46 18.73
PH RDC (P5) 1.40 0.18 10.98 2.32 17.64 1.92 26.69 19.56
PH Sous-sol (P5) 0.68 0.18 10.98 2.32 9.82 1.92 16.14 11.74

P(4G)
Niveau G(t/m²) Q(t/m²) S(m²) P.P(Poutre)(t) G'(t) Q'(t) Pu(t) Ps(t)
Sous-sol 0.57 0.4 2.49 0.64 2.0593 0.996 4.2741 3.0553
PH RDC 0.61 0.175 14.11 1.74 10.3471 2.46925 31.702 22.9764
PH 1er E 0.61 0.175 13.72 1.37 9.7392 2.401 17.289 12.5302
PH 2ème E 0.61 0.175 13.72 1.37 9.7392 2.401 17.289 12.5302
PH 3ème E 0.61 0.175 13.72 1.37 9.7392 2.401 17.289 12.5302
Terrasse 0.742 0.15 13.72 1.37 11.55024 2.058 19.22 13.9982

P(4E)
Niveau G(t/m²) Q(t/m²) S(m²) P.Propre(t) G'(t) Q'(t) Pu(t) Ps(t)
Sous-sol 0.57 0.4 10.72 1.34 7.4504 4.288 30.13 21.4284
PH RDC 0.61 0.175 4.96 1.12 4.1456 0.868 28.109 20.3636
PH 1er E 0.61 0.175 4.96 1.12 4.1456 0.868 28.109 20.3636
PH 2ème E 0.61 0.175 4.96 1.12 4.1456 0.868 28.109 20.3636
PH 3ème E 0.61 0.175 4.96 1.12 4.1456 0.868 28.109 20.3636
Terrasse 0.742 0.15 4.96 1.12 4.80032 0.744 28.806 20.8943
Nu(t) Ns(t) Nuc(t) Nsc(t)
28.00 20.61 28.00 20.61
29.36 21.51 57.36 42.12
17.75 12.91 75.11 55.03

Nu(t) Ns(t) Nuc(t) Nsc(t)


4.70146 3.36083 4.7015 3.36083
34.8727 25.274 39.574 28.6348
19.0184 13.7832 58.593 42.418
19.0184 13.7832 77.611 56.2013
19.0184 13.7832 96.629 69.9845
21.1418 15.3981 117.77 85.3825

Nu(t) Ns(t) Nuc(t) Nsc(t)


33.143 23.5712 33.143 23.5712
30.9194 22.4 64.062 45.9712
30.9194 22.4 94.982 68.3712
30.9194 22.4 125.9 90.7711
30.9194 22.4 156.82 113.171
31.6871 22.9838 188.51 136.155
P(A1)
Niveau G(t) Q(t) S (m²) p.p(poutres)(t) G'(t) Q'(t)
PH sous-sol 0.61 0.4 5.45 1.12 4.4445 2.18
PH RDC 0.61 0.175 5.45 0.964 4.2885 0.95375
PH 1er E 0.61 0.175 5.45 0.964 4.2885 0.95375
PH 2ème E 0.61 0.175 5.45 0.964 4.2885 0.95375
PH 3ème E 0.61 0.175 5.45 0.964 4.2885 0.95375
PH 4ème E 0.742 0.15 5.45 0.964 5.0079 0.8175

P(7F)
Niveau G(t) Q(t) S (m²) p.p(poutres)(t) G'(t) Q'(t)
PH sous-sol 0.57 0.4 6.25 1.1 4.6625 2.5
PH RDC 0.61 0.175 12.3 1.86 9.363 2.1525
PH 1er E 0.61 0.175 17.6 2.13 12.866 3.08
PH 2ème E 0.61 0.175 17.6 2.13 12.866 3.08
PH 3ème E 0.61 0.175 17.6 2.13 12.866 3.08
PH 4ème E 0.742 0.15 17.6 2.13 15.1892 2.64

P(A7)
Niveau G(t) Q(t) S (m²) p.p(poutres)(t) G'(t) Q'(t)
PH sous-sol 0.61 0.4 5.88 1.12 4.71 3.59
PH RDC 0.61 0.175 5.88 1.18 4.77 3.59
PH 1er E 0.61 0.175 5.88 1.04 4.63 3.59
PH 2ème E 0.61 0.175 5.88 1.04 4.63 3.59
PH 3ème E 0.61 0.175 5.88 1.04 4.63 3.59
PH 4ème E 0.742 0.15 5.88 1.04 5.40 4.36
Pu(t) Ps(t) Nu(t) Ns(t) Nuc(t) Nsc(t)
9.270075 6.6245 10.1970825 7.28695 10.1970825 7.28695
7.2201 5.24225 7.94211 5.766475 18.1391925 13.053425
7.2201 5.24225 7.94211 5.766475 26.0813025 18.8199
7.2201 5.24225 7.94211 5.766475 34.0234125 24.586375
7.2201 5.24225 7.94211 5.766475 41.9655225 30.35285
7.986915 5.8254 8.7856065 6.40794 50.751129 36.76079

Pu(t) Ps(t) Nu(t) Ns(t) Nuc(t) Nsc(t)


10.044375 7.1625 11.0488125 7.87875 11.0488125 7.87875
15.8688 11.5155 17.45568 12.66705 28.5044925 20.5458
21.9891 15.946 24.18801 17.5406 52.6925025 38.0864
21.9891 15.946 24.18801 17.5406 76.8805125 55.627
21.9891 15.946 24.18801 17.5406 101.068523 73.1676
24.46542 17.8292 26.911962 19.61212 127.980485 92.77972

Pu(t) Ps(t) Nu(t) Ns(t) Nuc(t) Nsc(t)


11.73 8.29 12.91 9.12 12.91 9.12
11.82 8.35 13.00 9.19 25.91 18.31
11.63 8.21 12.79 9.03 38.70 27.34
11.63 8.21 12.79 9.03 51.48 36.38
11.63 8.21 12.79 9.03 64.27 45.41
13.84 9.77 15.22 10.74 79.50 56.16
P(7A)
Niveau G(t/m²) Q(t/m²) S(m²) P.Propre(t) G'(t) Q'(t) Pu(t)
PH RDC 0.61 0.175 5.24 1.12 4.32 0.92 7.20
PH 1er E 0.61 0.175 5.24 1 4.20 0.92 7.04
PH 2ème E 0.61 0.175 5.24 1 4.20 0.92 7.04
PH 3ème E 0.61 0.175 5.24 1 4.20 0.92 7.04
Terrasse 0.742 0.15 5.24 1 4.89 0.79 7.78

P(3G)
Niveau G(t/m²) Q(t/m²) S(m²) P.Propre(t) G'(t) Q'(t) Pu(t)
PH RDC 0.61 0.175 14.64 1.31 10.2404 0.785 15.00204
PH 1er E 0.61 0.175 13.72 1.37 9.7392 0.785 14.86542
PH 2ème E 0.61 0.175 13.72 1.37 9.7392 0.785 14.86542
PH 3ème E 0.61 0.175 13.72 1.37 9.7392 0.785 14.86542
Terrasse 0.742 0.15 13.72 1.37 11.55024 0.892 17.470824

P(A5)
Niveau G(t) Q(t) S(m²) p.p(poutres)(t) G'(t) Q'(t) Pu(t)
PH RDC 0.61 0.175 16.12 2.23 12.0632 2.821 20.51682
PH 1er E 0.61 0.175 16.12 1.87 11.7032 2.821 20.03082
PH 2ème E 0.61 0.175 16.12 1.87 11.7032 2.821 20.03082
PH 3ème E 0.61 0.175 16.12 1.87 11.7032 2.821 20.03082
PH 4ème E 0.742 0.15 16.12 1.87 13.83104 2.418 22.298904
Ps(t) Nu(t) Ns(t) Nuc(t) Nsc(t)
5.23 7.92 5.76 7.92 5.76
5.11 7.74 5.62 15.67 11.38
5.11 7.74 5.62 23.41 17.01
5.11 7.74 5.62 31.16 22.63
5.67 8.56 6.24 39.71 28.87

Ps(t) Nu(t) Ns(t) Nuc(t) Nsc(t)


11.0254 16.502244 12.12794 16.502244 12.12794
10.9142 16.351962 12.00562 32.854206 24.13356
10.9142 16.351962 12.00562 49.206168 36.13918
10.9142 16.351962 12.00562 65.55813 48.1448
12.83224 19.2179064 14.115464 84.7760364 62.260264

Ps(t) Nu(t) Ns(t) Nuc(t) Nsc(t)


14.8842 22.568502 16.37262 22.568502 16.37262
14.5242 22.033902 15.97662 44.602404 32.34924
14.5242 22.033902 15.97662 66.636306 48.32586
14.5242 22.033902 15.97662 82.612926 64.30248
16.24904 24.5287944 17.873944 100.48687 82.176424