TRAVAUX DE CONSTRUCTION D'UN CLINIQUE DE JOUR AU CENTRE JEBHA

N° Nom de la tâche Durée Début Fin 03 Jul 22


10 Jul 22
17 Jul 22
24 Jul 22
31 Jul 22
07 Aoû 22
14 Aoû 22
21 Aoû 22
28 Aoû 04
22 Sep 22
11 Sep 22
18 Sep 22
25 Sep 02
22 Oct 09
22 Oct 22
16 Oct 22
23 Oct 30
22 Oct 06
22 Nov 22
13 Nov 22
20 Nov 27
22 Nov 04
22 Déc 22
11 Déc 22
18 Déc 22
25 Déc 22
01 Jan 23
08 Jan 23
15 Jan 23
22 Jan 23
29 Jan 23
05 Fév 23
12 Fév 23
19 Fév 23
26 Fév 23
05 Mar 12
23 Mar 23
19 Mar 26
23 Mar 02
23 Avr 23
09 Avr 23
16 Avr 23
23 Avr 23
30 Avr 23
07 Mai 23
14 Mai 23
21 Mai 23
28 Mai 23
04 Jui 23
11 Jui 23
18 Jui 23
25 Jui 23
02 Jul 23
09 Jul 23
16 Jul 23
23 Jul 23
30 Jul 23
06 Aoû 23
13 Aoû 23
20 Aoû 27
23 Aoû 03
23 Sep 23
10 Sep 23
17 Sep 23
24 Sep 23
01 Oct 23
08 Oct 23
15 Oct 23
22 Oct 29
23 Oct 05
23 Nov 23
12 Nov 23
19 Nov 23
26 Nov 03
23 Déc 23
10 Déc 23
17 Déc 23
24 Déc 23
31 Déc 23
07 Jan 24
14 Jan 24
21 Jan 24
28 Jan 24
1
TRAVAUX DE CONSTRUCTION 18 mois Mer 20/07/22 Mer 17/01/24 TRAVAUX DE CONSTRUCTION D’UNE CLINIQUE DU JOUR AU CENTRE JEBHA A LA COMMUNE DE MTIOUA

D’UNE CLINIQUE DU JOUR AU 18 mois


CENTRE JEBHA A LA COMMUNE
DE MTIOUA
2 INSTALLATION DE CHANTIER 45 jrs Mer 20/07/22 Jeu 29/09/22 INSTALLATION DE CHANTIER
45 jrs

3 PREPARTION;DECAPAGE ET NIVELLEMENT 15 jrs Mer 20/07/22 Ven 12/08/22


PREPARTION;DECAPAGE ET NIVELLEMENT DU TERRAIN
DU TERRAIN 15 jrs

4 298,38 jrs Jeu 15/09/22 Jeu 04/01/24 GROS OEUVRES BLOC 2-6
GROS OEUVRES BLOC 2-6
298,38 jrs

5 85 jrs Ven 16/09/22 Mar 31/01/23


FONDATIONS FONDATIONS
85 jrs
25 BOISEUR *15 FERRAILLEUR *20 OUVRIER *2 TRACEUR

6 30 jrs Ven 16/09/22 Jeu 03/11/22


FOUILLES EN MASSE ET EN FOUILLES EN MASSE ET EN RIGOULE DANS TOUT TERRAIN Y COMPRIS ROCHEAUX
RIGOULE DANS TOUT TERRAIN Y 30 jrs
COMPRIS ROCHEAUX

7 10 jrs Mer 09/11/22 Jeu 24/11/22


GROS BETON OU BETON DE GROS BETON OU BETON DE PROPRETE
PROPRETE 10 jrs

8
BETON POUR RADIER OU SEMELLES 15 jrs Mer 16/11/22 Ven 09/12/22 BETON POUR RADIER OU SEMELLES Y/C COFFRAGE, POSE D'ACIER ,RECEPTION ET COULAGE
Y/C COFFRAGE, POSE D'ACIER 15 jrs
,RECEPTION ET COULAGE

9 7 jrs Jeu 29/12/22 Mar 10/01/23


FUTS DE POTEAUX ET VOILES ET FUTS DE POTEAUX ET VOILES ET LANGRINE ( COFFRAGE ET BETONNAGE )
LANGRINE ( COFFRAGE ET 7 jrs
BETONNAGE )

10 5 jrs Jeu 05/01/23 Jeu 12/01/23


REMBLAIS POUR MIS A NIVEAU REMBLAIS POUR MIS A NIVEAU
5 jrs

11 5 jrs Mar 27/12/22 Mar 03/01/23


MISE A LA TERRE ET MISE A LA TERRE ET ASSAINISSEMENT
ASSAINISSEMENT 5 jrs

12 15 jrs Ven 06/01/23 Mar 31/01/23


HERISSON DES PIERRES SECHES HERISSON DES PIERRES SECHES COFFRAGE, POSE DE FERRAILLAGE ET BETONNAGE DALLAGE
COFFRAGE, POSE DE FERRAILLAGE 15 jrs
ET BETONNAGE DALLAGE

13 181 jrs Ven 06/01/23 Mar 24/10/23


NIVEAU RDC NIVEAU RDC
181 jrs
30 BOISEUR *20 FERRAILLEUR *20 OUVRIER * 10 MASSON *2 TRACEUR...

14 15 jrs Ven 06/01/23 Mar 31/01/23


COFFRAGE ET BETONNAGE DES COFFRAGE ET BETONNAGE DES POTEAUX
POTEAUX 15 jrs

15 50 jrs Mar 24/01/23 Jeu 13/04/23


COFFRAGE ET BETONNAGE DE COFFRAGE ET BETONNAGE DE PLANCHER ET ESCALIER
PLANCHER ET ESCALIER 50 jrs

16 35 jrs Mer 24/05/23 Mer 19/07/23


MACONNERIE COFFRAGE ET MACONNERIE COFFRAGE ET BETONNAGE (lintex,raidissr,appuis fené)
BETONNAGE (lintex,raidissr,appuis 35 jrs
fené)

17
ENDUIT INTERIEUR (ACCROCHAGE, 40 jrs Lun 21/08/23 Mar 24/10/23 ENDUIT INTERIEUR (ACCROCHAGE, DRESSAGE ET FINITION)
DRESSAGE ET FINITION) 40 jrs

18 136 jrs Ven 14/04/23 Ven 17/11/23


NIVEAU 1ER ETAGE NIVEAU 1ER ETAGE
136 jrs
20 BOISEUR *10 FERRAILLEUR *10 OUVRIER * 6 MASSON *2 TRACEUR...

19 15 jrs Ven 14/04/23 Mar 09/05/23


POTEAUX COFFRAGE ET POTEAUX COFFRAGE ET BETONNAGE
BETONNAGE 15 jrs

20 35 jrs Mar 02/05/23 Mar 27/06/23


COFFRAGE ET BETONNAGE DE COFFRAGE ET BETONNAGE DE PLANCHER ET ESCALIER
PLANCHER ET ESCALIER 35 jrs

21 25 jrs Lun 07/08/23 Jeu 14/09/23


MACONNERIE COFFRAGE ET MACONNERIE COFFRAGE ET BETONNAGE (lintex,raidissr,appuis fené)
BETONNAGE (lintex,raidissr,appuis 25 jrs
fené)

22
ENDUIT INTERIEUR (ACCROCHAGE, 20 jrs Mar 17/10/23 Ven 17/11/23 ENDUIT INTERIEUR (ACCROCHAGE, DRESSAGE ET FINITION)
DRESSAGE ET FINITION) 20 jrs

23 120 jrs Mar 27/06/23 Jeu 04/01/24


TERRASSE TERRASSE
120 jrs

24 25 jrs Mar 27/06/23 Lun 07/08/23


Coffrage et bétonnage d'acrotére Coffrage et bétonnage d'acrotére
25 jrs

25 50 jrs Lun 07/08/23 Mer 25/10/23


L'enduit Des Façades L'enduit Des Façades
50 jrs

26 55 jrs Lun 09/10/23 Jeu 04/01/24


réalisation d'étancheité (toiture réalisation d'étancheité (toiture terrasse)
terrasse) 55 jrs

Projet : msproj11 Tâche Jalon Récapitulatif du projet Jalons externes Jalon inactif Tâche manuelle Report récapitulatif manuel Début uniquement Échéance Progression manuelle
Date : Lun 31/10/22 Fractionnement Récapitulative Tâches externes Tâche inactive Récapitulatif inactif Durée uniquement Récapitulatif manuel Fin uniquement Avancement

GROUPEMENT STE BATIHALIM S.A.R.L ET YOUSRA LITAJHIZ S.A.R.L