ANA TOWER PARKING GRAFIC DETALIAT EXECUTIE LUCRARI

Anexa la Contractul
ID Task
Task Name % Duration Start Finish Baseline Start Baseline Finish Predecessors
Mode Complete
Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 PARCARE ANA TOWER 7% 174 days? Mon 08-04-19 Thu 12-12-19 Mon 08-04-19 Wed 11-12-19
2 Semnare CONTRACT 100% 1 day? Mon 08-04-19 Mon 08-04-19 Mon 08-04-19 Mon 08-04-19 08-04
3 Predare / Primire front de lucru 100% 1 day? Thu 11-04-19 Thu 11-04-19 Thu 11-04-19 Thu 11-04-19 2FS+2 days 11-04
4 Data de Incepere a Lucrarilor 100% 1 day? Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 3FS+1 day 15-04
5 Mobilizare 100% 5 days Tue 09-04-19 Mon 15-04-19 Tue 09-04-19 Mon 15-04-19 2;4FF
6 Finalizare Structura 0% 1 day? Wed 21-08-19 Wed 21-08-19 Wed 14-08-19 Wed 14-08-19 163;237;83 21-08
7 Finalizare Parcare Ana Tower 0% 1 day? Fri 01-11-19 Fri 01-11-19 Thu 31-10-19 Thu 31-10-19 243;239;244 01-11
8 Evenimente 60% 21 days Tue 16-04-19 Fri 17-05-19 NA NA
9 Intarziere livrare / montare sprijiniri la cota -7.50 100% 8 days Tue 16-04-19 Thu 25-04-19 NA NA 5
10 Modificare radier Plot 1 - Spalatorie auto 41% 16 days Tue 23-04-19 Fri 17-05-19 NA NA
11 Perioada de clarificari 88% 8 days Tue 23-04-19 Tue 07-05-19 NA NA
12 Transmitere plan actualizat sapatura 0% 0 days Tue 07-05-19 Tue 07-05-19 NA NA 11 07-05
13 Transmitere plan actualizat armare radier 0% 0 days Wed 08-05-19 Wed 08-05-19 NA NA 11FS+1 day 08-05
14 Livrare armatura radier Plot 1 0% 7 days Thu 09-05-19 Fri 17-05-19 NA NA 13
15 Durata suplimentara executie egalizare Plot 1 - implementare basa noua 0% 2 days Thu 09-05-19 Fri 10-05-19 NA NA 12;36
16 Durata de Executie 5% 139 days Mon 15-04-19 Thu 31-10-19 Mon 15-04-19 Wed 30-10-19
17 STRUCTURA 9% 94 days Mon 15-04-19 Thu 29-08-19 Mon 15-04-19 Wed 28-08-19
18 PLOT C (Plot 1 si Plot 2 din Radier) 10% 87 days Mon 15-04-19 Tue 20-08-19 Mon 15-04-19 Tue 13-08-19
19 ETAPA 2 - Placa peste S1 (-1,30) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
20 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 2FS+5 days 15-04
21 Armare incl. montare capiteluri si conectare la grinda de coronament 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 20 15-04
22 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 21 15-04
23 ETAPA 3 - Sapatura 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
24 Montare spraituri 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 22 15-04
25 Coborare NAS la cota maxima -8,90 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 22 15-04
26 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 22 15-04
27 Excavare Plot pana la cota -8,00 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 26;25 15-04
28 ETAPA 4 - Placa peste S3 (-7,50) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
29 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 27 15-04
30 Armare incl. montare capiteluri si conectare la peretele mulat 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 29 15-04
31 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 30 15-04
32 ETAPA 5 - Sapatura 89% 15 days Mon 15-04-19 Wed 08-05-19 Mon 15-04-19 Thu 02-05-19
33 Montare spraituri 80% 5 days Tue 30-04-19 Tue 07-05-19 Tue 16-04-19 Mon 22-04-19 31;5;9
34 Coborare NAS la cota maxim -13,40 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 31 15-04
35 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 31 15-04
36 Excavare Plot pana la cota -11,40 90% 8 days Mon 15-04-19 Wed 08-05-19 Mon 15-04-19 Wed 24-04-19 5FS-1 day;12FF;33FF+1 day
37 Spargere beton contaminat piloti 100% 3 days Mon 06-05-19 Wed 08-05-19 Thu 25-04-19 Thu 02-05-19 36FS-3 days
38 ETAPA 6 - Radier 0% 13 days Thu 09-05-19 Mon 27-05-19 Fri 03-05-19 Thu 23-05-19
39 Plot 1 0% 11 days Mon 13-05-19 Mon 27-05-19 Fri 03-05-19 Thu 16-05-19
40 Egalizare 0% 1 day Mon 13-05-19 Mon 13-05-19 Fri 03-05-19 Fri 03-05-19 37;15;12
41 Hidroizolatie 0% 3 days Wed 15-05-19 Fri 17-05-19 Mon 06-05-19 Wed 08-05-19 40;46
42 Armare si cofrare 0% 5 days Mon 20-05-19 Fri 24-05-19 Thu 09-05-19 Wed 15-05-19 41;14
43 Betonare 0% 1 day Mon 27-05-19 Mon 27-05-19 Thu 16-05-19 Thu 16-05-19 42
44 Plot 2 0% 10 days Thu 09-05-19 Wed 22-05-19 Mon 06-05-19 Thu 23-05-19
45 Egalizare 0% 1 day Thu 09-05-19 Thu 09-05-19 Mon 06-05-19 Mon 06-05-19 36;15SS
46 Hidroizolatie 0% 3 days Fri 10-05-19 Tue 14-05-19 Thu 09-05-19 Mon 13-05-19 45
47 Armare si cofrare 0% 5 days Wed 15-05-19 Tue 21-05-19 Thu 16-05-19 Wed 22-05-19 46
48 Betonare 0% 1 day Wed 22-05-19 Wed 22-05-19 Thu 23-05-19 Thu 23-05-19 47
49 ETAPA 7 si 8 - Eemente verticale S3 si S2 si placa peste S2 0% 40 days Tue 28-05-19 Tue 23-07-19 Fri 17-05-19 Wed 17-07-19
50 Plot 1 - S3 0% 8 days Tue 28-05-19 Thu 06-06-19 Fri 17-05-19 Fri 31-05-19
51 Hidroizolatii la peretii perimetrali 0% 2 days Tue 28-05-19 Wed 29-05-19 Fri 17-05-19 Mon 20-05-19 43
52 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 30-05-19 Wed 05-06-19 Tue 21-05-19 Mon 27-05-19 51
53 Sundare conectori nelson 0% 1 day Thu 30-05-19 Thu 30-05-19 Fri 24-05-19 Fri 24-05-19 43;48;51
54 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Fri 31-05-19 Thu 06-06-19 Mon 27-05-19 Fri 31-05-19 53
55 Plot 2 - S3 0% 16 days Thu 30-05-19 Fri 21-06-19 Fri 24-05-19 Fri 14-06-19
56 Hidroizolatii la peretii perimetrali 0% 3 days Thu 30-05-19 Mon 03-06-19 Fri 24-05-19 Tue 28-05-19 51;48
57 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 06-06-19 Wed 12-06-19 Wed 29-05-19 Tue 04-06-19 56;52
58 Sundare conectori nelson 0% 1 day Tue 04-06-19 Tue 04-06-19 Wed 29-05-19 Wed 29-05-19 56
59 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Fri 07-06-19 Thu 13-06-19 Mon 03-06-19 Fri 07-06-19 58;54
60 Finalizare placa peste S3 0% 5 days Fri 14-06-19 Fri 21-06-19 Mon 10-06-19 Fri 14-06-19 59
61 Plot 1 - S2 0% 15 days Mon 24-06-19 Fri 12-07-19 Tue 18-06-19 Mon 08-07-19
62 Hidroizolatii la peretii perimetrali 0% 2 days Mon 24-06-19 Tue 25-06-19 Tue 18-06-19 Wed 19-06-19 60
63 Armare, cofrare si betonare pereti perimetrali 0% 6 days Wed 26-06-19 Wed 03-07-19 Thu 20-06-19 Thu 27-06-19 62
64 Sundare conectori nelson 0% 1 day Wed 26-06-19 Wed 26-06-19 Thu 20-06-19 Thu 20-06-19 62
65 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Tue 02-07-19 Fri 05-07-19 Wed 26-06-19 Mon 01-07-19 64;63FS-2 days
66 Cofrare Placa peste S2 0% 2 days Mon 08-07-19 Tue 09-07-19 Tue 02-07-19 Wed 03-07-19 63;65;48FF+1 day
67 Armare Placa peste S2 0% 2 days Wed 10-07-19 Thu 11-07-19 Thu 04-07-19 Fri 05-07-19 66
68 Betonare 0% 1 day Fri 12-07-19 Fri 12-07-19 Mon 08-07-19 Mon 08-07-19 67
69 Plot 2 - S2 0% 20 days Wed 26-06-19 Tue 23-07-19 Thu 20-06-19 Wed 17-07-19
70 Hidroizolatii la peretii perimetrali 0% 3 days Wed 26-06-19 Fri 28-06-19 Thu 20-06-19 Mon 24-06-19 62
71 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 04-07-19 Wed 10-07-19 Fri 28-06-19 Thu 04-07-19 63;70
72 Sundare conectori nelson 0% 1 day Mon 01-07-19 Mon 01-07-19 Tue 25-06-19 Tue 25-06-19 70
73 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Tue 09-07-19 Fri 12-07-19 Wed 03-07-19 Mon 08-07-19 65;72;71FS-2 days
74 Cofrare Placa peste S2 0% 3 days Mon 15-07-19 Wed 17-07-19 Tue 09-07-19 Thu 11-07-19 73;116FF+1 day;128
75 Armare Placa peste S2 0% 3 days Thu 18-07-19 Mon 22-07-19 Fri 12-07-19 Tue 16-07-19 74
76 Betonare 0% 1 day Tue 23-07-19 Tue 23-07-19 Wed 17-07-19 Wed 17-07-19 75
77 ETAPA 9 - Elemente verticale S1 si finalizare placa peste S1 0% 19 days Wed 24-07-19 Tue 20-08-19 Thu 18-07-19 Tue 13-08-19
78 Plot 1 - S1 0% 19 days Wed 24-07-19 Tue 20-08-19 Thu 18-07-19 Tue 13-08-19
79 Hidroizolatii la peretii perimetrali 0% 2 days Wed 24-07-19 Thu 25-07-19 Thu 18-07-19 Fri 19-07-19 76
80 Armare, cofrare si betonare pereti perimetrali 0% 5 days Fri 26-07-19 Thu 01-08-19 Mon 22-07-19 Fri 26-07-19 79
81 Sundare conectori nelson 0% 1 day Fri 26-07-19 Fri 26-07-19 Mon 22-07-19 Mon 22-07-19 79
82 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Wed 31-07-19 Mon 05-08-19 Thu 25-07-19 Tue 30-07-19 81;80FS-2 days
83 Finalizare placa peste S1 0% 5 days Tue 13-08-19 Tue 20-08-19 Wed 07-08-19 Tue 13-08-19 88
84 Plot 2 - S1 0% 12 days Fri 26-07-19 Mon 12-08-19 Mon 22-07-19 Tue 06-08-19
85 Hidroizolatii la peretii perimetrali 0% 3 days Fri 26-07-19 Tue 30-07-19 Mon 22-07-19 Wed 24-07-19 79
86 Armare, cofrare si betonare pereti perimetrali 0% 5 days Fri 02-08-19 Thu 08-08-19 Mon 29-07-19 Fri 02-08-19 85;80
87 Sundare conectori nelson 0% 1 day Wed 31-07-19 Wed 31-07-19 Thu 25-07-19 Thu 25-07-19 85
88 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Wed 07-08-19 Mon 12-08-19 Thu 01-08-19 Tue 06-08-19 87;82;86FS-2 days
89 PLOT B (Plot 3 si Plot 4 din Radier) 7% 81 days Mon 15-04-19 Mon 12-08-19 Mon 15-04-19 Tue 13-08-19
90 ETAPA 2 - Placa peste S1 (-1,30) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
91 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 2FS+5 days 15-04
92 Armare incl. montare capiteluri si conectare la grinda de coronament 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 91 15-04
93 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 92 15-04
94 ETAPA 3 - Sapatura 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
95 Montare spraituri 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 93 15-04
96 Coborare NAS la cota maxima -8,90 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 93 15-04
97 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 93 15-04
98 Excavare Plot pana la cota -8,00 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 96;97 15-04
99 ETAPA 4 - Placa peste S3 (-7,50) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
100 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 98 15-04
101 Armare incl. montare capiteluri si conectare la peretele mulat 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 100 15-04
102 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 101 15-04
103 ETAPA 5 - Sapatura 90% 16 days Mon 15-04-19 Fri 10-05-19 Mon 15-04-19 Tue 14-05-19
104 Montare spraituri 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 102 15-04
105 Coborare NAS la cota maxim -13,40 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 102 15-04
106 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 102 15-04
107 Excavare Plot pana la cota -11,40 88% 8 days Tue 23-04-19 Tue 07-05-19 Thu 25-04-19 Thu 09-05-19 105;106;36SS+6 days;5
108 Spargere beton contaminat piloti 95% 3 days Wed 08-05-19 Fri 10-05-19 Fri 10-05-19 Tue 14-05-19 107
109 ETAPA 6 - Radier 0% 22 days Fri 10-05-19 Mon 10-06-19 Wed 15-05-19 Tue 11-06-19
110 Plot 3 0% 17 days Fri 10-05-19 Mon 03-06-19 Wed 15-05-19 Tue 04-06-19
111 Egalizare incl zona basa 0% 3 days Fri 10-05-19 Tue 14-05-19 Wed 15-05-19 Fri 17-05-19 45
112 Hidroizolatie 0% 4 days Wed 15-05-19 Mon 20-05-19 Mon 20-05-19 Thu 23-05-19 111
113 Armare basa 0% 2 days Tue 21-05-19 Wed 22-05-19 Fri 24-05-19 Mon 27-05-19 112
114 Betonare fund basa 0% 1 day Thu 23-05-19 Thu 23-05-19 Tue 28-05-19 Tue 28-05-19 113
115 Armare si cofrare radier 0% 5 days Mon 27-05-19 Fri 31-05-19 Tue 28-05-19 Mon 03-06-19 113;42;47
116 Betonare 0% 1 day Mon 03-06-19 Mon 03-06-19 Tue 04-06-19 Tue 04-06-19 115
117 Plot 4 0% 19 days Wed 15-05-19 Mon 10-06-19 Mon 20-05-19 Tue 11-06-19
118 Egalizare 0% 1 day Wed 15-05-19 Wed 15-05-19 Mon 20-05-19 Mon 20-05-19 111
119 Hidroizolatie 0% 3 days Tue 21-05-19 Thu 23-05-19 Fri 24-05-19 Tue 28-05-19 112;118
120 Armare si cofrare radier 0% 5 days Mon 03-06-19 Fri 07-06-19 Tue 04-06-19 Mon 10-06-19 119;115
121 Betonare 0% 1 day Mon 10-06-19 Mon 10-06-19 Tue 11-06-19 Tue 11-06-19 120
122 ETAPA 7 - Eemente verticale S3 si S2 0% 35 days Tue 04-06-19 Tue 23-07-19 Wed 05-06-19 Wed 24-07-19
123 Plot 3 - S3 0% 15 days Tue 04-06-19 Tue 25-06-19 Wed 05-06-19 Wed 26-06-19

Title: 2019.05.06 Grafic Executie Detaliat_rev 2 Page 1 of 2 Autor: Bogdan Bazarea


Status Date: Mon 06-05-19
ANA TOWER PARKING GRAFIC DETALIAT EXECUTIE LUCRARI
Anexa la Contractul
ID Task
Task Name % Duration Start Finish Baseline Start Baseline Finish Predecessors
Mode Complete
Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
124 Hidroizolatii la peretii perimetrali 0% 2 days Tue 04-06-19 Wed 05-06-19 Wed 05-06-19 Thu 06-06-19 116
125 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 06-06-19 Wed 12-06-19 Fri 07-06-19 Thu 13-06-19 124
126 Sundare conectori nelson 0% 1 day Thu 06-06-19 Thu 06-06-19 Fri 07-06-19 Fri 07-06-19 114;124
127 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Tue 11-06-19 Tue 18-06-19 Wed 12-06-19 Wed 19-06-19 126;125FS-2 days
128 Cofrare, armare, betonare rampa S3 0% 5 days Wed 19-06-19 Tue 25-06-19 Thu 20-06-19 Wed 26-06-19 127
129 Plot 4 - S3 0% 15 days Tue 11-06-19 Tue 02-07-19 Wed 12-06-19 Wed 03-07-19
130 Hidroizolatii la peretii perimetrali 0% 3 days Tue 11-06-19 Thu 13-06-19 Wed 12-06-19 Fri 14-06-19 121;124
131 Armare, cofrare si betonare pereti perimetrali 0% 5 days Fri 14-06-19 Fri 21-06-19 Tue 18-06-19 Mon 24-06-19 125;130
132 Sundare conectori nelson 0% 1 day Fri 14-06-19 Fri 14-06-19 Tue 18-06-19 Tue 18-06-19 114;121;130
133 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Thu 20-06-19 Tue 25-06-19 Fri 21-06-19 Wed 26-06-19 127;132;131FS-2 days
134 Finalizare placa peste S3 0% 5 days Wed 26-06-19 Tue 02-07-19 Thu 27-06-19 Wed 03-07-19 128
135 Plot 3 - S2 0% 17 days Wed 26-06-19 Thu 18-07-19 Thu 27-06-19 Fri 19-07-19
136 Hidroizolatii la peretii perimetrali 0% 3 days Wed 26-06-19 Fri 28-06-19 Thu 27-06-19 Mon 01-07-19 133
137 Armare, cofrare si betonare pereti perimetrali 0% 5 days Mon 01-07-19 Fri 05-07-19 Tue 02-07-19 Mon 08-07-19 136;128
138 Sundare conectori nelson 0% 1 day Mon 01-07-19 Mon 01-07-19 Tue 02-07-19 Tue 02-07-19 136
139 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Thu 04-07-19 Tue 09-07-19 Fri 05-07-19 Wed 10-07-19 138;137FS-2 days
140 Cofrare Placa peste S2 incl. rampa 0% 3 days Wed 10-07-19 Fri 12-07-19 Thu 11-07-19 Mon 15-07-19 139
141 Armare Placa peste S2 incl rampa 0% 3 days Mon 15-07-19 Wed 17-07-19 Tue 16-07-19 Thu 18-07-19 140
142 Betonare 0% 1 day Thu 18-07-19 Thu 18-07-19 Fri 19-07-19 Fri 19-07-19 141
143 Plot 4 - S2 0% 17 days Mon 01-07-19 Tue 23-07-19 Tue 02-07-19 Wed 24-07-19
144 Hidroizolatii la peretii perimetrali 0% 3 days Mon 01-07-19 Wed 03-07-19 Tue 02-07-19 Thu 04-07-19 136
145 Armare, cofrare si betonare pereti perimetrali 0% 4 days Mon 08-07-19 Thu 11-07-19 Tue 09-07-19 Fri 12-07-19 144;137
146 Sundare conectori nelson 0% 1 day Thu 04-07-19 Thu 04-07-19 Fri 05-07-19 Fri 05-07-19 144
147 Armare, cofrare si betonare stalpi si diafragme 0% 3 days Mon 08-07-19 Wed 10-07-19 Tue 09-07-19 Thu 11-07-19 146;139FS-2 days
148 Cofrare Placa peste S2 0% 3 days Mon 15-07-19 Wed 17-07-19 Tue 16-07-19 Thu 18-07-19 147;140
149 Armare Placa peste S2 0% 3 days Thu 18-07-19 Mon 22-07-19 Fri 19-07-19 Tue 23-07-19 148;141
150 Betonare 0% 1 day Tue 23-07-19 Tue 23-07-19 Wed 24-07-19 Wed 24-07-19 149
151 ETAPA 9 - Elemente verticale S1 si finalizare placa peste S1 0% 17 days Fri 19-07-19 Mon 12-08-19 Mon 22-07-19 Tue 13-08-19
152 Plot 3 - S1 0% 14 days Fri 19-07-19 Wed 07-08-19 Mon 22-07-19 Thu 08-08-19
153 Hidroizolatii la peretii perimetrali 0% 2 days Fri 19-07-19 Mon 22-07-19 Mon 22-07-19 Tue 23-07-19 142
154 Armare, cofrare si betonare pereti perimetrali 0% 5 days Tue 23-07-19 Mon 29-07-19 Wed 24-07-19 Tue 30-07-19 153
155 Sundare conectori nelson 0% 1 day Tue 23-07-19 Tue 23-07-19 Wed 24-07-19 Wed 24-07-19 153
156 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Fri 26-07-19 Thu 01-08-19 Mon 29-07-19 Fri 02-08-19 155;154FS-2 days
157 Cofrare, armare, betonare rampa S1 0% 4 days Fri 02-08-19 Wed 07-08-19 Mon 05-08-19 Thu 08-08-19 156
158 Plot 4 - S1 0% 14 days Wed 24-07-19 Mon 12-08-19 Thu 25-07-19 Tue 13-08-19
159 Hidroizolatii la peretii perimetrali 0% 3 days Wed 24-07-19 Fri 26-07-19 Thu 25-07-19 Mon 29-07-19 153;150
160 Armare, cofrare si betonare pereti perimetrali 0% 5 days Tue 30-07-19 Mon 05-08-19 Wed 31-07-19 Tue 06-08-19 159;154
161 Sundare conectori nelson 0% 1 day Mon 29-07-19 Mon 29-07-19 Tue 30-07-19 Tue 30-07-19 159
162 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Fri 02-08-19 Wed 07-08-19 Mon 05-08-19 Thu 08-08-19 160FS-2 days;161
163 Finalizare placa peste S1 0% 3 days Thu 08-08-19 Mon 12-08-19 Fri 09-08-19 Tue 13-08-19 162;157FS-1 day
164 PLOT A (Plot 5 si Plot 6, Plot 7 din Radier) 10% 83 days Mon 15-04-19 Wed 14-08-19 Mon 15-04-19 Tue 13-08-19
165 ETAPA 2 - Placa peste S1 (-1,30) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
166 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 2FS+5 days 15-04
167 Armare incl. montare capiteluri si conectare la grinda de coronament 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 166;5 15-04
168 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 167 15-04
169 ETAPA 3 - Sapatura 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
170 Montare spraituri 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 168 15-04
171 Coborare NAS la cota maxima -8,90 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 168 15-04
172 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 168 15-04
173 Excavare Plot pana la cota -8,00 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 171;172 15-04
174 ETAPA 4 - Placa peste S3 (-7,50) 100% 7 days Tue 16-04-19 Wed 24-04-19 Tue 16-04-19 Thu 25-04-19
175 Egalizare, curatare pereti mulati, hidroizolatie, folie 100% 3 days Tue 16-04-19 Thu 18-04-19 Tue 16-04-19 Fri 19-04-19 173;5FS-1 day
176 Armare incl. montare capiteluri si conectare la peretele mulat 100% 3 days Fri 19-04-19 Tue 23-04-19 Mon 22-04-19 Wed 24-04-19 175
177 Betonare 100% 1 day Wed 24-04-19 Wed 24-04-19 Thu 25-04-19 Thu 25-04-19 176
178 ETAPA 5 - Sapatura 43% 17 days Thu 25-04-19 Wed 22-05-19 Tue 30-04-19 Thu 23-05-19
179 Montare spraituri 0% 3 days Wed 08-05-19 Fri 10-05-19 Tue 30-04-19 Tue 30-04-19 177;33
180 Coborare NAS la cota maxim -13,40 100% 4 days Thu 25-04-19 Fri 03-05-19 Tue 30-04-19 Mon 06-05-19 177
181 Intarire beton 100% 6 days Thu 25-04-19 Tue 07-05-19 Tue 30-04-19 Wed 08-05-19 177
182 Excavare Plot pana la cota -11,40 0% 7 days Thu 09-05-19 Fri 17-05-19 Fri 10-05-19 Mon 20-05-19 180;181;36;107
183 Spargere beton contaminat piloti 0% 3 days Mon 20-05-19 Wed 22-05-19 Tue 21-05-19 Thu 23-05-19 182
184 ETAPA 6 - Radier 0% 20 days Thu 23-05-19 Thu 20-06-19 Fri 24-05-19 Wed 19-06-19
185 Plot 5 0% 13 days Thu 23-05-19 Mon 10-06-19 Fri 24-05-19 Fri 07-06-19
186 Egalizare 0% 2 days Thu 23-05-19 Fri 24-05-19 Fri 24-05-19 Mon 27-05-19 183
187 Hidroizolatie 0% 3 days Mon 27-05-19 Wed 29-05-19 Tue 28-05-19 Thu 30-05-19 186
188 Armare si cofrare radier 0% 5 days Mon 03-06-19 Fri 07-06-19 Fri 31-05-19 Thu 06-06-19 187;115
189 Betonare 0% 1 day Mon 10-06-19 Mon 10-06-19 Fri 07-06-19 Fri 07-06-19 188
190 Plot 6-7 0% 18 days Mon 27-05-19 Thu 20-06-19 Tue 28-05-19 Wed 19-06-19
191 Egalizare incl. basa 0% 3 days Mon 27-05-19 Wed 29-05-19 Tue 28-05-19 Thu 30-05-19 186
192 Hidroizolatie 0% 4 days Thu 30-05-19 Tue 04-06-19 Fri 31-05-19 Wed 05-06-19 187;191
193 Armare basa 0% 2 days Mon 10-06-19 Tue 11-06-19 Fri 07-06-19 Mon 10-06-19 188;192
194 Betonare fund basa 0% 1 day Wed 12-06-19 Wed 12-06-19 Tue 11-06-19 Tue 11-06-19 193
195 Armare si cofrare radier 0% 7 days Mon 10-06-19 Wed 19-06-19 Fri 07-06-19 Tue 18-06-19 188;192
196 Betonare 0% 1 day Thu 20-06-19 Thu 20-06-19 Wed 19-06-19 Wed 19-06-19 195
197 ETAPA 7 - Eemente verticale S3 si S2 0% 33 days Tue 11-06-19 Fri 26-07-19 Mon 10-06-19 Thu 25-07-19
198 Plot 5 - S3 0% 13 days Tue 11-06-19 Fri 28-06-19 Mon 10-06-19 Thu 27-06-19
199 Hidroizolatii la peretii perimetrali 0% 2 days Tue 11-06-19 Wed 12-06-19 Mon 10-06-19 Tue 11-06-19 189
200 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 13-06-19 Thu 20-06-19 Wed 12-06-19 Wed 19-06-19 199
201 Sundare conectori nelson 0% 1 day Fri 21-06-19 Fri 21-06-19 Thu 20-06-19 Thu 20-06-19 194;199;196
202 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Mon 24-06-19 Fri 28-06-19 Fri 21-06-19 Thu 27-06-19 201;200FS-2 days
203 Plot 6-7 - S3 0% 26 days Fri 21-06-19 Fri 26-07-19 Thu 20-06-19 Thu 25-07-19
204 Hidroizolatii la peretii perimetrali 0% 5 days Fri 21-06-19 Thu 27-06-19 Thu 20-06-19 Wed 26-06-19 199;196;21
205 Armare, cofrare si betonare pereti perimetrali 0% 8 days Fri 28-06-19 Tue 09-07-19 Thu 27-06-19 Mon 08-07-19 200;204
206 Sundare conectori nelson 0% 1 day Fri 28-06-19 Fri 28-06-19 Thu 27-06-19 Thu 27-06-19 194;204;196
207 Armare, cofrare si betonare stalpi si diafragme 0% 7 days Mon 08-07-19 Tue 16-07-19 Fri 05-07-19 Mon 15-07-19 202;206;205FS-2 days
208 Cofrare, armare, betonare scara S3 0% 7 days Fri 12-07-19 Mon 22-07-19 Thu 11-07-19 Fri 19-07-19 207FS-3 days
209 Finalizare placa peste S3 0% 4 days Tue 23-07-19 Fri 26-07-19 Mon 22-07-19 Thu 25-07-19 208
210 Plot 5 - S2 0% 14 days Fri 28-06-19 Wed 17-07-19 Thu 27-06-19 Tue 16-07-19
211 Hidroizolatii la peretii perimetrali 0% 2 days Fri 28-06-19 Mon 01-07-19 Thu 27-06-19 Fri 28-06-19 204
212 Armare, cofrare si betonare pereti perimetrali 0% 4 days Tue 02-07-19 Fri 05-07-19 Mon 01-07-19 Thu 04-07-19 211;202
213 Sundare conectori nelson 0% 1 day Tue 02-07-19 Tue 02-07-19 Mon 01-07-19 Mon 01-07-19 211
214 Armare, cofrare si betonare stalpi si diafragme 0% 3 days Thu 04-07-19 Mon 08-07-19 Wed 03-07-19 Fri 05-07-19 213;212FS-2 days
215 Cofrare Placa peste S2 0% 3 days Tue 09-07-19 Thu 11-07-19 Mon 08-07-19 Wed 10-07-19 214
216 Armare Placa peste S2 0% 3 days Fri 12-07-19 Tue 16-07-19 Thu 11-07-19 Mon 15-07-19 215
217 Betonare 0% 1 day Wed 17-07-19 Wed 17-07-19 Tue 16-07-19 Tue 16-07-19 216
218 Plot 6-7 - S2 0% 17 days Tue 02-07-19 Wed 24-07-19 Mon 01-07-19 Tue 23-07-19
219 Hidroizolatii la peretii perimetrali 0% 3 days Tue 02-07-19 Thu 04-07-19 Mon 01-07-19 Wed 03-07-19 211
220 Armare, cofrare si betonare pereti perimetrali 0% 4 days Mon 08-07-19 Thu 11-07-19 Fri 05-07-19 Wed 10-07-19 212;219
221 Sundare conectori nelson 0% 1 day Fri 05-07-19 Fri 05-07-19 Thu 04-07-19 Thu 04-07-19 219
222 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Wed 10-07-19 Mon 15-07-19 Tue 09-07-19 Fri 12-07-19 220FS-2 days;221
223 Cofrare Placa peste S2 0% 3 days Tue 16-07-19 Thu 18-07-19 Mon 15-07-19 Wed 17-07-19 222
224 Armare Placa peste S2 0% 3 days Fri 19-07-19 Tue 23-07-19 Thu 18-07-19 Mon 22-07-19 223
225 Betonare 0% 1 day Wed 24-07-19 Wed 24-07-19 Tue 23-07-19 Tue 23-07-19 224
226 ETAPA 9 - Elemente verticale S1 si finalizare placa peste S1 0% 20 days Thu 18-07-19 Wed 14-08-19 Wed 17-07-19 Tue 13-08-19
227 Plot 5 - S1 0% 10 days Thu 18-07-19 Wed 31-07-19 Wed 17-07-19 Tue 30-07-19
228 Hidroizolatii la peretii perimetrali 0% 2 days Thu 18-07-19 Fri 19-07-19 Wed 17-07-19 Thu 18-07-19 219;217
229 Armare, cofrare si betonare pereti perimetrali 0% 5 days Mon 22-07-19 Fri 26-07-19 Fri 19-07-19 Thu 25-07-19 228
230 Sundare conectori nelson 0% 1 day Mon 22-07-19 Mon 22-07-19 Fri 19-07-19 Fri 19-07-19 228
231 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Thu 25-07-19 Wed 31-07-19 Wed 24-07-19 Tue 30-07-19 230;229FS-2 days
232 Plot 67 - S1 0% 18 days Mon 22-07-19 Wed 14-08-19 Fri 19-07-19 Tue 13-08-19
233 Hidroizolatii la peretii perimetrali 0% 3 days Mon 22-07-19 Wed 24-07-19 Fri 19-07-19 Tue 23-07-19 228
234 Armare, cofrare si betonare pereti perimetrali 0% 5 days Mon 29-07-19 Fri 02-08-19 Fri 26-07-19 Thu 01-08-19 229;233
235 Sundare conectori nelson 0% 1 day Thu 25-07-19 Thu 25-07-19 Wed 24-07-19 Wed 24-07-19 233
236 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Thu 01-08-19 Wed 07-08-19 Wed 31-07-19 Tue 06-08-19 235;234FS-2 days
237 Finalizare placa peste S1 0% 5 days Thu 08-08-19 Wed 14-08-19 Wed 07-08-19 Tue 13-08-19 236
238 Armare, cofrare, betonare parapeti cota 0,00 0% 20 days Thu 01-08-19 Thu 29-08-19 Wed 31-07-19 Wed 28-08-19 237FF+10 days
239 INSTALATII 0% 113 days Tue 14-05-19 Mon 21-10-19 Mon 06-05-19 Fri 18-10-19
240 Instalatii inglobate in beton 0% 60 days Tue 14-05-19 Tue 06-08-19 Mon 06-05-19 Mon 29-07-19 40
241 Instalatii aparente 0% 65 days Mon 15-07-19 Mon 14-10-19 Tue 09-07-19 Tue 08-10-19 60FS+15 days
242 Instalatii exterioare 0% 60 days Mon 29-07-19 Mon 21-10-19 Fri 26-07-19 Fri 18-10-19 209
243 ARHITECTURA 0% 105 days Tue 28-05-19 Wed 23-10-19 Mon 20-05-19 Tue 15-10-19 240SS+10 days
244 AMENAJARI EXTERIOARE 0% 45 days Fri 30-08-19 Thu 31-10-19 Thu 29-08-19 Wed 30-10-19 237FS+10 days
245 Receptie 0% 20 days Fri 01-11-19 Thu 28-11-19 Thu 31-10-19 Wed 27-11-19 244;239;243
246 Demobilizare 0% 10 days Fri 29-11-19 Thu 12-12-19 Thu 28-11-19 Wed 11-12-19 245