Académique Documents
Professionnel Documents
Culture Documents
2019.05.06 Grafic Executie Detaliat - Rev 2 PDF
2019.05.06 Grafic Executie Detaliat - Rev 2 PDF
Anexa la Contractul
ID Task
Task Name % Duration Start Finish Baseline Start Baseline Finish Predecessors
Mode Complete
Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 PARCARE ANA TOWER 7% 174 days? Mon 08-04-19 Thu 12-12-19 Mon 08-04-19 Wed 11-12-19
2 Semnare CONTRACT 100% 1 day? Mon 08-04-19 Mon 08-04-19 Mon 08-04-19 Mon 08-04-19 08-04
3 Predare / Primire front de lucru 100% 1 day? Thu 11-04-19 Thu 11-04-19 Thu 11-04-19 Thu 11-04-19 2FS+2 days 11-04
4 Data de Incepere a Lucrarilor 100% 1 day? Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 3FS+1 day 15-04
5 Mobilizare 100% 5 days Tue 09-04-19 Mon 15-04-19 Tue 09-04-19 Mon 15-04-19 2;4FF
6 Finalizare Structura 0% 1 day? Wed 21-08-19 Wed 21-08-19 Wed 14-08-19 Wed 14-08-19 163;237;83 21-08
7 Finalizare Parcare Ana Tower 0% 1 day? Fri 01-11-19 Fri 01-11-19 Thu 31-10-19 Thu 31-10-19 243;239;244 01-11
8 Evenimente 60% 21 days Tue 16-04-19 Fri 17-05-19 NA NA
9 Intarziere livrare / montare sprijiniri la cota -7.50 100% 8 days Tue 16-04-19 Thu 25-04-19 NA NA 5
10 Modificare radier Plot 1 - Spalatorie auto 41% 16 days Tue 23-04-19 Fri 17-05-19 NA NA
11 Perioada de clarificari 88% 8 days Tue 23-04-19 Tue 07-05-19 NA NA
12 Transmitere plan actualizat sapatura 0% 0 days Tue 07-05-19 Tue 07-05-19 NA NA 11 07-05
13 Transmitere plan actualizat armare radier 0% 0 days Wed 08-05-19 Wed 08-05-19 NA NA 11FS+1 day 08-05
14 Livrare armatura radier Plot 1 0% 7 days Thu 09-05-19 Fri 17-05-19 NA NA 13
15 Durata suplimentara executie egalizare Plot 1 - implementare basa noua 0% 2 days Thu 09-05-19 Fri 10-05-19 NA NA 12;36
16 Durata de Executie 5% 139 days Mon 15-04-19 Thu 31-10-19 Mon 15-04-19 Wed 30-10-19
17 STRUCTURA 9% 94 days Mon 15-04-19 Thu 29-08-19 Mon 15-04-19 Wed 28-08-19
18 PLOT C (Plot 1 si Plot 2 din Radier) 10% 87 days Mon 15-04-19 Tue 20-08-19 Mon 15-04-19 Tue 13-08-19
19 ETAPA 2 - Placa peste S1 (-1,30) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
20 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 2FS+5 days 15-04
21 Armare incl. montare capiteluri si conectare la grinda de coronament 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 20 15-04
22 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 21 15-04
23 ETAPA 3 - Sapatura 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
24 Montare spraituri 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 22 15-04
25 Coborare NAS la cota maxima -8,90 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 22 15-04
26 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 22 15-04
27 Excavare Plot pana la cota -8,00 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 26;25 15-04
28 ETAPA 4 - Placa peste S3 (-7,50) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
29 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 27 15-04
30 Armare incl. montare capiteluri si conectare la peretele mulat 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 29 15-04
31 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 30 15-04
32 ETAPA 5 - Sapatura 89% 15 days Mon 15-04-19 Wed 08-05-19 Mon 15-04-19 Thu 02-05-19
33 Montare spraituri 80% 5 days Tue 30-04-19 Tue 07-05-19 Tue 16-04-19 Mon 22-04-19 31;5;9
34 Coborare NAS la cota maxim -13,40 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 31 15-04
35 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 31 15-04
36 Excavare Plot pana la cota -11,40 90% 8 days Mon 15-04-19 Wed 08-05-19 Mon 15-04-19 Wed 24-04-19 5FS-1 day;12FF;33FF+1 day
37 Spargere beton contaminat piloti 100% 3 days Mon 06-05-19 Wed 08-05-19 Thu 25-04-19 Thu 02-05-19 36FS-3 days
38 ETAPA 6 - Radier 0% 13 days Thu 09-05-19 Mon 27-05-19 Fri 03-05-19 Thu 23-05-19
39 Plot 1 0% 11 days Mon 13-05-19 Mon 27-05-19 Fri 03-05-19 Thu 16-05-19
40 Egalizare 0% 1 day Mon 13-05-19 Mon 13-05-19 Fri 03-05-19 Fri 03-05-19 37;15;12
41 Hidroizolatie 0% 3 days Wed 15-05-19 Fri 17-05-19 Mon 06-05-19 Wed 08-05-19 40;46
42 Armare si cofrare 0% 5 days Mon 20-05-19 Fri 24-05-19 Thu 09-05-19 Wed 15-05-19 41;14
43 Betonare 0% 1 day Mon 27-05-19 Mon 27-05-19 Thu 16-05-19 Thu 16-05-19 42
44 Plot 2 0% 10 days Thu 09-05-19 Wed 22-05-19 Mon 06-05-19 Thu 23-05-19
45 Egalizare 0% 1 day Thu 09-05-19 Thu 09-05-19 Mon 06-05-19 Mon 06-05-19 36;15SS
46 Hidroizolatie 0% 3 days Fri 10-05-19 Tue 14-05-19 Thu 09-05-19 Mon 13-05-19 45
47 Armare si cofrare 0% 5 days Wed 15-05-19 Tue 21-05-19 Thu 16-05-19 Wed 22-05-19 46
48 Betonare 0% 1 day Wed 22-05-19 Wed 22-05-19 Thu 23-05-19 Thu 23-05-19 47
49 ETAPA 7 si 8 - Eemente verticale S3 si S2 si placa peste S2 0% 40 days Tue 28-05-19 Tue 23-07-19 Fri 17-05-19 Wed 17-07-19
50 Plot 1 - S3 0% 8 days Tue 28-05-19 Thu 06-06-19 Fri 17-05-19 Fri 31-05-19
51 Hidroizolatii la peretii perimetrali 0% 2 days Tue 28-05-19 Wed 29-05-19 Fri 17-05-19 Mon 20-05-19 43
52 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 30-05-19 Wed 05-06-19 Tue 21-05-19 Mon 27-05-19 51
53 Sundare conectori nelson 0% 1 day Thu 30-05-19 Thu 30-05-19 Fri 24-05-19 Fri 24-05-19 43;48;51
54 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Fri 31-05-19 Thu 06-06-19 Mon 27-05-19 Fri 31-05-19 53
55 Plot 2 - S3 0% 16 days Thu 30-05-19 Fri 21-06-19 Fri 24-05-19 Fri 14-06-19
56 Hidroizolatii la peretii perimetrali 0% 3 days Thu 30-05-19 Mon 03-06-19 Fri 24-05-19 Tue 28-05-19 51;48
57 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 06-06-19 Wed 12-06-19 Wed 29-05-19 Tue 04-06-19 56;52
58 Sundare conectori nelson 0% 1 day Tue 04-06-19 Tue 04-06-19 Wed 29-05-19 Wed 29-05-19 56
59 Armare, cofrare si betonare stalpi si diafragme 0% 5 days Fri 07-06-19 Thu 13-06-19 Mon 03-06-19 Fri 07-06-19 58;54
60 Finalizare placa peste S3 0% 5 days Fri 14-06-19 Fri 21-06-19 Mon 10-06-19 Fri 14-06-19 59
61 Plot 1 - S2 0% 15 days Mon 24-06-19 Fri 12-07-19 Tue 18-06-19 Mon 08-07-19
62 Hidroizolatii la peretii perimetrali 0% 2 days Mon 24-06-19 Tue 25-06-19 Tue 18-06-19 Wed 19-06-19 60
63 Armare, cofrare si betonare pereti perimetrali 0% 6 days Wed 26-06-19 Wed 03-07-19 Thu 20-06-19 Thu 27-06-19 62
64 Sundare conectori nelson 0% 1 day Wed 26-06-19 Wed 26-06-19 Thu 20-06-19 Thu 20-06-19 62
65 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Tue 02-07-19 Fri 05-07-19 Wed 26-06-19 Mon 01-07-19 64;63FS-2 days
66 Cofrare Placa peste S2 0% 2 days Mon 08-07-19 Tue 09-07-19 Tue 02-07-19 Wed 03-07-19 63;65;48FF+1 day
67 Armare Placa peste S2 0% 2 days Wed 10-07-19 Thu 11-07-19 Thu 04-07-19 Fri 05-07-19 66
68 Betonare 0% 1 day Fri 12-07-19 Fri 12-07-19 Mon 08-07-19 Mon 08-07-19 67
69 Plot 2 - S2 0% 20 days Wed 26-06-19 Tue 23-07-19 Thu 20-06-19 Wed 17-07-19
70 Hidroizolatii la peretii perimetrali 0% 3 days Wed 26-06-19 Fri 28-06-19 Thu 20-06-19 Mon 24-06-19 62
71 Armare, cofrare si betonare pereti perimetrali 0% 5 days Thu 04-07-19 Wed 10-07-19 Fri 28-06-19 Thu 04-07-19 63;70
72 Sundare conectori nelson 0% 1 day Mon 01-07-19 Mon 01-07-19 Tue 25-06-19 Tue 25-06-19 70
73 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Tue 09-07-19 Fri 12-07-19 Wed 03-07-19 Mon 08-07-19 65;72;71FS-2 days
74 Cofrare Placa peste S2 0% 3 days Mon 15-07-19 Wed 17-07-19 Tue 09-07-19 Thu 11-07-19 73;116FF+1 day;128
75 Armare Placa peste S2 0% 3 days Thu 18-07-19 Mon 22-07-19 Fri 12-07-19 Tue 16-07-19 74
76 Betonare 0% 1 day Tue 23-07-19 Tue 23-07-19 Wed 17-07-19 Wed 17-07-19 75
77 ETAPA 9 - Elemente verticale S1 si finalizare placa peste S1 0% 19 days Wed 24-07-19 Tue 20-08-19 Thu 18-07-19 Tue 13-08-19
78 Plot 1 - S1 0% 19 days Wed 24-07-19 Tue 20-08-19 Thu 18-07-19 Tue 13-08-19
79 Hidroizolatii la peretii perimetrali 0% 2 days Wed 24-07-19 Thu 25-07-19 Thu 18-07-19 Fri 19-07-19 76
80 Armare, cofrare si betonare pereti perimetrali 0% 5 days Fri 26-07-19 Thu 01-08-19 Mon 22-07-19 Fri 26-07-19 79
81 Sundare conectori nelson 0% 1 day Fri 26-07-19 Fri 26-07-19 Mon 22-07-19 Mon 22-07-19 79
82 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Wed 31-07-19 Mon 05-08-19 Thu 25-07-19 Tue 30-07-19 81;80FS-2 days
83 Finalizare placa peste S1 0% 5 days Tue 13-08-19 Tue 20-08-19 Wed 07-08-19 Tue 13-08-19 88
84 Plot 2 - S1 0% 12 days Fri 26-07-19 Mon 12-08-19 Mon 22-07-19 Tue 06-08-19
85 Hidroizolatii la peretii perimetrali 0% 3 days Fri 26-07-19 Tue 30-07-19 Mon 22-07-19 Wed 24-07-19 79
86 Armare, cofrare si betonare pereti perimetrali 0% 5 days Fri 02-08-19 Thu 08-08-19 Mon 29-07-19 Fri 02-08-19 85;80
87 Sundare conectori nelson 0% 1 day Wed 31-07-19 Wed 31-07-19 Thu 25-07-19 Thu 25-07-19 85
88 Armare, cofrare si betonare stalpi si diafragme 0% 4 days Wed 07-08-19 Mon 12-08-19 Thu 01-08-19 Tue 06-08-19 87;82;86FS-2 days
89 PLOT B (Plot 3 si Plot 4 din Radier) 7% 81 days Mon 15-04-19 Mon 12-08-19 Mon 15-04-19 Tue 13-08-19
90 ETAPA 2 - Placa peste S1 (-1,30) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
91 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 2FS+5 days 15-04
92 Armare incl. montare capiteluri si conectare la grinda de coronament 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 91 15-04
93 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 92 15-04
94 ETAPA 3 - Sapatura 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
95 Montare spraituri 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 93 15-04
96 Coborare NAS la cota maxima -8,90 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 93 15-04
97 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 93 15-04
98 Excavare Plot pana la cota -8,00 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 96;97 15-04
99 ETAPA 4 - Placa peste S3 (-7,50) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 15-04
100 Egalizare (incl. folie) 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 98 15-04
101 Armare incl. montare capiteluri si conectare la peretele mulat 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 100 15-04
102 Betonare 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 101 15-04
103 ETAPA 5 - Sapatura 90% 16 days Mon 15-04-19 Fri 10-05-19 Mon 15-04-19 Tue 14-05-19
104 Montare spraituri 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 102 15-04
105 Coborare NAS la cota maxim -13,40 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 102 15-04
106 Intarire beton 100% 0 days Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 Mon 15-04-19 102 15-04
107 Excavare Plot pana la cota -11,40 88% 8 days Tue 23-04-19 Tue 07-05-19 Thu 25-04-19 Thu 09-05-19 105;106;36SS+6 days;5
108 Spargere beton contaminat piloti 95% 3 days Wed 08-05-19 Fri 10-05-19 Fri 10-05-19 Tue 14-05-19 107
109 ETAPA 6 - Radier 0% 22 days Fri 10-05-19 Mon 10-06-19 Wed 15-05-19 Tue 11-06-19
110 Plot 3 0% 17 days Fri 10-05-19 Mon 03-06-19 Wed 15-05-19 Tue 04-06-19
111 Egalizare incl zona basa 0% 3 days Fri 10-05-19 Tue 14-05-19 Wed 15-05-19 Fri 17-05-19 45
112 Hidroizolatie 0% 4 days Wed 15-05-19 Mon 20-05-19 Mon 20-05-19 Thu 23-05-19 111
113 Armare basa 0% 2 days Tue 21-05-19 Wed 22-05-19 Fri 24-05-19 Mon 27-05-19 112
114 Betonare fund basa 0% 1 day Thu 23-05-19 Thu 23-05-19 Tue 28-05-19 Tue 28-05-19 113
115 Armare si cofrare radier 0% 5 days Mon 27-05-19 Fri 31-05-19 Tue 28-05-19 Mon 03-06-19 113;42;47
116 Betonare 0% 1 day Mon 03-06-19 Mon 03-06-19 Tue 04-06-19 Tue 04-06-19 115
117 Plot 4 0% 19 days Wed 15-05-19 Mon 10-06-19 Mon 20-05-19 Tue 11-06-19
118 Egalizare 0% 1 day Wed 15-05-19 Wed 15-05-19 Mon 20-05-19 Mon 20-05-19 111
119 Hidroizolatie 0% 3 days Tue 21-05-19 Thu 23-05-19 Fri 24-05-19 Tue 28-05-19 112;118
120 Armare si cofrare radier 0% 5 days Mon 03-06-19 Fri 07-06-19 Tue 04-06-19 Mon 10-06-19 119;115
121 Betonare 0% 1 day Mon 10-06-19 Mon 10-06-19 Tue 11-06-19 Tue 11-06-19 120
122 ETAPA 7 - Eemente verticale S3 si S2 0% 35 days Tue 04-06-19 Tue 23-07-19 Wed 05-06-19 Wed 24-07-19
123 Plot 3 - S3 0% 15 days Tue 04-06-19 Tue 25-06-19 Wed 05-06-19 Wed 26-06-19