1.49 -1.45
P= 2.01 P= 1.99
-1.32 1.36
0.68 0.7 0.48 -1.87
D C B A
MOMENTOS POR CARGA VIVA
0.25 -0.25
P= 0.35 P= 0.35
-0.12 0.12
0.1 0.11 -0.03 -0.17
D C B A
MOMENTOS POR SISMO
2.91 2.78
P= 1.14 P= 1.14
2.52 2.67
1.7 2.89 4.78 1.24
D C B A
MOMENTOS MAYORADOS Mu = 1.4 *Mn + 1.7 *Mv
D C B A
MOMENTOS MAYORADOS Mu = 1.25 (Mn+Mv)+ 1 *S
D C B A
MOMENTOS MAYORADOS Mu = 1.25 (Mn+Mv)+ -1 *S
D C B A
MOMENTOS MAYORADOS Mu = 0.9 (Mn) + 1 *S
D C B A
MOMENTOS MAYORADOS Mu = 0.9 (Mn) + -1 *S
D C B A
COLUMNA 1-A: CARGAS Y MOMENTOS DE DISEÑO
1.25(D+L)+S 4.07 Tn 7.74 Tn 4.52 Tn.m 8.44 Tn.m 11.80 Tn 0.38 m 0.72 m
1.25(D+L)-S 1.79 Tn 5.04 Tn 4.91 Tn.m 10.43 Tn.m 6.82 Tn 0.42 m 0.88 m
0.9D+S 2.93 Tn 5.20 Tn 3.89 Tn.m 6.64 Tn.m 8.13 Tn 0.33 m 0.56 m
0.9D-S 0.67 Tn 2.50 Tn 3.71 Tn.m 9.13 Tn.m 3.17 Tn 0.31 m 0.77 m
1.4D+1.7L 9.73 Tn 7.01 Tn 2.90 Tn.m 1.04 Tn.m 16.74 Tn 0.14 m 0.05 m
5º PISO
1.25(D+L)+S 11.15 Tn 9.12 Tn 6.63 Tn.m 2.28 Tn.m 20.27 Tn 0.33 m 0.11 m
1.25(D+L)-S 5.85 Tn 3.10 Tn 1.58 Tn.m 4.08 Tn.m 8.95 Tn 0.08 m 0.20 m
0.9D+S 8.14 Tn 6.93 Tn 5.69 Tn.m 2.61 Tn.m 15.07 Tn 0.28 m 0.13 m
0.9D-S 2.84 Tn 0.91 Tn 2.51 Tn.m 3.75 Tn.m 3.75 Tn 0.12 m 0.18 m
1.4D+1.7L 17.00 Tn 12.23 Tn 2.90 Tn.m 1.08 Tn.m 29.23 Tn 0.08 m 0.03 m
4º PISO
1.25(D+L)+S 19.53 Tn 16.96 Tn 7.07 Tn.m 2.77 Tn.m 36.49 Tn 0.19 m 0.08 m
1.25(D+L)-S 10.09 Tn 4.32 Tn 2.05 Tn.m 4.65 Tn.m 14.41 Tn 0.06 m 0.13 m
0.9D+S 14.15 Tn 13.03 Tn 6.13 Tn.m 3.13 Tn.m 27.19 Tn 0.17 m 0.09 m
0.9D-S 4.71 Tn 0.39 Tn 2.99 Tn.m 4.29 Tn.m 5.11 Tn 0.08 m 0.12 m
1.4D+1.7L 24.23 Tn 17.47 Tn 2.83 Tn.m 1.07 Tn.m 41.70 Tn 0.05 m 0.02 m
3º PISO
1.25(D+L)+S 28.52 Tn 25.76 Tn 6.96 Tn.m 3.04 Tn.m 54.27 Tn 0.13 m 0.06 m
1.25(D+L)-S 13.66 Tn 4.60 Tn 2.06 Tn.m 4.89 Tn.m 18.25 Tn 0.04 m 0.09 m
0.9D+S 20.78 Tn 20.08 Tn 6.03 Tn.m 3.39 Tn.m 40.86 Tn 0.11 m 0.06 m
0.9D-S 5.92 Tn -1.08 Tn 2.99 Tn.m 4.53 Tn.m 4.84 Tn 0.06 m 0.08 m
1.4D+1.7L 31.40 Tn 22.71 Tn 2.90 Tn.m 1.20 Tn.m 54.11 Tn 0.040 m 0.016 m
2º PISO
1.25(D+L)+S 37.85 Tn 35.15 Tn 5.17 Tn.m 2.22 Tn.m 73.01 Tn 0.071 m 0.030 m
1.25(D+L)-S 16.77 Tn 4.27 Tn 0.15 Tn.m 4.30 Tn.m 21.05 Tn 0.002 m 0.059 m
0.9D+S 27.78 Tn 27.73 Tn 4.23 Tn.m 2.62 Tn.m 55.51 Tn 0.058 m 0.036 m
0.9D-S 6.70 Tn -3.15 Tn 1.09 Tn.m 3.90 Tn.m 3.55 Tn 0.015 m 0.053 m
1.4D+1.7L 38.48 Tn 27.95 Tn 2.39 Tn.m 0.87 Tn.m 66.44 Tn 0.026 m 0.009 m
1º PISO
1.25(D+L)+S 46.98 Tn 44.47 Tn 11.88 Tn.m 4.89 Tn.m 91.45 Tn 0.130 m 0.053 m
1.25(D+L)-S 19.94 Tn 4.03 Tn 10.53 Tn.m 5.60 Tn.m 23.97 Tn 0.115 m 0.061 m
0.9D+S 34.60 Tn 35.30 Tn 11.62 Tn.m 5.02 Tn.m 69.90 Tn 0.127 m 0.055 m
0.9D-S 7.56 Tn -5.14 Tn 10.78 Tn.m 5.47 Tn.m 2.42 Tn 0.118 m 0.060 m
DISEÑO
DISEÑO PARA EL PRIMER Y SEGUNDO PISO
Del predimensionamiento tenemos:
b= 0.30 m rec= 4.00 cm
h= 0.50 m f'c = 210 Kg/cm2
Cargas: Pu = 91.45 Tn fy = 4200 Kg/cm2
Mux= 11.88 Tn.m ɸest= 3/8 '' estribo
Muy= 5.60 Tn.m ɸb= 3/4 '' diametro asumido
𝑀𝑢𝑥 Asx
= 2.12 entonces: Asx = 2.12 *Asy
𝑀𝑢𝑦
2 ɸ 3/4 '' + 2 ɸ 5/8 ''
asumimos una cuantia de: ρ = 2.00 % Asy
2 ɸ 5/8 '' + 0 ɸ 5/8 ''
area de refuerzo = As = b*h*ρ = 30.00 cm2 0.50 m
2 ɸ 5/8 '' + 0 ɸ 5/8 ''
As = 2.12 *Asy + Asy
Asy = 9.62 cm2 2 ɸ 3/4 '' + 2 ɸ 5/8 ''
Asx= 20.38 cm2 Ast = 27.236 cm2
0.30 m
Pno = 377.28 Tn
Determinaiocion de Pnx
ρ = 0.0182
Rn = 0.108
𝑀𝑛𝑥 Carga resistente
𝑅𝑛 =
ɣ = 0.764 𝑓′ 𝑐 ∗ 𝐴𝑔 ∗ ℎ
1 1 1 1
= + −
𝑃𝑛 𝑃𝑛𝑥 𝑃𝑛𝑦 𝑃𝑛𝑜
entrando a la grafica del SP-17 para refuerzo en
4 caras, se tiene Pn = 232.37 Tn
ɣ = 0.7 → Kn = 0.88 Pu = 162.66 Tn
ɣ = 0.764 → Kn = 0.906 1.1Pu = 100.60 Tn O.K
ɣ = 0.8 → Kn = 0.92
𝑃𝑛𝑥
K𝑛 = 𝑓′𝑐∗𝐴𝑔 → Pnx = 285.24 Tn
Determinacion de Pny
ρ = 0.0182
Rn = 0.085
ɣ = 0.606
ɣ = 0.6 → Kn = 0.92
ɣ = 0.606 → Kn = 0.921
ɣ = 0.7 → Kn = 0.93
𝑃𝑛𝑦
K𝑛 = → Pny = 290.00 Tn
𝑓′ 𝑐∗𝐴𝑔
DISEÑO
DISEÑO PARA EL TERCER Y CUARTO PISO
Del predimensionamiento tenemos:
b= 0.30 m rec= 4.00 cm
h= 0.50 m f'c = 210 Kg/cm2
Cargas: Pu = 54.27 Tn fy = 4200 Kg/cm2
Mux= 7.07 Tn.m ɸest= 3/8 '' estribo
Muy= 4.89 Tn.m ɸb= 3/4 '' diametro asumido
𝑀𝑢𝑥 Asx
= 1.45 entonces: Asx = 1.45 *Asy
𝑀𝑢𝑦
2 ɸ 5/8 '' + 1 ɸ 1/2 ''
asumimos una cuantia de: ρ = 1.00 % Asy
2 ɸ 1/2 '' + 0 ɸ 5/8 ''
area de refuerzo = As = b*h*ρ = 15.00 cm2 0.50 m
2 ɸ 1/2 '' + 0 ɸ 5/8 ''
As = 1.45 *Asy + Asy
Asy = 6.13 cm2 2 ɸ 5/8 '' + 1 ɸ 1/2 ''
Asx= 8.87 cm2 Ast = 15.518 cm2
0.30 m
Pno = 330.16 Tn
Determinaiocion de Pnx
ρ = 0.0103
Rn = 0.064
𝑀𝑛𝑥 Carga resistente
𝑅𝑛 =
ɣ = 0.764 𝑓′ 𝑐 ∗ 𝐴𝑔 ∗ ℎ
1 1 1 1
= + −
𝑃𝑛 𝑃𝑛𝑥 𝑃𝑛𝑦 𝑃𝑛𝑜
entrando a la grafica del SP-17 para refuerzo en
4 caras, se tiene Pn = 233.58 Tn
ɣ = 0.7 → Kn = 0.88 Pu = 163.51 Tn
ɣ = 0.764 → Kn = 0.899 1.1Pu = 59.70 Tn O.K
ɣ = 0.8 → Kn = 0.91
SOLO CON LA CUANTIA MINIMA
𝑃𝑛𝑥
K𝑛 = 𝑓′𝑐∗𝐴𝑔 → Pnx = 283.23 Tn
Determinacion de Pny
ρ = 0.0103
Rn = 0.074
ɣ = 0.606
ɣ = 0.6 → Kn = 0.84
ɣ = 0.606 → Kn = 0.84
ɣ = 0.7 → Kn = 0.84
𝑃𝑛𝑦
K𝑛 = → Pny = 264.60 Tn
𝑓′ 𝑐∗𝐴𝑔
DISEÑO
DISEÑO PARA EL QUINTO PISO Y AZOTEA
Del predimensionamiento tenemos:
b= 0.30 m rec= 4.00 cm
h= 0.50 m f'c = 210 Kg/cm2
Cargas: Pu = 20.27 Tn fy = 4200 Kg/cm2
Mux= 6.63 Tn.m ɸest= 3/8 '' estribo
Muy= 10.43 Tn.m ɸb= 3/4 '' diametro asumido
𝑀𝑢𝑥 Asx
= 0.64 entonces: Asx = 0.64 *Asy
𝑀𝑢𝑦
4 ɸ 1/2 '' + 0 ɸ 1/2 ''
asumimos una cuantia de: ρ = 1.00 % Asy
2 ɸ 1/2 '' + 0 ɸ 5/8 ''
area de refuerzo = As = b*h*ρ = 15.00 cm2 0.50 m
2 ɸ 1/2 '' + 0 ɸ 5/8 ''
As = 0.64 *Asy + Asy
Asy = 9.17 cm2 4 ɸ 1/2 '' + 0 ɸ 1/2 ''
Asx= 5.83 cm2 Ast = 15.201 cm2
0.30 m
Pno = 328.88 Tn
Determinaiocion de Pnx
ρ = 0.0101
Rn = 0.060
𝑀𝑛𝑥 Carga resistente
𝑅𝑛 =
ɣ = 0.764 𝑓′ 𝑐 ∗ 𝐴𝑔 ∗ ℎ
1 1 1 1
= + −
𝑃𝑛 𝑃𝑛𝑥 𝑃𝑛𝑦 𝑃𝑛𝑜
entrando a la grafica del SP-17 para refuerzo en
4 caras, se tiene Pn = 225.13 Tn
ɣ = 0.7 → Kn = 0.86 Pu = 157.59 Tn
ɣ = 0.764 → Kn = 0.879 1.1Pu = 22.30 Tn O.K
ɣ = 0.8 → Kn = 0.89
SOLO CON LA CUANTIA MINIMA
𝑃𝑛𝑥
K𝑛 = 𝑓′𝑐∗𝐴𝑔 → Pnx = 276.93 Tn
Determinacion de Pny
ρ = 0.0101
Rn = 0.158
ɣ = 0.606
ɣ = 0.6 → Kn = 0.82
ɣ = 0.606 → Kn = 0.82
ɣ = 0.7 → Kn = 0.82
𝑃𝑛𝑦
K𝑛 = → Pny = 258.30 Tn
𝑓′ 𝑐∗𝐴𝑔
ESTRIBOS
según norma E-060 y E.030
- Zona de confinamiento Hc = 2.50 m
Lo = Hc/6 = 0.42 m
Lo = t (col.) 0.50 m
Lo = 0.50 m
So = 8*db(menor) 0.13 m
So = s/2 0.15 m
So = 0.10 m