PT WIJAYA KARYA BETON, Tbk.

SCHEDULE ERECTION BOX GIRDER & BARRIER


ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1 START 0 days Tue 7/19/16 Tue 7/19/16 7/19
2 ERECTION BOX GIRDER 561 days Sat 9/24/16 Sat 7/14/18 9/24 7/14
3 INSTALASI BOX GIRDER LG 1 - 67 Span
511 days Sat 9/24/16 Mon 5/7/18 9/24 5/7
4 Assembly LG 1 58 days Sat 9/24/16 Sun 11/20/16
5 JLKA 16 76 days Mon 11/21/16
Thu 2/9/17 11/21 2/9
6 P104 - P105 (40 M) 35 days Mon 11/21/16 Mon 12/26/16
7 P105 - P106 (40 M) 20 days Tue 12/27/16 Tue 1/17/17
8 P106 - P107 (40 M) 7 days Wed 1/18/17 Tue 1/24/17
9 P107 - P108 (40 M) 7 days Wed 1/25/17 Wed 2/1/17
10 P108 - P109 (40 M) 7 days Thu 2/2/17 Thu 2/9/17
11 JLKA 17 65 days Fri 2/10/17 Thu 4/20/17 2/10 4/20
12 P109 - P110 (40 M) 7 days Fri 2/10/17 Fri 2/17/17
13 P110 - P111 (40 M) 7 days Sat 2/18/17 Fri 2/24/17
14 P111 - P112 (40 M) 7 days Sat 2/25/17 Sat 3/4/17
15 P112 - P113 (30 M) 7 days Sun 3/5/17 Sat 3/11/17
16 P113 - P114 (40 M) 7 days Mon 3/13/17 Sun 3/19/17
17 P114 - P115 (40 M) 6 days Mon 3/20/17 Sat 3/25/17
18 P115 - P116 (40 M) 6 days Mon 3/27/17 Sat 4/1/17
19 P116 - P117 (40 M) 6 days Sun 4/2/17 Fri 4/7/17
20 P117 - P118 (40 M) 6 days Sat 4/8/17 Fri 4/14/17
21 P118 - P119 (40 M) 6 days Sat 4/15/17 Thu 4/20/17
22 JLKA 18 60 days Fri 4/21/17 Sat 7/15/17 4/21 7/15
23 P119 - P120 (40 M) 6 days Fri 4/21/17 Thu 4/27/17
24 P120 - P121 (40 M) 6 days Fri 4/28/17 Wed 5/3/17
25 P121 - P122 (40 M) 6 days Thu 5/4/17 Wed 5/10/17
26 P122 - P123 (40 M) 6 days Thu 5/11/17 Tue 5/16/17
27 P123 - P124 (40 M) 6 days Wed 5/17/17 Tue 5/23/17
28 P124 - P125 (40 M) 6 days Wed 5/24/17 Mon 5/29/17

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
29 P125 - P126 (40 M) 6 days Tue 5/30/17 Mon 6/5/17
30 P126 - P127 (40 M) 6 days Tue 6/6/17 Sun 6/11/17
31 P127 - P128 (40 M) 6 days Mon 6/12/17 Sun 7/9/17
32 P128 - P129 (40 M) 6 days Mon 7/10/17 Sat 7/15/17
33 JLKA 19 60 days Mon 7/17/17Tue 9/19/17 7/17 9/19
34 P129 - P130 (30 M) 6 days Mon 7/17/17 Sat 7/22/17
35 P130 - P131 (30 M) 6 days Sun 7/23/17 Fri 7/28/17
36 P131 - P132 (30 M) 6 days Sat 7/29/17 Fri 8/4/17
37 P132 - P133 (40 M) 6 days Sat 8/5/17 Thu 8/10/17
38 P133 - P134 (40 M) 6 days Fri 8/11/17 Fri 8/18/17
39 P134 - P135 (40 M) 6 days Sat 8/19/17 Thu 8/24/17
40 P135 - P136 (40 M) 6 days Fri 8/25/17 Thu 8/31/17
41 P136 - P137 (40 M) 6 days Fri 9/1/17 Wed 9/6/17
42 P137 - P138 (40 M) 6 days Thu 9/7/17 Wed 9/13/17
43 P138 - P139 (40 M) 6 days Thu 9/14/17 Tue 9/19/17
44 JLKA 20 54 days Wed 9/20/17Thu 11/16/17 9/20 11/16
45 P139 - P140 (40 M) 6 days Wed 9/20/17 Tue 9/26/17
46 P140 - P141 (40 M) 6 days Wed 9/27/17 Mon 10/2/17
47 P141 - P142 (40 M) 6 days Tue 10/3/17 Mon 10/9/17
48 P142 - P143 (40 M) 6 days Tue 10/10/17 Sun 10/15/17
49 P143 - P144 (40 M) 6 days Mon 10/16/17 Sat 10/21/17
50 P144 - P145 (40 M) 6 days Mon 10/23/17 Sat 10/28/17
51 P145 - P146 (40 M) 6 days Sun 10/29/17 Fri 11/3/17
52 P146 - P147 (40 M) 6 days Sat 11/4/17 Fri 11/10/17
53 P147 - P148 (40 M) 6 days Sat 11/11/17 Thu 11/16/17
54 JLKA 21 42 days Fri 11/17/17 Tue 1/23/18 11/17 1/23
55 P148 - P149 (40 M) 6 days Fri 11/17/17 Thu 11/23/17
56 P149 - P150 (40 M) 6 days Fri 11/24/17 Wed 11/29/17

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
57 P150 - P151 (40 M) 6 days Thu 11/30/17 Wed 12/6/17
58 P151 - P152 (40 M) 6 days Thu 12/7/17 Tue 12/12/17
59 P152 - P153 (30 M) 6 days Wed 12/13/17 Tue 12/19/17
60 P153 - P154 (30 M) 6 days Wed 12/20/17 Wed 1/17/18
61 P154 - P155 (30 M) 6 days Thu 1/18/18 Tue 1/23/18
62 JLKA 22 60 days Wed 1/24/18Thu 3/29/18 1/24 3/29
63 P155 - P156 (30 M) 6 days Wed 1/24/18 Tue 1/30/18
64 P156 - P157 (30 M) 6 days Wed 1/31/18 Mon 2/5/18
65 P157 - P158 (30 M) 6 days Tue 2/6/18 Mon 2/12/18
66 P158 - P159 (40 M) 6 days Tue 2/13/18 Sun 2/18/18
67 P159 - P160 (40 M) 6 days Mon 2/19/18 Sat 2/24/18
68 P160 - P161 (40 M) 6 days Mon 2/26/18 Sat 3/3/18
69 P161 - P162 (40 M) 6 days Sun 3/4/18 Fri 3/9/18
70 P162 - P163 (40 M) 6 days Sat 3/10/18 Fri 3/16/18
71 P163 - P164 (40 M) 6 days Sat 3/17/18 Thu 3/22/18
72 P164 - P165 (40 M) 6 days Fri 3/23/18 Thu 3/29/18
73 JLKA 23 36 days Fri 3/30/18 Mon 5/7/18 3/30 5/7
74 P165 - P166 (40 M) 6 days Fri 3/30/18 Wed 4/4/18
75 P166 - P167 (40 M) 6 days Thu 4/5/18 Wed 4/11/18
76 P167 - P168 (40 M) 6 days Thu 4/12/18 Tue 4/17/18
77 P168 - P169 (40 M) 6 days Wed 4/18/18 Tue 4/24/18
78 P169 - P170 (40 M) 6 days Wed 4/25/18 Mon 4/30/18
79 P170 - P171 (40 M) 6 days Tue 5/1/18 Mon 5/7/18
80 INSTALASI BOX GIRDER LG 2 - 56 Span
386 days Wed 1/25/17 Tue 5/1/18 1/25 5/1
81 Assembly LG 2 20 days Wed 1/25/17 Thu 2/16/17
82 JLKA 16 41 days Fri 2/17/17 Sat 4/1/17 2/17 4/1
83 P104 - P103 (40 M) 10 days Fri 2/17/17 Mon 2/27/17
84 P103 - P102 (40 M) 10 days Tue 2/28/17 Thu 3/9/17

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 3
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
85 P102 - P101 (40 M) 7 days Fri 3/10/17 Fri 3/17/17
86 P101 - P100 (40 M) 7 days Sat 3/18/17 Fri 3/24/17
87 P100 - P99 (40 M) 7 days Sat 3/25/17 Sat 4/1/17
88 JLKA 15 65 days Sun 4/2/17 Sat 6/10/17 4/2 6/10
89 P99 - P98 (40 M) 7 days Sun 4/2/17 Sat 4/8/17
90 P98 - P97 (40 M) 7 days Mon 4/10/17 Sun 4/16/17
91 P97 - P96 (40 M) 7 days Mon 4/17/17 Mon 4/24/17
92 P96 - P95 (30 M) 7 days Tue 4/25/17 Mon 5/1/17
93 P95 - P94 (30 M) 7 days Tue 5/2/17 Tue 5/9/17
94 P94 - P93 (35 M) 6 days Wed 5/10/17 Mon 5/15/17
95 P93 - P92 (40 M) 6 days Tue 5/16/17 Mon 5/22/17
96 P92 - P91 (30 M) 6 days Tue 5/23/17 Sun 5/28/17
97 P91 - P90 (30 M) 6 days Mon 5/29/17 Sat 6/3/17
98 P90 - P89 (30 M) 6 days Mon 6/5/17 Sat 6/10/17
99 JLKA 14 60 days Sun 6/11/17 Tue 9/5/17 6/11 9/5
100 P89 - P88 (30 M) 6 days Sun 6/11/17 Sat 7/8/17
101 P88 - P87 (30 M) 6 days Sun 7/9/17 Fri 7/14/17
102 P87 - P86 (30 M) 6 days Sat 7/15/17 Fri 7/21/17
103 P86 - P85 (30 M) 6 days Sat 7/22/17 Thu 7/27/17
104 P85 - P84 (30 M) 6 days Fri 7/28/17 Thu 8/3/17
105 P84 - P83 (30 M) 6 days Fri 8/4/17 Wed 8/9/17
106 P83 - P82 (30 M) 6 days Thu 8/10/17 Wed 8/16/17
107 P82 - P81 (30 M) 6 days Fri 8/18/17 Wed 8/23/17
108 P81 - P80 (30 M) 6 days Thu 8/24/17 Wed 8/30/17
109 P80 - P79 (40 M) 6 days Thu 8/31/17 Tue 9/5/17
110 JLKA 13 60 days Wed 9/6/17 Thu 11/9/17 9/6 11/9
111 P79 - P78 (40 M) 6 days Wed 9/6/17 Tue 9/12/17
112 P78 - P77 (40 M) 6 days Wed 9/13/17 Mon 9/18/17

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 4
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
113 P77 - P76 (40 M) 6 days Tue 9/19/17 Mon 9/25/17
114 P76 - P75 (40 M) 6 days Tue 9/26/17 Sun 10/1/17
115 P75 - P74 (40 M) 6 days Mon 10/2/17 Sat 10/7/17
116 P74 - P73 (40 M) 6 days Mon 10/9/17 Sat 10/14/17
117 P73 - P72 (40 M) 6 days Sun 10/15/17 Fri 10/20/17
118 P72 - P71 (40 M) 6 days Sat 10/21/17 Fri 10/27/17
119 P71 - P70 (40 M) 6 days Sat 10/28/17 Thu 11/2/17
120 P70 - P69 (40 M) 6 days Fri 11/3/17 Thu 11/9/17
121 JLKA 12 61 days Fri 11/10/17 Mon 2/5/18 11/10 2/5
122 P69 - P68 (40 M) 6 days Fri 11/10/17 Wed 11/15/17
123 P68 Pemotongan 2 Modul LG 7 days Thu 11/16/17Thu 11/23/17
124 P68 - P67 (25 M) 6 days Fri 11/24/17 Wed 11/29/17
125 P67 - P66 (25 M) 6 days Thu 11/30/17 Wed 12/6/17
126 P66 - P65 (25 M) 6 days Thu 12/7/17 Tue 12/12/17
127 P65 - P64 (30 M) 6 days Wed 12/13/17 Tue 12/19/17
128 P64 - P63 (25 M) 6 days Wed 12/20/17 Wed 1/17/18
129 P63 - P62 (25 M) 6 days Thu 1/18/18 Tue 1/23/18
130 P62 - P61 (25 M) 6 days Wed 1/24/18 Tue 1/30/18
131 P61 - P60 (25 M) 6 days Wed 1/31/18 Mon 2/5/18
132 JLKA 11 67 days Tue 2/6/18 Wed 4/18/18 2/6 4/18
133 P60 - P59 (25 M) 6 days Tue 2/6/18 Mon 2/12/18
134 P59 - P58 (30 M) 6 days Tue 2/13/18 Sun 2/18/18
135 P58 - P57 (30 M) 6 days Mon 2/19/18 Sat 2/24/18
136 P57 - P56 (25 M) 6 days Mon 2/26/18 Sat 3/3/18
137 P56 Penyambungan 2 Modul LG7 days Sun 3/4/18 Sat 3/10/18
138 P56 - P55 (35 M) 6 days Mon 3/12/18 Sat 3/17/18
139 P55 - P54 (35 M) 6 days Sun 3/18/18 Fri 3/23/18
140 P54 - P53 (35 M) 6 days Sat 3/24/18 Fri 3/30/18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 5
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
141 P53 - P52 (40 M) 6 days Sat 3/31/18 Thu 4/5/18
142 P52 - P51 (40 M) 6 days Fri 4/6/18 Thu 4/12/18
143 P51 - P50 (40 M) 6 days Fri 4/13/18 Wed 4/18/18
144 JLKA 10 12 days Thu 4/19/18 Tue 5/1/18
145 P50 - P49 (40 M) 6 days Thu 4/19/18 Wed 4/25/18
146 P49 - P48 (40 M) 6 days Thu 4/26/18 Tue 5/1/18
147 INSTALASI BOX GIRDER LG 3 - 46 Span
340 days Mon 5/15/17 Sat 7/14/18 5/15 7/14
148 Assembly LG 3 45 days Mon 5/15/17 Sun 7/23/17
149 JLKA 10 48 days Mon 7/24/17Thu 9/14/17 7/24 9/14
150 P48 - P47 (40 M) 10 days Mon 7/24/17 Thu 8/3/17
151 P47 - P46 (40 M) 10 days Fri 8/4/17 Mon 8/14/17
152 P46 - P45 (40 M) 7 days Tue 8/15/17 Tue 8/22/17
153 P45 - P44 (40 M) 7 days Wed 8/23/17 Wed 8/30/17
154 P44 - P43 (40 M) 7 days Thu 8/31/17 Wed 9/6/17
155 P43 - P42 (40 M) 7 days Thu 9/7/17 Thu 9/14/17
156 JLKA 9 52 days Fri 9/15/17 Thu 11/9/17 9/15 11/9
157 P42 - P41 (40 M) 7 days Fri 9/15/17 Thu 9/21/17
158 P41 - P40 (40 M) 7 days Fri 9/22/17 Fri 9/29/17
159 P40 - P39 (40 M) 7 days Sat 9/30/17 Fri 10/6/17
160 P39 - P38 (40 M) 7 days Sat 10/7/17 Sat 10/14/17
161 P38 - P37 (40 M) 6 days Sun 10/15/17 Fri 10/20/17
162 P37 - P36 (40 M) 6 days Sat 10/21/17 Fri 10/27/17
163 P36 - P35 (40 M) 6 days Sat 10/28/17 Thu 11/2/17
164 P35 - P34 (40 M) 6 days Fri 11/3/17 Thu 11/9/17
165 JLKA 8 24 days Fri 11/10/17 Tue 12/5/17 11/10 12/5
166 P34 - P33 (40 M) 6 days Fri 11/10/17 Wed 11/15/17
167 P33 - P32 (40 M) 6 days Thu 11/16/17 Wed 11/22/17
168 P32 - P31 (40 M) 6 days Thu 11/23/17 Tue 11/28/17

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 6
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
169 P31 - P30 (40 M) 6 days Wed 11/29/17 Tue 12/5/17
170 JLKA 6 24 days Wed 12/6/17Mon 1/22/18 12/6 1/22
171 P30 - P29 (35 M) 6 days Wed 12/6/17 Mon 12/11/17
172 P29 - P28 (30 M) 6 days Tue 12/12/17 Mon 12/18/17
173 P28 - P27 (30 M) 6 days Tue 12/19/17 Tue 1/16/18
174 P27 - P26 (30 M) 6 days Wed 1/17/18 Mon 1/22/18
175 JLKA 5 24 days Tue 1/23/18 Sat 2/17/18 1/23 2/17
176 P26 - P25 (35 M) 6 days Tue 1/23/18 Mon 1/29/18
177 P25 - P24 (35 M) 6 days Tue 1/30/18 Sun 2/4/18
178 P24 - P23 (40 M) 6 days Mon 2/5/18 Sat 2/10/18
179 P23 - P22 (40 M) 6 days Mon 2/12/18 Sat 2/17/18
180 JLKA 4 48 days Sun 2/18/18 Tue 4/10/18 2/18 4/10
181 P22 - P21 (40 M) 6 days Sun 2/18/18 Fri 2/23/18
182 P21 - P20 (40 M) 6 days Sat 2/24/18 Fri 3/2/18
183 P20 - P19 (35 M) DOUBLE BOX 6 days Sat 3/3/18 Thu 3/8/18
184 P19 - P18 (40 M) DOUBLE BOX 6 days Fri 3/9/18 Thu 3/15/18
185 P18 - P17 (40 M) DOUBLE BOX 6 days Fri 3/16/18 Wed 3/21/18
186 P17 - P16 (40 M) DOUBLE BOX 6 days Thu 3/22/18 Wed 3/28/18
187 P16 - P15 (40 M) DOUBLE BOX 6 days Thu 3/29/18 Tue 4/3/18
188 P15 - P14 (40 M) DOUBLE BOX 6 days Wed 4/4/18 Tue 4/10/18
189 JLKA 3 39 days Wed 4/11/18Tue 5/22/18 4/11 5/22
190 P14 - P13 (40 M) DOUBLE BOX 6 days Wed 4/11/18 Mon 4/16/18
191 P13 - P12 (40 M) DOUBLE BOX 6 days Tue 4/17/18 Mon 4/23/18
192 P12 - P11 (40 M) DOUBLE BOX 6 days Tue 4/24/18 Sun 4/29/18
193 Pergeseran LG 3 days Mon 4/30/18Wed 5/2/18
194 P11 - P12 (40 M) DOUBLE BOX 6 days Thu 5/3/18 Wed 5/9/18
195 P12 - P13 (40 M) DOUBLE BOX 6 days Thu 5/10/18 Tue 5/15/18
196 P13 - P14 (40 M) DOUBLE BOX 6 days Wed 5/16/18 Tue 5/22/18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 7
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
197 JLKA 4 36 days Wed 5/23/18Sat 7/14/18 5/23 7/14
198 P14 - P15 (40 M) DOUBLE BOX 6 days Wed 5/23/18 Mon 5/28/18
199 P15 - P16 (40 M) DOUBLE BOX 6 days Tue 5/29/18 Mon 6/4/18
200 P16 - P17 (40 M) DOUBLE BOX 6 days Tue 6/5/18 Mon 6/25/18
201 P17 - P18 (40 M) DOUBLE BOX 6 days Tue 6/26/18 Sun 7/1/18
202 P18 - P19 (40 M) DOUBLE BOX 6 days Mon 7/2/18 Sat 7/7/18
203 P19 - P20 (35 M) DOUBLE BOX 6 days Mon 7/9/18 Sat 7/14/18
204 INSTALASI BOX GIRDER LG 4 - 44 Span
328 days Mon 5/15/17 Sun 7/1/18 5/15 7/1
205 Assambly LG 4 45 days Mon 5/15/17 Sun 7/23/17
206 JLKA 8 41 days Mon 7/24/17Wed 9/6/17 7/24 9/6
207 P15' - P14' (40 M) 10 days Mon 7/24/17 Thu 8/3/17
208 P14' - P13' (40 M) 10 days Fri 8/4/17 Mon 8/14/17
209 P13' - P12' (40 M) 7 days Tue 8/15/17 Tue 8/22/17
210 P12' - P11' (40 M) 7 days Wed 8/23/17 Wed 8/30/17
211 P11' - P10' (40 M) 7 days Thu 8/31/17 Wed 9/6/17
212 JLKA 10 41 days Thu 9/7/17 Fri 10/20/17 9/7 10/20
213 P10' - P9' (40 M) 7 days Thu 9/7/17 Thu 9/14/17
214 P9' - P8' (40 M) 7 days Fri 9/15/17 Thu 9/21/17
215 P8' - P7' (40 M) 7 days Fri 9/22/17 Fri 9/29/17
216 P7' - P6' (40 M) 7 days Sat 9/30/17 Fri 10/6/17
217 P6' - P5' (40 M) 7 days Sat 10/7/17 Sat 10/14/17
218 P5' - P4' (40 M) 6 days Sun 10/15/17 Fri 10/20/17
219 JLKA 5 60 days Sat 10/21/17Tue 1/16/18 10/21 1/16
220 P4' - P3' (40 M) 6 days Sat 10/21/17 Fri 10/27/17
221 P3' - P2' (40 M) 6 days Sat 10/28/17 Thu 11/2/17
222 P2' - P1' (40 M) 6 days Fri 11/3/17 Thu 11/9/17
223 P1' - P0 (40 M) 6 days Fri 11/10/17 Wed 11/15/17
224 P0 - P1 (40 M) 6 days Thu 11/16/17 Wed 11/22/17

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 8
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
225 P1 - P2 (40 M) 6 days Thu 11/23/17 Tue 11/28/17
226 P2 - P3 (40 M) 6 days Wed 11/29/17 Tue 12/5/17
227 P3 - P4 (40 M) 6 days Wed 12/6/17 Mon 12/11/17
228 P4 - P5 (40 M) 6 days Tue 12/12/17 Mon 12/18/17
229 P5 - P6 (40 M) 6 days Tue 12/19/17 Tue 1/16/18
230 JLKA 1 6 days Wed 1/17/18Mon 1/22/18 1/17 1/22
231 P6 - P7 (40 M) DOUBLE BOX 6 days Wed 1/17/18 Mon 1/22/18
232 JLKA 2 6 days Tue 1/23/18 Mon 1/29/18 1/23 1/29
233 P7 - P8 (40 M) DOUBLE BOX 6 days Tue 1/23/18 Mon 1/29/18
234 JLKA 3 39 days Tue 1/30/18 Mon 3/12/18 1/30 3/12
235 P8 - P9 (40 M) DOUBLE BOX 6 days Tue 1/30/18 Sun 2/4/18
236 P9 - P10 (40 M) DOUBLE BOX 6 days Mon 2/5/18 Sat 2/10/18
237 P10 - P11 (40 M) DOUBLE BOX 6 days Mon 2/12/18 Sat 2/17/18
238 P11 PERGESERAN LG 3 days Sun 2/18/18 Tue 2/20/18
239 P11 - P10 (40 M) DOUBLE BOX 6 days Wed 2/21/18 Tue 2/27/18
240 P10 - P9 (40 M) DOUBLE BOX 6 days Wed 2/28/18 Mon 3/5/18
241 P9 - P8 (40 M) DOUBLE BOX 6 days Tue 3/6/18 Mon 3/12/18
242 JLKA 2 6 days Tue 3/13/18 Sun 3/18/18 3/13 3/18
243 P8 - P7 (40 M) DOUBLE BOX 6 days Tue 3/13/18 Sun 3/18/18
244 JLKA 1 6 days Mon 3/19/18Sat 3/24/18 3/19 3/24
245 P7 - P6 (40 M) DOUBLE BOX 6 days Mon 3/19/18 Sat 3/24/18
246 JLKA 6 30 days Mon 3/26/18Thu 4/26/18 3/26 4/26
247 P6 - P5'Bj (40 M) 6 days Mon 3/26/18 Sat 3/31/18
248 P5'Bj - P4'Bj (40 M) 6 days Sun 4/1/18 Fri 4/6/18
249 P4'Bj - P3'Bj (40 M) 6 days Sat 4/7/18 Fri 4/13/18
250 P3'Bj - P2'Bj (40 M) 6 days Sat 4/14/18 Thu 4/19/18
251 P2'Bj - P1'Bj (40 M) 6 days Fri 4/20/18 Thu 4/26/18
252 JLKA 8 12 days Fri 4/27/18 Wed 5/9/18 4/27 5/9

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 9
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
253 P1'Bj - P0'Bj (40 M) 6 days Fri 4/27/18 Wed 5/2/18
254 P0'Bj - P1Bj (40 M) 6 days Thu 5/3/18 Wed 5/9/18
255 JLKA 2 6 days Thu 5/10/18 Tue 5/15/18 5/10 5/15
256 P1Bj - P2Bj (40 M) 6 days Thu 5/10/18 Tue 5/15/18
257 JLKA 1 18 days Wed 5/16/18Mon 6/4/18 5/16 6/4
258 P2Bj - P3Bj (40 M) 6 days Wed 5/16/18 Tue 5/22/18
259 P3Bj - P4Bj (40 M) 6 days Wed 5/23/18 Mon 5/28/18
260 P4Bj - P5BJ (40 M) 6 days Tue 5/29/18 Mon 6/4/18
261 JLKA 9 12 days Tue 6/5/18 Sun 7/1/18 6/5 7/1
262 P5Bj - P6Bj (40 M) 6 days Tue 6/5/18 Mon 6/25/18
263 P6Bj - P7Bj (40 M) 6 days Tue 6/26/18 Sun 7/1/18
264 BARRIER, BALLAST STP, PEDESTRIAN 475 days Wed 1/25/17 Tue 8/21/18 1/25 8/21
265 P104 - PA2 455 days Wed 1/25/17 Sun 7/29/18 1/25 7/29
266 BARRIER P104 - P171 453 days Wed 1/25/17 Fri 7/27/18
267 BALLAST STP P104 - P171 453 days Thu 1/26/17 Sat 7/28/18
268 PEDESTRIAN P104 - P171 453 days Fri 1/27/17 Sun 7/29/18
269 P104 - P48 372 days Tue 2/28/17 Fri 5/18/18 2/28 5/18
270 BARRIER P104 - P48 366 days Tue 2/28/17 Sat 5/12/18
271 BALLAST STP P104 - P48 366 days Fri 3/3/17 Tue 5/15/18
272 PEDESTRIAN P104 - P48 366 days Mon 3/6/17 Fri 5/18/18
273 P48 - P10 301 days Wed 8/23/17 Mon 8/20/18 8/23 8/20
274 BARRIER P48 - P10 295 days Wed 8/23/17 Sun 8/12/18
275 BALLAST STP P48 - P10 295 days Sat 8/26/17 Wed 8/15/18
276 PEDESTRIAN STP P48 - P10 295 days Wed 8/30/17 Mon 8/20/18
277 P15" - P8BJ 295 days Thu 8/31/17 Tue 8/21/18 8/31 8/21
278 BARRIER P8BJ - P15' 289 days Thu 8/31/17 Mon 8/13/18
279 BALLAST STP P8BJ - P15' 289 days Sun 9/3/17 Thu 8/16/18
280 PEDESTRIAN STP P8BJ - P15' 289 days Wed 9/6/17 Tue 8/21/18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 10
PT WIJAYA KARYA BETON, Tbk. SCHEDULE ERECTION BOX GIRDER & BARRIER
ID Task Name Duration Start Finish 2016 2017 2018
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
281 FINISH 0 days Tue 8/21/18 Tue 8/21/18 8/21

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
Project: SCHEDULE KUALANAMU( Milestone Inactive Milestone Start-only
Date: Tue 1/24/17
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 11