Académique Documents
Professionnel Documents
Culture Documents
EMERSON Process Management – Educational Services Course 7012 - Rev 7 - 9/1/02 Copyrighted Material / Duplication Prohibited
3-3
TANK101 – Plant_Area_A
LEVEL-101
LI-101
FIC-102
XV-101
MTR-102
= =
Vers TANK-201
EMERSON Process Management – Educational Services Course 7012 - Rev 7 - 9/1/02 Copyrighted Material / Duplication Prohibited
3-4
TANK101 – Plant_Area_A
La simulation de procédé pré-configurée comporte deux zones de l'usine appelées
TANK101 et TANK201. TANK101, montré ci-dessus, contient les composants
suivants:
EMERSON Process Management – Educational Services Course 7012 - Rev 7 - 9/1/02 Copyrighted Material / Duplication Prohibited
3-5
TANK201 – Plant_Area_B
Vient de TANK-101
LIC-20X
FIC-20X
MTR-203
=
EMERSON Process Management – Educational Services Course 7012 - Rev 7 - 9/1/02 Copyrighted Material / Duplication Prohibited
3-6
TANK201 – Plant_Area_B
TANK201, comporte les composants suivants:
EMERSON Process Management – Educational Services Course 7012 - Rev 7 - 9/1/02 Copyrighted Material / Duplication Prohibited
3-7