Vous êtes sur la page 1sur 26

Bernat, S., Cambou, B. & Dubois, P. (1999). GeÂotechnique 49, No.

4, 427±452

Assessing a soft soil tunnelling numerical model using ®eld data

S . B E R NAT,  B. C A M B O U  a n d P. D U B O I S {

The aim of this paper is to assess a numerical Cet article a pour but d'eÂvaluer un modeÁle
soft soil tunnelling model, using ®eld data. The numeÂrique pour la construction d'un tunnel
lining of the tunnel to be studied was a fairly dans un sol meuble, en utilisant des donneÂes de
thick, very rigid structure. Given the low level terrain. Le reveÃtement du tunnel aÁ eÂtudier eÂtait
of applied stresses, lining deformation was une structure assez eÂpaisse et treÁs rigide. E Â tant
slight, and the deformation around the tunnel donne que les contraintes appliqueÂes eÂtaient fa-
essentially concerned the annular space created ibles, la deÂformation du reveÃtement eÂtait leÂgeÁre
between the soil and the lining during tunnel- et la deÂformation autour du tunnel eÂtait lieÂe
ling. This void was partially ®lled with injected essentiellement a l'espace annulaire creÂe entre le
grout. The primary purpose of this paper is to sol et la paroi pendant la construction. Ce vide
examine models that demonstrate soil±tunnelling eÂtait partiellement rempli de coulis injecteÂ. Cet
interactions. An empirical `decon®nement factor article a pour objet, principalement, d'examiner
ë' is then used to represent stress reduction les modeÁles qui montrent les interactions entre le
around tunnels during construction. In the ®rst sol et l'action de creusement du tunnel. Nous
model it is simply assumed that soil stresses utilisons ensuite un `facteur de deÂcon®nement ë9,
around the tunnel reduce linearly by a factor ë. obtenu de manieÁre empirique, pour repreÂsenter
The second analysis re®nes this notion and con- la baisse de contrainte autour des tunnels pen-
siders a temporary `recon®nement' stage in or- dant la construction. Dans le premier modeÁle,
der to represent both the grouting behind the nous preÂsumons simplement que les contraintes
lining once it is installed, and the hydrostatic dans le sol autour du tunnel baissent de facËon
pressure that acts on the impervious tunnel lineÂaire d'un facteur ë. La seconde analyse raf-
(pushing the lining up into the grout). Compari- ®ne cette notion et consideÁre une eÂtape de `re-
sons between these models and ®eld data meas- con®nement' temporaire a®n de repreÂsenter aÁ la
urements obtained in three fully instrumented fois l'injection de coulis derrieÁre la paroi une
areas of the Lyons-Vaise metro site will be fois que celle-ci est installeÂe et la pression hydro-
discussed. statique qui agit sur le tunnel eÂtanche (deÂplace-
ment vertical du revetement aÁ l'inteÂreur du
coulis). Nous commentons la comparaison entre
ces modeÁles et les mesures obtenues sur le ter-
KEYWORDS: ®eld instrumentation; numerical mod- rain dans trois zones entieÁrement instrumenteÂes
elling and analysis; settlement tunnels. sur le site du meÂtro de Lyon-Vaise.

INTRODUCTION and precise stratigraphy and digging technologies


The development of urban centres has led to an taken into account. This is where numerical models
increased need for tunnelling in soft soils in den- come in. The modelling discussed in this paper is
sely built-up areas. For such shallow tunnels, often based on:
built with slurry or earth pressure shields, the use
(a) an `elastic±plastic model' for soil modelling
of empirical methods (Attewell, 1977; Cording &
using the `CJS law', named after Cambou,
Hansmire, 1977) proves unsuitable if displacements
Jafari and Sidoroff, its creators;
around the tunnel are to be accurately calculated,
(b) the CESAR-LCPC Finite Element Method
program;
(c) a laboratory procedure and in situ tests to
de®ne the model constants.
Manuscript received 31 July 1997; revised manuscript As part of the Lyons metro works, a research
accepted 28 September 1998.
Discussion on this paper closes 5 November 1999; for scheme was set up to develop and assess a com-
further details see p. ii. plete procedure for forecasting movements induced
 EÂcole Centrale de Lyon. by tunnelling (Bernat et al., 1995a,b, 1996; Bernat,
{ Centre d'EÂtudes des Tunnels. 1996).

427
428 BERNAT, CAMBOU AND DUBOIS

THE WORK SITE Ministry of Research, and SYTRAL. The group


Site description (Amet et al., 1996) consisted of SEMALY (a metro-building company),
Existing urban conditions in the Lyons-Vaise the Lyons National Institute of Applied Sciences
sector meant that underground excavation for the (INSA), the EÂcole Centrale de Lyon (an engineering
metro was necessary (conventional cut-and-cover college) and the Centre d'EÂtudes des Tunnels
methods would have required signi®cant building (CETU). Instrumentation units were set up in two
demolition). Two tunnels, each 6´27 m in diameter monitoring areas: zone 1 and zone 2 (Fig. 5).
and 950 m long, were dug between June 1993 and
(a) Zone 1 consisted of two sections, S1 (Fig.
March 1995 under an overburden nowhere greater
6(a)) and S2 (Fig. 6(b)), located, respectively,
than 15 m. The ground to be excavated lay under
30 m and 65 m from the starting shaft in Vaise.
the water table and consisted mainly of silty allu-
The retaining wall of a 6 m high embankment
vial deposits with poor mechanical properties
explains the asymmetrical appearance of S1.
(Table 1 and Fig. 1).
(b) Zone 2 (Fig. 6(c)) is at the other end, about
Four major types of soil were encountered:
800 m from zone 1. It is symmetrical, but it
(a) Fill 3±5 m average thickness. should be noted in this case that the bedrock is
(b) Silty alluvial deposits in thin, more or less 3 m below the tunnels.
sandy or clayey soils. Some of these layers
Measurements were taken during the excavation of
were very sensitive to disturbance because the
the two tunnels T1 and T2 in S1, but only during
deposits contained so much natural water that
the excavation of T1 in S2 and of T1 in P2 (zone
they were almost liquid. The mechanical
2 is called P2).
characteristics indicated by pressuremeter,
penetrometer and laboratory tests were poor (a) Underground vertical movements were meas-
and indicated that there could be signi®cant ured by multipoint extensometers having ®ve
deformation. measuring points (A±D, then S going up
(c) Sandy±gravelly alluvial deposits, with some towards the surface) connected to an automatic
elements over 50 mm in diameter, and a few data-logger. An extensometer was installed in
over 500 mm that required the use of a crusher. the axis of the tunnel being examined (EX11
(d) A gneissic substratum was encountered at for T1 in S1, EX41 for T2 in S1, EX21 for T1
depths going from more than 80 m at Vaise in S2, and EX31 for T1 in P2), and others
station to less than 20 m at Gorge de Loup. were located on either side of the tunnel.
(b) Horizontal movements were measured on
These dif®cult conditions required the use of a
either side of the tunnel by inclinometers
TBM (tunnel-boring machine, Fig. 2) despite the
(I14 and I17 in S1, I24 in S2, I36 and I37 in
short tunnel length. Face support was ensured by
P2). Results were recorded manually, at the
bentonite slurry under pressure (around 100±
rate of one measurement every 50 cm.
200 kPa) to counteract prevailing water pore pres-
(c) Pore pressure cells were installed in low
sure and horizontal effective stress. Excavation was
permeable layers.
carried out using a semi-enclosed wheel (Fig. 3)
®tted with cutter bits and, where necessary, roller
bits for hard soil conditions. Excavated soil was
hydraulically mucked out, the slurry being pumped Analysing experimental curves
out and recycled. The tunnel was lined with precast Figures 33±39 show the development of vertical
1 m long concrete segments of 6 m external dia- movements, with time, of the extensometers located
meter and 0´35 m thickness installed under the on the tunnel axis, at the surface (point S) and near
protection of the TBM tail. In order to limit the tunnel crown (point A). Each of these four curves
ground destressing, the annular space of 13´5m highlights four main phases of separate vertical
between the outside of the tunnel lining segments displacements at the crown point levels (Fig. 7):
and the ground was injection-®lled with an inert
grout as excavation advanced (Fig. 4). Phase 0: very slight settlement (1±2 mm) before
the shield face passage.
Phase 1: sudden settlement (2±9 mm) as the TBM
Instrumentation (Kastner et al., 1995; Kastner & passes, related to alignment and shield
Ollier, 1996) operating speed.
The complex, dif®cult conditions of this work Phase 2: crown point rises 4 or 5 mm after the
provided an opportunity to set up a research project passage of the shield.
based on accurate on-site measuring in order to Phase 3: delayed settlement (5±11 mm) over a
develop and assess a complete procedure for fore- longer stabilization period, as a function
casting ground movements induced by tunnelling. of the overburden encountered above the
This research project was funded by the French tube, and geotechnical earth features.
Table 1. General geotechnical characteristics of the soil
Speci®c weight and water Atterberg limits Triaxial test Penetrometer Pressuremeter

SOFT SOIL TUNNELLING NUMERICAL MODEL


content

ãh: kN=m3 w: % w1 : % PI: % CI c9: kPa j9: 8 qC : MPa E: MPa P1 : MPa

First part of the layout (VAISE-VALMY)


Fill 19±21 4 0´5
Beige silt 18±21 35 58 26 0´9 0±30 29±35 ,2 ,4 ,0´8
Ochre silt 18±21 27 29 8 0´25 0±30 29±35 ,2 ,4 ,0´8
Grey clay 16±18 67 78 21 0´5 30±40 20±30 1 ,4 ,0´8
Violet clay 18´5 30±40 47 20 0´1 15 20 3 5 0´7±1´4
Sand and gravel 21 0 37 10±30 5±15 2
Second part of the layout (VALMY-BERTHET)
Fill 19±21
Brown silt 20±21 23 30 8 0´9 6 35
Ochre silt 20 24 30 8´6 0´5 0±30 37 0´5±4´5 1±20 0´5±1´4
Grey silt 20 26 27 5´6 0´6 77 30 0´5±4´5 1±20 0´5±1´4
Sand and gravel 21 .5 10±50 1±3

429
430 BERNAT, CAMBOU AND DUBOIS

rue de la Corderie
rue de la Claire

Pla rue des Bains

rue Cottin
rue St Pierre
rue Marietton
rue Roquette

de Vaise
rue Chinard
rue Laparte

s
ma
Impasse

de e Du
Recovery
Starting

re
shaft

Loi
c
shaft Station
BERTHET
VAISE VALMY

Reference level: 140.00


0 50 100 150 200 250 300 350 400 450 500 550 570 600 650 700 750 800 850 900

Backfill Sand and gravels Gneiss bed


Silt Conglomerate

Fig. 1. General geological pro®le along the T1 tunnel in the Lyon-Vaise work site

Air locks Erector Conveyor Segment lift Pilot cabin

R4
6m30

R1

R2 R3

Mucking pump Hydraulic unit Transformer Telescopic ducts


48m00
Cutter head no. 2
with discs Cutter head no. 1
and teeth
Thrust cylinders Backup R1 R2 R3 R4

R1 R2 R3 R3 R4

Fig. 2. Tunnel-boring machine (TBM) used in the Lyons-Vaise work site

Table 2 sums up the experimental data of the four triggered an upward movement of the impervious
phases relative to the crownpoint settlements of the segment inside the grout and, to a lesser degree, an
four sections being studied. Measurements showed upward movement of the overburden soil. In the
that the upward movement of the crown points in case of zone 2, where the settlements due to phase
phase 2 varies from 4 to 5 mm for each of the four 0 and phase 1 were slight, the upward movement
experimental sections. The beginning of this up- in phase 2 was predominant and the ®nal settle-
ward movement coincides with the beginning of ments were in inverse order compared with the
the grouting process, but its maximum is reached other three sections: in zone 2, ®nal surface settle-
between 4 and 8 m (or 24±48 h) later. Measure- ment was greater than ®nal crown settlement, and
ments recorded in zone 2 (Fig. 8) allowed three so intermediary phase 2 can no longer be ignored
types of results to be compared during the period in the corresponding modelling.
immediately following the grouting phase:
(a) vertical displacement of the crown point (black
MODELLING STRATEGY
curve), which rises 5 mm;
The proposed modelling strategy is based on the
(b) vertical displacement of the concrete segment
following:
(black dots) which rises 50 mm;
(c) a pressure measurement taken in the grouting,
(a) A constitutive model of the soil adapted to the
between the concrete segment and the soil
stress paths encountered during tunnelling
(grey curve).
(elastic±plastic CJS law developed in the Solid
Each curve peaked 20 h after grouting. This up- Mechanics Department of the EÂcole Centrale
ward movement effect thus seems to be due to de Lyon).
Archimedes' principle (hydrostatic pressure), which (b) A methodology to de®ne the CJS model
SOFT SOIL TUNNELLING NUMERICAL MODEL 431
(b) At the tunnel haunches, horizontal stress
decreases, producing plastic deformations from
an elastic±plastic approach standpoint.
(c) At the intermediate points, the principal
stresses rotate.

The CJS elastic±plastic constitutive model (Cambou


& Jafari, 1988; Cambou & Lanier, 1988) is well
adapted to these kinds of stress paths. Its deforma-
tion mechanism can be expressed by three terms:
(a) Non-linear elastic deformation.
(b) Isotropic plastic deformation. This is due to
the variation in mean stress, associated with a
scalar parameter of isotropic strain-hardening
and a yielding surface corresponding to a plane
perpendicular to the hydrostatic axis in the
principal stress areas.
(c) Plastic deformation. This is due to the
deviatoric stress variation reduced to the mean
stress value that is associated with an isotropic
strain-hardening scalar parameter and a kine-
matic strain-hardening tensor parameter. The
corresponding yielding surface is a cone with a
Fig. 3. The two wheels used for the TBM in the Lyon- varying aperture angle.
Vaise work site
Both yielding surfaces clearly establish a restricted
range for elastic behaviour. The law, based on two
constants based on laboratory tests (triaxial
isotropic and one kinematic strain-hardening me-
and oedometer tests) and in situ tests (with
chanisms, has twelve constants that can be identi-
pressuremeters).
®ed using conventional geotechnical tests (three
(c) A computation code (the CESAR ®nite ele-
triaxial tests at different con®ning pressures and
ments software developed at the French Central
one isotropic test or oedometer test) (Allouani,
Bridges and Highways Laboratory, LCPC).
1993). The `pressuremeter' test, commonly used
(d) An excavation model having a two-dimen-
for soil investigation in France, can also be consid-
sional approach in a plane orthogonal to the
ered to specify the values of some CJS parameters,
tunnel and using a stress release at the
using a ®tting technique.
periphery of the excavation called the `decon-
The main feature of the CJS model is its kine-
®nement' process.
matic strain-hardening, which enables the aniso-
tropy induced by loading to be taken into account.
The validation stage of the model was a major part
CJS constitutive model (Fig. 9) of the studies carried out by the French Coordi-
Excavating a tunnel produces complex loading nated Research Group (GRECO) for geomaterials
which generates main stress rotation associated (1986±1993). It was shown that the CJS model
with speci®c phenomena: gives reliable forecasts for homogeneous stress
paths, especially with reorientation of the main
(a) At the tunnel crown and bottom, vertical stress directions (Cambou & Jafari, 1988; Cambou &
decreases, producing mainly an elastic unload- Lanier, 1988; Cambou et al., 1990), as in the case
ing (for normally consolidated soil). of the rotation of the principal stress direction

Fig. 4. Grouting process at the end of the TBM tail


432 BERNAT, CAMBOU AND DUBOIS

VALMY Station Zone 2 BERTHET shaft

Towards
Gorge de Loup
Engineer: SYTRAL
VAISE Owner: SEMALY
Starting shaft Contractors: SOGEA, Campenon Bernard, GTM
Number of tunnels: 2
Tunnel diameter: 6.28 m each
Maximal tunnel gradient: 6%
Zone 1 Minimal curvature radius: 200 m
Maximal overburden over tunnels: 16 m
Excavation started on 10 June 1993
Excavation ended on 28 February 1995

Station Valmy Berthet


Vaise

First instrumented area


Second instrumented area
Zone 1
Zone 2

555 m underground Station 335 m underground


110 m length

Fig. 5. Tunnel alignment of the LYONS Metro D line extension, instrumented areas

22.05 m 24.60 m 14.00 m


. 23.90 m 12.00 m
24 65 m 11 90 m
.
22.07 m
8.00 m 5.80 m 24.00 m
S S
Backfill
EX 16 EX 33
D D
13.80 m 10 m EX 31
C 10.20 m
C
B
7.87 m B EX 21
EX 11
EX 41 EX 15 EX 22 A
A EX 32
EX 34
EX 13 T2 T1 T1
T2 T1
EX 23
I 36 I 37 3m
3.30 m I 17 I 24 Bedrock
I 14
4.80 m

(a) (b) (c)

Fig. 6. Instrumentation of the Lyon-Vaise tunnel alignment: (a) section S1 of zone 1; (b) section S2 of zone 1; (c)
Zone 2

occurring in tunnelling processes. The CJS model model evaluation stage in real tunnelling condi-
was also shown to be suitable for realistic simula- tions. This can only be considered an evaluation
tions of the behaviour of sand formation under stage in the present case, not a validation stage. In
stress generated by footings, load pressure, or the two-dimensional approach, forecasting quality
tunnel excavation (GRECO, 1995). After this vali- depends not only on the model capacity and com-
dation stage with centrifuged scale models (Rezgui, putation code used, but also on a number of
1993), the research programme carried out on the uncontrollable parameters in real-life conditions.
Lyons-Vaise site enabled the implementation of a These include approximate assessment of site
SOFT SOIL TUNNELLING NUMERICAL MODEL 433
Time

Vertical
displacement
of the crown
point

Ph0 Ph1 Ph2 Ph3

Beginning Passing Passing


of the the face the tail
monitoring

Passing the
TBM
Grouting process

Maximum of the crown point End of the


upward movement monitoring

Fig. 7. The four different phases of vertical displacement of the crown


points

Table 2. Absolute vertical displacements (v i ) and relative vertical displacements (dv i ˆv i 2v i21 ) for each phase no.
i, in mm
Phase 0 Phase 1 Phase 2 Phase 3
v0 dv1 v1 dv2 v2 dv3 v3
S1±T1: EXT11A ÿ1´7 ÿ7´8 ÿ9´5 ‡5´3 ÿ4´2 ÿ11´0 ÿ15´2
S1±T2: EXT41A ÿ2´0 ÿ8´8 ÿ10´8 ‡5´5 ÿ5´3 ÿ6´6 ÿ11´9
S2±T1: EXT21A ÿ1´3 ÿ2´7 ÿ4´0 ‡4´8 ‡0´8 ÿ9´0 ÿ8´2
P2±T1: EXT31A ÿ1´0 ÿ1´4 ÿ2´4 ‡5´4 ‡3´0 ÿ4´7 ÿ1´7

5 500
EX31A Pressure
4
Concrete upward movement: cm

segment 450
Settlement of EX31A: mm

3
400
Pressure: kPa

2
350
1
300
0
250
21

22 200

23 150
21 20.5 0 0.5 1 1.5 2 2.5 3
Days since grouting

Fig. 8. Zone 2: measurement of soil and tunnel vertical displacement,


and of pore pressure in the grout
434 BERNAT, CAMBOU AND DUBOIS

q S2 of zone 1 was 35 m. The two sections'


Elastic domain ,φ 2 stratigraphies were very similar but their geome-
φ
trical conditions differed due to a retaining wall
1
K e0,G e0,n ,B ,
:A
r fac
e
Deviatoric mechanism designed to hold back a 6 m high back®ll. Zone 2
su geometry was symmetrical, but the nearness of the
ure Isotropic and kinematic
ail
F hardening: bedrock (3 m under the tubes) should be noted. The
A,a,G0,Rc,β selected stratigraphies are presented in Figs 10
(section S1), 10(b) (section S2) and 10(c) (zone 2).
They show alternating silts, ®ne sands and clays (in
Yielding su
rface
p the excavation zone) interlaid with the surface ®ll
Isotropic mechanism and a sand and gravel underlayer. Tables 3±5
Isotropic hardening:
summarize the geometrical data of the three
K p0,n
(a) computation sections.

Identifying soil layers for CJS parameters. Dur-


S1 ing investigation sessions in the two test zones, core
boring (for laboratory tests) and ®eld pressuremeter
tests were carried out. The de®nition of the CJS
model constants initially consisted of performing
oedometer and triaxial CD laboratory tests. Avail-
able test results (summarized on the left of Fig.
10(a) for zone 1, and Fig. 10(c) for zone 2) were
entered into the various computer programs used
for CJS law identi®cation. The ®rst parameter sets
were thus de®ned for silty clay layers in the tube
vicinity of the sections considered. These sets
Yielding surface became input for the numerical modelling of
Deviatoric mechanism pressuremeter tests. These models were compared
Isotropic and kinematic with the results of in situ tests, and the selected
S2
hardening
S3 parameters were then re®ned and speci®c local site
Failure surface conditions included. Figs 11(a) and 11(b), for
example, show simulated and experimental labora-
(b) tory tests carried out in the violet clay of zone 1.
Fig. 11(c) shows pressuremeter tests at depths of 13
Fig. 9. Hardening mechanisms, yielding and failure
surfaces and constants, of the CJS constitutive model:
and 14 m in S1 (the pressuremeter tests were
(a) ( p, q) plane; (b) deviatoric plane carried out using an unloading±reloading inter-
mediate cycle, allowing the elastic constants to be
more accurately de®ned). These results show that
geometry and stratigraphy, unavoidable soil re- one of the model constant sets corresponds closely
moulding during material core sampling (making to all the test results, despite the fact that all the
identi®cation of a given layer very dif®cult), scanty stress path tests are very different. Where no
knowledge of initial, pre-excavation formation con- laboratory tests were available, the ®rst set of
ditions, and badly controlled excavation modelling. constants was de®ned using average values that had
Model comparisons thus enable not only the model been estimated for different types of soils, including
capacity and computation code to be tested, but clay, silt, dense sand and loose sand (Maleki, 1998).
also the whole two-dimensional procedure, includ- This ®rst set was then optimized, comparing the
ing the four items mentioned above. numerical modelling of pressuremeter tests with
experimental results. This procedure, based on
pressuremeter tests, is useful because traditional
Identifying model parameters of the layers of the soil investigations in France use a large range of
computation sections concerned (Bernat et al., pressuremeter tests and not many laboratory tests.
1995a,b)

Identifying soil layers. Before computation sec- Computation code CESAR-LCPC using the ®nite
tion models can be set up, their stratigraphy must element method
be de®ned. The various core samples collected in The mesh designed for the ®nite element meth-
the area were used and pressuremeter tests were od calculation is ®ner close to the tubes (where
carried out to determine layer thickness. The gradients are steep) and enlarged laterally to avoid
distance between the two design sections S1 and boundary effects (which are signi®cant with a
SOFT SOIL TUNNELLING NUMERICAL MODEL 435

Tests T 5 triaxial
O 5 oedometer
T O P P 5 pressure meter
1 Fill

1 2 2 Water table
Beige silt

2 2 Ochre silt

2 2 2 Grey clay

1 Tunnel Tunnel Grey sand


T2 T1
1 1 2 Violet clay

1 Sand and gravel

(a)

Fill

Water table Beige silt

Ochre silt

Grey clay

Grey sand
Tunnel Tunnel
Violet clay
T2 T1
Grey silt

Violet clay

Sand and gravel

(b)

Fig. 10. Continued overleaf

back®ll, as in zone 1). Imposed boundary condi- in fact demonstrated that excess pressures gener-
tions consist of blocking horizontal displacements ated by tunnelling operations generally dissipate in
on the sides, and vertical displacements in the a few hours. (Fig. 14, Kastner et al., 1995). The
lower part of the mesh. In addition to the various experimental settlements drawn with respect to
geological layers to be identi®ed, the mesh is time integrate two elements: the changing distance
designed to monitor the tunnelling and supporting to the working face (this plays an important role in
techniques from the formation changes observed in the boundary condition at the periphery of the
the areas to be excavated (the mesh used for S1 is tunnel), and the possible increase of strain resulting
presented in Figs 12 and 13). from soil consolidation. This second element is in
All the computations were carried out in drained fact reckoned to occur rapidly, and the proposed
conditions (effective stresses under the water table). modelling was designed to consider only the soil
Pore pressure measurements taken in the low per- state after consolidation (drained conditions and
meable layer (silt located at the top of the tunnel) effective stresses) for each stage of calculation.
436 BERNAT, CAMBOU AND DUBOIS

Tests
T O P
1 Fill
Water table
3 3
Silt 1

1 1 1 Silt 2
1 2 Silt 3
1 Sand
1 1 1 Silt 4
Tunnel
1 1 1 T1 Clay
1 Sand

1 Sand and gravel

Bedrock

(c)
Fig. 10. Stratigraphical sections of the Lyon-Vaise work site: (a)
zone 1, section S2; (b) zone 8, section S2; (c) zone 2

Table 3. General characteristics of zone 1, section S1


Layers Level NGF top Depth top Depth top Thickness
left right

1) Fill 167´97±173´9 0 0 1´72±7.65


2) Beige silt (dry) 166´25 1´72 7´65 1´25
2b) Beige silt 165 2´97 8´9 1´85
3) Ochre silt 163´15 4´82 10´75 2´45
Layers 4) Grey clay 160´7 7´27 13´2 2´25
5) Grey sand 158´45 9´52 15´45 2´60
6) Violet clay 155´85 12´12 18´05 2´85
7) Sand and gravel 153 14´97 20´9
Top tunnel 1 160´10 13´79
Centre tunnel 1 156´97 16´93
Tunnel Bottom tunnel 1 153´83 20´06
Top tunnel 2 160´10 7´86
Centre tunnel 2 156´97 11
Bottom tunnel 2 153´83 14´13

The initial stress condition of the back®ll behind tion in the plane perpendicular to the shield ad-
the retaining wall in zone 1 was not geostatic; it vance (Panet & Guenot, 1982). This two-
was de®ned using a preliminary settlement compu- dimensional approach appeared to be justi®ed in
tation, under natural weight. This computation may the Lyons-Vaise case, since settlements recorded
be carried out in one or two phases, since the ahead of the working face in phase 0 were always
back®ll was probably formed after the sedimentary minor.
constitution of the soil. Two methods are suitable for tunnel modelling
in two-dimensions.

Two-dimensional excavation modelling Procedure 1: tunnelling is simulated by a stress


Presentation. Stress evolution generated by tun- boundary condition at the periphery of the tunnel
nel excavation is essentially three-dimensional, The principle (see ®rst part of Fig. 15) is to
since it depends on the distance to the working remove the soil inside the excavation and to re-
face. A signi®cant (but conventional) simpli®cation place it by ®ctitious stress supporting vectors
was applied by considering a plane strain calcula- which equilibrate the initial state. Tunnel modelling
SOFT SOIL TUNNELLING NUMERICAL MODEL 437
Table 4. General characteristics of zone 1, section S2
Layers Level NGF Depth top Thickness
top left

1) Fill 168´12 0 2´12


2) Beige silt (dry) 166´00 2´12 1´00
2b) Beige silt 165´00 3´12 1´50
3) Ochre silt 163´50 4´62 2´70
Layers 4) Grey clay 160´80 7´32 3´20
5) Grey sand 1 157´60 10´52 2´00
6) Violet clay 1 155´60 12´52 1´50
5b) Grey sand 2 154´10 14´02 0´90
6b) Violet clay 2 153´20 14´92 1´90
7) Sand and gravel 151´30 16´82
Top tunnel 1 158´10 10´015
Centre tunnel 1 154´97 13´15
Tunnel Bottom tunnel 1 151´83 16´285
Top tunnel 2 158´23 9´885
Centre tunnel 2 155´10 13´02
Bottom tunnel 2 151´96 16´155

Table 5. General characteristics of zone 2


Layers Level NGF Depth top Thickness
top left

1) Fill 168´35 0 3´00


2) Silt 1 165´35 3´00 4´00
3) Silt 2 161´35 7´00 2´00
4) Silt 3 159´35 9´00 2´00
Layers 5) Sand 157´35 11´00 1´00
6) Silt 4 156´35 12´00 1´00
7) Grey clay 155´35 13´00 1´50
8) Sand 153´85 14´50 1´50
9) Sand and gravels 152´35 16´00 3´50
10) Bedrock 148´85 19´50
Top tunnel 1 158´14 10´20
Tunnel Centre tunnel 1 155´01 13´34
Bottom tunnel 1 151´87 16´47

consists of progressively releasing all the compo- Procedure 2: modelling the soil±lining interaction
nents of the stress vector acting on the excavation (Bernat et al., 1997)
periphery. The reducing factor is called the `decon- This more complex modelling (see second part
®nement factor' (or stress release factor), written ë. of Fig. 15) consists of direct taking into account of
In such modelling with no support in the tunnel, the interaction between soil and structure. A ®rst
the stress boundary condition can continue until decon®nement is considered, and then the tunnel
the total cancelling of the vectors for ë equals (including lining and grout) is taken into account
100%. But in the case of tunnel lining, the decon- and the decon®nement factor is increased to 100%.
®nement factor never reaches 100% because stabi- The ®nal stress state will result from the inter-
lization occurs at a lower value that corresponds to action between the lining, the grout and the soil ±
the interaction between soil and structure. The it will no longer be determined by the value of ë f
problem is to calculate this ®nal factor ë f , as- as in procedure 1.
sumed to be representative of the whole tunnelling The ®rst procedure uses only one parameter ë f
process. ë f is dif®cult to estimate a priori but can whose de®nition will be analysed later.
be determined a posteriori by comparison between The second procedure seems more realistic but
modelling and measurements. is also more complex to use because it is necessary
438 BERNAT, CAMBOU AND DUBOIS
20
Experiment 700

ε1: %

dV : cm3
16
600
12

8 500
Simulation
4
σ: kPa 400
0
0 50 100 150 200 250 300 350 400
6 300
σ1 2 σ3
σ3

5
Exp-14m
4 Simulation 200
Simu-14m
3 Simu-13m
100 Exp-13m
2 Experiment
1 DP: kPa
ε1: % 0
0 0 200 400 600 800 1000
0 5 10 15 20 25

Fig. 11. Oedometer (a) and triaxial (b) tests carried out in the violet clay of zone 1. (c) Pressuremeter
tests carried out in the violet clay of zone 1 and 13 m and 14 m depth

Fig. 12. Mesh of section S1, zone 1

to model the complete interaction between the soil


and the structure. This particularly implies taking
into account the mechanical characteristics of the
grout, which goes from a ¯uid state to a solid state
after being injected between the concrete segment
and the soil. For these reasons, only the ®rst
procedure will be presented in this paper. The
second procedure was analysed and compared with
the ®rst in Bernat's thesis in 1996, and will be
presented in a future paper.

General analysis of stress paths around unlined


tunnels. An initial general analysis was carried out
Fig. 13. Mesh of tunnel T1, S1 to better understand the different stress paths
SOFT SOIL TUNNELLING NUMERICAL MODEL 439
80

70

Hydrostatic pressure: kPa


60

50

40
Upward
30 phase

20
Passing
the face
10 Grouting

0
25 24 23 22 21 0 1 2 3 4 5 6 7 8 9 10
Days before or after passing the face

Fig. 14. Pore pressure measurement at the crown of S1±T1

Excavation

λ 5 0% 0 , λ , 100% λ 5 100%

T0
Without lining

(1 2 λ) T0
0
λ T0
T0
T0 T0 T0
Soil Soil Soil
Cavity Cavity Cavity
With lining at λ1

T0
(1 2 λ1) T0 Ts

λ1 T0 T0
T0
T0 T0
Soil Soil Soil
Tr
Cavity Cavity Lining

Fig. 15. Two ways of modelling tunnelling

occurring around the tunnel (Lee & Rowe, 1989), obtain realistic results, constants of the two models
and to compare the local behaviour indicated by the (MC and CJS) were de®ned using triaxial test data
CJS model with the MC model (the Mohr± obtained on silty sand. To account for the
Coulomb elastic±perfectly plastic model) in a dependence of the Young modulus on depth,
simple homogeneous theoretical case study. The ®ctitious 3 m thick layers were used for this
tunnel was represented by a circular 3 m radius imaginary case study. The Young's modulus used
cross-section and an overburden the thickness of in MC was the secant modulus at 50% of the failure
two diameters. The soil was considered to be stress from the triaxial test simulated using the CJS
homogeneous. For the sake of simplicity, the initial model, with con®ning pressure near the horizontal
stress state was considered to be located on the K0 stress in the middle of each layer (Figs 16 and 17).
line. In the calculation procedure, this stress state It should be noted that this type of `MC-equivalent
corresponded to certain values of hardening para- Young's modulus' takes into account plastic defor-
meters which had been initially calculated. To mations. The stress paths of various points (located
440 BERNAT, CAMBOU AND DUBOIS
300 200 .
.
Triaxial simulated test at K0 line
180 5
195 kPa of confining pressure MC criterion . 4
250
Line defining the MC Isotropic line
160
.

Minor principal stress σ1: kPa


.
equivalent Young modulus 3
200 140 .
Stress: kPa

.
1 2
120 .
150
Around 50% of the 1 2
100 .
maximum stress
100 3
80 .
52.2% 4
. 5
50 60 45%
MC equivalent point 1
Young modulus 40 Each point 5 an increment point 2
0 of 10% of deconfinement . point 3
0 0.2 0.4 0.6 0.8 1 1.2 1.4 20 point 4
point 5
Strain: % 0
0 20 40 60 80 100 120 140 160 180 200
Fig. 16. Modelling of a triaxial test with CJS para-
Minor principal stress σ2: kPa
meters and de®nition of an equivalent Young modulus
(for MC)
200
K0 line
MC criterion 5
15 180
12 . . . 4
Vertical distance from T1 centre line: m

.
9 . .
Isotropic line
160
6
Minor principal stress σ1: kPa

.
.
3 140 3
0
23 E-MC .
51 2
26 E-CJS 120
4
29 . 1 2
212 100
215 . 3
3
218 80
221 57.5% 5
4
224 60 1 2 45%
227 point 1
230 40 point 2
233 . point 3
236 20 point 4
239 point 5
0 20 40 60 80
100 120 140 160 180 0
10 30 50 70 90 110 130 150 170 0 20 40 60 80 100 120 140 160 180 200
Young modulus value: MPa
Minor principal stress σ2: kPa
Fig. 17. Confrontation of CJS and MC Young modulus
with depth Fig. 18. Effective stress paths around an unlined
tunnel: MC (a) and CJS (b) simulations until
ë ˆ 100%
at the excavation periphery) obtained by ®nite
element analysis were drawn in the principal stress
plan (Figs 18(a) for MC and 18(b) for CJS). 30%). The paths then follow the plastic
criterion, which is not exactly the same for
(a) All effective stress paths start from the K0 the two models because of the plane strain
line. paths considered.
(b) At the crown and the bottom, excavation (d) The points located 458 above and below the
produces a decrease in vertical stress, follow- haunches follow the same kind of paths, but
ing an elastic unloading path as far as the more progressively. Rotation of the principal
isotropic state where the principal directions directions occurred here so that the initial one
are inverted (for ë near 50%). Vertical stress (which was vertical and horizontal) rotated
then continues to decrease and the path reaches such that the minor principal stress took the
the failure point. radial direction. It should be noted that for
(c) At the haunches, excavation induces horizontal values of ë under 30%, MC modelling leads to
unloading, which leads, more quickly in MC stress states that satisfy elastic conditions.
than in CJS, to the plastic state (for ë close to Even for high values of ë, the calculation
SOFT SOIL TUNNELLING NUMERICAL MODEL 441
shows (Fig. 19) that the plastic strains remain throughout the tunnel length. This point will be
near the tunnel haunches, in a very small area. analysed and commented on later when considering
®eld data. On the Lyons-Vaise site it was decided
In the case of the Lyons-Vaise site where the to use the value of the vertical displacements of
measurements correspond to small values of ë (as the measurement point closest to the excavation
we will see later), the MC model works essentially (EX11A for S1±T1, EX21A for S2±T1, EX31A
as an elastic model, giving only reversible defor- for P2±T1 and EX41A for S1±T2) for ®tting
mation. In such cases, the CJS model, which shows purposes.
irrecoverable strains even for small values of ë, is
much more realistic, particularly if an unloading±
reloading cycle (to be explained below) has to be Determination of ëf using the ®nal measurements
taken into account. The curves of settlement with time of the
`crown' points are detailed later. It should be noted
that the settlement curves for the three points at
EXCAVATION MODELLING AS A STRESS the crown of zone 1 have almost the same slope
BOUNDARY CONDITION before and after the upward phase 2, and that this
In the `convergence±con®nement' method upward movement observed at the crown point is
(Panet & Guenot, 1982), some empirical formula- practically negligible at the surface. In this zone it
tions were put forward to determine the ë f value seems that this intermediate upward phase has no
to be used for deep tunnelling models in hard rock. effect on the ®nal state. The ë f value was there-
In the case of shallow tunnels in soft soil, this ë f fore adjusted (Fig. 20) so as to give good agree-
information does not seem realistic. In the Lyons- ment between calculated and recorded ®nal
Vaise case, this ®nal factor was estimated for settlement value at the crown point level for zone
section S1 before the beginning of the work ± a 1 (the case of zone 2 is discussed later). It should
value of about 35% leads to surface settlements be added that these ®nal values corresponded to
between 20 and 30 mm (Bernat, 1995). A more the last measurements carried out before instru-
accurate ë f value can be obtained by ®tting the mentation removal and they had not yet been fully
modelling results and ®eld data together. This stabilized.
measurement can be carried out at the beginning
of the work and would be of great interest if a Excavation of the ®rst (T1) tube in zone 1. It can
realistic forecast is required throughout the length. be observed that despite substantially different
This procedure would only be of interest if it could geometrical and stratigraphical conditions, the two
be demonstrated that ë f is approximately constant sections S1 and S2 of zone 1 show ®nal settlements

λ 5 30% λ 5 40% λ 5 50% λ 5 60% λ 5 70% λ 5 80% λ 5 90% λ 5 100%

Fig. 19. Development of plastic areas around the tunnel during MC tunnelling modelling

5 5
Experimental settlements: mm

Calculated settlements: mm

EX31A
0 0
P2: EX31A: 21.7 mm λ 5 2.8%

25 25
S2: EX21A: 28.2 mm
210 EX21A
210
λ 5 11.3%
S1-T2: EX41A: 211.9 mm
EX41A
215 215
S1-T1: EX11A: 215.2 mm λ 5 18.2%
EX11A
λ 5 11.5%
220 220
210 0 10 20 30 40 50 60 70 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time since the passing of the face: days Deconfinement factor: %

Fig. 20. Settlement of the crown point of each four sections: (a) experiment; (b) CJS modelling
442 BERNAT, CAMBOU AND DUBOIS

Vertical distance from T1 centre line: m


corresponding to the same ë f ± close to 12% after 18
excavation of the ®rst tunnel. This seems to con®rm 16
EX13-T1-cjs
EX13-T1-mc
that such a factor can be explained primarily by the 14 EX13-T1-exp
tunnelling technique used. 12
Surface
10
T1 excavation in S1 8
CJS and MC models give reasonable modelling 6
of surface settlements and, in particular, anticipate 4
the movement of the settlement trough centre 2
towards the retaining wall (Fig. 21). The fairly 0
close harmony between MC simulations and ®eld 22
data can be explained as follows: 218 216 214 212 210 28 26 24 22 0
(a) In the case being analysed, loading increased Vertical displacement: mm
continuously and the deformations around the (a)
tunnel were relatively small (essentially in the

Vertical distance from T1 centre line: m


elastic domain). 18
(b) The elastic characteristics were de®ned from 16 Surface
the pressuremeter test; in other words these 14
characteristics included some non-linear phe- 12
nomena. 10
8
Figure 22 shows good concordance between
6
modelling and experimental measurements from
4
two extensometers in S1 (showing how settlement EX11-T1-cjs
2
varied with depth), placed respectively on the left EX11-T1-mc
EX11-T1-exp
and at the crown of T1. It is interesting to plot the 0
displacements calculated at the tunnel periphery. In 22
218 216 214 212 210 28 26 24 22 0
terms of vertical displacement around the tunnel
Vertical displacement: mm
(Fig. 23), the crown settlement (from 16 mm in
CJS to 18 mm in MC) and the bottom upward (b)
movement (from 2 mm in CJS to 5´5 mm in MC)
Fig. 22. Extensometer EX13 (a) and EX11 (b) of S1±
should be noted. The back®ll-related asymmetry T1 (CJS and MC modelling with ë ˆ 11:5%, and ®eld
that can be observed substantially increased settle- data `exp')
ment on the right side of the tunnel. For CJS
calculation, a left-haunch 2 mm settlement and a 5
right-haunch 7 mm settlement were recorded. In

Up
Vertical displacements: mm

terms of horizontal displacements around the tun- 0


nel, Fig. 24 shows inward-converging horizontal
displacements (in particular calculated with the 25
CJS model) for the tunnel periphery at haunch T1v-cjs
T1v-mc
height. However, this phenomenon was limited to a 210
very short stretch of the tunnel because inclin-
ometer measurements (Fig. 25) show that at a 215 Left Right
Crown haunch Bottom haunch Crown
0 220
Vertical displacements: mm

0 45 90 135 180 225 270 315 360


22
Angle (8)
24
Fig. 23. Vertical displacements at the periphery of T1
26 in S1 (CJS and MC modelling with ë ˆ 11:5%)
28
210 certain distance from the tunnel a ground outward
cuv-T1-cjs movement is observed at haunch height. This phe-
212 cuv-T1-mc
cuv-T1-exp nomenon is described very well by the CJS model
214 but is not present in the MC model.
230 220 210 0 10 20 30
Horizontal distance from T1 centre line: m Excavation of T1 in S2
Fig. 21. Surface settlement: modelling (in CJS and in For S2, instrumented only for the excavation of
MC with ë ˆ 11:5%) and ®eld date (`exp') for S1±T1 T1, the curves in Fig. 26 show good concordance
SOFT SOIL TUNNELLING NUMERICAL MODEL 443
of the computed results with the surface settlement 0
trough (Fig. 26), the width of which is slightly

Vertical displacements: mm
21
overestimated by the calculation, and the extens- cuv-T1-cjs
22
ometer at the crown EX21 (Fig. 27). As regards cuv-T1-exp
horizontal displacements (Fig. 28), CJS computa- 23
tion anticipated a lateral outward movement ®ve
24
times lower than that observed. This measurement,
double that in S1, is not related to an increase in 25
grouting pressure for S2 and has not been ex-
26
plained.
27
Comparison of the vertical movements induced in 250 230 210 10 20 30
S1 and S2 Horizontal distance from T1 centre line: m
It should be noted that experience produces Fig. 26. Surface settlement: modelling (in CJS with
settlement values whose signi®cance decreases with ë ˆ 11:5%) and ®eld data (`exp') for S2±T1
tunnel depth between S1 and S2. Computation
predicted such differences in settlements between

Vertical distance from T1 centre line: m


the two sections, since they decreased from 14
15´2 mm at the crown for S1 to 8´2 mm at the
crown for S2, for the same ë f close to 12%. This 12
can be explained because for the same ë f value,
10
incremental unloading will be less for the smaller
value of overburden where the initial stresses are 8
smaller.
6

4 EX21-T1-cjs
4 EX21-T1-exp
To the right
Horizontal displacements: mm

T1u-cjs
2
T1u-mc
2 29 28 27 26 25 24 23 22 21 0
Vertical displacements: mm
0
Fig. 27. Extensometer EX21 of S2±T1 (CJS modelling
with ë ˆ 11:5%, and ®eld data `exp')
22

Excavation of the second tube (T2) in zone 1.


24 Left Right
Crown haunch Bottom haunch Crown
Excavation of T2 in S1
26
0 45 90 135 180 225 270 315 360
For the second tube excavation in S1, the com-
Angle (8)
putation±experience adjustment yielded a ®nal de-
con®nement factor close to 18%, bearing in mind
Fig. 24. Horizontal displacements at the periphery of that the grout around the ®rst tube T1 had been
T1±S1 (CJS and MC modelling with ë ˆ 11:5%) consolidated. This ë f increase could be related to
Vertical distance from T1 centre line: m

16
14
12
10
8
6
4
2
0
22
24 I14-T1-cjs I17-T1-cjs
I14-T1-mc I17-T1-mc
26 I14-T1-exp I17-T1-exp
28
210
25 24 23 22 21 0 1 2 25 24 23 22 21 0 1 2
Horizontal displacements: mm Horizontal displacements: mm

Fig. 25. Inclinometer I14 and I17 of S1±T1 (CJS and MC modelling with ë ˆ 11:5%, and ®eld data `exp')
444 BERNAT, CAMBOU AND DUBOIS

10

Vertical distance from T1 centre line: m


8 I24-T1-cjs
I24-T1-exp
6
4
2
0
22
24
26
28
210
26 25 24 23 22 21 0 1 2
Horizontal displacements: mm

Fig. 28. Inclinometer I24 of S2±T1 (CJS modelling with ë ˆ 11:5%,


and ®eld data `exp')

a technological change ± the TBM ran into a hard Vertical distance from T1 centre line: m
17
conglomerate zone, and so the cutting head was EX41-T2-cjs
EX41-T2-exp
15
changed for the boring of tunnel T2. This second EX11-T2-cjs
head was more suited to dealing with hard ground, 13 EX11-T2-exp
but less adapted to soft ground. The settlement 11 EX41 EX41
trough at the surface (Fig. 29) was shallower than simu
exp
that of the ®rst excavation, owing to the lower 9
EX11
overburden above the tube. Modelling always gives 7 EX11 simu
the back®ll in¯uence (on the right-hand side) actu- exp
5
ally observed at the experimental trough level.
Extensometers (Fig. 30) show experimental meas- 3
urements in concordance with computed results. 212 210 28 26 24 22 0
CJS modelling slightly underestimates settlements Vertical displacements: mm
at the EX11 level, but the trough alignment shows
that such a phenomenon is limited locally and then Fig. 30. Extensometers EX41 and EX11 in S1±T2
(CJS modelling with ëT1 ˆ 11:5% and ëT2 ˆ 18%,
has a reverse trend close to the trough sides. ®eld data `exp')

Comparing ®nal modelling settlements of both sec-


tions of zone 1
Section S2 was not instrumented during the
0 second excavation operation. Modelling results are
presented with an 18% factor for the excavation of
Vertical displacements: mm

22 the second tunnel. In S1, dominating settlements


were generated by the ®rst excavation due to the
24 signi®cant overburden over the T1 tube (Fig. 31).
In S2, dominating settlements were generated by
26 the second excavation related to a higher decon-
®nement factor for the same overburden between
28 cuv-T2-cjs T1 and T2 (Fig. 32).
cuv-T2-exp
210 Conclusions for zone 1
230 220 210 0 10 20 30 (a) These various comparisons between experi-
Horizontal distance from T1 centre line: m mental and modelling curves demonstrated that
Fig. 29. Surface settlement in S1±T2 (CJS modelling the whole proposed procedure (and in parti-
with ë ˆ 11:5% for T1 and ë ˆ 18% for T2, ®eld data cular the conventional decon®nement mode)
`exp') enabled modelling in good agreement with the
SOFT SOIL TUNNELLING NUMERICAL MODEL 445
0 (e) This calculation in one stage of decon®nement
cannot be applied in zone 2, where ®nal crown
Vertical displacements: mm

22
24 vertical displacements were smaller than ®nal
T2
26 surface settlements.
28
210 T1
212
Modelling a `recon®nement' cycle
In order to take into account the intermediate
214 cuv-S1-T1-cjs
T112 cuv-S1-T2-cjs
phase 2 (which is not without importance in zone
216
cuv-S1-T112-cjs 2), new modelling was carried out by imposing a
218 decon®nement factor value adjusted to the settle-
240 230 220 210 0 10 20 30 40 ment changes with time at the crown points.
Horizontal distance from T1 centre line: m Because of the minor settlements recorded in phase
Fig. 31. Surface settlement in S1±T1, S1±T2 and S1± 0, this phase was integrated into the following
T1 ‡ 2 CJS modelling with ëT1 ˆ 11:5% and settlement phase 1. Three phases were modelled:
ëT2 ˆ 18% the ®rst settlement phase 0±1 was modelled by a
®rst decon®nement until ë1, an upward movement
0
phase 2 was modelled by an intermediate stress
increase (called `recon®nement') of äë2 to ë2, and
Vertical displacements: mm

22
a second settlement phase 3 modelled by a second
24
T1
decon®nement of äë3 to ë3. Figs 18±21 and Table
26 T2
6 give the results of this analysis which brings out
28
T112 the following elements.
210
212 As far as the excavation of tubes T1 and T2 in
214 cuv-S2-T1-cjs section S1 is concerned, the modelling of the
cuv-S2-T2-cjs
216 cuv-S2-T112-cjs
intermediate stress increase phase of phase 2 has
218
no effect on ®nal settlements. It should nevertheless
240 230 220 210 0 10 20 30 40 be noticed that intermediate stress increase was
Horizontal distance from T1 centre line: m
simulated in S1±T1 for a factor twice as low as the
®nal factor (Fig. 33(b)), while it was observed in S1±
Fig. 32. Surface settlement in S2±T1, S2±T2 and S2± T2 for a factor close to the ®nal factor (Fig. 34(b)).
T1 ‡ 2 CJS modelling with ëT1 ˆ 11:5% and The intermediate stress increase phase had to be
ëT2 ˆ 18% continued in both cases up to a factor close to 0%, as
if grouting and hydrostatic pressure restored initial
phenomena observed under tunnelling condi- ®eld pressure. Modelling clearly shows the phenom-
tions. enon of crown point rising, and, to a lesser degree,
(b) The adjustment of ë f in zone 1 gave a ®nal that of the surface points. Decon®nement then occurs
factor that was close to 12% for T1 excavation. in the reverse order of the intermediate stress increase
The same value was then found in the two stage, on the right-hand side of the reloading curve
cases (S1±T1 and S2±T1) where the same up, then returning to the initial curve. This shows
excavation process and the same alignment elastic-type behaviour during the cycle.
were present but where different geometrical
and stratigraphical conditions were recorded. Conversely, the intermediate stress increase
Maximum settlements decreased from phase of phase 2 has a signi®cant effect on ®nal
15´2 mm to 8´2 mm between the two sections, settlements in S2 and zone 2. It should be observed
this decrease having been accurately predicted that in both cases (Figs 35b and 36b) intermediate
by the calculation for the same ë f of 12%. stress increase modelling does not stop at 0%, but
(c) The adjustment of ë f in section S1 gave a goes beyond this value to reach negative factors
®nal factor close to 18% for the second (T2) applying a pressure higher than that existing under
tunnel excavation. In the same geometrical and initial conditions before the start of excavation.
stratigraphical conditions in S1, this increase When reaching the negative factors, the intermedi-
of ë f between the excavation of the two ate stress increase curves of phase 2 are no longer
tunnels T1 and T2 could be explained by a linear. This non-linearity announces signi®cant
technological change. irreversible deformations. The phase 3 decon®ne-
(d) These results proved that with the same layout ment phase following phase 2 is illustrated by a
conditions in zone 1. The ®nal decon®nement curve which no longer links up with that obtained
factor seems to depend essentially on the by ignoring the intermediate stage (extension of
technical conditions. phase 1). Finally, at the end of the excavating
446 BERNAT, CAMBOU AND DUBOIS

Table 6. Absolute decon®nement factor (ë i ) and relative decon®nement factor (äëi ˆ ë i 2 ë i21 ) for each phase no.
i, in %
Ph1 ‡ 2 ‡ 3 Ph1 Ph2 Ph3
Tunnel Section: ®tting point ëf ë1 äë2 ë2 äë3 ë3
T1 S1: EXT11A 11´5 7´7 ÿ10´4 ÿ2´7 14´6 11´9
T1 S2±T1: EXT21A 11´3 6´0 ÿ11´9 ÿ5´9 19´1 13´2
T1 P2±T1: EXT31A 2´8 3´9 ÿ13´1 ÿ9´5 14´0 4´5
T2 S1±T2: EXT41A 18´2 17´0 ÿ17´2 ÿ0´2 18´5 18´3

0 0
EX11A EX41A
Vertical displacements: mm

Vertical displacements: mm
22 EX11S EX41S
22
24
26 24

28 26
210 Passing 28
212 the face
214 210

216 212
220 0 20 40 60 210 0 10 20 30 40 50 60
Time: days
Time: days
(a)
(a)

0 0
EX11S-cjs EX41S-cjs
Vertical displacements: mm
Vertical displacements: mm

22 EX11A-cjs EX41A-cjs
22
24
24
26
28 26
210
28
212
210
214
216 212
232221 0 1 2 3 4 5 6 7 8 9 10 11 12 21 1 3 5 7 9 11 13 15 17 19
Deconfinement factor: % Deconfinement factor: %
(b) (b)

Fig. 33. Excavation of T1±S1: (a) measurements of Fig. 34. Excavation of T2±S1: (a) measurements of
EX11A and EX11S settlements; (b) modelling of EX41A and EX41S settlements; (b) modelling of
EX11A and EX11S settlements EX41A and EX41S settlements

procedure, modelling anticipated surface settle- Conclusion: the relative value of each decon®ne-
ments higher than those at the crown in S2 and ment±recon®nement phase.
zone 2. The phenomena recorded for zone 2 (Fig.
36a) were obtained from the model. The phase- (a) Phase 0±1 (before the passage of the TBM)
by-phase patterns (Figs 37±39) correspond very seems to be related to the speci®c layout
well with the actual results, and the modelling (Table 7). ë1 is around 4% in horizontal and
results concerning the decon®nement±recon®ne- straight-line alignment (P2), and about 6±8%
ment phases, depending on the technology used. with a slope and curvature in the tunnel
In the same way, this phenomenon was recorded alignment (S1 and S2). The TBM's 48 h halt
experimentally in S2 during the 5-day period under section S1 may explain the highest value
following grouting (Fig. 35(a)). of 8%.
SOFT SOIL TUNNELLING NUMERICAL MODEL 447
1 3
EX21A EX31A

Vertical displacements: mm
Vertical displacements: mm

EX21S EX31S
21 1.5

23
0
25
21.5
27

29 23
210 0 10 20 30 40 50 60 25 0 5 10 15 20 25 30
Time: days Time: days
(a) (a)

1 3
EX21S-cjs EX31S-cjs
Vertical displacements: mm

Vertical displacements: mm
0
EX21A-cjs 2 EX31A-cjs
21
22 1
23
0
24
25 21
26 22
27
28 23
29 24
27 24 21 2 5 8 11 14 211 29 27 25 23 21 1 3 5
Deconfinement factor: % Deconfinement factor: %
(b) (b)

Fig. 35. Excavation of T1±S2: (a) measurements of Fig. 36. Excavation of T1±zone 2: (a) measurements of
EX21A and EX21S settlements; (b) modelling of EX31A and EX31S settlements; (b) modelling of
EX21A and EX21S settlements EX31A and EX31S settlements

(b) Phase 2 seems to be of the same order of (e) MC simulations have not been presented in
magnitude for all three instrumented sections this section because they led to unrealistic
(äë2 is between 10% and 13%). The small results (surface soil heaving): the MC model is
differences observed could be explained by known to give unrealistic forecasts for cyclic
different grout pressure values, especially in loadings.
zone 2 and S1±T2, where grout pressure was
increased.
(c) Phase 3 certainly has an essential link with
grout consolidation, because very close values Grouting ¯uid properties (Bernat, 1996)
have been found (äë3 is between 14% and The grout injected behind the segments is inert
19%). It can be assumed that these values and consists of a ®ller material, bentonite and
depend on the density of the injected grout, water. Its ¯uid behaviour means that it cannot bear
linked to grout pressure, and on the overburden any shear stress. Thus actual shear stress evolution
on which the ®nal stress state depends (Table (shear decon®nement) at the excavation periphery
8). is certainly higher than radial stress evolution
(d) Because of the cutter-head change between the (radial decon®nement). In order to better under-
excavation of the two tunnels, there is only one stand these two mechanisms, radial-only, then
set of ®eld data in these changed technological shear-only, decon®nements were simulated for S1±
conditions. It is therefore very dif®cult to T1. It should be noted that the decrease of shear
analyse the values obtained and in particular stresses on the inner face of the excavation was
whether the observed increase in ë1 and äë2 is only a boundary condition. This does not imply
due to this change or to the in¯uence of the that the shear stresses in the soil around the tunnel
®rst tunnel. could be signi®cantly reduced.
448 BERNAT, CAMBOU AND DUBOIS

0.5 14

Vertical distance from T1 centre line: m


12
0 Ph2
10
Vertical displacements: mm

20.5 8
6
21 Ph1 Ph1
4 Ph2
21.5 2
Ph3
Ph3 Ph1
Ph2 0
22
Ph3 22
22.5
24
23 26
230 224 218 212 26 0 6 12 18 24 30 21.5 21 20.5 0 0.5 1
Horizontal distance from T1 centre line: m Horizontal displacements: mm
(a) (a)

0.5 14

Vertical distance from T1 centre line: m


12
0
Ph2
Vertical displacements: mm

10
20.5 8
6
21
4
Ph1
21.5 2
Ph1
22 Ph2 0
Ph3 22 Ph1
22.5 Ph3 Ph2
24 Ph3
23 26
230 224 218 212 26 0 6 12 18 24 30 21.5 21 20.5 0 0.5 1
Horizontal distance from T1 centre line: m Horizontal displacements: mm
(b) (b)

Fig. 37. Excavation of tunnel T1±zone 2: comparison Fig. 38. Excavation of tunnel T1±zone 2: comparison
modelling-®eld data for the surface settlement (three modelling-®eld data for the Inclinometer I36 (three
different phases). (a) Experiment. (b) Simulation different phases). (a) Experiment. (b) Simulation

(a) The diagram shown in Fig. 40 illustrates the increased lateral outward movement as com-
settlement changes for the two extreme points pared to radial decon®nement. This is con-
EX11A and EX11S of crown extensometer ®rmed by the plot of simulated inclinometric
EX11 in S1, as a function of the decon®ne- measurements (Fig. 41(c) for I14 and I17).
ment type selected. The 15´2 mm value meas- (c) Plotting the vertical displacement on EX11
ured experimentally at EX11A was obtained (Fig. 41(e)) shows that in a purely shear
for a radial decon®nement factor of 12´5% and decon®nement case, the maximum value is no
for a shear decon®nement factor of 92%. This longer located at the crown point but at some
demonstrates that the displacements measured distance from it. Measurements do not show
are compatible with large shear decon®nement such a phenomenon.
factors. (d) It should be noted that the crown ®tting gives
(b) Plotting the horizontal displacements calcu- surface settlements of the same order of
lated at the T1 excavation periphery (Fig. magnitude for both kinds of decon®nement
41(b)) demonstrates that shear decon®nement (Fig. 41(d)).
SOFT SOIL TUNNELLING NUMERICAL MODEL 449
14 Conclusions
Vertical distance from T1 centre line: m

(a) Decon®nement can be used as a boundary


12
EX31
condition until a ®nal factor or possibly with
Ph3 EX31 Ph1 an intermediate `recon®nement' cycle, both
10 Ph1 Ph2 experimentally determined. This allows displa-
Ph3 cements measured in the ground, especially
8 surface settlements, to be found.
(b) The analysis proved that the whole tunnelling
EX31 process cannot be modelled by a shear-only
6
Ph2 decon®nement. On the other hand, by correctly
forecasting lateral outward movement related
4
to the shear-only decon®nement calculation, it
also showed that part of the tunnelling process
2 (probably in phase 1) could be modelled by
24 23 22 21 0 1 2 3 4 increasing the shear release factor relative to
Vertical displacements: mm the radial one.
(a)

CONCLUSION
14
The ®eld data obtained on the Lyons-Vaise
metro was used to evaluate an excavation model-
Vertical distance from T1 centre line: m

EX31
ling procedure using the ®nite element method.
12
Ph3
Ph1 The various model results-to-®eld-data comparisons
Ph2 demonstrated that the computation strategy selected
10 Ph3 led to reasonably accurate forecasting when based
EX31 on actual working conditions, with a basic know-
8 Ph1 ledge of soil layers and of the decon®nement
factor. When adjusting the observations of a few
6 measurements at the beginning of the tunnelling
EX31
Ph2
operation, an accurate assessment of the decon®ne-
4
ment factor enables good forecasting over the
whole site to be obtained despite constant changes
in geometrical and stratigraphical elements.
2
Two cases can be noted:
24 23 22 21 0 1 2 3 4
Vertical displacements: mm (a) In more dif®cult excavation conditions (slopes
(b) and bends), the initial settlement phase 0±1 is
important relative to the upward movement of
Fig. 39. Excavation of tunnel T1±zone 2: comparison phase 2. In that case, an analysis of ®nal
modelling-®eld data for the Extensometer EX31 (three conditions is suf®cient and modelling can be
different phases). (a) Experiment. (b) Simulation done in only one decon®nement stage. The

Table 7. Layout conditions and TBM halt beneath instrumented sections


Section S1±T1 S2±T1 P2±T1 S1±T2
Overburden 13´8 m 10 m 10´2 m 7´9 m
Horizontal Descent x x x
alignment Straight line x
Vertical Left bend x x x
alignment Straight line x
Halt Before section ÿ1 m ÿ1 m ÿ2 m
of (1/2 day) (1 day) (3´5 days)
TBM Under section 2´5 days 2´5 days
450 BERNAT, CAMBOU AND DUBOIS

Table 8. Comparison of relative crown settlement, relative decon®nement factor


and overburden in phase 3
Crown point Overburden: m äv3: mm äë3: %
EXT11A 13´8 ÿ11´0 14´6
EXT41A 7´9 ÿ6´6 18´5
EXT21A 10´0 ÿ9´0 19´1
EXT31A 10´2 ÿ4´7 14´0

0
EX11S: radial deconf.
22 EX11A: radial deconf.
EX11A: shear deconf.
Vertical displacements: mm

24 EX11S: shear deconf.

26
EX11S
28 EX11S dec-shear
dec-rad
210
EX11A
dec-shear
212

214 EX11A
dec-rad
216
210 0 10 20 30 40 50 60 70 80 90 100
Radial or shear ‘deconfinement’ factor: %

Fig. 40. Excavation of T1±S1: EX11A and EX11S modelling of radial


and shear `decon®nement'

analysis proved that for the same tunnelling This modelling based on a decon®nement pro-
technique, this factor is approximately constant cedure does not require the mechanical properties
on the length (about 12% in the case studied, with of the grout to be determined, and seems to give
a slurry-pressurized TBM and the ®rst wheel). reasonable forecasts for surface settlements due to
(b) In the best excavation conditions (horizontal and shallow tunnelling. It thus appears to be a very
linear), the upward intermediate phase 2 can no simple way of obtaining good assessment of possi-
longer be ignored. Modelling using the `decon- ble damage related to shallow tunnelling in soft
®nement factor' with an intermediary `decon- soil. But it must be noted that ë is only a
®nement±recon®nement' cycle seems to give mathematical strategem and has no physical rea-
realistic results as far as ground displacements lity. In the case of shallow tunnels in particular,
are concerned. The ®rst decon®nement phase 0± the weight equilibrium of the tunnel is not com-
1 (4±8% with the ®rst wheel for T1 excavation, pletely satis®ed by such modelling, and the loads
18% with the second wheel for T2 excavation) to at the periphery of the excavation are certainly
be simulated seems to be essentially related to the not representative of the real values applied to the
TBM digging process, to the layout conditions concrete segments. Therefore if precise informa-
and to the TBM speed. The `recon®nement' tion is needed on the upward movement of the
phase 2 (ÿ10% to ÿ17%) is related to the tunnel and on the stress inside the lining (useful
grouting and to the upward movement of the for segment design), it is better to try to take into
tunnel inside the grout under hydrostatic pres- account real interactions between soil and struc-
sure. The second decon®nement phase 3 (14± ture. These two approaches will be compared in
20%) is essentially related to the consolidation of another paper to appear soon in Computers and
the grout injected in its ¯uid state. Geotechnics.
SOFT SOIL TUNNELLING NUMERICAL MODEL 451
4 10

Horizontal displacements: mm
Radial ‘deconf.’
Vertical displacements: mm

2 Shear ‘deconf.’
5
0
22
0
24
26 25
Radial ‘deconf.’
28 Shear ‘deconf.’
210 210
212 Left Right Crown Left Right Crown
Crown Crown
214 haunch Bottom haunch 215 haunch Bottom haunch
216
218 220
0 45 90 135 180 225 270 315 360 0 45 90 135 180 225 270 315 360
Angle (8) Angle (8)

(a) (b)
Vertical distance from T1 centre line: m

Radial ‘deconf.’
16 Shear ‘deconf.’ Field data
14 Inclinometer
12 Inclinometer I14 S1–T1
I17 S1–T1
10
8
6
4
2
0
22
24
26
28
210
210292827262524232221 0 1 2 3 4 5 210292827262524232221 0 1 2 3 4 5
Horizontal displacement: mm Horizontal displacement: mm
(c)
Vertical distance from T1 centre line: m

0 18
Radial ‘deconf.’ Radial ‘deconf.’
Vertical displacements: mm

22 Shear ‘deconf.’ 16 Shear ‘deconf.’


Field data
14
24
Field data 12
26
10
28
8
210 6
212 4
214 2
230 220 210 0 10 20 30 218 216 214 212 210 28
Vertical distance from T1 centre line: m Vertical displacements: mm
(d) (e)

Fig. 41. Simulation of different stress release cases: (a) vertical displacements of T1±S1; (b) horizontal
displacements of T1±S1; (c) lateral displacements of I14 and I17 after T1 excavation; (d) surface settlements
after T1 excavation; (e) vertical displacements of EX11 after T1 excavation

REFERENCES Attewell, P. B. (1977). Ground movements caused by


Allouani, M. (1993). Identi®cation des lois de comporte- tunnelling in soil. Proceedings of the large ground
ment de sols. De®nition de la strateÂgie et de la qualite movements and structures conference, Cardiff, pp.
de l'identi®cation. Thesis EÂcole Centrale de Lyon. 812±848.
Amet, J. C., Guibert, G. & Schwenzfeier, A. (1996). Bernat, S. (1996). ModeÂlisation des deÂformations induites
Shield-experience on Line D Extension Lyons Metro. par le creusement d'un tunnel-Application au meÂtro
Proceedings of the North American Tunneling 96, de Lyons-Vaise. Thesis, Ecole Centrale de Lyon.
Washington, 27±33. Bernat, S., Cambou, B. & Dubois, P. (1995a). Modelling
452 BERNAT, CAMBOU AND DUBOIS

of the excavation during tunnelling in soft soil. Pro- ments autour des tunnels en terrain tendre. TOS
ceedings of the 5th international symposium on nu- (Tunnels et Ouvrages Souterrains) Nos 22, 23, 24.
merical models in geo-mechanics (NUMOG V), GRECO (1995). La modeÂlisation numeÂrique du comporte-
Davos, 471±476. ment des ouvrages souterrains et sa validation. In Les
Bernat, S., Ollier, C., Cambou B., Kastner, R., Dubois, P. geÂomateÂriaux, avanceÂes reÂcentes en calcul d'ouvrages
& Guilbert, G. (1995b). Des geÂomateÂriaux aux ouv- (eds F. Darve, P. Y. Hicher and J. H. Reynouard),
rages, creusement de tunnels en terrains meubles. In pp. 229±252. Paris: HermeÁs.
ExpeÂrimentation sur chantier, modeÂlisation et valida- Kastner, R. & Ollier, C. (1996). In situ monitoring of
tion (eds C. Petit, G. Pijaudier-Cabot and J. H. the Lyons Metro, Line D Extension. Proceedings of
Reynouard), pp. 283±322. Paris: Hermes. the international symposium of Technical Committee
Bernat, S., Cambou, B. & Dubois, P. (1996). Numerical TC 28, Underground construction in soft ground,
modelling of tunneling in soft soil. Proceedings of the London, pp. 701±706.
international symposium of Technical Committee TC Kastner, R., Ollier, C., Bernat, S. & Cambou, B. (1995).
28, Underground construction in soft ground, London, Monitoring of a tunnel excavated in soft ground with
pp. 465±470. a pressure tunnel boring machine. Validation of a
Bernat, S., Cambou, B. & Purwaningsih, S. (1997). modelling procedure. Proceedings of the 4th interna-
Modelling of soil-structure interaction during tunnel- tional symposium of `®eld measurements in geomecha-
ling in soft soil. Proceedings of the 9th international nics', FMGM 95, Bergame, 145±153.
conference of the international association for compu- Lee, K. M. & Rowe, R. K. (1989). Deformations caused
ter methods and advances in geomechanics (IACMAG by surface loading and tunnelling: the role of elastic
97), Wuhan, 1377±1382. anisotropy. GeÂotechnique 39, No. 1, 125±140.
Cambou, B. & Jafari, K. (1988). ModeÁle de comporte- Maleki, M. (1998). ModeÁles de comportement de sols
ment des sols non-coheÂrents. Rev. FrancËaise GeÂotech- hierarchiseÂs. Thesis EÂcole Centrale de Lyon.
nique, No. 44, 43±45. Panet, M. & Guenot, A. (1982). Analysis of convergence
Cambou, B. & Lanier, J. (1988). Induced anisotropy in behind the face of a tunnel. Proceedings of Tunnelling
cohesionless soil: experiments and modellings. Com- '82, London, 197±204.
puters Geotech., 6, 291±311. Peck, R. B. (1969). Deep excavations and tunnelling in
Cambou, B., Dubujet, P. & Doanh, T. (1990). Undrained soft ground. Proceedings of the 7th international
cyclic loading with reorientation of principal axes: conference on soil mechanism foundation engineering,
experiments and modelling. Proceedings of the 3rd 225±290.
international conference on constitutive laws for en- Rezgui, B. (1993). Validation de code de calcul et de
gineering material: theory and applications, Tucson. modeÁle de comportement sur ouvrage type. Thesis
Cording, E. J. & Hansmire, W. H. (1977). Les deÂplace- EÂcole Centrale de Lyon.

Vous aimerez peut-être aussi