PLANNING DE REALISATION DU PARKING SIDI BOU NAFAE

ID Task Name Duration Start Finish Predecessors 2024


August September October November December January February March April May June
10/07 17/0724/07 31/0707/08 14/0821/08 28/0804/09 11/09 18/0925/0902/1009/10 16/1023/10 30/1006/11 13/1120/11 27/11 04/1211/12 18/1225/12 01/0108/01 15/0122/01 29/0105/02 12/0219/0226/02 04/0311/03 18/0325/03 01/0408/04 15/0422/04 29/0406/05 13/0520/05 27/0503/06 10/0617/06 24/06
1
2 Planning Général 240 days Mon 24/07/23 Fri 21/06/24
3 OSCT 0 days Mon 24/07/23 Mon 24/07/23 24/07
4 Ajournement des travaux pour pompage 18 days Fri 28/07/23 Tue 22/08/23
5 Ajournement partiel pour confortement 50 days Mon 23/10/23 Fri 29/12/23
6 SOUTENNEMENTS 25 days Mon 01/01/24 Fri 02/02/24 5
7 Soutennement I 1 wk Mon 01/01/24 Fri 05/01/24
8 Soutennement II 1 wk Mon 08/01/24 Fri 12/01/24 7
9 Soutennement III 1 wk Mon 15/01/24 Fri 19/01/24 8
10 Soutennement IV 1 wk Mon 22/01/24 Fri 26/01/24 9
11 Soutennement V 1 wk Mon 29/01/24 Fri 02/02/24 10
12
13 BLOC 1 188 days Wed 23/08/23 Fri 10/05/24 4
14 Joint 1 188 days Wed 23/08/23 Fri 10/05/24
15 Joint 1-1 15 days Mon 22/04/24 Fri 10/05/24 28
16 Terrassement 1 wk Mon 22/04/24 Fri 26/04/24
17 Béton armé pour fondations 1 wk Mon 29/04/24 Fri 03/05/24 16
18 Béton armé en élévation 1 wk Mon 06/05/24 Fri 10/05/24 17
19 Joint 1-2 45 days Wed 23/08/23 Tue 24/10/23
20 Terrassement 4 wks Wed 23/08/23 Tue 19/09/23
21 Béton armé pour fondations 3 wks Wed 04/10/23 Tue 24/10/23 20FS+2 wks
22 Béton armé en élévation 2 wks Wed 11/10/23 Tue 24/10/23 21FF
23 Joint 2 55 days Wed 23/08/23 Tue 07/11/23
24 Terrassement 4 wks Wed 23/08/23 Tue 19/09/23
25 Béton armé pour fondations 3 wks Wed 27/09/23 Tue 17/10/23 24FS+1 wk
26 Béton armé en élévation 3 wks Wed 18/10/23 Tue 07/11/23 25
27 BLOC 2 168 days Wed 30/08/23 Fri 19/04/24 4
28 Joint 1 15 days Mon 01/04/24 Fri 19/04/24 42
29 Terrassement 1 wk Mon 01/04/24 Fri 05/04/24
30 Béton armé pour fondations 1 wk Mon 08/04/24 Fri 12/04/24 29
31 Béton armé en élévation 1 wk Mon 15/04/24 Fri 19/04/24 30
32 Joint 2 60 days Wed 30/08/23 Tue 21/11/23
33 Terrassement 4 wks Wed 30/08/23 Tue 26/09/23 4FS+1 wk
34 Béton armé pour fondations 3 wks Wed 11/10/23 Tue 31/10/23 33FS+2 wks
35 Béton armé en élévation 3 wks Wed 01/11/23 Tue 21/11/23 34
36 Joint 3 55 days Wed 06/09/23 Tue 21/11/23
37 Terrassement 3 wks Wed 06/09/23 Tue 26/09/23 4FS+2 wks
38 Béton armé pour fondations 3 wks Wed 11/10/23 Tue 31/10/23 37FS+2 wks
39 Béton armé en élévation 3 wks Wed 01/11/23 Tue 21/11/23 38
40 BLOC 3 158 days Wed 23/08/23 Fri 29/03/24 4
41 Bloc 3-1 158 days Wed 23/08/23 Fri 29/03/24
42 Joint 1 15 days Mon 11/03/24 Fri 29/03/24 5;11;55
43 Terrassement 1 wk Mon 11/03/24 Fri 15/03/24
44 Béton armé pour fondations 1 wk Mon 18/03/24 Fri 22/03/24 43
45 Béton armé en élévation 1 wk Mon 25/03/24 Fri 29/03/24 44
46 Joint 2 113 days Wed 23/08/23 Fri 26/01/24 4
47 Terrassement 6 wks Wed 23/08/23 Tue 03/10/23
48 Béton armé pour fondations 2 wks Mon 01/01/24 Fri 12/01/24 5
49 Béton armé en élévation 2 wks Mon 15/01/24 Fri 26/01/24 48
50 Joint 3 113 days Wed 23/08/23 Fri 26/01/24 4
51 Terrassement 6 wks Wed 23/08/23 Tue 03/10/23
52 Béton armé pour fondations 2 wks Mon 01/01/24 Fri 12/01/24 5
53 Béton armé en élévation 2 wks Mon 15/01/24 Fri 26/01/24 52
54 Bloc 3-2 45 days Mon 08/01/24 Fri 08/03/24
55 Joint 1 15 days Mon 19/02/24 Fri 08/03/24 5;10;9;59
56 Terrassement 1 wk Mon 19/02/24 Fri 23/02/24
57 Béton armé pour fondations 1 wk Mon 26/02/24 Fri 01/03/24 56
58 Béton armé en élévation 1 wk Mon 04/03/24 Fri 08/03/24 57
59 Joint 2 15 days Mon 29/01/24 Fri 16/02/24 5;8;63
60 Terrassement 1 wk Mon 29/01/24 Fri 02/02/24
61 Béton armé pour fondations 1 wk Mon 05/02/24 Fri 09/02/24 60
62 Béton armé en élévation 1 wk Mon 12/02/24 Fri 16/02/24 61
63 Joint 3 15 days Mon 08/01/24 Fri 26/01/24 5;7
64 Terrassement 1 wk Mon 08/01/24 Fri 12/01/24
65 Béton armé pour fondations 1 wk Mon 15/01/24 Fri 19/01/24 64
66 Béton armé en élévation 1 wk Mon 22/01/24 Fri 26/01/24 65
67
68 Travaux de second oeuvre et de finitions 30 days Mon 13/05/24 Fri 21/06/24 13;27;40
69 Etanchéité sur terrasses 2 wks Mon 13/05/24 Fri 24/05/24
70 Revetement sur dallage et terrasses 1 mon Mon 27/05/24 Fri 21/06/24 69
71 Plomberie 1 mon Mon 13/05/24 Fri 07/06/24
72 Electricité 1 mon Mon 13/05/24 Fri 07/06/24
73 Menuiserie 1 mon Mon 13/05/24 Fri 07/06/24
74 Peinture 1 mon Mon 13/05/24 Fri 07/06/24

Project: Planning Parking Sidi Bounafae Task Progress Summary External Tasks Deadline
Date: Fri 12/01/24 Split Milestone Project Summary External Milestone