Jan '21 18 Jan '21 25 Jan '21 01 Feb '21 08 Feb '21 15 Feb '21 22 Feb '21 01 Mar '21 08 Mar '21 15 Mar '21 22 Mar '21 29 Mar '21 05 Apr '21 12 Apr '21 19 Apr '21 26 Apr '21 03 May '21 10 May '21 17 May '21 24 May '21 31 May '21 07 Jun '21
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 PROJET DE 0 days 0 days Sat 16/01/21 Sat 16/01/21 PROJET DE CONSTRUCTION D'UN BATIMENT
CONSTRUCTION 16/01
D'UN BATIMENT
2 DEBUT 0 days 0 days Sat 16/01/21 Sat 16/01/21 DEBUT
16/01
3 Installation de 11 days 11 days Mon Mon
chantier 06/09/21 20/09/21
4 Réalisation des 5 days 5 days Mon Fri 24/09/21
terrassements et 20/09/21
chemins d'accès
5 Implantation 4 days 4 days Fri 24/09/21 Wed
batiment par 29/09/21
6 géometre
Fouilles semelles 25 days 25 days Sat 02/10/21 Wed
isolées Zone sous-sol 03/11/21
7 Coulage semelles 25 days 25 days Sat 02/10/21 Wed
isolées Zone sous-sol 03/11/21
8 Coffrage 25 days 25 days Sat 02/10/21 Wed
pré-poteaux 03/11/21
9 Coulage longrines 32 days 32 days Wed Thu
27/10/21 09/12/21
10 Réalisation des 7 days 7 days Mon Tue
remblais sous 29/11/21 07/12/21
dallage et
11 Ferraillage dallage 3 days 3 days Sat 11/12/21 Tue
14/12/21
12 Coulage dallage 3 days 3 days Thu Sat 16/10/21
14/10/21
13 Tracage et coffrage 33 days 33 days Sat 16/10/21 Tue
poteaux 30/11/21
14 Coulage poteaux 6 days 6 days Fri 19/11/21 Fri 26/11/21
Sous sol
15 Elévation du Mur de 3 days 3 days Sun Tue
soutènement 19/12/21 21/12/21
16 Dalle plancher haut 24 days 24 days Fri 01/10/21 Mon
Sous sol 01/11/21
17 Elévation poteaux 41 days 41 days Mon Mon
RDC 18/01/21 15/03/21 Elévation poteaux RDC
18 Dalle 1er étage 30 days 30 days Thu Wed
08/07/21 18/08/21
19 Elévation poteaux 51 days 51 days Sun Thu
1er Etage 25/04/21 01/07/21
20 Charpente et Toiture 64 days 64 days Tue Wed
toles bac Alu 7/10 10/08/21 03/11/21
21 Crépissage interieur 94 days 94 days Tue Wed
et extérieur finition 20/04/21 25/08/21
22 Plafond 45 days 45 days Tue Fri 08/10/21
10/08/21
23 Electricité 210 days 210 days Tue Tue
10/08/21 24/05/22
24 Staff : réalisations 46 days 46 days Tue Fri 18/06/21
des plaques 20/04/21
25 Staff : pose plaques 46 days 46 days Tue Fri 18/06/21
20/04/21
26 Plomberie 205 days 205 days Thu Thu
15/07/21 21/04/22
27 Climatisation 205 days 205 days Fri 20/08/21 Fri 27/05/22
Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
07 Jun '21 14 Jun '21 21 Jun '21 28 Jun '21 05 Jul '21 12 Jul '21 19 Jul '21 26 Jul '21 02 Aug '21 09 Aug '21 16 Aug '21 23 Aug '21 30 Aug '21 06 Sep '22 13 Sep '22 20 Sep '22 27 Sep '22 04 Oct '22 11 Oct '22 18 Oct '22 25 Oct '22 01 Nov '22 08 Nov '22 15 Nov '22 22 Nov '22 29 Nov '22
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Installation de chantier
Coffrage pré-poteaux
Coulage dallage
Plafond
Amenagement Parking
Construction de la barrière
Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 2
06 Dec '22 13 Dec '22 20 Dec '22 27 Dec '22 03 Jan '22 10 Jan '22 17 Jan '22 24 Jan '22 31 Jan '22 07 Feb '22 14 Feb '22 21 Feb '22 28 Feb '22 07 Mar '22 14 Mar '22 21 Mar '22 28 Mar '22 04 Apr '22 11 Apr '22 18 Apr '22 25 Apr '22 02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Coulage longrines
Ferraillage dallage
Electricité
Plomberie
Climatisation
Peinture : Murs interieurs et exterieurs avec une peinture de type pantex ou assimilées
Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 3
30 May '22 06 Jun '22 13 Jun '22 20 Jun '22 27 Jun '22 04 Jul '22 11 Jul '22 18 Jul '22 25 Jul '22 01 Aug '22 08 Aug '22 15 Aug '22 22 Aug '22 29 Aug '22 05 Sep '23 12 Sep '23 19 Sep '23 26 Sep '23 03 Oct '23 10 Oct '23 17 Oct '23 24 Oct '23 31 Oct '23 07 Nov '23 14 Nov '23 21 Nov '23
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Climatisation
Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 4