ID Task Task Name Work Duration Start Finish 11 Jan '21 18 Jan '21 25 Jan '21 01 Feb '21

Jan '21 18 Jan '21 25 Jan '21 01 Feb '21 08 Feb '21 15 Feb '21 22 Feb '21 01 Mar '21 08 Mar '21 15 Mar '21 22 Mar '21 29 Mar '21 05 Apr '21 12 Apr '21 19 Apr '21 26 Apr '21 03 May '21 10 May '21 17 May '21 24 May '21 31 May '21 07 Jun '21
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 PROJET DE 0 days 0 days Sat 16/01/21 Sat 16/01/21 PROJET DE CONSTRUCTION D'UN BATIMENT
CONSTRUCTION 16/01
D'UN BATIMENT
2 DEBUT 0 days 0 days Sat 16/01/21 Sat 16/01/21 DEBUT
16/01
3 Installation de 11 days 11 days Mon Mon
chantier 06/09/21 20/09/21
4 Réalisation des 5 days 5 days Mon Fri 24/09/21
terrassements et 20/09/21
chemins d'accès
5 Implantation 4 days 4 days Fri 24/09/21 Wed
batiment par 29/09/21
6 géometre
Fouilles semelles 25 days 25 days Sat 02/10/21 Wed
isolées Zone sous-sol 03/11/21
7 Coulage semelles 25 days 25 days Sat 02/10/21 Wed
isolées Zone sous-sol 03/11/21
8 Coffrage 25 days 25 days Sat 02/10/21 Wed
pré-poteaux 03/11/21
9 Coulage longrines 32 days 32 days Wed Thu
27/10/21 09/12/21
10 Réalisation des 7 days 7 days Mon Tue
remblais sous 29/11/21 07/12/21
dallage et
11 Ferraillage dallage 3 days 3 days Sat 11/12/21 Tue
14/12/21
12 Coulage dallage 3 days 3 days Thu Sat 16/10/21
14/10/21
13 Tracage et coffrage 33 days 33 days Sat 16/10/21 Tue
poteaux 30/11/21
14 Coulage poteaux 6 days 6 days Fri 19/11/21 Fri 26/11/21
Sous sol
15 Elévation du Mur de 3 days 3 days Sun Tue
soutènement 19/12/21 21/12/21
16 Dalle plancher haut 24 days 24 days Fri 01/10/21 Mon
Sous sol 01/11/21
17 Elévation poteaux 41 days 41 days Mon Mon
RDC 18/01/21 15/03/21 Elévation poteaux RDC
18 Dalle 1er étage 30 days 30 days Thu Wed
08/07/21 18/08/21
19 Elévation poteaux 51 days 51 days Sun Thu
1er Etage 25/04/21 01/07/21
20 Charpente et Toiture 64 days 64 days Tue Wed
toles bac Alu 7/10 10/08/21 03/11/21
21 Crépissage interieur 94 days 94 days Tue Wed
et extérieur finition 20/04/21 25/08/21
22 Plafond 45 days 45 days Tue Fri 08/10/21
10/08/21
23 Electricité 210 days 210 days Tue Tue
10/08/21 24/05/22
24 Staff : réalisations 46 days 46 days Tue Fri 18/06/21
des plaques 20/04/21
25 Staff : pose plaques 46 days 46 days Tue Fri 18/06/21
20/04/21
26 Plomberie 205 days 205 days Thu Thu
15/07/21 21/04/22
27 Climatisation 205 days 205 days Fri 20/08/21 Fri 27/05/22

28 Carrelage: pose sur 45 days 45 days Fri 20/08/21 Tue


tous les niveaux 19/10/21
29 Peinture : 5 days 5 days Fri 20/08/21 Thu
Grattage,mastiquage 26/08/21
et ponçage des murs
30 Peinture : Murs 66 days 66 days Wed Sat 11/12/21
interieurs et 15/09/21
exterieurs avec une
peinture de type
pantex ou assimilées
31 Faux Plafond ayant 66 days 66 days Thu Wed
une peinture de type 15/07/21 13/10/21
pantimat ou
32 Menuiserie bois / 15 days 15 days Wed Mon
Alu 15/09/21 04/10/21
33 Amenagement 76 days 76 days Thu Tue
Parking 15/07/21 26/10/21
34 Construction de la 76 days 76 days Thu Tue
barrière 15/07/21 26/10/21
35 Essais d'électricité 76 days 76 days Thu Tue
,plomberie et 15/07/21 26/10/21
climatisation
36 Finition et mise en 11 days 11 days Thu Thu
service livraison 25/11/21 09/12/21
37 FIN DES TRAVAUX 0 days 0 days Sat 16/01/21 Sat 16/01/21 FIN DES TRAVAUX
16/01

Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1
07 Jun '21 14 Jun '21 21 Jun '21 28 Jun '21 05 Jul '21 12 Jul '21 19 Jul '21 26 Jul '21 02 Aug '21 09 Aug '21 16 Aug '21 23 Aug '21 30 Aug '21 06 Sep '22 13 Sep '22 20 Sep '22 27 Sep '22 04 Oct '22 11 Oct '22 18 Oct '22 25 Oct '22 01 Nov '22 08 Nov '22 15 Nov '22 22 Nov '22 29 Nov '22
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Installation de chantier

Réalisation des terrassements et chemins d'accès

Implantation batiment par géometre

Fouilles semelles isolées Zone sous-sol

Coulage semelles isolées Zone sous-sol

Coffrage pré-poteaux

Coulage dallage

Tracage et coffrage poteaux

Coulage poteaux Sous sol

Dalle plancher haut Sous sol

Dalle 1er étage

Elévation poteaux 1er Etage

Charpente et Toiture toles bac Alu 7/10

Crépissage interieur et extérieur finition

Plafond

Staff : réalisations des plaques

Staff : pose plaques

Carrelage: pose sur tous les niveaux

Peinture : Grattage,mastiquage et ponçage des murs

Faux Plafond ayant une peinture de type pantimat ou assimilées

Menuiserie bois / Alu

Amenagement Parking

Construction de la barrière

Essais d'électricité ,plomberie et climatisation

Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 2
06 Dec '22 13 Dec '22 20 Dec '22 27 Dec '22 03 Jan '22 10 Jan '22 17 Jan '22 24 Jan '22 31 Jan '22 07 Feb '22 14 Feb '22 21 Feb '22 28 Feb '22 07 Mar '22 14 Mar '22 21 Mar '22 28 Mar '22 04 Apr '22 11 Apr '22 18 Apr '22 25 Apr '22 02 May '22 09 May '22 16 May '22 23 May '22 30 May '22
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Coulage longrines

Réalisation des remblais sous dallage et compactage

Ferraillage dallage

Tracage et coffrage poteaux

oulage poteaux Sous sol

Elévation du Mur de soutènement

Electricité

Plomberie

Climatisation

Peinture : Murs interieurs et exterieurs avec une peinture de type pantex ou assimilées

Finition et mise en service livraison

Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 3
30 May '22 06 Jun '22 13 Jun '22 20 Jun '22 27 Jun '22 04 Jul '22 11 Jul '22 18 Jul '22 25 Jul '22 01 Aug '22 08 Aug '22 15 Aug '22 22 Aug '22 29 Aug '22 05 Sep '23 12 Sep '23 19 Sep '23 26 Sep '23 03 Oct '23 10 Oct '23 17 Oct '23 24 Oct '23 31 Oct '23 07 Nov '23 14 Nov '23 21 Nov '23
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Climatisation

Project: PLANNING DES TRAVA Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Tue 28/12/21 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 4