DATACENTER WATANIA

BIRKHADEM

ID

Nom de la tche

Duration

Planning prvisionnel DC-BKH-WTA rev 002

195 days? Wed 22/01/14 Wed

URBANISATION DU DATACENTER OOREDOO A BIRKHADEM

REUNION DE DEMARRAGE ET ODS

Phase Etude

HVAC

Start

OOREDOO

Finish

%
Decem 01 Januar 01 Febru 01 March 01 April
01 May
01 June 01 July
01 August 01 Septe 01 Octobe 01 Novem 01 Dec
Compl 9/1 3/1 6/0 0/0 3/0 7/0 3/0 7/0 1/0 4/0 8/0 2/0 6/0 9/0 3/0 7/0 1/0 4/0 8/0 1/0 5/0 9/0 3/1 7/1 0/1 4/1 8/1
07/07/14
26/11/14 38%

195 days?

Wed 22/01/14

Wed 26/11/14

38%

0 days

Wed 22/01/14

Wed 22/01/14 100%

157,75 days?

Wed 22/01/14

Mon 29/09/14

50%

22,75 days?

Mon 12/05/14

Mon 16/06/14

73%

15,75 days

Wed 14/05/14

Thu 05/06/14 100%

1 day

Sun 08/06/14

Mon 09/06/14

0,88 days?

Thu 05/06/14

Thu 05/06/14 100%

22/01

note de calcul HVAC & bilan thermique

schma de principe HVAC

Validation Note de calcul bilan thermique

Fiche d'agrment groupe froid

0 days

Mon 12/05/14

Mon 12/05/14 100%

12/05

Fiche d'agrment changeurs thermique

0 days

Mon 12/05/14

Mon 12/05/14 100%

12/05

10

Validation client groupe froid et changeurs thermiques

0 days

Mon 09/06/14

Mon 09/06/14

0%

11

fiche d'agrment system de traitement d'air

1 day

Sun 08/06/14

Mon 09/06/14

0%

12

fiche d'agrment adoucisseur

0 days

Mon 12/05/14

Mon 12/05/14 100%

13

approbation systme de traitement d'air

2 days

Tue 10/06/14

Thu 12/06/14

0%

14

approbation adoucisseur

21 days?

Tue 13/05/14

Mon 16/06/14

79%

15

fiche d'agrment pompes

1 day

Tue 10/06/14

Wed 11/06/14

0%

16

fiche d'agrment vanneries ,manometre et accessoires d'installation

1 day?

Wed 11/06/14

Thu 12/06/14

0%

17

validation Pompes

1 day

Wed 11/06/14

Thu 12/06/14

0%

18

Validation vanneries ,manometre et accessoires d'installation

1 day

Thu 12/06/14

Sun 15/06/14

0%

95,75 days?

Wed 22/01/14

Sun 22/06/14

94%

19

Rack et Urbanisation

20

plan d'urbanisation de la salle

5 days

Tue 01/04/14

Tue 08/04/14 100%

21

approbation Plan d'urbanisation

1 day?

Thu 12/06/14

Sun 15/06/14

22

Fiche d'agrment racks et accessoires

23

approbation Rack et accessoires

24

0 days

Tue 08/04/14

Tue 08/04/14 100%

Wed 22/01/14

Wed 04/06/14 100%

Fiche d'agrment confinement

5 days

Mon 09/06/14

Mon 16/06/14

0%

25

approbation confinement

3 days

Tue 17/06/14

Sun 22/06/14

0%

26

Fiche d'agrment PDU

9,13 days

Wed 09/04/14

Wed 23/04/14 100%

27

approbation client PDU

27,13 days

Wed 23/04/14

Wed 04/06/14 100%

106,38 days?

Sun 02/02/14

Sun 20/07/14

13%

10 days

Wed 11/06/14

Thu 26/06/14

0%
0%

Courant Fort

29

dossier Etude lectricit courant fort

30

Validation Dossier d'tude lectricit courant fort

5 days

Thu 26/06/14

Sun 06/07/14

31

Fiche d'agrment transformateur de puissance

0 days

Sun 02/02/14

Sun 02/02/14 100%

32

approbation client transformateur de puissance

0,88 days

Mon 10/02/14

Tue 11/02/14 100%

33

Fiche d'agrment batterie de compensation et filtrage

3 days

Sun 06/07/14

Wed 09/07/14

0%

34

approbation batterie de compensation et filtrage

1 day?

Wed 09/07/14

Thu 10/07/14

0%

35

Fiche d'agrment CEP

5 days

Mon 12/05/14

Mon 19/05/14 100%

36

approbation CEP

7 days

Sun 08/06/14

Tue 17/06/14

0%

37

Fiche d'agrment TGBT et TD

7 days

Sun 06/07/14

Wed 16/07/14

0%

38

Approbation TGBT et TD

2 days

Wed 16/07/14

Sun 20/07/14

0%

39

note de calcule d'clairage

3 days

Mon 16/06/14

Thu 19/06/14

0%

40

fiche agrment Eclairage

1 day

Thu 19/06/14

Sun 22/06/14

0%

41

approbation Eclairage

2 days

Sun 22/06/14

Tue 24/06/14

0%

28,5 days?

Mon 19/05/14

Tue 01/07/14

29%

42

Projet : DC-BKH-WTA

SNEF ALGERIE

Amnagement, faux plancher et mise la terre

09/06

12/05

Avec la ligne
d'avancement on
fait apparaitre un
glissement de 4
semaine en
moyenne

60%

85,75 days?

28

Ligne
d'avancement au
07/07/2014

0%

08/04

02/02

Task

Milestone

Rolled Up Critical Task

Split

Group By Summary

Critical Task

Summary

Rolled Up Milestone

External Tasks

Deadline

Progress

Rolled Up Task

Rolled Up Progress

Project Summary

Page 1

PLANNING PREVISIONNEL REV 004

DATACENTER WATANIA
ID

BIRKHADEM

Nom de la tche

Duration
7 days?

Tue 03/06/14

%
Decem 01 Januar 01 Febru 01 March 01 April
01 May
01 June 01 July
01 August 01 Septe 01 Octobe 01 Novem 01 Dec
Compl 9/1 3/1 6/0 0/0 3/0 7/0 3/0 7/0 1/0 4/0 8/0 2/0 6/0 9/0 3/0 7/0 1/0 4/0 8/0 1/0 5/0 9/0 3/1 7/1 0/1 4/1 8/1
Thu 12/06/14
0%
07/07/14

Validation Note de calcule Plancher technique

1 day?

Sun 15/06/14

Mon 16/06/14

0%

45

Fiche d'agrment faux plancher

5 days

Mon 16/06/14

Mon 23/06/14

0%

46

approbation faux plancher

1 day?

Mon 23/06/14

Tue 24/06/14

0%

47

Fiche d'agrment peinture

2 days

Mon 23/06/14

Thu 26/06/14

0%

48

approbation Peinture

1 day?

Thu 26/06/14

Sun 29/06/14

0%

49

fiche d'agrment traitement des sols

2 days

Thu 26/06/14

Mon 30/06/14

0%

50

Approbation traitement des sols

1 day?

Mon 30/06/14

Tue 01/07/14

0%

51

fiche d'agrment chemin des cbles

11,38 days

Mon 19/05/14

Tue 03/06/14 100%

43

Note de calcule plancher technique

44

Start

OOREDOO

Finish

52

approbation chemin des cbles

2 days

Mon 16/06/14

Wed 18/06/14

0%

53

fiche d'agrment mise a la terre

3 days

Sun 22/06/14

Wed 25/06/14

0%

54

approbation mise a la terre

1 day?

Wed 25/06/14

Thu 26/06/14

0%

55

fiche d'agrment systme paratonnerre

1 day?

Thu 26/06/14

Sun 29/06/14

0%

56

approbation systme paratonnerre

1 day?

Sun 29/06/14

Mon 30/06/14

0%

46,25 days?

Tue 22/04/14

Thu 03/07/14

37%

57

Courant Faible

58

Plan cblage structur

5 days

Tue 22/04/14

Thu 05/06/14 100%

59

approbation plan de cblage structur

1 day?

Thu 26/06/14

Sun 29/06/14

0%

60

Fiche d'agrment infrastructure de cblage

0,88 days

Thu 26/06/14

Sun 29/06/14

0%

61

Approbation infrastructure de cblage

1,75 days

Sun 29/06/14

Tue 01/07/14

0%

62

plan signalisation et balisage scurit

3 days

Thu 26/06/14

Tue 01/07/14

0%

63

fiche d'agrment signalisation

1 day?

Tue 01/07/14

Wed 02/07/14

0%

64
65

approbation signalisation
System de supervision

66

schma de principe systme de supervision

67

Fiche d'agrment Logiciel Rizone et contrleurs du systme de supervis

68

approbation client Rizone et contrleurs

69

DOSSIER D'EXECUTION

1 day?

Wed 02/07/14

Thu 03/07/14

0%

48,88 days

Tue 08/04/14

Mon 23/06/14

31%

1 day

Tue 08/04/14

Wed 09/04/14 100%

1,75 days

Tue 08/04/14

Wed 09/04/14 100%

6 days

Sun 15/06/14

Mon 23/06/14

0%

128 days?

Sun 09/03/14

Mon 29/09/14

4%

70

dossier d'excution HVAC

7 days

Thu 10/07/14

Tue 22/07/14

0%

71

Validation du dossier d'excution HVAC

5 days

Tue 22/07/14

Tue 29/07/14

0%

72

Dossier d'excution Rack et Urbanisation

7 days

Thu 03/07/14

Tue 15/07/14

0%

73

Validation du dossier d'excution Rack et Urbanisation

5 days

Tue 15/07/14

Wed 23/07/14

0%

74

Dossier d'excution Courant Fort

87,63 days?

Sun 09/03/14

Sun 27/07/14

14%

0 days

Sun 09/03/14

Sun 09/03/14 100%

75

dossier d'excution transformateur

76

Approbation dossier d'excution poste transformateur

3,5 days?

Mon 10/03/14

77

Plan d'implantation et dtail Caniveau

3 days

Sun 15/06/14

Wed 18/06/14

0%

78

dossier d'excution caniveau

3 days

Wed 18/06/14

Mon 23/06/14

0%

79

Approbation dossier d'excution caniveau

1 day?

Mon 23/06/14

Tue 24/06/14

0%

80

Dossier de fabrication TGBT & TD

3 days

Sun 20/07/14

Wed 23/07/14

0%

81

Approbation du dossier de fabrication TGBT & TD

1 day?

Thu 24/07/14

Sun 27/07/14

0%

82

Dossier d'excution CEP et accessoires

1 day?

Wed 18/06/14

Thu 19/06/14

0%

83

Validation dossier d'excution CEP et Accessoires

1 day?

Thu 19/06/14

Sun 22/06/14

0%

84

dossier d'excution clairage

3 days

Tue 24/06/14

Mon 30/06/14

0%

85

validation dossier d'excution Eclairage

1 day?

Mon 30/06/14

Tue 01/07/14

0%

Projet : DC-BKH-WTA

SNEF ALGERIE

09/03

Thu 13/03/14 100%

Task

Milestone

Rolled Up Critical Task

Split

Group By Summary

Critical Task

Summary

Rolled Up Milestone

External Tasks

Deadline

Progress

Rolled Up Task

Rolled Up Progress

Project Summary

Page 2

PLANNING PREVISIONNEL REV 004

DATACENTER WATANIA
ID

BIRKHADEM

Nom de la tche

Duration

Start

OOREDOO

Finish

86

dossier d'excution de la protection et distribution lectrique

3 days

Sun 20/07/14

%
Decem 01 Januar 01 Febru 01 March 01 April
01 May
01 June 01 July
01 August 01 Septe 01 Octobe 01 Novem 01 Dec
Compl 9/1 3/1 6/0 0/0 3/0 7/0 3/0 7/0 1/0 4/0 8/0 2/0 6/0 9/0 3/0 7/0 1/0 4/0 8/0 1/0 5/0 9/0 3/1 7/1 0/1 4/1 8/1
Wed 23/07/14
0%
07/07/14

87

validation dossier d'excution de la protection et distribution lectri

1 day?

Thu 24/07/14

Sun 27/07/14

0%

88

Dossier d'excution Amnagement, faux plancher et mise la terre

7 days

Wed 02/07/14

Mon 14/07/14

0%

89

Validation du Dossier d'excution Amnagement, faux plancher et mise

7 days

Mon 14/07/14

Thu 24/07/14

0%

90

Dossier D'excution Courant Faible

7 days

Wed 03/09/14

Sun 14/09/14

0%

91

validation du dossier d'excution Courant Faible

7 days

Mon 15/09/14

Wed 24/09/14

0%

92

Dossier d'excution Systme de supervision

7 days

Sun 07/09/14

Wed 17/09/14

0%

93

validation du dossier d'excution systme de supervision

7 days

Wed 17/09/14

Mon 29/09/14

0%

123,88 days

Sun 09/03/14

Sun 21/09/14

36%

108,88 days

Sun 09/03/14

Wed 27/08/14

47%

94
95

Phase Approvisionnement
ETTABLISSEMENT DES COMMANDES IMPORTEE ET LOCAL

96

commande transformateur

97

rception usine transformateur

98

commande confinement, racks, climatisation et systme de


supervision (commande Rittal)

99

ouverture LC confinement, racks, climatisation et systme de


supervision (commande Rittal)

100

0 days

Thu 10/04/14

Thu 10/04/14 100%

34,13 days

Sun 13/04/14

Tue 03/06/14 100%

9,63 days

Sun 09/03/14

Sun 23/03/14 100%

16 days

Thu 24/04/14

Thu 22/05/14 100%

rception usine FAT des produits Rittal

8 days

Thu 12/06/14

Wed 25/06/14

0%

101

commande CEP

3 days

Sun 22/06/14

Wed 25/06/14

0%

102

commande TGBT, TD

1 day

Sun 27/07/14

Mon 28/07/14

0%

103

rception usine TGBT, TD

1 day

Wed 20/08/14

Thu 21/08/14

0%

104

commande system clim groupe de froid etadoucisseur et vannerie

45 days

Tue 17/06/14

Wed 27/08/14

0%

105

commande faux plancher et matriels tiers

10 days

Wed 02/07/14

Thu 17/07/14

0%

102 days

Sun 13/04/14

Sun 21/09/14

26%

106

LIVRAISON SUR SITE DES EQUIPEMENTS

107

livraison transformateur et cble de puissance

35 days

Sun 13/04/14

Wed 04/06/14 100%

108

arrive au port d'Alger: confinement, racks, climatisation,


PDU,(fourniture Rittal)

42 days

Sun 25/05/14

Mon 28/07/14

0%

109

ddouanement et livraison sur site confinement, racks, climatisation,


PDU,(fourniture Rittal)

20 days

Tue 29/07/14

Thu 28/08/14

0%

110

livraison CEP

1 day

Thu 21/08/14

Sun 24/08/14

0%

111

livraison centrale prod. eau froide (Groupe de froid et accessoires)

15 days

Wed 27/08/14

Sun 21/09/14

0%

112

livraison TGBT, TD

1 day

Thu 21/08/14

Sun 24/08/14

0%

113

livraison faux plancher et matriel tiers

20 days

Thu 17/07/14

Tue 19/08/14

0%

114

REALISATION ET INSTALLATION DES EQUIPEMENTS

110,25 days?

Tue 03/06/14

Wed 26/11/14

5%

115

pose et installation du transformateur sur cabine

1 day

Tue 03/06/14

Wed 04/06/14 100%

116

ouverture du mur de clture et maonnerie de finition

5,25 days?

Thu 05/06/14

Thu 12/06/14 100%

117

prise en main de la salle

1 day

Sun 29/06/14

Mon 30/06/14

0%

118

nettoyage

2 days

Mon 30/06/14

Wed 02/07/14

0%

119

traage du chemin de cble arien

1 day

Wed 02/07/14

Thu 03/07/14

0%

120

pose du chemin de cble arien

4 days

Thu 03/07/14

Thu 10/07/14

0%

121

traitement poxy au sol

3 days

Thu 10/07/14

Tue 15/07/14

0%

122

traitement peinture sur mur

5 days

Tue 15/07/14

Wed 23/07/14

0%

123

pose tuyauterie de climatisation intrieures

7 days

Mon 30/06/14

Thu 10/07/14

0%

124

confection socle pour GEG et freecoler en terrasse

5 days

Thu 28/08/14

Sun 07/09/14

0%

Projet : DC-BKH-WTA

SNEF ALGERIE

10/04

Task

Milestone

Rolled Up Critical Task

Split

Group By Summary

Critical Task

Summary

Rolled Up Milestone

External Tasks

Deadline

Progress

Rolled Up Task

Rolled Up Progress

Project Summary

Page 3

PLANNING PREVISIONNEL REV 004

DATACENTER WATANIA
ID

BIRKHADEM

Nom de la tche

Duration

Start

OOREDOO

Finish

125

pose GEG et freecoler en terrasse

1 day

Sun 21/09/14

%
Decem 01 Januar 01 Febru 01 March 01 April
01 May
01 June 01 July
01 August 01 Septe 01 Octobe 01 Novem 01 Dec
Compl 9/1 3/1 6/0 0/0 3/0 7/0 3/0 7/0 1/0 4/0 8/0 2/0 6/0 9/0 3/0 7/0 1/0 4/0 8/0 1/0 5/0 9/0 3/1 7/1 0/1 4/1 8/1
Mon 22/09/14
0%
07/07/14

126

pose pompes, ballon et adoucisseur

1 day

Mon 22/09/14

Tue 23/09/14

0%

127

pose tuyauterie de climatisation extrieures et raccordement des


equipements

10 days

Tue 23/09/14

Thu 09/10/14

0%

128

implantation pivot et traverses du faux plancher

5 days

Tue 19/08/14

Wed 27/08/14

0%

129

maillage MALT

3 days

Wed 27/08/14

Mon 01/09/14

0%

130

pose chemin de cble en faux plancher

1 day

Mon 01/09/14

Tue 02/09/14

0%

131

pose plaque faux plancher et finition

2 days

Wed 03/09/14

Sun 07/09/14

0%

132

installation CEP et boite d'alimentation

5 days

Sun 07/09/14

Sun 14/09/14

0%

133

installation TGBT et TD

1 day

Sun 24/08/14

Mon 25/08/14

0%

134

installation confinement, racks, PDU, LCP

10 days

Thu 28/08/14

Mon 15/09/14

0%

135

installation CMC de supervision, sonde, cble dtecteur de fuite d'eau

5 days

Mon 15/09/14

Mon 22/09/14

0%

136

pose racks rseau

3 days

Tue 23/09/14

Sun 28/09/14

0%

137

tirage de cble CU

10 days

Sun 28/09/14

Mon 13/10/14

0%

138

Tirage dce cble FO

5 days

Mon 13/10/14

Tue 21/10/14

0%

139

pose panneaux de brassage CU et FO

8 days

Tue 21/10/14

Mon 03/11/14

0%

140

test et mise en route des equipements

5 days

Mon 03/11/14

Tue 11/11/14

0%

141

configuration et programmation du logiciel DCIM Rizone

5 days

Tue 11/11/14

Wed 19/11/14

0%

142

mise en service

5 days

Wed 19/11/14

Wed 26/11/14

0%

Le chemin critique nous renseigne que :


La validation non encore faite des fiches d'agrment par le client a eu un impact majeur sur le glissement du planning.
IL est impratif donc et ce afin de rsorber se retard d'avoir l'approbation de toute les fiches concernant les quipements imports et pouvoir ensuite reprendre le planning en
optimisant les dlais de construction.

Projet : DC-BKH-WTA

SNEF ALGERIE

Task

Milestone

Rolled Up Critical Task

Split

Group By Summary

Critical Task

Summary

Rolled Up Milestone

External Tasks

Deadline

Progress

Rolled Up Task

Rolled Up Progress

Project Summary

Page 4

PLANNING PREVISIONNEL REV 004