Titik P Q P Q
( cm ) ( cm ) (m) (m)
P0 3.4 2.5 170 125
p1 2.7 2 135 100
p2 2 0.1 100 5
p3 1.3 0.7 65 35
p4 1 1 50 50
p5 0.2 1.7 10 85
p6 1.5 0.4 75 20
p7 1.4 0.4 70 20
p8 0.3 1.4 15 70
p9 0.8 0.8 40 40
P10 1.1 0.4 55 20
P11 0.3 0.9 15 45
P12 0.9 0.2 45 10
P13 1.1 0.9 55 45
P14 0.1 0.8 5 40
P15 0.1 0.8 5 40
P16 0.9 0.1 45 5
P17 1 0.9 50 45
P18 0.3 0.9 15 45
P19 0.5 0.8 25 40
P20 1 0.1 50 5
P21 0.5 0.6 25 30
P22 0.9 1.1 45 55
P23 0.4 0.5 20 25
P24 0.5 0.2 25 10
P25 0.1 0.6 5 30
P26 0.3 0.4 15 20
P27 1.1 0.7 55 35
P28 1.1 1.2 55 60
P29 1.7 2.2 85 110
P30 0.9 0.1 45 5
P31 1 1 50 50
P32 0.6 0.3 30 15
P33 0.5 0.4 25 20
P34 1.3 1 65 50
P35 1 1.2 50 60
P36 0.9 0.1 45 5
P37 0.1 0.9 5 45
P38 1.4 1 70 50
P39 1.2 0.1 60 5
P40 0.9 0.3 45 15
P41 1.3 0.2 65 10
P42 0.2 0.8 10 40
P43 0.4 0.5 20 25
P44 0.6 0.3 30 15
P45 0.1 0.5 5 25
PERHITUNGAN TINGGI PATOK
90.97
90.81
90.60
90.48
90.41
90.33
90.28
90.22
90.21
90.20
90.29
90.31
90.32
90.29
90.27
90.31
90.38
90.45
90.67
90.93
91.06
91.13
90.92
90.70
90.05
89.63
89.17
88.85
88.77
88.64
88.45
88.14
87.86
87.54
88.00
86.92
86.58
86.51
86.50
86.55
86.61
86.41
86.29
85.83
85.19
84.71
84.33
84.04
TOTAL
Titik Stasiun A B P Q A { ( P / P + Q ) x ( A B ) }
( M )
P10 0+ 475 90.00 90.50 15.00 40.00 90.00 - { 0.27 x -0.50 } 90.14
P11 0+ 500 90.00 90.50 40.00 15.00 90.00 - { 0.73 x -0.50 } 90.36
P12 0+ 525 90.00 90.50 10.00 55.00 90.00 - { 0.15 x -0.50 } 90.08
P13 0+ 550 90.00 90.50 15.00 50.00 90.00 - { 0.23 x -0.50 } 90.12
P14 0+ 600 90.00 90.50 50.00 10.00 90.00 - { 0.83 x -0.50 } 90.42
P15 0+ 650 90.00 90.50 50.00 55.00 90.00 - { 0.48 x -0.50 } 90.24
P16 0+ 700 90.00 90.50 50.00 50.00 90.00 - { 0.50 x -0.50 } 90.25
P17 0+ 750 90.00 90.50 55.00 50.00 90.00 - { 0.52 x -0.50 } 90.26
P18 0+ 800 90.50 91.00 5.00 50.00 90.50 - { 0.09 x -0.50 } 90.55
P19 0+ 850 90.50 91.00 30.00 45.00 90.50 - { 0.40 x -0.50 } 90.70
P20 0+ 900 91.00 91.50 15.00 15.00 91.00 - { 0.50 x -0.50 } 91.25
P21 0+ 925 91.00 91.50 25.00 10.00 91.00 - { 0.71 x -0.50 } 91.36
P22 0+ 975 90.50 91.00 20.00 25.00 90.50 - { 0.44 x -0.50 } 90.72
TOTAL
Titik Stasiun A B P Q A { ( P / P + Q ) x ( A B ) }
( M )
P23 1+ 000 90.50 91.00 30.00 20.00 90.50 - { 0.60 x -0.50 } 90.80
P24 1+ 025 89.50 90.50 50.00 10.00 89.50 - { 0.83 x -1.00 } 90.33
P25 1+ 075 89.50 90.00 10.00 60.00 89.50 - { 0.14 x -0.50 } 89.57
P26 1+ 125 88.50 89.50 40.00 25.00 88.50 - { 0.62 x -1.00 } 89.12
P27 1+ 175 88.50 89.00 40.00 5.00 88.50 - { 0.89 x -0.50 } 88.94
P28 1+ 200 88.50 89.00 15.00 30.00 88.50 - { 0.33 x -0.50 } 88.67
P29 1+ 225 88.50 89.00 35.00 5.00 88.50 - { 0.88 x -0.50 } 88.94
P30 1+ 250 88.00 88.50 15.00 35.00 88.00 - { 0.30 x -0.50 } 88.15
P31 1+ 300 88.00 88.50 40.00 35.00 88.00 - { 0.53 x -0.50 } 88.27
P32 1+ 350 87.50 88.00 35.00 5.00 87.50 - { 0.88 x -0.50 } 87.94
P33 1+ 400 87.00 88.00 35.00 20.00 87.00 - { 0.64 x -1.00 } 87.64
P34 1+ 450 87.00 88.50 5.00 60.00 87.00 - { 0.08 x -1.50 } 87.12
P35 1+ 475 86.50 87.00 30.00 20.00 86.50 - { 0.60 x -0.50 } 86.80
P36 1+ 500 86.50 87.00 5.00 45.00 86.50 - { 0.10 x -0.50 } 86.55
P37 1+ 550 86.00 87.00 20.00 45.00 86.00 - { 0.31 x -1.00 } 86.31
P38 1+ 600 86.00 87.00 30.00 30.00 86.00 - { 0.50 x -1.00 } 86.50
P39 1+ 625 86.50 87.00 5.00 55.00 86.50 - { 0.08 x -0.50 } 86.54
P40 1+ 650 86.50 87.00 35.00 15.00 86.50 - { 0.70 x -0.50 } 86.85
P41 1+ 675 86.00 87.00 20.00 35.00 86.00 - { 0.36 x -1.00 } 86.36
P42 1+ 725 86.00 86.50 50.00 5.00 86.00 - { 0.91 x -0.50 } 86.45
P43 1+ 775 85.50 86.00 40.00 25.00 85.50 - { 0.62 x -0.50 } 85.81
P44 1+ 825 85.00 85.50 40.00 25.00 85.00 - { 0.62 x -0.50 } 85.31
P45 1+ 875 84.50 85.00 5.00 35.00 84.50 - { 0.13 x -0.50 } 84.56
TABEL PROFIL MEMANJANG
DI GAMBAR DI LAPANGAN
NO
SUDUT 360 2 3.14 R JUMLAH SUDUT 360 2 3.14 R JUMLAH
TIKUNGAN 1 73 360 2 1.75 2.5 1.77 73 360 2 3.14 175 222.85
TIKUNGAN 2 80 360 2 2.45 2.3 2.50 80 360 2 3.14 245 341.91
TIKUNGAN 3 50 360 2 1.4 2.5 0.97 50 360 2 3.14 140 122.11
TIKUNGAN 4 90 360 2 1.6 3 2.40 90 360 2 3.14 160 251.20
TIKUNGAN 5 100 360 2 3.14 2 3.49 100 360 2 3.14 100 174.44
TABEL PERHITUNGAN
Keterangan
Datar
Datar
Datar
Datar
Datar
`
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
TABEL PERHITUNGAN
Keterangan
Datar
Datar
Datar
Datar
Datar
Datar
TABEL PERHITUNGAN
Keterangan
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
Datar
PERHITUNGAN TINGGI TITIK
P
P0 0+ 000 = A - {( P + Q ) x ( A - B )}
90
= 90.50 - {( 90 + 5 ) x ( 90.50 - 91.00 )}
90
= 90.50 - {( 95 ) x ( -0.50 )}
= 90.50 - {( 0.95 ) x ( -0.50 )}
= 90.50 - ( -0.474 )
= 90.974 M
P
P1 0+ 50 = A - {( P + Q )x( A - B )}
65
= 90.50 - {( 65 + 40 )x( 90.50 - 91.00 )}
65
= 90.50 - {( 105 )x( -0.50 )}
= 90.50 - {( 0.62 )x( -0.50 )}
= 90.50 - ( -0.310 )
= 90.810 M
P
P2 0+ 100 = A - {( P + Q ) x ( A - B )}
25
= 90.50 - {( 25 + 95 ) x ( 90.50 - 91.00 )}
25
= 90.50 - {( 120 ) x ( -0.50 )}
= 90.50 - {( 0.21 ) x ( -0.50 )}
= 90.50 - ( -0.104 )
= 90.604 M
P
P3 0+ 150 = A - {( P + Q )x( A - B )}
135
= 90.00 - {( 135 + 5 )x( 90.00 - 90.50 )}
135
= 90.00 - {( 140 )x( -0.50 )}
= 90.00 - {( 0.96 )x( -0.50 )}
= 90.00 - ( -0.482 )
= 90.482 M
P
P4 0+ 175 = A - {( P + Q ) x ( A - B )}
110
= 90.00 - {( 110 + 25 ) x ( 90.00 - 90.50 )}
110
= 90.00 - {( 135 ) x ( -0.50 )}
= 90.00 - {( 0.81 ) x ( -0.50 )}
= 90.00 - ( -0.407 )
= 90.407 M
P
P5 0+ 200 = A - {( P + Q ) x ( A - B )}
85
= 90.00 - {( 85 + 45 ) x ( 90.00 - 90.50 )}
85
= 90.00 - {( 130 ) x ( -0.50 )}
= 90.00 - {( 0.65 ) x ( -0.50 )}
= 90.00 - ( -0.327 )
= 90.327 M
P
P6 0+ 225 = A - {( P + Q ) x ( A - B )}
65
= 90.00 - {( 65 + 50 ) x ( 90.00 - 90.50 )}
65
= 90.00 - {( 115 ) x ( -0.50 )}
= 90.00 - {( 0.57 ) x ( -0.50 )}
= 90.00 - ( -0.283 )
= 90.283 M
P
P7 0+ 250 = A - {( P + Q ) x ( A - B )}
40
= 90.00 - {( 40 + 50 ) x ( 90.00 - 90.50 )}
40
= 90.00 - {( 90 ) x ( -0.50 )}
= 90.00 - {( 0.44 ) x ( -0.50 )}
= 90.00 - ( -0.222 )
= 90.222 M
P
P8 0+ 275 = A - {( P + Q )x( A - B )}
35
= 90.00 - {( 35 + 50 )x( 90.00 - 90.50 )}
35
= 90.00 - {( 85 )x( -0.50 )}
= 90.00 - {( 0.41 )x( -0.50 )}
= 90.00 - ( -0.206 )
= 90.206 M
P
P9 0+ 300 = A - {( P + Q ) x ( A - B )}
30
= 90.00 - {( 30 + 45 ) x ( 90.00 - 90.50 )}
30
= 90.00 - {( 75 ) x ( -0.50 )}
= 90.00 - {( 0.40 ) x ( -0.50 )}
= 90.00 - ( -0.200 )
= 90.200 M
P
P10 0+ 350 = A - {( P + Q ) x ( A - B )}
40
= 90.00 - {( 40 + 30 ) x ( 90.00 - 90.50 )}
40
= 90.00 - {( 70 ) x ( -0.50 )}
= 90.00 - {( 0.57 ) x ( -0.50 )}
= 90.00 - ( -0.286 )
= 90.286 M
P
P11 0+ 400 = A - {( P + Q ) x ( A - B )}
40
= 90.00 - {( 40 + 25 ) x ( 90.00 - 90.50 )}
40
= 90.00 - {( 65 ) x ( -0.50 )}
= 90.00 - {( 0.62 ) x ( -0.50 )}
= 90.00 - ( -0.308 )
= 90.308 M
P
P12 0+ 450 = A - {( P + Q ) x ( A - B )}
35
= 90.00 - {( 35 + 20 ) x ( 90.00 - 90.50 )}
35
= 90.00 - {( 55 ) x ( -0.50 )}
= 90.00 - {( 0.64 ) x ( -0.50 )}
= 90.00 - ( -0.318 )
= 90.318 M
P
P13 0+ 500 = A - {( P + Q ) x ( A - B )}
35
= 90.00 - {( 35 + 25 ) x ( 90.00 - 90.50 )}
35
= 90.00 - {( 60 ) x ( -0.50 )}
= 90.00 - {( 0.58 ) x ( -0.50 )}
= 90.00 - {( 0.58 )x( -0.50 )}
= 90.00 - ( -0.292 )
= 90.292 M
P
P14 0+ 525 = A - {( P + Q ) x ( A - B )}
35
= 90.00 - {( 35 + 30 ) x ( 90.00 - 90.50 )}
35
= 90.00 - {( 65 ) x ( -0.50 )}
= 90.00 - {( 0.54 ) x ( -0.50 )}
= 90.00 - ( -0.269 )
= 90.269 M
P
P15 0+ 550 = A - {( P + Q ) x ( A - B )}
40
= 90.00 - {( 40 + 25 ) x ( 90.00 - 90.50 )}
40
= 90.00 - {( 65 ) x ( -0.50 )}
= 90.00 - {( 0.62 ) x ( -0.50 )}
= 90.00 - ( -0.308 )
= 90.308 M
P
P16 0+ 575 = A - {( P + Q ) x ( A - B )}
45
= 90.00 - {( 45 + 15 ) x ( 90.00 - 90.50 )}
45
= 90.00 - {( 60 ) x ( -0.50 )}
= 90.00 - {( 0.75 ) x ( -0.50 )}
= 90.00 - ( -0.375 )
= 90.375 M
P
P17 0+ 600 = A - {( P + Q ) x ( A - B )}
50
= 90.00 - {( 50 + 5 ) x ( 90.00 - 90.50 )}
50
= 90.00 - {( 55 ) x ( -0.50 )}
= 90.00 - {( 0.91 ) x ( -0.50 )}
= 90.00 - ( -0.455 )
= 90.455 M
P
P18 0+ 650 = A - {( P + Q )x( A - B )}
15
= 90.50 - {( 15 + 30 )x( 90.50 - 91.00 )}
15
= 90.50 - {( )x( -0.50 )}
= 90.50 - {( 45 )x( -0.50 )}
= 90.50 - {( 0.33 )x( -0.50 )}
= 90.50 - ( -0.167 )
= 90.667 M
P
P19 0+ 700 = A - {( P + Q ) x ( A - B )}
30
= 90.50 - {( 30 + 5 ) x ( 90.50 - 91.00 )}
30
= 90.50 - {( 35 ) x ( -0.50 )}
= 90.50 - {( 0.86 ) x ( -0.50 )}
= 90.50 - ( -0.429 )
= 90.929 M
P
P20 0+ 725 = A - {( P + Q ) x ( A - B )}
5
= 91.00 - {( 5 + 35 ) x ( 91.00 - 91.50 )}
5
= 91.00 - {( 40 ) x ( -0.50 )}
= 91.00 - {( 0.13 ) x ( -0.50 )}
= 91.00 - ( -0.063 )
= 91.063 M
P
P21 0+ 750 = A - {( P + Q ) x ( A - B )}
10
= 91.00 - {( 10 + 30 ) x ( 91.00 - 91.50 )}
10
= 91.00 - {( 40 ) x ( -0.50 )}
= 91.00 - {( 0.25 ) x ( -0.50 )}
= 91.00 - ( -0.125 )
= 91.125 M
P
P22 0+ 775 = A - {( P + Q ) x ( A - B )}
25
= 90.50 - {( 25 + 5 ) x ( 90.50 - 91.00 )}
25
= 90.50 - {( 30 ) x ( -0.50 )}
= 90.50 - {( 0.83 ) x ( -0.50 )}
= 90.50 - ( -0.417 )
= 90.917 M
P
P23 0+ 800 = A - {( P + Q ) x ( A - B )}
10
= 90.50 - {( 10 + 15 ) x ( 90.50 - 91.00 )}
10
= 90.50 - {( 25 ) x ( -0.50 )}
= 90.50 - {( 0.40 ) x ( -0.50 )}
= 90.50 - ( -0.200 )
= 90.700 M
P
P24 0+ 850 = A - {( P + Q ) x ( A - B )}
30
= 89.50 - {( 30 + 25 ) x ( 89.50 - 90.50 )}
30
= 89.50 - {( 55 ) x ( -1.00 )}
= 89.50 - {( 0.55 ) x ( -1.00 )}
= 89.50 - ( -0.545 )
= 90.045 M
P
P25 0+ 875 = A - {( P + Q ) x ( A - B )}
5
= 89.50 - {( 5 + 15 ) x ( 89.50 - 90.00 )}
5
= 89.50 - {( 20 ) x ( -0.50 )}
= 89.50 - {( 0.25 ) x ( -0.50 )}
= 89.50 - ( -0.125 )
= 89.625 M
P
P26 0+ 925 = A - {( P + Q ) x ( A - B )}
60
= 88.50 - {( 60 + 30 ) x ( 88.50 - 89.50 )}
60
= 88.50 - {( 90 ) x ( -1.00 )}
= 88.50 - {( 0.67 ) x ( -1.00 )}
= 88.50 - ( -0.667 )
= 89.167 M
P
P27 1+ 975 = A - {( P + Q ) x ( A - B )}
45
= 88.50 - {( 45 + 20 ) x ( 88.50 - 89.00 )}
45
= 88.50 - {( 65 ) x ( -0.50 )}
= 88.50 - {( 0.69 ) x ( -0.50 )}
= 88.50 - ( -0.346 )
= 88.846 M
P
P28 1+ 25 = A - {( P + Q )x( A - B )}
60
= 88.50 - {( 60 + 50 )x( 88.50 - 89.00 )}
60
= 88.50 - {( 110 )x( -0.50 )}
= 88.50 - {( 0.55 )x( -0.50 )}
= 88.50 - ( -0.273 )
= 88.773 M
P
P29 1+ 050 = A - {( P + Q ) x ( A - B )}
30
= 88.50 - {( 30 + 80 ) x ( 88.50 - 89.00 )}
30
= 88.50 - {( 110 ) x ( -0.50 )}
= 88.50 - {( 0.27 ) x ( -0.50 )}
= 88.50 - ( -0.136 )
= 88.636 M
P
P30 1+ 075 = A - {( P + Q ) x ( A - B )}
45
= 88.00 - {( 45 + 5 ) x ( 88.00 - 88.50 )}
45
= 88.00 - {( 50 ) x ( -0.50 )}
= 88.00 - {( 0.90 ) x ( -0.50 )}
= 88.00 - ( -0.450 )
= 88.450 M
P
P31 1+ 100 = A - {( P + Q ) x ( A - B )}
10
= 88.00 - {( 10 + 25 ) x ( 88.00 - 88.50 )}
10
= 88.00 - {( 35 ) x ( -0.50 )}
= 88.00 - {( 0.29 ) x ( -0.50 )}
= 88.00 - ( -0.143 )
= 88.143 M
P
P32 1+ 125 = A - {( P + Q ) x ( A - B )}
25
= 87.50 - {( 25 + 10 ) x ( 87.50 - 88.00 )}
25
= 87.50 - {( 35 ) x ( -0.50 )}
= 87.50 - {( 0.71 ) x ( -0.50 )}
= 87.50 - ( -0.357 )
= 87.857 M
P
P33 1+ 150 = A - {( P + Q )x( A - B )}
35
= 87.00 - {( 35 + 30 )x( 87.00 - 88.00 )}
35
= 87.00 - {( 65 )x( -1.00 )}
= 87.00 - {( 0.54 )x( -1.00 )}
= 87.00 - ( -0.538 )
= 87.538 M
P
P34 1+ 175 = A - {( P + Q ) x ( A - B )}
20
= 87.00 - {( 20 + 10 ) x ( 87.00 - 88.50 )}
20
= 87.00 - {( 30 ) x ( -1.50 )}
= 87.00 - {( 0.67 ) x ( -1.50 )}
= 87.00 - ( -1.000 )
= 88.000 M
P
P35 1+ 225 = A - {( P + Q ) x ( A - B )}
25
= 86.50 - {( 25 + 5 ) x ( 86.50 - 87.00 )}
25
= 86.50 - {( 30 ) x ( -0.50 )}
= 86.50 - {( 0.83 ) x ( -0.50 )}
= 86.50 - ( -0.417 )
= 86.917 M
P
P36 1+ 275 = A - {( P + Q ) x ( A - B )}
5
= 86.50 - {( 5 + 25 ) x ( 86.50 - 87.00 )}
5
= 86.50 - {( 30 ) x ( -0.50 )}
= 86.50 - {( 0.17 ) x ( -0.50 )}
= 86.50 - ( -0.083 )
= 86.583 M
P
P37 1+ 325 = A - {( P + Q ) x ( A - B )}
95
= 86.00 - {( 95 + 90 ) x ( 86.00 - 87.00 )}
95
= 86.00 - {( 185 ) x ( -1.00 )}
= 86.00 - {( 0.51 ) x ( -1.00 )}
= 86.00 - ( -0.514 )
= 86.514 M
P
P38 1+ 350 = A - {( P + Q )x( A - B )}
50
= 86.00 - {( 50 + 50 )x( 86.00 - 87.00 )}
50
= 86.00 - {( 100 )x( -1.00 )}
= 86.00 - {( 0.50 )x( -1.00 )}
= 86.00 - ( -0.500 )
= 86.500 M
P
P39 1+ 375 = A - {( P + Q ) x ( A - B )}
5
= 86.50 - {( 5 + 50 ) x ( 86.50 - 87.00 )}
5
= 86.50 - {( 55 ) x ( -0.50 )}
= 86.50 - {( 0.09 ) x ( -0.50 )}
= 86.50 - ( -0.045 )
= 86.545 M
P
P40 1+ 425 = A - {( P + Q ) x ( A - B )}
10
= 86.50 - {( 10 + 35 ) x ( 86.50 - 87.00 )}
10
= 86.50 - {( 45 ) x ( -0.50 )}
= 86.50 - {( 0.22 ) x ( -0.50 )}
= 86.50 - ( -0.111 )
= 86.611 M
P
P41 1+ 450 = A - {( P + Q ) x ( A - B )}
35
= 86.00 - {( 35 + 50 ) x ( 86.00 - 87.00 )}
35
= 86.00 - {( 85 ) x ( -1.00 )}
= 86.00 - {( 0.41 ) x ( -1.00 )}
= 86.00 - ( -0.412 )
= 86.412 M
P
P42 1+ 475 = A - {( P + Q ) x ( A - B )}
20
= 86.00 - {( 20 + 15 ) x ( 86.00 - 86.50 )}
20
= 86.00 - {( 35 ) x ( -0.50 )}
= 86.00 - {( 0.57 ) x ( -0.50 )}
= 86.00 - ( -0.286 )
= 86.286 M
P
P43 1+ 500 = A - {( P + Q )x( A - B )}
20
= 85.50 - {( 20 + 10 )x( 85.50 - 86.00 )}
20
= 85.50 - {( 30 )x( -0.50 )}
= 85.50 - {( 0.67 )x( -0.50 )}
= 85.50 - ( -0.333 )
= 85.833 M
P
P44 1+ 550 = A - {( P + Q ) x ( A - B )}
15
= 85.00 - {( 15 + 25 ) x ( 85.00 - 85.50 )}
15
= 85.00 - {( 40 ) x ( -0.50 )}
= 85.00 - {( 0.38 ) x ( -0.50 )}
= 85.00 - ( -0.188 )
= 85.188 M
P
P45 1+ 600 = A - {( P + Q ) x ( A - B )}
25
= 84.50 - {( 25 + 35 ) x ( 84.50 - 85.00 )}
25
= 84.50 - {( 60 ) x ( -0.50 )}
= 84.50 - {( 0.42 ) x ( -0.50 )}
= 84.50 - ( -0.208 )
= 84.708 M
P
P46 1+ 650 = A - {( P + Q ) x ( A - B )}
50
= 84.00 - {( 50 + 25 ) x ( 84.00 - 84.50 )}
50
= 84.00 - {( 75 ) x ( -0.50 )}
= 84.00 - {( 0.67 ) x ( -0.50 )}
= 84.00 - ( -0.333 )
= 84.333 M
P
P47 1+ 700 = A - {( P + Q ) x ( A - B )}
5
= 84.00 - {( 5 + 55 ) x ( 84.00 - 84.50 )}
5
= 84.00 - {( 60 ) x ( -0.50 )}
= 84.00 - {( 0.08 ) x ( -0.50 )}
= 84.00 - ( -0.042 )
= 84.042 M
IV. PERHITUNGAN ALINYEMEN HORIZONTAL ( tipe Spiral-Spiral )
TIKUNGAN I
Diketahui :
R = 125 m
Vr = 60 Km/Jam
∆ = 52 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 125 ( 0.1 + 0.153 )
= 15875 x 0.253
= 63.375 Km/Jam
Syarat Aman : Vt > Vr
63.375 > 60 Aman !
Vr²
R =
127 ( e + fm )
min
3600
=
127 ( 0,080 + 0.153 )
= 121.66 m
k* = 0.4993795
p* = p* x Ls
= 0.0162394 x 56.69
= 0.921
k* = k* x Ls
= 0.4993795 x 56.69
= 28.312
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 125 + 0.921 ) x Tg ( 1/2 x 52 ) + 28.312
= ( 125.921 ) x Tg ( 26 ) + 28.312
= 121.4884478436 m
(R+p)
Es = R
Cos 1/2 ∆
( 125 + 0.921 )
= 125 = 31.646 m
0.8038568606
Kesimpulan :
L < 2 Ts 113.39 < 242.976895687
Diketahui :
R = 125 m
Vr = 60 Km/Jam
∆ = 60 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 125 ( 0.1 + 0.153 )
= 15875 x 0.253
= 63.375 Km/Jam
1432.4 1432.4
D = = = 11.459 ⁰
R 125.00
Os = 1/2 x D = 1/2 x 60 = 30.00 ⁰
D 60
L =
360
x 2 x R =
360
x 2 x 3.14 x 125 = 130.83 m
Vr²
R =
127 ( e + fm )
min
3600
=
127 ( 0,080 + 0.153 )
= 121.66 m
p* = 0.0177462
k* = 0.4992603
p* = p* x Ls
= 0.0177462 x 65.42
= 1.161
k* = k* x Ls
= 0.4992603 x 65.42
= 32.660
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 125 + 1.161 ) x Tg ( 1/2 x 60 ) + 32.660
= ( 126.161 ) x Tg ( 30 ) + 32.660
= 129.4666059126
(R+p)
Es = R
Cos 1/2 ∆
( 125 + 1.161 )
= 125 = 34.022 m
0.7933533403
Kesimpulan :
L < 2 Ts 130.83 < 258.933211825
Diketahui :
R = 100 m
Vr = 60 Km/Jam
∆ = 115 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 100 ( 0.1 + 0.153 )
= 12700 x 0.253
= 56.684 Km/Jam
1432.4 1432.4
D = = = 14.324 ⁰
R 100.00
Os = 1/2 x D = 1/2 x 115 = 57.50 ⁰
D 115
L =
360
x 2 x R =
360
x 2 x 3.14 x 100 = 200.61 m
Vr²
R =
127 ( e + fm )
min
3600
=
127 ( 0,080 + 0.153 )
= 121.66 m
p* = 0.0177462
k* = 0.4992603
p* = p* x Ls
= 0.0177462 x 100.31
= 1.780
k* = k* x Ls
= 0.4992603 x 100.31
= 50.079
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 100 + 1.780 ) x Tg ( 1/2 x 115 ) + 50.079
= ( 101.780 ) x Tg ( 57.5 ) + 50.079
= 137.0069501805 m
(R+p)
Es = R
Cos 1/2 ∆
( 100 + 1.780 )
= 100 = 33.850 m
0.7604059656
Kesimpulan :
L < 2 Ts 200.61 < 274.013900361
Diketahui :
R = 115 m
Vr = 60 Km/Jam
∆ = 67 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 115 ( 0.1 + 0.153 )
= 14605 x 0.253
= 60.787 Km/Jam
1432.4 1432.4
D = = = 12.456 ⁰
R 115.00
Os = 1/2 x D = 1/2 x 67 = 33.50 ⁰
D 67
L =
360
x 2 x R =
360
x 2 x 3.14 x 115 = 134.41 m
e = min0,080
Ls = 60 m
min :
Syarat Aman Ls < Ls
60 < 67.20 Aman !
min
Vr²
R =
127 ( e + fm )
min
3600
=
127 ( 0,080 + 0.153 )
= 121.66 m
p* = 0.0177462
k* = 0.4992603
p* = p* x Ls
= 0.0177462 x 67.20
= 1.193
k* = k* x Ls
= 0.4992603 x 67.20
= 33.553
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 115 + 1.193 ) x Tg ( 1/2 x 67 ) + 33.553
= ( 116.193 ) x Tg ( 33.5 ) + 33.553
= 90.2235812201 m
(R+p)
Es = R
Cos 1/2 ∆
( 115 + 1.193 )
= 115 = 14.276 m
0.8987940463
Kesimpulan :
L < 2 Ts 134.41 < 180.44716244
Diketahui :
R = 100 m
Vr = 60 Km/Jam
∆ = 100 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 100 ( 0.1 + 0.153 )
= 12700 x 0.253
= 56.684 Km/Jam
1432.4 1432.4
D = = = 14.324 ⁰
R 100.00
Os = 1/2 x D = 1/2 x 100 = 50.00 ⁰
D 100
L =
360
x 2 x R =
360
x 2 x 3.14 x 100 = 174.44 m
e = 0,080
Ls = 60 m
min
Vr²
R =
min 127 ( e + fm )
3600
=
127 ( 0,080 + 0.153 )
= 121.66 m
p* = 0.020784
k* = 0.4989893
p* = p* x Ls
= 0.020784 x 87.22
= 1.813
k* = k* x Ls
= 0.4989893 x 87.22
= 43.523
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 100 + 1.813 ) x Tg ( 1/2 x 100 ) + 43.523
= ( 101.813 ) x Tg ( 50 ) + 43.523
= 130.4793243996 m
(R+p)
Es = R
Cos 1/2 ∆
( 100 + 1.813 )
= 100 = 33.893 m
0.7604059656
Kesimpulan :
L < 2 Ts 174.44 < 260.958648799
TIKUNGAN I
Diketahui :
R = 175 m
Vr = 60 Km/Jam
∆ = 73 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 175 ( 0.1 + 0.153 )
= 22225 x 0.253
= 74.986 Km/Jam
Syarat Aman : Vt > Vr
74.986 > 60 Aman !
e = 0,080
Ls min = 60 m
Vr²
R min =
127 ( e + fm )
3600
=
=
127 ( 0,080 + 0.153 )
= 121.66 m
k* = 0.4995383
p* = p* x Ls
= 0.0139928 x 111.43
= 1.559
k* = k* x Ls
= 0.4995383 x 111.43
= 55.662
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 175 + 1.559 ) x Tg ( 1/2 x 73 ) + 55.662
= ( 176.559 ) x Tg ( 36.5 ) + 55.662
= 159.693
(R+p)
Es = R
Cos 1/2 ∆
( 175 + 1.559 )
= 175 = 44.640 m
0.8038568606
Kesimpulan :
L < 2 Ts 222.85 < 319.385498501
/2 lebar jalan) / Ls
TIKUNGAN II
Diketahui :
R = 245 m
Vr = 60 Km/Jam
∆ = 80 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 245 ( 0,10 + 0.153 )
= 31115 x 0.253
= 88.725 Km/Jam
Syarat Aman : Vt > Vr
88.725 > 60 Aman !
e = 0,080
Ls min = 60 m
Vr²
R min =
127 ( e + fm )
3600
=
127 ( 0,080 + 0.153 )
= 121.66 m
Syarat Tikungan Spiral - Spiral : ∆c = Lc = 0
k* = 0.4995383
p* = p* x Ls
= 0.0139928 x 170.96
= 2.392
k* = k* x Ls
= 0.4995383 x 170.96
= 85.399
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 245 + 2.392 ) x Tg ( 1/2 x 80 ) + 85.399
= ( 247.392 ) x Tg ( 40 ) + 85.399
= 107.609
(R+p)
Es = R
Cos 1/2 ∆
( 245 + 2.392 )
= 245 = 30.249 m
0.8987940463
Kesimpulan :
L < 2 Ts 341.91 < 215.218419418
/2 lebar jalan) / Ls
TIKUNGAN III
Diketahui :
R = 140 m
Vr = 60 Km/Jam
∆ = 50 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 140 ( 0.10 + 0.153 )
= 17780 x 0.253
= 67.070 Km/Jam
1432.4 1432.4
D = = = 10.231 ⁰
R 140.00
Os = 1/2 x D = 1/2 x 50 = 25.00 ⁰
D 50
L =
360
x 2 x R =
360
x 2 x
e = 0.080
Ls min = 60 m
Vr²
R =
min 127 ( e + fm )
3600
=
127 ( 0.080 + 0.153 )
= 121.66 m
Syarat Tikungan Spiral - Spiral : ∆c = Lc = 0
p* = 0.0139928
k* = 0.4995383
p* = p* x Ls
= 0.0139928 x 61.06
= 0.854
k* = k* x Ls
= 0.4995383 x 61.06
= 30.500
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 140 + 0.854 ) x Tg ( 1/2 x 50 ) + 30.500
= ( 140.854 ) x Tg ( 25 ) + 30.500
= 165.170
(R+p)
Es = R
Cos 1/2 ∆
( 140 + 0.854 )
= 140 = 37.543 m
0.7933533403
Kesimpulan :
L < 2 Ts 122.11 < 330.339176303
/2 lebar jalan) / Ls
TIKUNGAN IV
Diketahui :
R = 100 m
Vr = 60 Km/Jam
∆ = 100 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 100 ( 0.10 + 0.153 )
= 12700 x 0.253
= 56.684 Km/Jam
1432.4 1432.4
D = = = 14.324 ⁰
R 100.00
Os = 1/2 x D = 1/2 x 100 = 50.00 ⁰
D 100
L =
360
x 2 x R =
360
x 2 x
e = 0.080
Ls min = 60 m
Vr²
R =
min 127 ( e + fm )
3600
=
127 ( 0.080 + 0.153 )
= 121.66 m
Syarat Tikungan Spiral - Spiral : ∆c = Lc = 0
p* = 0.0139928
k* = 0.4995383
p* = p* x Ls
= 0.0139928 x 87.22
= 1.220
k* = k* x Ls
= 0.4995383 x 87.22
= 43.571
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 100 + 1.220 ) x Tg ( 1/2 x 100 ) + 43.571
= ( 101.220 ) x Tg ( 50 ) + 43.571
= 182.318
(R+p)
Es = R
Cos 1/2 ∆
( 100 + 1.220 )
= 100 = 33.114 m
0.7604059656
Kesimpulan :
L < 2 Ts 174.44 < 364.635408952
/2 lebar jalan) / Ls
IV. PERHITUNGAN ALINYEMEN HORIZONTAL ( tipe Spiral-Circle-Spiral )
TIKUNGAN I
Diketahui :
R = 175 m
Vr = 60 Km/Jam
∆ = 73 ⁰
c = 0,4 s/d 0,8.. (koefisien peralihan kecepatan)
= 0.4
Direncanakan menggunakan jenis tikungan Spiral - Spiral
Vt = 127 x R ( e + fm )
maka ;
Vt = 127 x 175 ( 0.1 + 0.153 )
= 22225 x 0.253
= 74.986 Km/Jam
Syarat Aman : Vt > Vr
74.986 > 60 Aman !
e = 0.080
Ls min = 60 m
Vr²
R =
R min =
127 ( e + fm )
3600
=
127 ( 0.080 + 0.153 )
= 121.66 m
k* = 0.4995383
p* = p* x Ls
= 0.0139928 x 111.43
= 1.559
k* = k* x Ls
= 0.4995383 x 111.43
= 55.662
Ts = ( R + p ) x Tg 1/2 ∆ + k
= ( 175 + 1.559 ) x Tg ( 1/2 x 73 ) + 55.662
= ( 176.559 ) x Tg ( 36.5 ) + 55.662
= 159.693
(R+p)
Es = R
Cos 1/2 ∆
( 175 + 1.559 )
= 175 = 44.640 m
0.8038568606
Kesimpulan :
L < 2 Ts 222.85 < 319.385498501