N° DESIGNATION
Unité Quantité PU
I. Caniveaux maçonnés
I.1 Maçonnerie des caniveaux m3 157.750
I.1.1 Moellons Benne 54.870 80,000
I.1.2 Sable Benne 17.604 80,000
I.1.3 Ciment Sac 276.063 26,000
II. Buses maçonnées
II.2 Nouvelles maçonnerie des buses m3 60.774
II.2.1 Moellons Benne 21.139 80,000
II.2.2 Gravier Benne 5.426 120,000
II.2.3 Sable Benne 2.713 80,000
II.2.4 Ciment Sac 127.625 26,000
II.3 Béton de forme des buses m3 1.386
II.3.1 Gravier Benne 0.354 120,000
II.3.2 Sable Benne 1.000 80,000
II.3.3 Ciment Sac 8.316 26,000
III Contruction des ponçeaux
III.1 Ponçeau KARIBA
III.1.1 Tablier en rondins (long 4,5m)
III.1.1.1 Rondins pce 25.000 30,000
III.1.1.2 Feuillards de fer pour assemblage des rondins 0.000 80,000
III.1.2 Appuis maçonnés + Ailes m3 35.700
III.1.2.1 Moellons Benne 12.417 80,000
III.1.2.2 Gravier Benne 3.187 120,000
III.1.2.3 Sable Benne 1.594 80,000
III.1.2.4 Ciment Sac 74.970 35,000
III.1.3 Dalle de sol m2 44.000
III.1.3.1 Moellons Benne 3.061 80,000
III.1.3.2 Gravier Benne 1.122 120,000
III.1.3.3 Sable Benne 0.561 80,000
III.1.3.4 Ciment Sac 39.600 35,000
III.2 Ponçeau GATUNGURU
III.2.1 Tablier en rondins (long 3,3m)
III.2.1.1 Rondins pce 25.000 30,000
III.2.1.2 Feuillards de fer pour assemblage des rondins
III.2.2 Appuis maçonnés + Ailes m3 35.700
III.2.2.1 Moellons Benne 12.417 80,000
III.2.2.2 Gravier Benne 3.187 120,000
III.2.2.3 Sable Benne 1.594 80,000
III.2.2.4 Ciment Sac 74.970 35,000
III.2.3 Dalle de sol m2 30.500
III.2.3.1 Moellons Benne 3.183 80,000
III.2.3.2 Gravier Benne 1.167 120,000
III.2.3.3 Sable Benne 0.583 80,000
III.2.3.4 Ciment Sac 27.450 35,000
III.3 Ponçeau RUGOMERO
III.3.1 Tablier + Poutres + Entretoise m3 8.900
III.3.1.1 Gravier Benne 2.270 120,000
III.3.1.2 Sable Benne 1.135 80,000
III.3.1.3 Ciment Sac 62.300 35,000
III.3.1.4 Fer à béton HA 6 Longeur 17.393 11,000
III.3.1.5 Fer à béton HA 8 Longeur 34.755 20,000
III.3.1.6 Fer à béton HA 10 Longeur 41.114 23,000
III.3.1.7 Fer à béton HA 12 Longeur 21.812 35,000
III.3.1.8 Fil à ligaturer kg 42.600 5,000
III.3.1.9 Planches pour coffrage (2,5m) pce 126.000 3,000
III.3.1.10 Madriers pour coffrage (2,5m) pce 47.000 3,000
III.3.1.11 Chevrons pour coffrage (2,5m) pce 76.000 1,500
III.3.1.12 Etaies pce 191.000 1,500
III.3.1.13 Clous (5cm) kg 25.000 5,000
III.3.1.14 Clous (8cm) kg 25.000 5,000
III.3.1.15 Clous (10cm) kg 25.000 5,000
III.3.2 Appuis maçonnés + Ailes m3 35.700
III.3.2.1 Moellons Benne 12.417 80,000
III.3.2.2 Gravier Benne 3.187 120,000
III.3.2.3 Sable Benne 1.594 80,000
III.3.2.4 Ciment Sac 74.970 35,000
III.3.3 Dalle de sol m2 51.200
III.3.3.1 Moellons Benne 5.343 80,000
III.3.3.2 Gravier Benne 1.959 120,000
III.3.3.3 Sable Benne 0.979 80,000
III.3.3.4 Ciment Sac 46.080 35,000
IV Buse KANYOMVYI
III.4.1 Appuis maçonnés + Gabillons m3 17.850
III.4.1.1 Moellons Benne 10.383 80,000
III.4.1.2 Gravier Benne 1.594 120,000
III.4.1.3 Sable Benne 0.797 80,000
III.4.1.4 Ciment Sac 37.485 35,000
III.4.1.5 Gabillon Caisse 12.000 160,000
III.4.2 Dalle de sol m2 6.250
III.4.2.1 Moellons Benne 0.652 80,000
III.4.2.2 Gravier Benne 0.159 120,000
III.4.2.3 Sable Benne 0.080 80,000
III.4.2.4 Ciment Sac 5.625 35,000
TOTAL
PT
12,975,509
4,389,565
1,408,319
7,177,625
6,216,102
5,877,462
1,691,103
651,075
217,025
3,318,260
338,640
42,424
80,000
216,216
26,094,688
6,687,723
750,000 5.625
750,000 0.675
- 0.700
4,127,282
993,391
382,456
127,485
2,623,950
1,810,441
244,870
134,678
44,893
1,386,000
6,279,354
750,000
750,000
-
4,127,282
993,391
382,456
127,485
2,623,950
1,402,072
254,609
140,035
46,678
960,750
13,127,611
6,646,688 6.750
272,417 1.350 1.6
90,806 0.800
2,180,500 8.900
191,323
695,090 Fer à béton HA 6 Longeur 189.740 17.392833
945,630 Fer à béton HA 8 Longeur 34.755
763,420 Fer à béton HA 10 Longeur 41.114
213,002 Fer à béton HA 12 Longeur 237.950 21.812083
378,000
141,000
114,000
286,500
125,000
125,000
125,000
4,127,282
993,391
382,456
127,485
2,623,950
2,353,642
427,409
235,075
78,358
1,612,800
4,592,110
4,317,554
830,609
191,228
63,743
1,311,975
1,920,000
274,556
52,174
19,130
6,377
196,875
49,878,409
24,331
Devis quantitatif et estimatif
PT
6,080,668
693,498
1,705,344
10,712,101
75,000
76,500
125,000
160,000
19,628,111
750,000
750,000
-
4,789,843
2,139,930
713,310
14,633,850
2,125,000
191,323
625,581
945,630
763,420
213,002
1,920,000
378,000
141,000
114,000
286,500
125,000
125,000
125,000
240,000
32,095,389
51,723,500
7,288,598
1,217,944
1,860,361
13,384,990
75,000
76,500
125,000
160,000
24,188,394
750,000
750,000
-
4,006,957
1,963,089
654,363
13,209,405
2,125,000
1,212,954
307,973
423,290
1,970,879
374,074
-
351,000
129,000
106,500
265,500
125,000
125,000
125,000
240,000
29,214,983
53,403,377
10,777,099
834,672
3,153,044
18,609,230
150,000
151,500
250,000
192,000
34,117,544
250,000
750,000
1,500,000
-
5,133,913
2,639,985
879,995
19,106,637
2,550,000
217,276
-
622,148
2,593,713
223,801
-
450,400
168,000
136,500
340,500
125,000
125,000
125,000
240,000
38,177,868 79000715
72,295,412
Latérite 250,000,000
pont Nyabigozi 100,000,000
Ponceaux et caniveau 150,000,000
150,000 500,000,000
220,860
1,800,000
105,000
1,000,000
396,000 8,400,000
54,000
90,000
2,800,000
1,000,000
7,615,860
185,038,149
90,263 200,000,000
Lot 1: Piste Migende - Nyabigozi 16,900,000
1 Moellons Benne 136.000 80,000 10,880,000
2 Gravier Benne 24.000 120,000 2,880,000
3 Sable Benne 31.000 80,000 2,480,000
4 Cordons Rouleau 20.000 8,000 160,000
5 Clous 12cmkg 50.000 5,000 250,000
6 Sac pce 250.000 800 200,000
7 Bidon pce 10.000 5,000 50,000
Lot 2 : Piste Nyabigozi - Bugama - Ruyaga 17,820,000
1 Moellons Benne 142.000 80,000 11,360,000
2 Gravier Benne 27.000 120,000 3,240,000
3 Sable Benne 32.000 80,000 2,560,000
4 Cordons Rouleau 20.000 8,000 160,000
5 Clous 12cmkg 50.000 5,000 250,000
6 Sac pce 250.000 800 200,000
7 Bidon pce 10.000 5,000 50,000
Lot 3: Piste Ntende Buswana 24,292,000
2 Moellons Benne 199 80,000 15,920,000
1 Gravier Benne 29 120,000 3,480,000
3 Sable Benne 50 80,000 4,000,000
4 Cordons Rouleau 24.000 8,000 192,000
5 Clous 12cmkg 50.000 5,000 250,000
6 Sac pce 500.000 800 400,000
7 Bidon pce 10.000 5,000 50,000
Total 59,012,000
28,786
Devis des matériaux en bois
20 50 20
45
65
25
59
B+b 149 75
h 65 45
h 4842.5 1687.5 3155 0.3155
1989.3537
2387.2244
20
100
12
190.4
Buse maçonnée couverte de dallette en B.A
Coupe transversale
100cm
Dallette en Béton armé 20
100
30 30cm 60 30
20
Dallette en béton armé
A A
50
100
20
100
15
100
Coupe transversale
15
450
138 Ciment Gravier Sable
Dallette (1*05*0,2) 359 251.3 8.3246377 4.1623188
Dallette (1,5*05*0,2) 138 144.9 4.8 2.4
Total dallette 497 396.2 13.124638 6.5623188
HA 10
557.04833
304.98
862.02833
N° DESIGNATION Unité Quantité PU PT
GRAVIER 37.51 120,000 120,038
SABLE 21.77 80,000 1,741,600
CIMENT 1,293.56 33,000 42,687,480
FAB 12 1,122.46 35,000 39,286,100
FABE 10 190.8 25,000 4,770,000
FAB 8 74.5 17,000 1,266,500
MOELLONS 73.93 80,000 5,914,400
PLANCHES 1009 5,000 5,045,000
Tuyeau PVC (Ø=3/4) longeur 2 30,000 60,000
Clous 6cm 50 5,000 250,000
Clous 8cm 50 5,000 250,000
clous 10cm 100 5,000 500,000
Clous 12cm 50 5,000 250,000
Cale à étaies 10338 150 1,550,700
FAL 417.85 5,000 2,089,250
PERCHES 5169.9 1,500 7,754,850
MADRIERS 1492.92 5,000 7,464,600
GABIONS 60 160,000 9,600,000
Garde-fou métallique ff 1 10,000,000 10,000,000
TOTAL 140,600,518
10338
1,550,700.00
Spécifications techniques
1. Moellons
2. Sable
Le sable pour béton armé, béton et mortier doit avoir un équivalent de sable supérieur à 75%.
Le sable ne doit pas contenir de matières gypseuses, oxydes, pyrites, matières organiques, vases, etc…
L'équipe du volet construction peut prescrire le lavage du sable en cas de nécessité.
3. Gravillons
4. Ciment
La haute adhérence sera garantie par des nervures en saillie sur le corps de l'armature ou par torsion d'un profi
à section non circulaire ou par les deux procédés à la fois.
Les nervures seront longitudinales ou transversales, elles pourront etre combinées.
Toutefois, dans ce dernier cas, les nervure transversales ne devront pas joindre les nervures longitudinales.
upérieur à 75%.
organiques, vases, etc…