Tipo Abscisa Longitud Materiales Estructura (m3) Costos


[4] Art [5] Art 500 [13] Terraplen
Seccion
Punto m m 320 Concreto Mr reforzado con
(millones)
Subbase 40 Geotextil forte 90
0
0.01 0.02 0.02 0.033
PC 0.01
4.99 10.087 9.981 16.469
5
5 10.678 10.61 17.507
10
5 10.641 10.586 17.467
15
5 8.025 7.998 13.196
20
5 8.015 7.998 13.196
25
5 9.777 9.756 16.098
30
5 11.152 11.133 18.37
35
5 10.17 10.001 16.501
40
1.463 3.024 2.927 4.829
PT 41.463
0.02 0.041 0.04 0.066
PC 41.483
3.517 7.316 7.034 11.606
45
5 10.175 9.993 16.489
50
5 11.043 11.008 18.163
55
5 8.225 8.2 13.529
60
5 8.027 7.998 13.196
65
5 8.646 8.634 14.246
70
5 11.144 11.114 18.339
75
5 10.197 10 16.5
80
2.937 5.945 5.874 9.693
PT 82.937
0.02 0.04 0.04 0.066
PC 82.957
2.043 4.101 4.087 6.744
85
5 10.478 10.461 17.26
90
5 11.322 11.219 18.511
95
5 8.148 8.032 13.253
100
5 8.087 7.998 13.196
105
5 8.297 8.206 13.539
110
5 12.103 11.865 19.577
115
5 11.086 10.819 17.851
120
4.41 9.05 8.821 14.554
PT 124.41
0.02 0.041 0.04 0.066
PC 124.43
0.57 1.172 1.14 1.881
125
5 10.234 10.057 16.594
130
5 11.939 11.714 19.329
135
5 8.78 8.735 14.412
140
5 8.009 7.998 13.196
145
5 8.066 7.997 13.196
150
5 9.987 9.91 16.352
155
5 10.323 10.18 16.798
160
5 10.283 9.998 16.496
165
0.883 1.791 1.767 2.916
PT 165.883
0.01 0.02 0.02 0.033
165.893
0
Totales Volúmenes (m3) : 325.705 322.01 531.316
Costos Totales (millones) :