DONNEES

DALLAGE= 0.15

FOUILLES EN Longueur de Largeur de Profond Béton Aciers


Nbre Fouilles Latérite Grave BP
MASSE fouille = fouille = fouille = dallage dallage

Ep latérite = 1 20.00 15.00 0.00 0.00 94.78 0.00 0.00 28.43 2085
0.5
Ep grave =

Ep BP =
0 0.00 94.78 0.00 0.00 28.43 2085.23
0.395
823.67

TERRASSEMENTS & BETONS ET COFFRAGES


Béton de Remblai P Coffrage Coffrage
SOCLES= 110.43 Nbr Dimension Volume béton Fouilles
propreté
Latérite Grave 0/40 Excédent
Fouilles rad V+B
L/D l ou S H/E Radier Voiles+Berceau
Prof, fouilles = RAFT 6500 200KL 1 6.50 3.14 0.6 19.900 48.572 3.524 10.572 10.572 36.472 12.100 12.246
1.10 RAFT 6500 150KL 1 6.50 3.14 0.6 19.900 48.572 3.524 10.572 10.572 36.472 12.100 12.246
BP = RAFT 5300 100KL 1 5.30 3.14 0.6 13.230 34.272 2.375 7.124 7.124 24.251 10.021 9.985
0.1 RAFT 5300 100KL 1 5.30 3.14 0.6 13.230 34.272 2.375 7.124 7.124 24.251 10.021 9.985
Laterite
0.3
Gravel =
0.3

Prof, fouilles =
1.50

SPt 0.000 0.000 0.000 0.000 0.000

SOMME 23.6 74.104


4 23.6 74.104 0.600 66.260 0.000 165.688 11.797 35.391 35.391 121.446 44.242 44.462 0.000
LT= S=
33.18 208.09

20 832.36 25.08619650392

663.6 ACIERS SEMELLES ET FUTS


Nbr ECIERS
Futs sur: HA6 HA8 HA10 HA12 HA14 HA16 HA20 HA25 HA32 HA40
RAFT 6500 200KL 1 0 0 79.60 829.16 829.16 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
RAFT 6500 150KL 1 0 0 79.60 829.16 829.16 0 0 0 0 0
0 0 0 0.00 0.00 0 0 0 0 0
RAFT 5300 100KL 1 0 0 52.92 551.27 551.27 0 0 0 0 0
0 0 0.0 0 0 0 0 0 0 0
RAFT 5300 100KL 1 0 0 52.92 551.27 551.27 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0

SOMME 0 0
4 - - 265.0 2,760.8 2,760.8 - - - - - -
0.222 0.395 0.617 0.888 1.208 1.578 2.466 3.847 6.336 9.896

POIDS - - 164 2,452 3,335 - - - - -

SEMELLES
Béton de Débord
Longrine= 0 Nbr Dimension Fouilles Laterite Grave 0/40 Coffrage Prof, fouilles
Volume béton propreté fouille
L l H/E
F1 0 0.7 0.7 0.2 0.098 0.000 0.000 0.000 0.000 0.000 0.000 0.900 0.200

BP
0.1
Good earth
0
Gravel
0
SOMME 0 0.49
0 0 0 0.200 0.000 0.000 0.000 0.000 0.000 0.000
LT= S=

FUTS
Nbr Dimension Volume béton Coffrage
Futs sur: L l H/E
F1 0 0.2 0.2 0.9 0.036 0.000 0.360 0.000
0 0.000 0.000 0.000 0.000
0
0
0
0
0
0
0
0

SOMME 0 0.04
0 0 0 0.900 0.000 0.000
LT= S=

ACIERS SEMELLES ET FUTS


Nbr ECIERS
Futs sur: HA6 HA8 HA10 HA12 HA14 HA16 HA20 HA25 HA32 HA40
F1 0 0 0 0 0 0 0 0 0 0 0
F1 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0

SOMME 0 0
0 - - - - - - - - - -
0.222 0.395 0.617 0.888 1.208 1.578 2.466 3.847 6.336 9.896
POIDS - - - - - - - - - - -

LONGRINE
LONGRINE FOUILLES EN RIGOLES ACIER
Longueur Largeur H Longrine Nbre Volume Coffrage TN Longueur Largeur H Nbre Volume HA8
Lg1 0 0.2 0.2 1 0.000 0.000 67.73 0.000 0.6 0.5 1 0 0.27 0
Lg2 0.000 0.000 FFL
Lg3 0.000 0.000 68
Lg4 0.000 0.000
Lg5 0.000 0.000
Lg6 0.000 0.000
TOTAL béton 0.000 0.000 0.000 0.000 0.600 0.500 1.000 0.000 0.000
0.395
0.000

SOUBASSEMENT
MACONNERIE 20 PLEINS BETON DE PROPRETE
Longueur Largeur H Nbre Surf Enduit ext Longueur Largeur H Nbre Volume
Long 0.000 0.2 0.45 1 0.000 0.000 0.000 0.6 0.1 1 0
Déd futs 0.000
Déd raid 0.000
0.000
0.000
0.000
TOTAL béton 0.000 0.000 0.000 0.000 0.600 0.100 1.000 0.000
165.688

5,950

7,140.3
ACIER
HA10
0.00

0.000
0.617
0.000 -
BENIN-GDIZ GLO-DJIGBE

BENIN _ RO PLANT FOUNDATION

BOQ FOR RO PLANT FOUNDATION

Sr.
ITEM DESCRIPTION UNIT QTY Rate AMOUNT (CFA)
No.

I CIVIL WORK

A PREPERATION, MOBILIZATION & DEMOBILIZATION


Mobilization of all the Equipment, manpower, necessary resource
1 AU 1.00 850,000 850,000
(One time expenses)
2 Demobilization AU 1.00 120,000 120,000
3 Site establishment, temporary works on site by Contractor AU 1.00 100,000 100,000
4 Supply, assembly and dismantling of façade scaffolding AU 1.00 0 0
5 Supply and installation of fencing and safety devices AU 1.00 100,000 100,000

B EARTHWORK
Earth Work in Excavation in all kinds of soil (Excluding rock &
boulders) and backfilling in foundation trenches, column pits using
1.01 mechanical means, from existing ground level including dressing of CuM 173.97 4,000 695,891
sides and bottom to final level, to receive PCC and ramming
bottom. Storage of excavation materials in one place.
1.02 Excess earth to be removed from the site CuM 127.52 3,000 382,556
Providing and filling in Plinth, foundation and wherever required as
per direction of the Engineer, in layer not exceeding 200 mm.
2
Thick, compacted including watering, ramming, consolidating and
dressing etc. at all lead and lifts.
2.01 With available good earth CuM 46.45 2,000 92,908
2.02 Good earth to be Brought from outside CuM 0.00 8,500 0
2.03 Silty sand CuM 0.00 8,500 0
2.04 Laterite compacted at 95% CuM 136.68 9,500 1,298,486
2.05 Crushed gravel class 0/40 under foundation CuM 37.16 26,000 966,173
2.06 Crushed gravel class 0/25 under foundation CuM 0.00 26,000 0
2.07 Providing and laying plastic film polyane (200 microns minimum) SqM 189.57 1,500 284,349
Providing and placing bituminous dampproufing membrane to
2.08 SqM 0.00 15,500 0
concrete surface

Providing and injecting the chemical emulsion for pre constructional


antitermite treatment and creating a chemical barrier under and all-
round the column pits, walls, trenches, top surface, of plinth, filling
3 SqM 0.00 1,200 0
junction wall and floor, along the external perimeter of the building,
expansion joints, surrounding of the pipes, and conduits, etc.
complete. (Plinth area shall be measured.)

C CONCRETE WORK
Laying plain cement concrete C15 (Min. cement content of 150
1 Kg/CuM) under foundations Footings/beams including formwork at CuM 12.03 70,000 842,304
all levels & height

Laying, Placement, pouring of cement concrete according to the


2 design mix, including all piping and lifts, vibration, curing as per
instructions for :
2.01 foundation, footing, raft CuM 72.89 90,000 6,559,768
2.02 pedestals CuM 0.00 90,000 0
2.03 bottom beams, lintel chaining CuM 0.00 90,000 0
2.04 Damp proof coarse on external concrete wall SqM 0.00 4,000 0
Flooring including joints and floor finishing with power trowel
2.05 CuM 28.43 90,000 2,559,144
(15cm)
2.06 concrete wall (sails) CuM 0.00 90,000 0
2.07 concrete slab including beams CuM 0.00 90,000 0
2.08 concrete staircase CuM 0.00 90,000 0

Shuttering with plywood including struting and proping etc. &


3
removal of formwork etc. for pedestals
3.01 foundation, footing, raft SqM 48.91 6,000 293,452
3.02 pedestals SqM 0.00 15,000 0
3.03 bottom beams, lintel chaining and grade slab SqM 0.00 15,000 0
3.04 Flooring including joints and floor finishing with power trowel SqM 0.00 4,000 0
3.05 concrete wall SqM 0.00 15,000 0
3.06 concrete slab including beams SqM 0.00 15,000 0
3.07 concrete staircase SqM 0.00 15,000 0

P/L HYSD bars grade Fe-400, cutting, bending, hooking, binding


with 18 Guage MS binding wire, double fold to tie the bars in
position, keeping in position during concreting by means of stays,
blocks, ties, spacers, chairs, hangers etc. all complete as per
drawing and according to relevant Local codes. for all lead & lift
4 below and above Plinth level. to the entire satisfaction of Engineer. Kg. 7,790.02 1,200 9,348,019
Payment of steel shall be made as per drawing and approved bar
bending schedule and paid on the basis of the sectional weights of
bar. The rate shall include cost of laps, chairs, spacers etc., binding
wire, cover blocks which will not be measured separately for
payment.

CIVIL WORK AMOUNT 24,493,050

II ASSEMBLY WORK

I PRELIMINARY WORK
2.1 Anchor bolt sealing Au 1 -

TOTAL FOR ASSEMBLY WORK 0

TOTAL AMOUNT excl. VAT 24,493,050


BENIN-GDIZ GLO-DJIGBE

BENIN _ RO PLANT FOUNDATION

BOQ FOR RO PLANT FOUNDATION

Sr.
ITEM DESCRIPTION UNIT QTY Rate AMOUNT (CFA)
No.

I CIVIL WORK

A PREPERATION, MOBILIZATION & DEMOBILIZATION


Mobilization of all the Equipment, manpower, necessary resource
1 AU 1.00 0
(One time expenses)
2 Demobilization AU 1.00 0
3 Site establishment, temporary works on site by Contractor AU 1.00 0
4 Supply, assembly and dismantling of façade scaffolding AU 1.00 0
5 Supply and installation of fencing and safety devices AU 1.00 0

B EARTHWORK
Earth Work in Excavation in all kinds of soil (Excluding rock &
boulders) and backfilling in foundation trenches, column pits using
1.01 mechanical means, from existing ground level including dressing of CuM 173.97 0
sides and bottom to final level, to receive PCC and ramming
bottom. Storage of excavation materials in one place.
1.02 Excess earth to be removed from the site CuM 127.52 0
Providing and filling in Plinth, foundation and wherever required as
per direction of the Engineer, in layer not exceeding 200 mm.
2
Thick, compacted including watering, ramming, consolidating and
dressing etc. at all lead and lifts.
2.01 With available good earth CuM 46.45 0
2.02 Good earth to be Brought from outside CuM 0.00 0
2.03 Silty sand CuM 0.00 0
2.04 Laterite compacted at 95% CuM 136.68 0
2.05 Crushed gravel class 0/40 under foundation CuM 37.16 0
2.06 Crushed gravel class 0/25 under foundation CuM 0.00 0
2.07 Providing and laying plastic film polyane (200 microns minimum) SqM 189.57 0
Providing and placing bituminous dampproufing membrane to
2.08 SqM 0.00 0
concrete surface

Providing and injecting the chemical emulsion for pre constructional


antitermite treatment and creating a chemical barrier under and all-
round the column pits, walls, trenches, top surface, of plinth, filling
3 SqM 0.00 0
junction wall and floor, along the external perimeter of the building,
expansion joints, surrounding of the pipes, and conduits, etc.
complete. (Plinth area shall be measured.)

C CONCRETE WORK
Laying plain cement concrete C15 (Min. cement content of 150
1 Kg/CuM) under foundations Footings/beams including formwork at CuM 12.03 0
all levels & height

Laying, Placement, pouring of cement concrete according to the


2 design mix, including all piping and lifts, vibration, curing as per
instructions for :
2.01 foundation, footing, raft CuM 72.89 0
2.02 pedestals CuM 0.00 0
2.03 bottom beams, lintel chaining CuM 0.00 0
2.04 Damp proof coarse on external concrete wall SqM 0.00 0
Flooring including joints and floor finishing with power trowel
2.05 CuM 28.43 0
(15cm)
2.06 concrete wall (sails) CuM 0.00 0
2.07 concrete slab including beams CuM 0.00 0
2.08 concrete staircase CuM 0.00 0

Shuttering with plywood including struting and proping etc. &


3
removal of formwork etc. for pedestals
3.01 foundation, footing, raft SqM 48.91 0
3.02 pedestals SqM 0.00 0
3.03 bottom beams, lintel chaining and grade slab SqM 0.00 0
3.04 Flooring including joints and floor finishing with power trowel SqM 0.00 0
3.05 concrete wall SqM 0.00 0
3.06 concrete slab including beams SqM 0.00 0
3.07 concrete staircase SqM 0.00 0

P/L HYSD bars grade Fe-400, cutting, bending, hooking, binding


with 18 Guage MS binding wire, double fold to tie the bars in
position, keeping in position during concreting by means of stays,
blocks, ties, spacers, chairs, hangers etc. all complete as per
drawing and according to relevant Local codes. for all lead & lift
4 below and above Plinth level. to the entire satisfaction of Engineer. Kg. 7,790.02 0
Payment of steel shall be made as per drawing and approved bar
bending schedule and paid on the basis of the sectional weights of
bar. The rate shall include cost of laps, chairs, spacers etc., binding
wire, cover blocks which will not be measured separately for
payment.

CIVIL WORK AMOUNT 0

II ASSEMBLY WORK

A PRELIMINARY WORK
3.1 Anchor bolt sealing Au 1 -

TOTAL FOR ASSEMBLY WORK 0

TOTAL AMOUNT excl. VAT 0


BENIN-GDIZ GLO-DJIGBE

BENIN _ RO PLANT FOUNDATION

BOQ FOR RO PLANT FOUNDATION

CIVIL WORK
Sr. No. ITEM DESCRIPTION QTY (Kg) QTY (TONNE)

CIVIL WORK

1 Aciers HA6 0.00 -

2 Aciers HA8 947.21 0.95

3 Aciers HA10 188.06 0.19

4 Aciers HA12 2,819.37 2.82

5 Aciers HA14 3,835.37 3.84

6 Aciers HA16 0.00 -

7 Aciers HA20 0.00 -

8 Aciers HA25 0.00 -

TOTAL 7,790.02 7.790