Vous êtes sur la page 1sur 49

Projet de Subdivision en 22 lots à vocation residentiel fait sous les dispositions

Traverse Marks Coordinates LGM 2012 de L'Economic Development Board (Smart City Scheme) regulations 2015
STN
Reference point - GPS 108 (Schoenfeld)
Traverse Marks Eastings (m) Northings (m) Description GN 128 de 2015 , d'un terrain de portant le PIN0000, situe dans le N
1 GPS 108 260,062.31 372,185.02 Brass bolt in concrete
district de Riviere du Remaprt lieu dit "HAUTE RIVE", appartenant à "AZURI
Method of Survey : GPS 1
Boundary Coordinates LGM 2012 EV3
SMART CITY COMPANY LTD" suivant TV202204/001464. Client
AZURI SMART CITY
124m² COMPANY LTD
Eastings (m) Northings (m)
1 265084.08 369382.69 Plan

Projet de subdivision en 22 lots

11.44m
dev.
2 265147.29 369328.54
3 265062.22 369234.34 Lieu District

4 265020.88 369269.09 40 Haute Rive Rivière du Rempart


.1
2m
Echelle Format Mesuré Date

10.40m
Site Location Haute Rive

dev.
1 1/750 A3 01/10/23
341m² Terrain appartenant à
34
.7
1m AZURI SMART CITY COMPANY LTD District Rivière du Rempart Dessiné Vérifié Référence du dossier

TV202204/001464
2 dev. Owner AZURI SMART CITY Notes de révision Rév. par Date

m
dev.
300m²

9.77
9.27m
31 COMPANY LTD
.0
5m
3
dev.
Area of survey 8147.00m²
273m² dev.

9.4 v.
0m
9.25m 9.27m
Terrain appartenant à

de
28
AZURI SMART CITY COMPANY LTD .7
6m 30
.4 Total area of plot 6388.00m²
TV202204/001464 4 2
257m² dev.
dev. 22 m (1 to 22 )
9.26m 282m²

9.2 ev.
1m
9.23m
EV4

d
27
.5 31
.0 89m² Area of road and 906.00m²
5
3m 4m 2 Reserves

9. ev.
m
251m² dev.
dev. 21

d
Area of green space

16
9.20m 9.21m
288m²
853.00m² Notes

0m
27
.3 31

9.4
6 .8
m 6 m 5m Title Deed TV TV202204/001464
dev.

E GE
253m²
16

9.19m dev. 20
9.

RG AR
27 9.20m 296m² Land Surveyor Mark Doger de Spéville

LA E L

8m
.8
3m 32

DE m D

9.3
7 .8
4m
m

Date 01/10/2023

0M .00

9m
257m² dev.
16

19

1.3 E 5
9.

9.1
9.18m
28 306m²

DE D
. 15

E UN
Source of plan New Survey

7m
8 m 34

RV MM

9.3
.0
259m² dev. 3

8m
m

SE O
RE IN C
18

9.1
28 9.17m
.2 314m²

EM
9
EV1 m
CH
33

8m
145m² .7
9m

9.3
dev.

7m
9.16m 17
1
9. 9.
17
m
303m²

4m
32
.3

4.3
6m
m

9. m
16

16 16 95
4.
9.

m
291m²
9 31
m

302m² .1 m
PLAN DE SITUATION
1

1m 21
.9

9. 9.
32

16
m 15
10 Approximate Centroid Coordinates (UTM 40S)
m

280m²
5

29
.9

302m² .8 m
32

9. 21
16
m
2m
9. 573475mE, 7777848mN
EV2
4 11
8m

495m² dev.
.9

302m²
32

9. 9.25m
9. 16
17 m Terrain appartenant à
m
12
m

AZURI SMART CITY COMPANY LTD


02

303m²
.

TV202204/001464
33

9. 12 Rivière du Rempart
16 .8
m 0m
13
5m
.0

303m²
33

Haute Rive IRS Co Ltd


9. TV 8649/51
16
m
14
m
09

AZ 325m² Îlot Du Mort


.
33

UR .1 9
I S Ter
Land belonging to

dev.
Haute Rive IRS Co Ltd (HRHL)

6m TV 8649 N°51

M rai 33.55m Pte Bonhomme

Rivière du Rempart
Land belonging to Haute Rive

A n
Ocean Front living Ltd (HRHL)
TV 8649/50

TV RT ap
20 CI pa 9.
16
22 TY rte
Surplus land belonging
to Haute Rive Holding Ltd

m TV 8580/29

G
23547.76m²

04 C na
O /0 OM nt
01 à
O 46 PA 8.
18 Pte
DL
Land belonging to Haute Rive
Ocean Front living Ltd (HRHL)
TV 8649/51

4 NY m
Barachois de
AN LT
D 3 B04
8686.00m²
l'Embarcadère
DS B02
6460.00m²
B05
3035.00m²
B06
2273.00m²

-P
B03
9148.00m²

GO MARK DOGER DE SPÉVILLE


O OD
ST LA
B08
42605.00m²
Arpenteur Juré
E ND
DE S
-P
OS
FL

SITE
TE
AC DE
FL
Q AC
RO Q
B1
Resr Resr
AD 5 Land Surveyors & Property Valuer
6

1, Park Hotel Lane,


A

B1 C10
Rue St. Clement,
Curepipe.
5 20272.00m² Phone: 675 3559 - 674 3494
E: admin@cdds.mu
VAT.27440418
D07
D01
11881.00m²
BRN: C16139719
157413.00m²
11043.16m² L'ensemble des travaux, tous les plans et documents

Aucun ne peut ou
retransmis sous quelque forme que ce soit sans
MEP Concept Design Report

Azuri Smart City Company Ltd


Block B10
Ariza

Mechanical, Electrical and Public Health & ICT


Engineering Services

Revision B

GMF Ltd (Est. 1989)


Corner Avenue des Capucines and Avenue Trianon 1 – Quatre Bornes 72238 – Mauritius

T +230 466 1172 | E info@gmfbet.mu | W www.gmfbet.mu | BRN C07008315 | VAT 20090057


Block B10 Ariza

Report Reference: MEP Concept Report Rev B

Revision Date Scope of Revision Prepared by Issued Appro'd Issued On


by by
Rev 0 21.09.2023 FOR COMMENT/APPROVAL SS SS TM 21.09.2023
Rev A 25.09.2023 Revised as per Client comments SS SS TM 25.09.2023
Rev B 29.09.2023 Revised as per Client comments SS SS TM 29.09.2023

If the document is marked "draft" it is deemed to be uncontrolled and is issued for comment and further
development only.

QMS Document ENG/CDR – 01.05.20 - Rev 0


Block B10 Ariza

1 INTRODUCTION 3

1.1 Project Description 3

2 DESIGN CRITERIA 4

2.1 Mechanical Design Criteria 4


2.1.1 External Design Conditions 4
2.1.2 Internal Design Conditions 4
2.1.3 Air infiltration 4
2.1.4 Heat Gains 5
2.1.5 Ventilation Rates 5
2.1.6 Acoustic Criteria 6

2.2 Electrical Design Criteria 6


2.2.1 Lighting 7

2.3 Sustainable Design Criteria 7

3 UTILITIES 7

3.1 Waste & Sewer Service 7

3.2 Domestic Cold Water Service 8

3.3 Electrical Service 8

3.4 ICT/ Telecom Service 8

4 PUBLIC HEALTH ENGINEERING SYSTEMS 8

4.1 Above Ground Drainage 8

4.2 Cold Water Service 8

4.3 Hot Water Service 9

4.4 Irrigation 9

4.5 Gas Service 9

4.6 Swimming Pool 9

1
Block B10 Ariza

4.7 Rain water harvesting 9

5 AIR CONDITIONING AND VENTILATION 10

5.1 Air Conditioning 10

5.2 VENTILATION 10
5.2.1 General Ventilation 10
5.2.2 Extract Ventilation 10

6 ELECTRICAL SYSTEMS 10

6.1 Electrical Power Distribution within the Villa 10

6.2 SMALL POWER 10

6.3 STANDBY POWER 11

6.4 LIGHTING SYSTEM 11

7 SURGE PROTECTION 11

8 CONTAINMENT 11

9 ICT SYSTEMS – STRUCTURED CABLING (DATA AND TELEPHONY) 11

9.1 Closed Circuit Television (CCTV) 12

9.2 Intruder Alarm system 12

9.3 BEMS System 12

2
Block B10 Ariza

1 Introduction

1.1 Project Description

This Concept Report has been prepared by GMF Consulting Engineers Ltd and commissioned by Azuri Smart
City Company Ltd. The project consists of 22nos 3-bedroom villas.
The proposed utilities strategies are subject to agreement with the Azuri estate and the Local Utility
Authorities (CEB, CWA, WWMA and Mauritius Fire & Rescue Service MFRS).

The villas are to be a newly constructed and the building services comprise of the following: -
• Above ground drainage
• Domestic Water Services
• Cooling service
• Extract Ventilation
• Air conditioning
• Pool filtration system
• Sewage treatment plant
• Irrigation system
• Electrical Power Distribution
• Internal, External Lighting and Controls
• Small power
• Standalone Fire Detection in kitchen
• CCTV and Security
• Access Control
• IT / Telecommunications systems
• AV/TV Systems

All new installations will be designed, installed, tested, and commissioned to comply with the current Mauritian
Regulations, best practice guidelines. Guidance documents will be sought from CIBSE Guides.

The services will be designed to give due consideration to Azuri Smart City sustainable design guidelines and
good practice with a view to minimise energy, water and materials whilst also providing an enhanced
environment for living.

3
Block B10 Ariza

2 Design Criteria

The MEP design has been based upon the following criteria:

2.1 Mechanical Design Criteria

2.1.1 External Design Conditions


Table 1 - External design conditions

Summer Winter

320C dry bulb 260C dry bulb

80 % Relative Humidity 75 % Relative Humidity

2.1.2 Internal Design Conditions


Table 2 - Internal design conditions

Summer Design Condition Winter Design Condition

Area % RH or % RH or
Internal Internal temp
(Control/ No (Control/ No
temp (°C) (°C)
Control) Control)

Living Areas Uncontrolled Uncontrolled Uncontrolled Uncontrolled

Dining Areas Uncontrolled Uncontrolled Uncontrolled Uncontrolled

Kitchen Uncontrolled Uncontrolled Uncontrolled Uncontrolled

Bedrooms 24 ± 2 Uncontrolled Uncontrolled Uncontrolled

General Storage Uncontrolled Uncontrolled Uncontrolled Uncontrolled

Circulation Uncontrolled Uncontrolled Uncontrolled Uncontrolled

WC’s Uncontrolled Uncontrolled Uncontrolled Uncontrolled

Bathrooms Uncontrolled Uncontrolled Uncontrolled Uncontrolled

2.1.3 Air infiltration

An allowance of 0.25 air changes per hour will be made for air infiltration

4
Block B10 Ariza

2.1.4 Heat Gains


Table 3 - Heat gains

Parameter Sensible Heat Latent Heat

People 90 W 60W

Lighting 6-12W/m2 -

Equipment 10 W/m2 -

2.1.5 Ventilation Rates


Table 4 - Ventilation rates

Room Ventilation Strategy Ventilation Rate

Living Areas Natural with Ceiling fans -

Dining Areas Natural with Ceiling fans -

Recirculation hood + openable Subject to kitchen hood


Kitchen
windows specification. Min 60l/s

Natural with openable -


windows.
Provision for ceiling fans to be
Master Bedroom
allowed in all bedrooms
Comfort Cooling Air
Conditioning

Natural with openable -


windows
Bedrooms
Comfort Cooling Air
Conditioning

General Storage Uncontrolled -

Circulation Uncontrolled -

WC without Mechanical Extract Ventilation Min 5 ACH (air changes


openable window (with run-on timer) per hour)

Mechanical Extract Ventilation Min 5 ACH (air changes


Bathrooms
(with run-on timer) per hour)

5
Block B10 Ariza

2.1.6 Acoustic Criteria

Based upon building services equipment only.


Table 5 - Acoustic criteria

Area Noise (NR)

Living Areas 30

Dining Areas 35

Kitchen 45

Master Bedroom 25

Bedrooms 25

General Storage -

Circulation -

WC -

Bathrooms -

2.2 Electrical Design Criteria

Table 6 – Electrical design criteria

Item Data

BS7671:2018 – 18th Edition - IEE wiring Regulations.


Electrical Installations Earthing TN Systems

Lighting: 6-12W/m2

Power: 10W/m2
Electrical Loads
Mechanical: 10 W/m2 (in applicable areas)

All electrical loads will be confirmed during next design stage.

6
Block B10 Ariza

2.2.1 Lighting
Table 7 – Lighting design criteria

Area: Lux Level: At: Comments:

Living Areas 150-200 750mm AFFL

Dining Areas 150-200 750mm AFFL

Kitchen 200-300 750mm AFFL Lighting level will

150 750mm AFFL depend on ID/Arch


Bedrooms
light fittings selection
General Storage 100 750mm AFFL
for ambience/mood

200 750mm AFFL lighting


Circulation

WC 150 750mm AFFL

Bathrooms 150 750mm AFFL

Note: No Dimming system.

2.3 Sustainable Design Criteria

There are currently no formal sustainability ratings proposed for this scheme. However sustainable
design features and guidelines from the Azuri Smart City will be adopted where applicable.

3 Utilities

3.1 Waste & Sewer Service

For each villa plot, the above ground waste and sewage disposal will be a gravity network and will be
connected to the main infrastructure sewage network.

7
Block B10 Ariza

3.2 Domestic Cold Water Service

Domestic cold water service will be provided by the main cold water infrastructure network and will
connect to a water meter in a dedicated underground chamber at the site boundary.
The billing and maintenance will be done by the AZSC syndic, and the network will be of HDPE PN10
piping and associated accessories.

3.3 Electrical Service

Electrical power will be provided by the AZSC infrastructure electrical distribution network and terminate
to the plot in a dedicated dry service hub electrical/ICT connection enclosure at the site boundary.
Each villa will be fed by 1 underground electrical cable terminating at the villa terminal distribution board.
The Electrical meter will be located either in the service hub or meter room (subject to agreement with
CEB).

3.4 ICT/ Telecom Service

A connection box will be provided in the store for the tel/data distribution.

4 Public Health Engineering Systems

4.1 Above Ground Drainage

The waste & sewer system for the residential unit comprises of main collection pipes which run below
ground and connect to a main infrastructure sewage network.
The wastewater from showers and wash hand basin is collected through a gully trap before
connecting to the plot sewer network.
All kitchen waste will be discharged into a grease trap prior to connecting to the plot sewer network.
All wash hand basins and sinks will be fitted with a bottle trap to mitigate risks of odour nuisance.
All showers will be fitted with shower floor drains with integrated odour trap.

4.2 Cold Water Service

A pressurised cold water network will be provided by AZSC to feed each villa with a water meter
(Syndic Check Meter) located at the site boundary.
The main cold water reticulation will be in HDPE pipe buried underground and will be connected to
the terminal manifolds.

8
Block B10 Ariza

The terminal distribution will be done through a PEX network feeding each sanitary ware on a one to
one basis through a common manifold.
An Isolating valve will be provided for each terminal point of the cold water distribution network.

4.3 Hot Water Service

The hot water production system comprises of a solar water heater system. The solar water heater
will be located on the roof.
The hot water tank will be equipped with a stand-by electrical emersion heating element.
The hot water main distribution from the solar water tank to terminal distribution manifold will be done
in CPVC pipes complete with thermal insulation. All piping shall drop in technical riser to feed the
terminal manifolds.
The terminal distribution will be done through a PEX network feeding each sanitary ware on a one to
one basis through a common manifold.
An isolating valve will be provided at each feeder point at the hot water manifold.
No system of hot water recirculation through a loop has been allowed for.

4.4 Irrigation

Garden taps will be provided for irrigation and cleaning purposes. This will be tapped off from the
main pressurized irrigation network of AZSC.

4.5 Gas Service

No gas service has been allowed for at this stage.

4.6 Swimming Pool

Swimming pool will be an overflow type pool (TBC). Pool plant, lighting and equipment will be provided
by the pool specialist contractor.
The pool pump room will be a semi-buried enclosure provided by the pool specialist contractor which
will be detailed further by the specialist contractor.
Pool make-up water will be fed from the pressurised cold water supply.

4.7 Rain water harvesting

No rain water harvesting has been allowed at this stage.

9
Block B10 Ariza

5 Air Conditioning and Ventilation

5.1 Air Conditioning

Pipework for air conditioning is provided to the bedrooms for inverter type DX split unit system. The
indoor unit shall be located on the wall and the outdoor unit externally.
Condensate piping will collect condensate water from the DX indoor units and discharges to ground
into a local soakaway. U-traps will be provided at each connection of the condensate pipes.

Figure 1: 1 Wall mounted AC unit

5.2 Ventilation

5.2.1 General Ventilation

The residential unit will be predominantly naturally ventilated via openable windows and veranda
doors.

5.2.2 Extract Ventilation

WC without openable window will be fitted with mechanical extract ventilation with a delay timer linked
to the light switch.
Extraction to kitchen will be either a carbon filter recirculation type or an air extract system.

6 Electrical Systems

6.1 Electrical Power Distribution within the Villa

Each Villa will have an electrical distribution board installed in the vicinity of the kitchen/store. The
power and lighting points including the external lighting points within the premises will be fed from this
electrical distribution board.

6.2 Small Power

There are both normal (13A socket) and (16A socket) distribution at the bedrooms. Generally, 13A
Sockets shall be allowed for other areas. No UPS power is being provided.

10
Block B10 Ariza

6.3 Standby Power

No standby power is envisaged for the system; owners will not be authorised to install standby
generators.

6.4 Lighting System

Surface mounted light fittings have been proposed – Details for the fittings shall be by the ID/Architect.
All fittings shall be individually controlled via local light switch; no dimming system is envisaged.

7 Surge Protection

Adequate surge protection devices shall be allowed at the electrical panel.

8 Containment

Containment for ICT will be provided by conduit provisions.

9 ICT Systems – Structured cabling (Data and Telephony)

The network infrastructure set up will consist of conduits for fibre services from Mauritius Telecom
(MT) and/or other operators (For example Emtel).

The fibre from Mauritius Telecom or other operators shall terminate at a specific agreed location and
from there another conduit shall be allowed to one data point and telephone point at the
living/bedrooms and two Wireless Access Point (WAP) for adequate Wi-Fi coverage in the Villa.
A telephone point shall also be provided in the living room.

During application to the service provider, the total number of points and telephone extensions points
shall be communicated so that the service provider makes allowance for all data and telephone points
and provide the correct active equipment which shall route all traffic to the router.

The containment set will be designed such that other service providers can still deploy service to the
house. It will only be a matter of changing the main router equipment.

Note: The cost for this equipment is not included in the MEP Budget.

11
Block B10 Ariza

9.1 Closed Circuit Television (CCTV)

No CCTV system or containment has been provided.

9.2 Intruder Alarm system

No Intruder Alarm system or containment has been provided.

9.3 BEMS System

A building energy reporting meter has been included that can be linked to the Azuri Estate
Management system.

12
ARIZA TOWNHOUSES AT PLOT B10, AZURI

AZURI SMART CITY COMPANY LTD

DESIGN CONCEPT REPORT

SEPTEMBER 2023

7 Remy Ollier Street, Beau Bassin, MAURITIUS


Tel: (230) 466 2777 Fax: (230) 467 7984

E-mail: administration@sjpce.com
DOCUMENT CONTROL
Title: ARIZA TOWNHOUSES AT PLOT B10, AZURI

AZURI SMART CITY COMPANY LTD

DESIGN CONCEPT REPORT

Document No:

https://sjpce.sharepoint.com/sites/2023/Shared
Document Path: Documents/[124]/B.DOCUMENTS/REPORTS/DESIGN
CONCEPT REPORT/DESIGN CONCEPT REPORT-
EDB_28.09.23.docx
Status: Copy No:

Name Signature Date

Prepared by: N.Ramdawor (NR) 28/09/2023

Checked by: M.Jadav (MJ) 28/09/2023

Revision Record

Rev. Date By Summary of Changes Chkd Aprvd


TABLE OF CONTENTS

Item Description Page

1 INTRODUCTION 1

1.1 Project Description 1

1.2 Project Team 1

1.3 The Site 2

1.3.1 Site Topography 2

1.4 Expected Ground Conditions 3

1.4.1 Expected Groundwater Conditions 4

2 DESIGN OF ROAD INFRASTRUCTURE 5

2.1 Design Standards 5

2.2 Proposed Road Section 5

3 DESIGN OF STORMWATER DRAINAGE SYSTEM 7

3.1 Overall Drainage Concept 7

3.2 Design Standards 7

3.3 Design Principles 7

4 STRUCTURAL ENGINEERING DESIGN 9

4.1 Brief Description of Building Structure 9

4.2 Design Standards 9

4.3 Durability 10

4.4 Fire Rating 10

4.5 Wind Effects 10

4.6 Dead Loads and Imposed Loads 10

4.7 Earth Pressure 10

4.8 External Openings 11

5 SUSTAINABILITY PRINCIPLES 12

(i)
5.1 Advocating the use of locally sourced building materials 12

5.2 Advocating the use of efficiently designed concrete elements 12

5.3 Design for longer service life 12

5.4 Advocating the use of sustainable concrete 12

APPENDIX A: DRAWINGS

23-124-L1002 – P1 – ROAD & DRAINAGE LAYOUT


23-124-L1-P2 – FOUNDATION & GROUND FLOOR LAYOUT
23-124-L2-P2 – SECTIONS TO FOUNDATION & GROUND FLOOR
23-124-L3-P2 – FIRST FLOOR LAYOUT
23-124-L4-P2 – SECTIONS TO FIRST FLOOR
23-124-L5-P2 – ROOF LAYOUT
23-124-L6-P2 – SECTIONS TO ROOF

(ii)
1 INTRODUCTION
This report summarises the salient data, assumptions, and principles to be used in the civil and
structural engineering design for the residential development in Plot B10 at Azuri Ocean and Golf
Village, Roches Noires.

It should be highlighted that at the time of submission of this report, the project is still at Stage 2- Concept
Design as per RIBA Plan of Work 2020.

It is therefore understood that this document is being issued with in-progress preliminary drawings to
provide an indication of the likely extent and nature of the structural and infrastructural works on the
project. It is emphasised that the structural and infrastructural designs are not complete, and may
change with architectural or client changes, and as the project progresses towards Stage 4 – Technical
Design Stage.

1.1 Project Description

The project, as presented in Figure 1-1, consists of the construction of 11 blocks of semi-detached
townhouses with associated infrastructural works including roadworks, provision of services,
construction of on-plot stormwater drainage system etc.

Figure 1-1: Proposed site plan

1.2 Project Team


Client/Promoter Azuri Smart City Company Ltd
Project Manager Pro-Pillar Ltd
Architect Macbeth Architects & Designers Ltd

1
Civil and Structural Engineer Servansingh Jadav and Partners Consulting Engineers Ltd
MEP Engineers GMF Ltd
Quantity Surveyors MLC Quantity Surveyors

1.3 The Site

The site is situated within the Azuri Ocean and Golf Village at Roches Noires in the district of Rivere du
Rempart. It is situated within the Quartier Du Barachois zone within the whole Azuri Village Masterplan
and has an area of 8084 m2. The site is still partially under sugarcane cultivation as shown in Figure
1-2.

Figure 1-2: General site location

The site is bounded as follows:

• Along the Northern side: The future primary smart city road
• Along the Eastern Side: Green space (forming part of the Azuri masterplan)
• Along the Southern Side: The existing B15 Road
• Along the Western Side: The B08 plot consisting of a residential morcellement.

1.3.1 Site Topography

The site is sloping in nature and its elevation varies from 5.40 m to 10.6 m AMSL.

The slope analysis of the site has shown that in general, the site tends to slope in a North-Easternly
direction and has an average slope of approximately 4%.

Since the slope is less than 10%, the risk of landslide is insignificant, and this implies there is no need
for any slope stability analysis according to PPG 9.

2
Figure 1-3: Contour lines within site boundaries

Figure 1-4: General site slopes

1.4 Expected Ground Conditions

A geotechnical investigation shall be carried out on the plot once the concept stage is completed. This
investigation will consist of trial pits, coreholes as well as in-situ and laboratory testing to ascertain the
engineering properties of the underlying ground before the foundation design is finalised.

3
Geotechnical information gathered from the B08 plot located just adjacent to the B10 site suggest that
the site is likely to be covered by a layer of topsoil, under which a layer of Firm reddish brown high
plasticity silty CLAY - Completely Weathered Basalt (CWB) is expected. In principle, these conditions
are considered favourable for shallow foundation options (strip footing/ pad footings) may be used for
low-rise building projects. However, these will be confirmed after receipt of the findings of the
geotechnical investigation.

1.4.1 Expected Groundwater Conditions

Groundwater table was not encountered during the investigation for the B08 site and is therefore not
deemed to affect the proposed founding solutions for the project. However, this will be confirmed after
receipt of the findings of the geotechnical investigation.

4
2 DESIGN OF ROAD INFRASTRUCTURE
The internal road will provide access to 22 townhouses only and has been designed as a 5.0m wide
local access road in accordance with the requirements of the local authorities. The design criteria are
summarised in Table 2-1.

Table 2-1: Design criteria for internal road

Road Function Exclusively local access roads

Gently sloping with average slope of approximately


Terrain Type
4%
Private cars, vans, ambulances, fire services
Types of vehicles
vehicles and delivery goods vehicles.
5.0 m wide road made up of a single lane for two-
Road width
way traffic.
Longitudinal road gradient Varies from 1.0 to 5%
Design Speed 10 km/hr
Min cross-fall/camber road gradient 2.5%
Min 6.0 m at junction of the internal road with the
Turning Radius main smart city road.
Min. 3.0m at the internal junctions.

2.1 Design Standards

The following publications shall be used for the design of the road network:

• Overseas Road Note 29 and 31 from Transport and Research Development Laboratory of the
Department of Environment of United Kingdom.
• Overseas Road Note 6 from Transport and Research Development Laboratory of the Department
of Environment of United Kingdom.
• Planning Policy Guidance by Ministry of Housing and Lands of the Government of Mauritius.

2.2 Proposed Road Section

The proposed road corridor as shown in Figure 2-1 consists of a 5.0m wide paved roadway with a
centrally placed stormwater drain. The trenches and manholes for M&E services will all be located within
the road corridor and will be carefully coordinated to ensure easy access for maintenance.

5
Figure 2-1: Typical Road sections

6
3 DESIGN OF STORMWATER DRAINAGE SYSTEM
The stormwater drainage design for this project has been designed by adopting a holistic approach of
the Quartier du Barachois zone within the Azuri Village. Due consideration has been given to the
existing drainage facilities which have already been provided in the masterplan to channel the
stormwater to a safe discharge point.

3.1 Overall Drainage Concept

The design of the stormwater drainage system shall seek to attenuate the flows from the project site
such that the post-development outflow rate is equal or less than the value as defined by the
masterplanning team for this B10 plot.

3.2 Design Standards

The following codes and publications shall be used for the design of the internal stormwater drainage
system:

• BS EN 752 Drain and Sewer System outside buildings


• Study of Land Drainage System of the Island of Mauritius (April 2003) carried out by Gibb in
association with Water and Power Consultancy Services (India) Ltd for the Ministry of Public
Utilities
• Drainage Manual by South Africa National Road Agency
• Planning Policy Guidance by Ministry of Housing and Lands

3.3 Design Principles

The following design principles have been considered for the stormwater drainage design:

• The whole stormwater drainage system shall be designed for a 1-in-25-year return period as
required by the Land Drainage Authority.
• Runoff from the roof of each block will be routed through catchpits and underground PVC pipes
which ultimately connect into a common drain on the garden side of each building -see Error!
Reference source not found. and drawing 23-124-L1002 Rev P1 in Appendix A.
• These common drains will have specific discharge points into the main stormwater network of the
smart city as defined by the masterplanning team both in terms of location and invert levels as
illustrated in Figure 3-2.
• Surface runoff from the road will be channelled into a centrally placed RC drain with gratings at
suitable intervals to enable efficient capture of stormwater and easy maintenance.

7
• Figure 3-1: Extract from stormwater drainage layout

Figure 3-2: Overall stormwater drainage layout for the project

8
4 STRUCTURAL ENGINEERING DESIGN
4.1 Brief Description of Building Structure

All the townhouse blocks are identical and are Ground + 1 units with approximate overall dimensions
of 11.4m by 15.65m. The maximum floor-to-floor dimension is 3.45m.

The structure of all the villas shall consist of reinforced concrete slabs, beams, and columns. The
perimeter of the buildings shall consist of 200mm thick load bearing hollow blocks coupled with
reinforced concrete frames, consisting of beams and columns where applicable. Structural load-bearing
block-walls shall be generally 150 or 200mm thick while non-structural internal dividing walls shall be
100 or 150mm thick.

The foundations of the buildings shall consist of isolated pad and strip footings, and the ground floor
slab shall consist of an in-situ on-grade floor slab.

A set of preliminary structural drawings have been given in Appendix A.

Figure 4-1: Typical architectural ground floor layout of each villa

4.2 Design Standards

• All designs for reinforced concrete structures shall be carried out in accordance with BS 8110
“Structural Use of Concrete”.
• All designs for steel structures shall be carried out in accordance with BS5950 “Structural Use of

9
Steelwork in Building” or BS449 “The Use of Structural Steel in Building”. Protection against
corrosion shall be provided as per BS 5493 “Protective coating of Iron and Steel Structures
against Corrosion” for achieving a “very long” life to first maintenance – typically 20 years or
more.
• All designs for structural masonry shall be carried out in accordance with BS5628 “Structural Use
of Masonry”.
• Foundations shall be designed in accordance with BS8004 “Code of Practice for Foundations”.
• Water retaining concrete structures shall be designed in accordance with BS8007 “Code of
Practice for Design of Concrete Structures for Retaining Aqueous Liquids”.
• For any other types of structures, the design shall be carried out in accordance with the relevant
British Standards.

4.3 Durability

The buildings shall have a normal service life of at least 60 years with minimal maintenance. All
structural members should be designed to last for the life of the buildings in the environmental conditions
at the site. The following exposure classifications and minimum concrete strengths have been adopted
based on Table 3.2 of BS 8110-11997:

• External elements: Severe


• Internal elements: Mild

4.4 Fire Rating

All load-bearing walls and R.C. elements have been sized accordingly to achieve the required minimum
period of fire resistance according to the Mauritian Fire Code. All structural elements shall have a
minimum fire rating of 30 minutes.

4.5 Wind Effects

All structures as well as cladding, roofing, windows, etc. shall be designed for withstanding cyclonic
winds. Winds loads shall be calculated in accordance with CP3 “Basic Data for the Design of Buildings”,
Chapter V “Loading”, Part 2 “Wind Loads” for a maximum cyclonic wind speed of 280 km/hr.

4.6 Dead Loads and Imposed Loads

Dead loads and imposed loads shall generally be for residential usage in accordance with BS 6399
“Design Loading for Buildings”, Part 1 “Code of Practice for Dead and Imposed Loads”.

4.7 Earth Pressure

Earth pressures on retaining structures, where required, shall be determined in accordance with BS
8002: 1994 Code of Practice for “Earth Retaining Structures”.

10
4.8 External Openings

The external doors, windows, louvers, etc. shall be in aluminium. They shall be detailed and specified
by the Architect and their procurement shall be done on a Design and Build basis. SJPCE shall provide
a set of structural performance specifications for the aluminium elements and glazing to enable the
suppliers to design the openings and produce shop drawings. Calculations shall be carried out in
accordance with BS 8118 “Structural Use of Aluminium, and members together with fixing details
proposed by the suppliers shall be checked for strength and serviceability requirements against cyclonic
winds. The calculations and shop drawings shall be vetted and commented by SJPCE prior to
manufacture.

11
5 SUSTAINABILITY PRINCIPLES
5.1 Advocating the use of locally sourced building materials

In the local Mauritian context, concrete is the most popular and cheapest building material as compared
to steel and timber because its major constituent, that is, aggregates are locally sourced. In line with
the principles of sustainable development, we have chosen to use concrete hollow blocks and
reinforced concrete as the main building materials to minimise international sourcing thereby reducing
significant energy use on the transport of building materials which counts towards the overall
environmental impacts of the material and hence the buildings.

5.2 Advocating the use of efficiently designed concrete elements

The sizing of reinforced concrete elements shall be optimised while conforming to the specified strength
and serviceability requirements to reduce the use of cement whose production is known to be
responsible for a significant proportion of greenhouse gas emissions.

5.3 Design for longer service life

According to the International Green Construction Code (IGCC), the design service life of building
structures should not be less than 60 years. To ensure longevity of the buildings’ service life, we shall
adopt a set of comprehensive and strict quality control measures to ensure that good quality of
construction materials (especially concrete) is used on site and make sure that proper design, detailing,
and construction methods are employed. These practices will ensure better material durability which in
turn results into less frequent maintenance and replacement, and better adaptability to future
reconfigurations. This reduces the natural resources required for manufacturing and the amount of
money spent on installation and the associated labour.

5.4 Advocating the use of sustainable concrete

The manufacture of cement is a very energy-intensive process, and the worldwide production of cement
is responsible for 5% of carbon dioxide emissions. For this reason, we shall advocate the use of
concrete in which a percentage of cement is replaced by fly ash which is locally sourced.

END OF REPORT

12
APPENDIX A:
PRELIMINARY DRAWINGS
8.75m
8.50m
8.25m
8.00m

N
W
7.75m

0m

S
7.5

E
10.50m
25m
7.

10.00m
9.75m
9.25m

10.25m
9.25m

9.50m
9.50m
9.25m m
7.00
9.00m
8.75m
8.50m

SOAKAWAY 3.0m DEEP


8.25m

8.00m

7.75m

7.50m
GOODLANDS - POSTE DE FLACQ ROAD B15

m
7.25
SOAKAWAY 3.0m DEEP

7.0
0m

7.0
0m

5.75m
NOTES : CLIENT PROJECT DESCRIPTION Drawn

Checked

Date
DRAWING TITLE Format A1 Format A2 Format A3
Rev.
Drawing Number
REV. Date Issues REV. By Date Description
L2
3

L2
3

2 2
L2 L2

L2
1

L2
1

NOTES :

Drawn
Checked

Drawing Number Rev. Scale


Date
Rev. By Date Description Rev. Date Issue
NOTES :

Drawn
Checked

Drawing Number Rev. Scale


Date
Rev. By Date Description Rev. Date Issue
L4
4

L4
L4 3
2

L4
2

L4
3

L4
4

L4
5 5 1
L4 L4

L4
1

NOTES :

Drawn
Checked

Drawing Number Rev. Scale


Date
Rev. By Date Description Rev. Date Issue
NOTES :

Drawn
Checked

Drawing Number Rev. Scale


Date
Rev. By Date Description Rev. Date Issue
L6
L6
1
3

L6
2

L6
3

L6
L6
1
2

5 5
L6 L6

L6
3

L6
4

NOTES :

Drawn
Checked

Drawing Number Rev. Scale


Date
Rev. By Date Description Rev. Date Issue
NOTES :

Drawn
Checked

Drawing Number Rev. Scale


Date
Rev. By Date Description Rev. Date Issue
B10 – Ariza

PROJECT BRIEF

Project: B10 – Ariza

Date: 03 October 2023

PB Revision: Project Brief Revision #0

Land size: 8147 m2

No. of Units: 22 Townhouses

Size of units GEA – 163.7m2 of each villa (minimum size)

No. of bedrooms 1 type of Townhouse will be available:


3 bedrooms on First Floor – 1 bedroom includes bathroom

Other features • Guest toilet


• Common Bathroom
• Open Plan Living / Kitchen Area
• Utility Kitchen
• Cupboards / storage in rooms
• Two Parking per Townhouse
• Two Stores
• Veranda

• On option:
- Outdoor gazebo
- Pool Deck and Standard Pool/Plunge Pool
- Extension of terrace with/without pergola
- Covered carport
B10 – Ariza

PROJECT FEATURES

No. Description

1 Number of plots: 22

Average built area per unit / Plot


2 163.7 m2
Sizes:

3 Average price/ plot (VAT Excl.) : MUR 19,600,000.00


Ariza – B10

PROJECT TEAM

Title Company Representative


Client Azuri Smart City Company Ltd Nicolas Rey
Jérôme Ritter
Vedita Ramlochun

Architect Macbeth Architects & Designers Ltd Alistair Macbeth


Sarah Maram Beebeejaun

Project Manager Propillar Ltd Thierry Park

Quantity Surveyor MLC Construction Cost Consultants Shilpa Nahaboo


Avishay Kumar Reetun

Structural and Civil Engineer Servansingh Jadav & Partners Manish Jadav
Consulting Engineers Limited Nitish Ramdawor

MEP Consultant GMF Ltd Asraf Wahedally


Shashi Sanmukhiya

Landscape Architect Mooneeram Associates Ltd Ashvin Mooneeram


Oudeshsingh Rutty

Land Surveyor CDDS Ltd Christophe Chasteau


Azuri Smart City
B10 – Ariza
Key Milestone & Project Implementation
Obtention of no-
Application for objection letter for
development with development and
Handover of
EDB commercialization
Start of construction Villas to owners
29th September 2023 27th October 2023
April 2024 (17 months) December 2025

1 2 3 4 5 6 7

Launch of sales Clearance from


05th October 2023 Signature of “Contrat EDB on
de Réservation completion of
Préliminaire” project
1st November 2023 October 2025
job no. consult. stage location sheet no. rev.

ARIZA A1 CAP B10 A

Modification to
site boundary 6036m² revisions
1. ISSUE FOR NO-OBJECTION LETTER
date rev.
26.09.23 A SB
ini.

Distribution
Pillar/Metric Cubicle

Green Areas

Drain

PROJECT INFORMATION
C03 issued
GENERAL NOTES

SITE AREA: 8147.00 SQM


%
E 1.5
SLOP
3224m² 1 DO NOT SCALE FROM THIS DRAWING. USE FIGURED
DIMENSIONS ONLY.
2 ALL LEVELS & DIMENSIONS TO BE CHECKED ON
SITE BEFORE WORK COMMENCES.
3 THE ARCHITECT SHALL NOT BE HELD RESPONSIBLE
PLOT PLOT AREA (m2) FOR DIMENSIONAL ERRORS IF NOT NOTIFIED AT
TH02
THE TIME OF COMMENCING WORK ON SITE.
TH01 282.1 SLOP
E 1.5
%

4 CUTTING & FILLING TO BE DETERMINED ON SITE


TH02 341.2 %
E 1.5
SLOP
WHEN COMMENCING WORK.
TH03 288.7 5 DIMENSIONS ARE GIVEN IN MILLIMETRES UNLESS
TH04 SLOP
E 1.5
%

OTHERWISE STATED.
TH04 300.0
TH05 296.4
TH06 273.1 %
E 1.5

TH07 306.3
SLOP

TH08 257.0
TH09 314.1 TH06
TH10 250.7
SLOP
E 1.5
%

TH11 303.0 %
E 1.5
SLOP

SLOP

TH12 252.8
E 1.5
%

SLOP
E 1.5
%

TH08 %5

TH13 290.7
.1 E
PO
LS

TH01
TH14 256.7 SLOP
E 1.5
%

TH15 279.8 %
SLOP
E 1.5

TH16 258.6
TH17 325.7 TH10 TH03 %5
.1 E
PO
LS

TH18 303.7 SLOP


E 1.5
%

TH19 303.2
TH20 302.8 %
E 1.5
SLOP

SLOP
E 1.5
%

TH21 302.3 TH12 SLOP


E 1.5
%

%5
.1 E
PO
LS

TH22 302.0 TH05


6390.9 m2
SLOP
E 1.5
%

%
E 1.5
SLOP

TH14 TH07
%5
.1 E
PO
LS

SLOP
E 1.5
%

%
E 1.5
SLOP

SLOP

TH16
E 1.5
%

SLOP
E 1.5
%

%5

TH09
.1 E
PO
L S

SLOP
E 1.5
%

MACBETH ARCHITECTS & DESIGNERS LTD. Architect and Designers


TH11
%5
.1 EP
2nd Floor Light House, Vivéa Business Park - Saint Pierre 81430, Mauritius
Ramírez.
Suárez
Hugo
Arq.
de
Ramos.P.
Espitia
Francisco
Arq.
de
Arguelles.P.
Romero
A.
Adrian
Arq.
de
Hernández.P.
Guerrero
Enrique
Arq.
de
P.
OL
S

T + (230) 433 8876 F + (230) 433 8883


Ramírez.
Suárez
Hugo
Arq.
de
Ramos.P.
Espitia
Francisco
Arq.
de
Arguelles.P.
Romero
A.
Adrian
Arq.
de
Hernández.P.
Guerrero
Enrique
Arq.
de
P.
E. Administration < macbeth@macbeth.mu>
SLOP

W. www.macbeth.mu
E 1.5
%

%5
.1 E

VAT No. : 27432993


PO
LS

TH13
SLOP
E 1.5
%

SLOP
E 1.5
%
%
E 1.5
SLOP

TH22
Ramírez.
Suárez
Hugo
Arq.
de
Ramos.P.
Espitia
Francisco
Arq.
de
Arguelles.P.
Romero
A.
Adrian
Arq.
de
Hernández.P.
Guerrero
Enrique
Arq.
de
P.
Ramírez.
Suárez
Hugo
Arq.
de
Ramos.P.
Espitia
Francisco
Arq.
de
Arguelles.P.
Romero
A.
Adrian
Arq.
de
Hernández.P.
Guerrero
Enrique
Arq.
de
P.
TH15
SLOP

C02a
E 1.5
%

%5
.1 E
PO
LS

TH21
%
E 1.5
SLOP

SLOP
E 1.5
%

3917m²
%
E 1.5
SLOP

TH20
Ramírez.
Suárez
Hugo
Arq.
de
Ramos.P.
Espitia
Francisco
Arq.
de
Arguelles.P.
Romero
A.
Adrian
Arq.
de
Hernández.P.
Guerrero
Enrique
Arq.
de
P.
Ramírez.
Suárez
Hugo
Arq.
de
Ramos.P.
Espitia
Francisco
Arq.
de
Arguelles.P.
Romero
A.
Adrian
Arq.
de
Hernández.P.
Guerrero
Enrique
Arq.
de
P.
SLOP
E 1.5
%

TH19
%
E 1.5
SLOP

SLOP
E 1.5
%

Ramírez.
Suárez
Hugo
Arq.
de
Ramos.P.
Espitia
Francisco
Arq.
de
Arguelles.P.
Romero
A.
Adrian
Arq.
de
Hernández.P.
Guerrero
Enrique
Arq.
de
P.
%
E 1.5
SLOP

TH18
THIS DRAWING IS COPYRIGHT
job
SLOP
E 1.5
%

CONSTRUCTION OF 22 TOWNHOUSES AT AZURI B10


TH17
%
E 1.5
SLOP

client

AZURI SMART CITY COMPANY. LTD


site

AZURI OCEAN & GOLF VILLAGE, ROCHES NOIRES

C01 drawing title

SITE PLAN
D02b 10545m² scale date started drawn by
AS SHOWN MAY 2023 SB
job no. consult. stage location sheet no. rev.

ARIZA A1 CAP B10 A


3751m² c Macbeth Architects cad file HR23/DWG/A1-MAD/CAP
AZURI SMART CITY

BLOCK B10 ARIZA

PROJECT COST BREAKDOWN

BUILDERS WORK 122,764,055

MEP WORKS 31,059,000

PRELIMINARIES & GENERAL REQUIREMENTS 25,037,000

ESCALATION 9,000,000

CONTINGENCY 9,000,000

EXTERNAL WORKS 22,659,000

ANCILLARY BUILDING 0

INFRASTRUCTURE WORKS 2,091,500

TOTAL CONSTRUCTION COST 221,610,555

PROFESSIONAL FEES 23,256,655

Vous aimerez peut-être aussi