N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021

Tâche A S O N D J F M A M J J A S
1 PLANNING GENERAL GH 06 450 jrs Mer 05/08/20 Jeu 14/07/22

2 Ordre de service 0 jr Mer 05/08/20 Mer 05/08/20 05/08


3 Installation du chantier 15 jrs Mer 05/08/20 Jeu 27/08/20 Installation du chantier
4 Gros œuvre 281 jrs Jeu 27/08/20 Ven 12/11/21

5 Travaux d'infrastructure 62 jrs Jeu 27/08/20 Jeu 03/12/20

6 ZONE 1 54 jrs Jeu 27/08/20 Ven 20/11/20

7 IMM K 19 jrs Jeu 27/08/20 Lun 28/09/20 IMM K


8 IMM J 19 jrs Mer 16/09/20 Jeu 15/10/20 IMM J
9 IMM I 18 jrs Lun 05/10/20 Mar 03/11/20 IMM I
10 IMM H 19 jrs Jeu 22/10/20 Ven 20/11/20 IMM H
11 ZONE 2 48 jrs Lun 14/09/20 Ven 27/11/20

12 IMM G 18 jrs Lun 14/09/20 Lun 12/10/20 IMM G


13 IMMF 14 jrs Mer 30/09/20 Jeu 22/10/20 IMMF
14 IMM E 18 jrs Lun 12/10/20 Lun 09/11/20 IMM E
15 IMM D 19 jrs Mer 28/10/20 Ven 27/11/20 IMM D
16 ZONE 3 42 jrs Mar 29/09/20 Jeu 03/12/20

17 IMM C 18 jrs Mar 29/09/20 Mar 27/10/20 IMM C


18 IMM B 19 jrs Jeu 15/10/20 Lun 16/11/20 IMM B
19 IMM A 19 jrs Mer 04/11/20 Jeu 03/12/20 IMM A
20 Béton armé en élévation 149 jrs Lun 28/09/20 Mer 19/05/21

21 POTEAUX ET VOILES 132 jrs Lun 28/09/20 Jeu 22/04/21

22 ZONE 1 124 jrs Lun 28/09/20 Ven 09/04/21

23 IMM K 88 jrs Lun 28/09/20 Ven 12/02/21

24 S.Sol 5 jrs Lun 28/09/20 Lun 05/10/20 S.Sol


25 RDC 3 jrs Lun 02/11/20 Jeu 05/11/20 RDC
26 1er étage 3 jrs Jeu 03/12/20 Mar 08/12/20 1er étage
27 2ème étage 3 jrs Mer 06/01/21 Lun 11/01/21 2ème étage
28 3ème étage 3 jrs Lun 08/02/21 Ven 12/02/21 3ème étage
29 IMM J 89 jrs Jeu 15/10/20 Jeu 04/03/21

30 S.Sol 6 jrs Jeu 15/10/20 Lun 26/10/20 S.Sol


31 RDC 3 jrs Ven 20/11/20 Mer 25/11/20 RDC
32 1er étage 3 jrs Jeu 24/12/20 Mar 29/12/20 1er étage
33 2ème étage 3 jrs Mar 26/01/21 Lun 01/02/21 2ème étage
34 3ème étage 3 jrs Lun 01/03/21 Jeu 04/03/21 3ème étage
35 IMM I 85 jrs Mar 03/11/20 Mar 16/03/21

36 S.Sol 6 jrs Mar 03/11/20 Mer 11/11/20 S.Sol


37 RDC 3 jrs Lun 07/12/20 Ven 11/12/20 RDC
38 1er étage 3 jrs Jeu 07/01/21 Mar 12/01/21 1er étage
39 2ème étage 3 jrs Lun 08/02/21 Ven 12/02/21 2ème étage
40 3ème étage 3 jrs Jeu 11/03/21 Mar 16/03/21 3ème étage
41 IMM H 89 jrs Ven 20/11/20 Ven 09/04/21

42 S.Sol 6 jrs Ven 20/11/20 Mar 01/12/20 S.Sol


43 RDC 3 jrs Lun 28/12/20 Jeu 31/12/20 RDC

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 1
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
44 1er étage 3 jrs Ven 29/01/21 Mer 03/02/21 1er étage
45 2ème étage 3 jrs Mer 03/03/21 Mar 09/03/21 2ème étage
46 3ème étage 3 jrs Mar 06/04/21 Ven 09/04/21 3ème étage
47 ZONE 2 99 jrs Lun 12/10/20 Mar 16/03/21

48 IMM G 81 jrs Lun 12/10/20 Mar 16/02/21

49 S.Sol 6 jrs Lun 12/10/20 Mer 21/10/20 S.Sol


50 RDC 3 jrs Ven 13/11/20 Mer 18/11/20 RDC
51 1er étage 3 jrs Lun 14/12/20 Jeu 17/12/20 1er étage
52 2ème étage 3 jrs Mar 12/01/21 Lun 18/01/21 2ème étage
53 3ème étage 3 jrs Jeu 11/02/21 Mar 16/02/21 3ème étage
54 IMMF 73 jrs Jeu 22/10/20 Lun 15/02/21

55 S.Sol 6 jrs Jeu 22/10/20 Ven 30/10/20 S.Sol


56 RDC 3 jrs Ven 20/11/20 Mer 25/11/20 RDC
57 1er étage 3 jrs Jeu 17/12/20 Mer 23/12/20 1er étage
58 2ème étage 3 jrs Mer 13/01/21 Mar 19/01/21 2ème étage
59 3ème étage 3 jrs Mer 10/02/21 Lun 15/02/21 3ème étage
60 IMM E 81 jrs Lun 09/11/20 Mar 16/03/21

61 S.Sol 6 jrs Lun 09/11/20 Mer 18/11/20 S.Sol


62 RDC 3 jrs Ven 11/12/20 Mer 16/12/20 RDC
63 1er étage 3 jrs Lun 11/01/21 Jeu 14/01/21 1er étage
64 2ème étage 3 jrs Mer 10/02/21 Lun 15/02/21 2ème étage
65 3ème étage 3 jrs Jeu 11/03/21 Mar 16/03/21 3ème étage
66 ZONE 3 113 jrs Mar 27/10/20 Jeu 22/04/21

67 IMM D 89 jrs Ven 27/11/20 Ven 16/04/21

68 S.Sol 6 jrs Ven 27/11/20 Lun 07/12/20 S.Sol


69 RDC 3 jrs Lun 04/01/21 Jeu 07/01/21 RDC
70 1er étage 3 jrs Jeu 04/02/21 Mar 09/02/21 1er étage
71 2ème étage 3 jrs Mer 10/03/21 Lun 15/03/21 2ème étage
72 3ème étage 3 jrs Lun 12/04/21 Ven 16/04/21 3ème étage
73 IMM C 85 jrs Mar 27/10/20 Mer 10/03/21

74 S.Sol 6 jrs Mar 27/10/20 Jeu 05/11/20 S.Sol


75 RDC 3 jrs Mar 01/12/20 Ven 04/12/20 RDC
76 1er étage 3 jrs Jeu 31/12/20 Mer 06/01/21 1er étage
77 2ème étage 3 jrs Mar 02/02/21 Ven 05/02/21 2ème étage
78 3ème étage 3 jrs Jeu 04/03/21 Mer 10/03/21 3ème étage
79 IMM B 89 jrs Lun 16/11/20 Lun 05/04/21

80 S.Sol 6 jrs Lun 16/11/20 Mar 24/11/20 S.Sol


81 RDC 3 jrs Mar 22/12/20 Ven 25/12/20 RDC
82 1er étage 3 jrs Ven 22/01/21 Mer 27/01/21 1er étage
83 2ème étage 3 jrs Jeu 25/02/21 Mar 02/03/21 2ème étage
84 3ème étage 3 jrs Mar 30/03/21 Lun 05/04/21 3ème étage
85 IMM A 89 jrs Jeu 03/12/20 Jeu 22/04/21

86 S.Sol 6 jrs Jeu 03/12/20 Lun 14/12/20 S.Sol

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 2
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
87 RDC 3 jrs Ven 08/01/21 Mer 13/01/21 RDC
88 1er étage 3 jrs Jeu 11/02/21 Mar 16/02/21 1er étage
89 2ème étage 3 jrs Mar 16/03/21 Lun 22/03/21 2ème étage
90 3ème étage 3 jrs Lun 19/04/21 Jeu 22/04/21 3ème étage
91 PLANCHER ET POUTRES 143 jrs Mer 07/10/20 Mer 19/05/21

92 ZONE 1 135 jrs Mer 07/10/20 Jeu 06/05/21

93 IMM K 99 jrs Mer 07/10/20 Jeu 11/03/21

94 S.Sol 15 jrs Mer 07/10/20 Jeu 29/10/20 S.Sol


95 RDC 16 jrs Ven 06/11/20 Mer 02/12/20 RDC
96 1er étage 16 jrs Jeu 10/12/20 Mar 05/01/21 1er étage
97 2ème étage 16 jrs Mar 12/01/21 Ven 05/02/21 2ème étage
98 3ème étage 16 jrs Lun 15/02/21 Jeu 11/03/21 3ème étage
99 IMM J 99 jrs Mar 27/10/20 Mer 31/03/21

100 S.Sol 15 jrs Mar 27/10/20 Jeu 19/11/20 S.Sol


101 RDC 16 jrs Ven 27/11/20 Mer 23/12/20 RDC
102 1er étage 16 jrs Mer 30/12/20 Lun 25/01/21 1er étage
103 2ème étage 16 jrs Mar 02/02/21 Ven 26/02/21 2ème étage
104 3ème étage 16 jrs Lun 08/03/21 Mer 31/03/21 3ème étage
105 IMM I 94 jrs Ven 13/11/20 Ven 09/04/21

106 S.Sol 14 jrs Ven 13/11/20 Ven 04/12/20 S.Sol


107 RDC 15 jrs Lun 14/12/20 Mer 06/01/21 RDC
108 1er étage 15 jrs Mer 13/01/21 Ven 05/02/21 1er étage
109 2ème étage 15 jrs Lun 15/02/21 Mer 10/03/21 2ème étage
110 3ème étage 15 jrs Mer 17/03/21 Ven 09/04/21 3ème étage
111 IMM H 99 jrs Mer 02/12/20 Jeu 06/05/21

112 S.Sol 15 jrs Mer 02/12/20 Ven 25/12/20 S.Sol


113 RDC 16 jrs Lun 04/01/21 Mer 27/01/21 RDC
114 1er étage 16 jrs Jeu 04/02/21 Mar 02/03/21 1er étage
115 2ème étage 16 jrs Mer 10/03/21 Lun 05/04/21 2ème étage
116 3ème étage 16 jrs Lun 12/04/21 Jeu 06/05/21 3ème étage
117 ZONE 2 107 jrs Jeu 22/10/20 Jeu 08/04/21

118 IMM G 89 jrs Jeu 22/10/20 Jeu 11/03/21

119 S.Sol 13 jrs Jeu 22/10/20 Mer 11/11/20 S.Sol


120 RDC 14 jrs Jeu 19/11/20 Ven 11/12/20 RDC
121 1er étage 14 jrs Ven 18/12/20 Lun 11/01/21 1er étage
122 2ème étage 14 jrs Mar 19/01/21 Mar 09/02/21 2ème étage
123 3ème étage 14 jrs Mer 17/02/21 Jeu 11/03/21 3ème étage
124 IMMF 79 jrs Mar 03/11/20 Ven 05/03/21

125 S.Sol 11 jrs Mar 03/11/20 Jeu 19/11/20 S.Sol


126 RDC 12 jrs Ven 27/11/20 Mer 16/12/20 RDC
127 1er étage 12 jrs Jeu 24/12/20 Mar 12/01/21 1er étage
128 2ème étage 12 jrs Mer 20/01/21 Lun 08/02/21 2ème étage
129 3ème étage 12 jrs Mar 16/02/21 Ven 05/03/21 3ème étage

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 3
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
130 IMM E 89 jrs Jeu 19/11/20 Jeu 08/04/21

131 S.Sol 13 jrs Jeu 19/11/20 Jeu 10/12/20 S.Sol


132 RDC 14 jrs Jeu 17/12/20 Ven 08/01/21 RDC
133 1er étage 14 jrs Lun 18/01/21 Lun 08/02/21 1er étage
134 2ème étage 14 jrs Mar 16/02/21 Mer 10/03/21 2ème étage
135 3ème étage 14 jrs Mer 17/03/21 Jeu 08/04/21 3ème étage
136 ZONE 3 123 jrs Ven 06/11/20 Mer 19/05/21

137 IMM D 99 jrs Mer 09/12/20 Jeu 13/05/21

138 S.Sol 15 jrs Mer 09/12/20 Jeu 31/12/20 S.Sol


139 RDC 16 jrs Ven 08/01/21 Mer 03/02/21 RDC
140 1er étage 16 jrs Jeu 11/02/21 Mar 09/03/21 1er étage
141 2ème étage 16 jrs Mar 16/03/21 Ven 09/04/21 2ème étage
142 3ème étage 16 jrs Lun 19/04/21 Jeu 13/05/21 3ème étage
143 IMM C 94 jrs Ven 06/11/20 Lun 05/04/21

144 S.Sol 14 jrs Ven 06/11/20 Lun 30/11/20 S.Sol


145 RDC 15 jrs Lun 07/12/20 Mer 30/12/20 RDC
146 1er étage 15 jrs Jeu 07/01/21 Lun 01/02/21 1er étage
147 2ème étage 15 jrs Lun 08/02/21 Mer 03/03/21 2ème étage
148 3ème étage 15 jrs Jeu 11/03/21 Lun 05/04/21 3ème étage
149 IMM B 99 jrs Jeu 26/11/20 Ven 30/04/21

150 S.Sol 15 jrs Jeu 26/11/20 Ven 18/12/20 S.Sol


151 RDC 16 jrs Lun 28/12/20 Jeu 21/01/21 RDC
152 1er étage 16 jrs Ven 29/01/21 Mer 24/02/21 1er étage
153 2ème étage 16 jrs Mer 03/03/21 Lun 29/03/21 2ème étage
154 3ème étage 16 jrs Mar 06/04/21 Ven 30/04/21 3ème étage
155 IMM A 99 jrs Mar 15/12/20 Mer 19/05/21

156 S.Sol 15 jrs Mar 15/12/20 Jeu 07/01/21 S.Sol


157 RDC 16 jrs Ven 15/01/21 Mar 09/02/21 RDC
158 1er étage 16 jrs Mer 17/02/21 Lun 15/03/21 1er étage
159 2ème étage 16 jrs Mar 23/03/21 Ven 16/04/21 2ème étage
160 3ème étage 16 jrs Ven 23/04/21 Mer 19/05/21 3ème étage
161 MACONNERIE 85 jrs Lun 08/03/21 Lun 19/07/21

162 ZONE 1 74 jrs Jeu 11/03/21 Mar 06/07/21

163 IMM K 38 jrs Jeu 11/03/21 Mar 11/05/21

164 RDC 8 jrs Jeu 11/03/21 Mer 24/03/21 RDC


165 1 ér étage 10 jrs Mer 24/03/21 Jeu 08/04/21 1 ér étage
166 2 ème étage 10 jrs Jeu 08/04/21 Ven 23/04/21 2 ème étage
167 3 ème étage 10 jrs Ven 23/04/21 Mar 11/05/21 3 ème étage
168 IMM J 38 jrs Jeu 01/04/21 Lun 31/05/21

169 RDC 8 jrs Jeu 01/04/21 Mar 13/04/21 RDC


170 1 ér étage 10 jrs Mer 14/04/21 Jeu 29/04/21 1 ér étage
171 2 ème étage 10 jrs Jeu 29/04/21 Ven 14/05/21 2 ème étage
172 3 ème étage 10 jrs Ven 14/05/21 Lun 31/05/21 3 ème étage

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 4
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
173 IMM I 38 jrs Ven 09/04/21 Mer 09/06/21

174 RDC 8 jrs Ven 09/04/21 Jeu 22/04/21 RDC


175 1 ér étage 10 jrs Jeu 22/04/21 Ven 07/05/21 1 ér étage
176 2 ème étage 10 jrs Lun 10/05/21 Mar 25/05/21 2 ème étage
177 3 ème étage 10 jrs Mar 25/05/21 Mer 09/06/21 3 ème étage
178 IMM H 38 jrs Jeu 06/05/21 Mar 06/07/21

179 RDC 8 jrs Jeu 06/05/21 Mer 19/05/21 RDC


180 1 ér étage 10 jrs Mer 19/05/21 Ven 04/06/21 1 ér étage
181 2 ème étage 10 jrs Ven 04/06/21 Lun 21/06/21 2 ème étage
182 3 ème étage 10 jrs Lun 21/06/21 Mar 06/07/21 3 ème étage
183 ZONE 2 59 jrs Lun 08/03/21 Mar 08/06/21

184 IMM G 38 jrs Jeu 11/03/21 Mar 11/05/21

185 RDC 8 jrs Jeu 11/03/21 Mer 24/03/21 RDC


186 1 ér étage 10 jrs Mer 24/03/21 Jeu 08/04/21 1 ér étage
187 2 ème étage 10 jrs Jeu 08/04/21 Ven 23/04/21 2 ème étage
188 3 ème étage 10 jrs Ven 23/04/21 Mar 11/05/21 3 ème étage
189 IMM F 38 jrs Lun 08/03/21 Mer 05/05/21

190 RDC 8 jrs Lun 08/03/21 Jeu 18/03/21 RDC


191 1 ér étage 10 jrs Ven 19/03/21 Lun 05/04/21 1 ér étage
192 2 ème étage 10 jrs Lun 05/04/21 Mar 20/04/21 2 ème étage
193 3 ème étage 10 jrs Mar 20/04/21 Mer 05/05/21 3 ème étage
194 IMM E 38 jrs Jeu 08/04/21 Mar 08/06/21

195 RDC 8 jrs Jeu 08/04/21 Mer 21/04/21 RDC


196 1 ér étage 10 jrs Mer 21/04/21 Jeu 06/05/21 1 ér étage
197 2 ème étage 10 jrs Jeu 06/05/21 Lun 24/05/21 2 ème étage
198 3 ème étage 10 jrs Lun 24/05/21 Mar 08/06/21 3 ème étage
199 ZONE 3 67 jrs Lun 05/04/21 Lun 19/07/21

200 IMM D 38 jrs Jeu 13/05/21 Mar 13/07/21

201 RDC 8 jrs Jeu 13/05/21 Mer 26/05/21 RDC


202 1 ér étage 10 jrs Mer 26/05/21 Jeu 10/06/21 1 ér étage
203 2 ème étage 10 jrs Jeu 10/06/21 Ven 25/06/21 2 ème étage
204 3 ème étage 10 jrs Ven 25/06/21 Mar 13/07/21 3 ème étage
205 IMM C 35 jrs Lun 05/04/21 Ven 28/05/21

206 RDC 8 jrs Lun 05/04/21 Ven 16/04/21 RDC


207 1 ér étage 9 jrs Ven 16/04/21 Ven 30/04/21 1 ér étage
208 2 ème étage 9 jrs Ven 30/04/21 Ven 14/05/21 2 ème étage
209 3 ème étage 9 jrs Ven 14/05/21 Ven 28/05/21 3 ème étage
210 IMM B 38 jrs Ven 30/04/21 Mer 30/06/21

211 RDC 8 jrs Ven 30/04/21 Jeu 13/05/21 RDC


212 1 ér étage 10 jrs Jeu 13/05/21 Ven 28/05/21 1 ér étage
213 2 ème étage 10 jrs Ven 28/05/21 Lun 14/06/21 2 ème étage
214 3 ème étage 10 jrs Lun 14/06/21 Mer 30/06/21 3 ème étage
215 IMM A 38 jrs Mer 19/05/21 Lun 19/07/21

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 5
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
216 RDC 8 jrs Mer 19/05/21 Mar 01/06/21 RDC
217 1 ér étage 10 jrs Mar 01/06/21 Jeu 17/06/21 1 ér étage
218 2 ème étage 10 jrs Jeu 17/06/21 Ven 02/07/21 2 ème étage
219 3 ème étage 10 jrs Ven 02/07/21 Lun 19/07/21 3 ème étage
220 ENDUIT INTERIEUR 136 jrs Mer 14/04/21 Ven 12/11/21

221 ZONE 1 70 jrs Mer 14/04/21 Lun 02/08/21

222 IMM K 24 jrs Mer 14/04/21 Jeu 20/05/21

223 Enduit projeté plâtre


24 jrs Mer 14/04/21 Jeu 20/05/21 Enduit projeté plâtre
224 Enduit ciment 11 jrs Jeu 29/04/21 Lun 17/05/21 Enduit ciment
225 IMM J 24 jrs Ven 21/05/21 Lun 28/06/21

226 Enduit projeté plâtre


24 jrs Ven 21/05/21 Lun 28/06/21 Enduit projeté plâtre
227 Enduit ciment 11 jrs Lun 07/06/21 Mer 23/06/21 Enduit ciment
228 IMM I 22 jrs Mar 29/06/21 Lun 02/08/21

229 Enduit 22 jrs Mar 29/06/21 Lun 02/08/21 Enduit projeté plâtre
projeté
230 Enduit ciment11 jrs Mer 14/07/21 Ven 30/07/21 Enduit ciment
231 IMM H 24 jrs Mer 09/06/21 Ven 16/07/21

232 Enduit 24 jrs Mer 09/06/21 Ven 16/07/21 Enduit projeté plâtre
projeté
233 Enduit ciment10 jrs Jeu 24/06/21 Ven 09/07/21 Enduit ciment
234 ZONE 2 70 jrs Ven 16/07/21 Jeu 04/11/21

235 IMM G 24 jrs Ven 16/07/21 Mar 24/08/21

236 Enduit projeté plâtre


24 jrs Ven 16/07/21 Mar 24/08/21 Enduit projeté plâtre
237 Enduit ciment 10 jrs Lun 02/08/21 Mar 17/08/21 Enduit ciment
238 IMM F 22 jrs Mar 24/08/21 Mar 28/09/21

239 Enduit projeté plâtre


22 jrs Mar 24/08/21 Mar 28/09/21 Enduit pr
240 Enduit ciment 10 jrs Mer 08/09/21 Jeu 23/09/21 Enduit cime
241 IMM E 45 jrs Mer 25/08/21 Jeu 04/11/21

242 Enduit projeté plâtre


24 jrs Mar 28/09/21 Jeu 04/11/21

243 Enduit ciment 11 jrs Mer 25/08/21 Ven 10/09/21 Enduit ciment
244 ZONE 3 96 jrs Mer 16/06/21 Ven 12/11/21

245 IMM D 24 jrs Mer 16/06/21 Jeu 22/07/21

246 Enduit projeté plâtre


24 jrs Mer 16/06/21 Jeu 22/07/21 Enduit projeté plâtre
247 Enduit ciment 11 jrs Jeu 01/07/21 Lun 19/07/21 Enduit ciment
248 IMM C 24 jrs Ven 23/07/21 Lun 30/08/21

249 Enduit projeté plâtre


24 jrs Ven 23/07/21 Lun 30/08/21 Enduit projeté plâtre
250 Enduit ciment 11 jrs Lun 09/08/21 Mer 25/08/21 Enduit ciment
251 IMM B 24 jrs Mar 31/08/21 Mer 06/10/21

252 Enduit projeté plâtre


24 jrs Mar 31/08/21 Mer 06/10/21

253 Enduit ciment 11 jrs Mer 15/09/21 Ven 01/10/21

254 IMM A 24 jrs Jeu 07/10/21 Ven 12/11/21

255 Enduit projeté plâtre


24 jrs Jeu 07/10/21 Ven 12/11/21

256 Enduit ciment 11 jrs Ven 22/10/21 Mar 09/11/21

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 6
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
257 ENDUIT FACADE 116 jrs Mar 11/05/21 Mar 09/11/21

258 ZONE 1 75 jrs Mar 11/05/21 Lun 06/09/21

259 IMM K 20 jrs Mar 11/05/21 Jeu 10/06/21 IMM K


260 IMM J 20 jrs Jeu 10/06/21 Mar 13/07/21 IMM J
261 IMM I 15 jrs Mar 13/07/21 Mer 04/08/21 IMM I
262 IMM H 20 jrs Jeu 05/08/21 Lun 06/09/21 IMM H
263 ZONE 2 50 jrs Mar 11/05/21 Mer 28/07/21

264 IMM G 18 jrs Mar 11/05/21 Mar 08/06/21 IMM G


265 IMM F 16 jrs Mar 08/06/21 Ven 02/07/21 IMM F
266 IMM E 16 jrs Ven 02/07/21 Mer 28/07/21 IMM E
267 ZONE 3 76 jrs Mar 13/07/21 Mar 09/11/21

268 IMM D 20 jrs Mar 13/07/21 Jeu 12/08/21 IMM D


269 IMM C 16 jrs Jeu 12/08/21 Mar 07/09/21 IMM C
270 IMM B 20 jrs Mar 07/09/21 Ven 08/10/21

271 IMM A 20 jrs Ven 08/10/21 Mar 09/11/21

272 FLUIDE 306 jrs Ven 19/03/21 Jeu 14/07/22

273 ZONE 1 241 jrs Mer 24/03/21 Jeu 07/04/22

274 IMM K 153 jrs Mer 24/03/21 Ven 19/11/21

275 RDC 141 jrs Mer 24/03/21 Lun 01/11/21

276 Alimentation et 3 jrs Mer 24/03/21 Lun 29/03/21 Alimentation et Evacuation


Evacuation

277 Appareils sanitaires4 jrs Mar 26/10/21 Lun 01/11/21

278 1er étage 135 jrs Jeu 08/04/21 Lun 08/11/21

279 Alimentation et 3 jrs Jeu 08/04/21 Mar 13/04/21 Alimentation et Evacuation


Evacuation

280 Appareils sanitaires4 jrs Mar 02/11/21 Lun 08/11/21

281 2eme étage 129 jrs Ven 23/04/21 Ven 12/11/21

282 Alimentation et 3 jrs Ven 23/04/21 Jeu 29/04/21 Alimentation et Evacuation


Evacuation

283 Appareils sanitaires4 jrs Lun 08/11/21 Ven 12/11/21

284 3eme étage 123 jrs Mar 11/05/21 Ven 19/11/21

285 Alimentation et 3 jrs Mar 11/05/21 Ven 14/05/21 Alimentation et Evacuation


Evacuation

286 Appareils sanitaires4 jrs Lun 15/11/21 Ven 19/11/21

287 IMM J 170 jrs Mer 14/04/21 Jeu 06/01/22

288 RDC 158 jrs Mer 14/04/21 Ven 17/12/21

289 Alimentation et 3 jrs Mer 14/04/21 Lun 19/04/21 Alimentation et Evacuation


Evacuation

290 Appareils sanitaires4 jrs Lun 13/12/21 Ven 17/12/21

291 1er étage 152 jrs Jeu 29/04/21 Ven 24/12/21

292 Alimentation et 3 jrs Jeu 29/04/21 Mar 04/05/21 Alimentation et Evacuation


Evacuation

293 Appareils sanitaires4 jrs Ven 17/12/21 Ven 24/12/21

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 7
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
294 2eme étage 146 jrs Ven 14/05/21 Jeu 30/12/21

295 Alimentation et 3 jrs Ven 14/05/21 Mer 19/05/21 Alimentation et Evacuation


Evacuation

296 Appareils sanitaires4 jrs Ven 24/12/21 Jeu 30/12/21

297 3eme étage 140 jrs Lun 31/05/21 Jeu 06/01/22

298 Alimentation et 3 jrs Lun 31/05/21 Ven 04/06/21 Alimentation et Evacuation


Evacuation

299 Appareils sanitaires4 jrs Jeu 30/12/21 Jeu 06/01/22

300 IMM I 182 jrs Lun 10/05/21 Ven 18/02/22

301 RDC 170 jrs Lun 10/05/21 Mar 01/02/22

302 Alimentation et 3 jrs Lun 10/05/21 Jeu 13/05/21 Alimentation et Evacuation


Evacuation

303 Appareils sanitaires4 jrs Mar 25/01/22 Mar 01/02/22

304 1er étage 164 jrs Mar 25/05/21 Lun 07/02/22

305 Alimentation et 3 jrs Mar 25/05/21 Ven 28/05/21 Alimentation et Evacuation


Evacuation

306 Appareils sanitaires4 jrs Mar 01/02/22 Lun 07/02/22

307 2eme étage 158 jrs Mer 09/06/21 Lun 14/02/22

308 Alimentation et 3 jrs Mer 09/06/21 Lun 14/06/21 Alimentation et Evacuation


Evacuation

309 Appareils sanitaires4 jrs Lun 07/02/22 Lun 14/02/22

310 3eme étage 145 jrs Mar 06/07/21 Ven 18/02/22

311 Alimentation et 3 jrs Mar 06/07/21 Ven 09/07/21 Alimentation et Evacuation


Evacuation

312 Appareils sanitaires4 jrs Lun 14/02/22 Ven 18/02/22

313 IMM H 205 jrs Mer 19/05/21 Jeu 07/04/22

314 RDC 193 jrs Mer 19/05/21 Ven 18/03/22

315 Alimentation et 3 jrs Mer 19/05/21 Mar 25/05/21 Alimentation et Evacuation


Evacuation

316 Appareils sanitaires4 jrs Lun 14/03/22 Ven 18/03/22

317 1er étage 187 jrs Ven 04/06/21 Ven 25/03/22

318 Alimentation et 3 jrs Ven 04/06/21 Mer 09/06/21 Alimentation et Evacuation


Evacuation

319 Appareils sanitaires4 jrs Lun 21/03/22 Ven 25/03/22

320 2eme étage 181 jrs Lun 21/06/21 Jeu 31/03/22

321 Alimentation et 3 jrs Lun 21/06/21 Jeu 24/06/21 Alimentation et Evacuation


Evacuation

322 Appareils sanitaires4 jrs Ven 25/03/22 Jeu 31/03/22

323 3eme étage 175 jrs Mar 06/07/21 Jeu 07/04/22

324 Alimentation et 3 jrs Mar 06/07/21 Ven 09/07/21 Alimentation et Evacuation


Evacuation

325 Appareils sanitaires4 jrs Ven 01/04/22 Jeu 07/04/22

326 ZONE 2 257 jrs Ven 19/03/21 Jeu 28/04/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 8
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
327 IMM G 205 jrs Mer 24/03/21 Mer 09/02/22

328 RDC 193 jrs Mer 24/03/21 Ven 21/01/22

329 Alimentation et 3 jrs Mer 24/03/21 Lun 29/03/21 Alimentation et Evacuation


Evacuation

330 Appareils sanitaires4 jrs Lun 17/01/22 Ven 21/01/22

331 1er étage 187 jrs Jeu 08/04/21 Jeu 27/01/22

332 Alimentation et 3 jrs Jeu 08/04/21 Mar 13/04/21 Alimentation et Evacuation


Evacuation

333 Appareils sanitaires4 jrs Ven 21/01/22 Jeu 27/01/22

334 2eme étage 181 jrs Ven 23/04/21 Jeu 03/02/22

335 Alimentation et 3 jrs Ven 23/04/21 Jeu 29/04/21 Alimentation et Evacuation


Evacuation

336 Appareils sanitaires4 jrs Ven 28/01/22 Jeu 03/02/22

337 3eme étage 175 jrs Mar 11/05/21 Mer 09/02/22

338 Alimentation et 3 jrs Mar 11/05/21 Ven 14/05/21 Alimentation et Evacuation


Evacuation

339 Appareils sanitaires4 jrs Jeu 03/02/22 Mer 09/02/22

340 IMM F 236 jrs Ven 19/03/21 Ven 25/03/22

341 RDC 224 jrs Ven 19/03/21 Lun 07/03/22

342 Alimentation et 3 jrs Ven 19/03/21 Mer 24/03/21 Alimentation et Evacuation


Evacuation

343 Appareils sanitaires4 jrs Mar 01/03/22 Lun 07/03/22

344 1er étage 218 jrs Lun 05/04/21 Lun 14/03/22

345 Alimentation et 3 jrs Lun 05/04/21 Jeu 08/04/21 Alimentation et Evacuation


Evacuation

346 Appareils sanitaires4 jrs Mar 08/03/22 Lun 14/03/22

347 2eme étage 212 jrs Mar 20/04/21 Ven 18/03/22

348 Alimentation et 3 jrs Mar 20/04/21 Ven 23/04/21 Alimentation et Evacuation


Evacuation

349 Appareils sanitaires4 jrs Lun 14/03/22 Ven 18/03/22

350 3eme étage 206 jrs Mer 05/05/21 Ven 25/03/22

351 Alimentation et 3 jrs Mer 05/05/21 Mar 11/05/21 Alimentation et Evacuation


Evacuation

352 Appareils sanitaires4 jrs Lun 21/03/22 Ven 25/03/22

353 IMM E 236 jrs Mer 21/04/21 Jeu 28/04/22

354 RDC 224 jrs Mer 21/04/21 Ven 08/04/22

355 Alimentation et 3 jrs Mer 21/04/21 Lun 26/04/21 Alimentation et Evacuation


Evacuation

356 Appareils sanitaires4 jrs Lun 04/04/22 Ven 08/04/22

357 1er étage 218 jrs Jeu 06/05/21 Ven 15/04/22

358 Alimentation et 3 jrs Jeu 06/05/21 Mer 12/05/21 Alimentation et Evacuation


Evacuation

359 Appareils sanitaires4 jrs Ven 08/04/22 Ven 15/04/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 9
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
360 2eme étage 212 jrs Lun 24/05/21 Jeu 21/04/22

361 Alimentation et 3 jrs Lun 24/05/21 Jeu 27/05/21 Alimentation et Evacuation


Evacuation

362 Appareils sanitaires4 jrs Ven 15/04/22 Jeu 21/04/22

363 3eme étage 206 jrs Mar 08/06/21 Jeu 28/04/22

364 Alimentation et 3 jrs Mar 08/06/21 Ven 11/06/21 Alimentation et Evacuation


Evacuation

365 Appareils sanitaires4 jrs Jeu 21/04/22 Jeu 28/04/22

366 ZONE 3 288 jrs Ven 16/04/21 Jeu 14/07/22

367 IMM D 173 jrs Mer 26/05/21 Mar 22/02/22

368 RDC 161 jrs Mer 26/05/21 Jeu 03/02/22

369 Alimentation et 3 jrs Mer 26/05/21 Lun 31/05/21 Alimentation et Evacuation


Evacuation

370 Appareils sanitaires4 jrs Ven 28/01/22 Jeu 03/02/22

371 1er étage 155 jrs Jeu 10/06/21 Mer 09/02/22

372 Alimentation et 3 jrs Jeu 10/06/21 Mar 15/06/21 Alimentation et Evacuation


Evacuation

373 Appareils sanitaires4 jrs Jeu 03/02/22 Mer 09/02/22

374 2eme étage 149 jrs Ven 25/06/21 Mer 16/02/22

375 Alimentation et 3 jrs Ven 25/06/21 Jeu 01/07/21 Alimentation et Evacuation


Evacuation

376 Appareils sanitaires4 jrs Jeu 10/02/22 Mer 16/02/22

377 3eme étage 143 jrs Mar 13/07/21 Mar 22/02/22

378 Alimentation et 3 jrs Mar 13/07/21 Ven 16/07/21 Alimentation et Evacuation


Evacuation

379 Appareils sanitaires4 jrs Mer 16/02/22 Mar 22/02/22

380 IMM C 227 jrs Ven 16/04/21 Ven 08/04/22

381 RDC 215 jrs Ven 16/04/21 Mar 22/03/22

382 Alimentation et 3 jrs Ven 16/04/21 Mer 21/04/21 Alimentation et Evacuation


Evacuation

383 Appareils sanitaires4 jrs Mar 15/03/22 Mar 22/03/22

384 1er étage 210 jrs Ven 30/04/21 Lun 28/03/22

385 Alimentation et 3 jrs Ven 30/04/21 Mer 05/05/21 Alimentation et Evacuation


Evacuation

386 Appareils sanitaires4 jrs Mar 22/03/22 Lun 28/03/22

387 2eme étage 205 jrs Ven 14/05/21 Lun 04/04/22

388 Alimentation et 3 jrs Ven 14/05/21 Mer 19/05/21 Alimentation et Evacuation


Evacuation

389 Appareils sanitaires4 jrs Lun 28/03/22 Lun 04/04/22

390 3eme étage 200 jrs Ven 28/05/21 Ven 08/04/22

391 Alimentation et 3 jrs Ven 28/05/21 Mer 02/06/21 Alimentation et Evacuation


Evacuation

392 Appareils sanitaires4 jrs Lun 04/04/22 Ven 08/04/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 10
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
393 IMM B 241 jrs Jeu 13/05/21 Ven 27/05/22

394 RDC 229 jrs Jeu 13/05/21 Lun 09/05/22

395 Alimentation et 3 jrs Jeu 13/05/21 Mar 18/05/21 Alimentation et Evacuation


Evacuation

396 Appareils sanitaires4 jrs Mar 03/05/22 Lun 09/05/22

397 1er étage 223 jrs Ven 28/05/21 Lun 16/05/22

398 Alimentation et 3 jrs Ven 28/05/21 Mer 02/06/21 Alimentation et Evacuation


Evacuation

399 Appareils sanitaires4 jrs Mar 10/05/22 Lun 16/05/22

400 2eme étage 217 jrs Lun 14/06/21 Ven 20/05/22

401 Alimentation et 3 jrs Lun 14/06/21 Ven 18/06/21 Alimentation et Evacuation


Evacuation

402 Appareils sanitaires4 jrs Lun 16/05/22 Ven 20/05/22

403 3eme étage 211 jrs Mer 30/06/21 Ven 27/05/22

404 Alimentation et 3 jrs Mer 30/06/21 Lun 05/07/21 Alimentation et Evacuation


Evacuation

405 Appareils sanitaires4 jrs Lun 23/05/22 Ven 27/05/22

406 IMM A 259 jrs Mar 01/06/21 Jeu 14/07/22

407 RDC 247 jrs Mar 01/06/21 Ven 24/06/22

408 Alimentation et 3 jrs Mar 01/06/21 Lun 07/06/21 Alimentation et Evacuation


Evacuation

409 Appareils sanitaires4 jrs Lun 20/06/22 Ven 24/06/22

410 1er étage 241 jrs Jeu 17/06/21 Ven 01/07/22

411 Alimentation et 3 jrs Jeu 17/06/21 Mar 22/06/21 Alimentation et Evacuation


Evacuation

412 Appareils sanitaires4 jrs Ven 24/06/22 Ven 01/07/22

413 2eme étage 235 jrs Ven 02/07/21 Jeu 07/07/22

414 Alimentation et 3 jrs Ven 02/07/21 Mer 07/07/21 Alimentation et Evacuation


Evacuation

415 Appareils sanitaires4 jrs Ven 01/07/22 Jeu 07/07/22

416 3eme étage 229 jrs Lun 19/07/21 Jeu 14/07/22

417 Alimentation et 3 jrs Lun 19/07/21 Jeu 22/07/21 Alimentation et Evacuation


Evacuation

418 Appareils sanitaires4 jrs Jeu 07/07/22 Jeu 14/07/22

419 ELECTRICITE 306 jrs Ven 19/03/21 Jeu 14/07/22

420 ZONE 3 241 jrs Mer 24/03/21 Jeu 07/04/22

421 IMM K 153 jrs Mer 24/03/21 Ven 19/11/21

422 RDC 141 jrs Mer 24/03/21 Lun 01/11/21

423 pose de tubage 3 jrs Mer 24/03/21 Lun 29/03/21 pose de tubage éléctrique
éléctrique

424 Tirage filerie 2 jrs Jeu 27/05/21 Lun 31/05/21 Tirage filerie
425 Pose appareillage 4 jrs Mar 26/10/21 Lun 01/11/21
et lustrerie

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 11
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
426 1er étage 135 jrs Jeu 08/04/21 Lun 08/11/21

427 pose de tubage 3 jrs Jeu 08/04/21 Mar 13/04/21 pose de tubage éléctrique
éléctrique

428 Tirage filerie 2 jrs Lun 31/05/21 Mer 02/06/21 Tirage filerie
429 Pose appareillage 4 jrs Mar 02/11/21 Lun 08/11/21
et lustrerie

430 2eme étage 129 jrs Ven 23/04/21 Ven 12/11/21

431 pose de tubage 3 jrs Ven 23/04/21 Jeu 29/04/21 pose de tubage éléctrique
éléctrique

432 Tirage filerie 2 jrs Jeu 03/06/21 Lun 07/06/21 Tirage filerie
433 Pose appareillage 4 jrs Lun 08/11/21 Ven 12/11/21
et lustrerie

434 3eme étage 123 jrs Mar 11/05/21 Ven 19/11/21

435 pose de tubage 3 jrs Mar 11/05/21 Ven 14/05/21 pose de tubage éléctrique
éléctrique

436 Tirage filerie 2 jrs Lun 07/06/21 Mer 09/06/21 Tirage filerie
437 Pose appareillage 4 jrs Lun 15/11/21 Ven 19/11/21
et lustrerie

438 IMM J 170 jrs Mer 14/04/21 Jeu 06/01/22

439 RDC 158 jrs Mer 14/04/21 Ven 17/12/21

440 pose de tubage 3 jrs Mer 14/04/21 Lun 19/04/21 pose de tubage éléctrique
éléctrique

441 Tirage filerie 2 jrs Mer 09/06/21 Ven 11/06/21 Tirage filerie
442 Pose appareillage 4 jrs Lun 13/12/21 Ven 17/12/21
et lustrerie

443 1er étage 152 jrs Jeu 29/04/21 Ven 24/12/21

444 pose de tubage 3 jrs Jeu 29/04/21 Mar 04/05/21 pose de tubage éléctrique
éléctrique

445 Tirage filerie 2 jrs Ven 11/06/21 Mar 15/06/21 Tirage filerie
446 Pose appareillage 4 jrs Ven 17/12/21 Ven 24/12/21
et lustrerie

447 2eme étage 146 jrs Ven 14/05/21 Jeu 30/12/21

448 pose de tubage 3 jrs Ven 14/05/21 Mer 19/05/21 pose de tubage éléctrique
éléctrique

449 Tirage filerie 2 jrs Mer 16/06/21 Ven 18/06/21 Tirage filerie
450 Pose appareillage 4 jrs Ven 24/12/21 Jeu 30/12/21
et lustrerie

451 3eme étage 140 jrs Lun 31/05/21 Jeu 06/01/22

452 pose de tubage 3 jrs Lun 31/05/21 Ven 04/06/21 pose de tubage éléctrique
éléctrique

453 Tirage filerie 2 jrs Ven 18/06/21 Mar 22/06/21 Tirage filerie
454 Pose appareillage 4 jrs Jeu 30/12/21 Jeu 06/01/22
et lustrerie

455 IMM I 182 jrs Lun 10/05/21 Ven 18/02/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 12
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
456 RDC 170 jrs Lun 10/05/21 Mar 01/02/22

457 pose de tubage 3 jrs Lun 10/05/21 Jeu 13/05/21 pose de tubage éléctrique
éléctrique

458 Tirage filerie 2 jrs Mar 22/06/21 Jeu 24/06/21 Tirage filerie
459 Pose appareillage 4 jrs Mar 25/01/22 Mar 01/02/22
et lustrerie

460 1er étage 164 jrs Mar 25/05/21 Lun 07/02/22

461 pose de tubage 3 jrs Mar 25/05/21 Ven 28/05/21 pose de tubage éléctrique
éléctrique

462 Tirage filerie 2 jrs Jeu 24/06/21 Lun 28/06/21 Tirage filerie
463 Pose appareillage 4 jrs Mar 01/02/22 Lun 07/02/22
et lustrerie

464 2eme étage 158 jrs Mer 09/06/21 Lun 14/02/22

465 pose de tubage 3 jrs Mer 09/06/21 Lun 14/06/21 pose de tubage éléctrique
éléctrique

466 Tirage filerie 2 jrs Mar 29/06/21 Jeu 01/07/21 Tirage filerie
467 Pose appareillage 4 jrs Lun 07/02/22 Lun 14/02/22
et lustrerie

468 3eme étage 148 jrs Jeu 01/07/21 Ven 18/02/22

469 pose de tubage 3 jrs Mar 06/07/21 Ven 09/07/21 pose de tubage éléctrique
éléctrique

470 Tirage filerie 2 jrs Jeu 01/07/21 Lun 05/07/21 Tirage filerie
471 Pose appareillage 4 jrs Lun 14/02/22 Ven 18/02/22
et lustrerie

472 IMM H 205 jrs Mer 19/05/21 Jeu 07/04/22

473 RDC 193 jrs Mer 19/05/21 Ven 18/03/22

474 pose de tubage 3 jrs Mer 19/05/21 Mar 25/05/21 pose de tubage éléctrique
éléctrique

475 Tirage filerie 2 jrs Mar 28/09/21 Jeu 30/09/21

476 Pose appareillage 4 jrs Lun 14/03/22 Ven 18/03/22


et lustrerie

477 1er étage 187 jrs Ven 04/06/21 Ven 25/03/22

478 pose de tubage 3 jrs Ven 04/06/21 Mer 09/06/21 pose de tubage éléctrique
éléctrique

479 Tirage filerie 2 jrs Jeu 30/09/21 Lun 04/10/21

480 Pose appareillage 4 jrs Lun 21/03/22 Ven 25/03/22


et lustrerie

481 2eme étage 181 jrs Lun 21/06/21 Jeu 31/03/22

482 pose de tubage 3 jrs Lun 21/06/21 Jeu 24/06/21 pose de tubage éléctrique
éléctrique

483 Tirage filerie 2 jrs Lun 04/10/21 Mer 06/10/21

484 Pose appareillage 4 jrs Ven 25/03/22 Jeu 31/03/22


et lustrerie

485 3eme étage 175 jrs Mar 06/07/21 Jeu 07/04/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 13
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
486 pose de tubage 3 jrs Mar 06/07/21 Ven 09/07/21 pose de tubage éléctrique
éléctrique

487 Tirage filerie 2 jrs Jeu 07/10/21 Lun 11/10/21

488 Pose appareillage 4 jrs Ven 01/04/22 Jeu 07/04/22


et lustrerie

489 ZONE 3 257 jrs Ven 19/03/21 Jeu 28/04/22

490 IMM G 205 jrs Mer 24/03/21 Mer 09/02/22

491 RDC 193 jrs Mer 24/03/21 Ven 21/01/22

492 pose de tubage 3 jrs Mer 24/03/21 Lun 29/03/21 pose de tubage éléctrique
éléctrique

493 Tirage filerie 2 jrs Jeu 30/09/21 Lun 04/10/21

494 Pose appareillage 4 jrs Lun 17/01/22 Ven 21/01/22


et lustrerie

495 1er étage 187 jrs Jeu 08/04/21 Jeu 27/01/22

496 pose de tubage 3 jrs Jeu 08/04/21 Mar 13/04/21 pose de tubage éléctrique
éléctrique

497 Tirage filerie 2 jrs Lun 04/10/21 Mer 06/10/21

498 Pose appareillage 4 jrs Ven 21/01/22 Jeu 27/01/22


et lustrerie

499 2eme étage 181 jrs Ven 23/04/21 Jeu 03/02/22

500 pose de tubage 3 jrs Ven 23/04/21 Jeu 29/04/21 pose de tubage éléctrique
éléctrique

501 Tirage filerie 2 jrs Jeu 07/10/21 Lun 11/10/21

502 Pose appareillage 4 jrs Ven 28/01/22 Jeu 03/02/22


et lustrerie

503 3eme étage 175 jrs Mar 11/05/21 Mer 09/02/22

504 pose de tubage 3 jrs Mar 11/05/21 Ven 14/05/21 pose de tubage éléctrique
éléctrique

505 Tirage filerie 2 jrs Lun 11/10/21 Mer 13/10/21

506 Pose appareillage 4 jrs Jeu 03/02/22 Mer 09/02/22


et lustrerie

507 IMM F 232 jrs Ven 19/03/21 Ven 18/03/22

508 RDC 224 jrs Ven 19/03/21 Lun 07/03/22

509 pose de tubage 3 jrs Ven 19/03/21 Mer 24/03/21 pose de tubage éléctrique
éléctrique

510 Tirage filerie 2 jrs Mer 13/10/21 Ven 15/10/21

511 Pose appareillage 4 jrs Mar 01/03/22 Lun 07/03/22


et lustrerie

512 1er étage 218 jrs Lun 05/04/21 Lun 14/03/22

513 pose de tubage 3 jrs Lun 05/04/21 Jeu 08/04/21 pose de tubage éléctrique
éléctrique

514 Tirage filerie 2 jrs Ven 15/10/21 Mar 19/10/21

515 Pose appareillage 4 jrs Mar 08/03/22 Lun 14/03/22


et lustrerie

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 14
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
516 2eme étage 212 jrs Mar 20/04/21 Ven 18/03/22

517 pose de tubage 3 jrs Mar 20/04/21 Ven 23/04/21 pose de tubage éléctrique
éléctrique

518 Tirage filerie 2 jrs Mer 20/10/21 Ven 22/10/21

519 Pose appareillage 4 jrs Lun 14/03/22 Ven 18/03/22


et lustrerie

520 3eme étage 194 jrs Mer 05/05/21 Lun 07/03/22

521 pose de tubage 3 jrs Mer 05/05/21 Mar 11/05/21 pose de tubage éléctrique
éléctrique

522 Tirage filerie 2 jrs Ven 22/10/21 Mar 26/10/21

523 Pose appareillage 4 jrs Mar 01/03/22 Lun 07/03/22


et lustrerie

524 IMM E 236 jrs Mer 21/04/21 Jeu 28/04/22

525 RDC 224 jrs Mer 21/04/21 Ven 08/04/22

526 pose de tubage 3 jrs Mer 21/04/21 Lun 26/04/21 pose de tubage éléctrique
éléctrique

527 Tirage filerie 2 jrs Mar 26/10/21 Jeu 28/10/21

528 Pose appareillage 4 jrs Lun 04/04/22 Ven 08/04/22


et lustrerie

529 1er étage 218 jrs Jeu 06/05/21 Ven 15/04/22

530 pose de tubage 3 jrs Jeu 06/05/21 Mer 12/05/21 pose de tubage éléctrique
éléctrique

531 Tirage filerie 2 jrs Jeu 28/10/21 Lun 01/11/21

532 Pose appareillage 4 jrs Ven 08/04/22 Ven 15/04/22


et lustrerie

533 2eme étage 212 jrs Lun 24/05/21 Jeu 21/04/22

534 pose de tubage 3 jrs Lun 24/05/21 Jeu 27/05/21 pose de tubage éléctrique
éléctrique

535 Tirage filerie 2 jrs Mar 02/11/21 Jeu 04/11/21

536 Pose appareillage 4 jrs Ven 15/04/22 Jeu 21/04/22


et lustrerie

537 3eme étage 206 jrs Mar 08/06/21 Jeu 28/04/22

538 pose de tubage 3 jrs Mar 08/06/21 Ven 11/06/21 pose de tubage éléctrique
éléctrique

539 Tirage filerie 2 jrs Jeu 04/11/21 Lun 08/11/21

540 Pose appareillage 4 jrs Jeu 21/04/22 Jeu 28/04/22


et lustrerie

541 ZONE 3 288 jrs Ven 16/04/21 Jeu 14/07/22

542 IMM D 173 jrs Mer 26/05/21 Mar 22/02/22

543 RDC 161 jrs Mer 26/05/21 Jeu 03/02/22

544 pose de tubage 3 jrs Mer 26/05/21 Lun 31/05/21 pose de tubage éléctrique
éléctrique

545 Tirage filerie 2 jrs Ven 24/09/21 Mar 28/09/21 Tirage file

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 15
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
546 Pose appareillage 4 jrs Ven 28/01/22 Jeu 03/02/22
et lustrerie

547 1er étage 155 jrs Jeu 10/06/21 Mer 09/02/22

548 pose de tubage 3 jrs Jeu 10/06/21 Mar 15/06/21 pose de tubage éléctrique
éléctrique

549 Tirage filerie 2 jrs Mar 28/09/21 Jeu 30/09/21

550 Pose appareillage 4 jrs Jeu 03/02/22 Mer 09/02/22


et lustrerie

551 2eme étage 149 jrs Ven 25/06/21 Mer 16/02/22

552 pose de tubage 3 jrs Ven 25/06/21 Jeu 01/07/21 pose de tubage éléctrique
éléctrique

553 Tirage filerie 2 jrs Jeu 30/09/21 Lun 04/10/21

554 Pose appareillage 4 jrs Jeu 10/02/22 Mer 16/02/22


et lustrerie

555 3eme étage 143 jrs Mar 13/07/21 Mar 22/02/22

556 pose de tubage 3 jrs Mar 13/07/21 Ven 16/07/21 pose de tubage éléctrique
éléctrique

557 Tirage filerie 2 jrs Lun 04/10/21 Mer 06/10/21

558 Pose appareillage 4 jrs Mer 16/02/22 Mar 22/02/22


et lustrerie

559 IMM C 227 jrs Ven 16/04/21 Ven 08/04/22

560 RDC 215 jrs Ven 16/04/21 Mar 22/03/22

561 pose de tubage 3 jrs Ven 16/04/21 Mer 21/04/21 pose de tubage éléctrique
éléctrique

562 Tirage filerie 2 jrs Jeu 07/10/21 Lun 11/10/21

563 Pose appareillage 4 jrs Mar 15/03/22 Mar 22/03/22


et lustrerie

564 1er étage 210 jrs Ven 30/04/21 Lun 28/03/22

565 pose de tubage 3 jrs Ven 30/04/21 Mer 05/05/21 pose de tubage éléctrique
éléctrique

566 Tirage filerie 2 jrs Lun 11/10/21 Mer 13/10/21

567 Pose appareillage 4 jrs Mar 22/03/22 Lun 28/03/22


et lustrerie

568 2eme étage 205 jrs Ven 14/05/21 Lun 04/04/22

569 pose de tubage 3 jrs Ven 14/05/21 Mer 19/05/21 pose de tubage éléctrique
éléctrique

570 Tirage filerie 2 jrs Mer 13/10/21 Ven 15/10/21

571 Pose appareillage 4 jrs Lun 28/03/22 Lun 04/04/22


et lustrerie

572 3eme étage 200 jrs Ven 28/05/21 Ven 08/04/22

573 pose de tubage 3 jrs Ven 28/05/21 Mer 02/06/21 pose de tubage éléctrique
éléctrique

574 Tirage filerie 2 jrs Ven 15/10/21 Mar 19/10/21

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 16
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
575 Pose appareillage 4 jrs Lun 04/04/22 Ven 08/04/22
et lustrerie

576 IMM B 241 jrs Jeu 13/05/21 Ven 27/05/22

577 RDC 229 jrs Jeu 13/05/21 Lun 09/05/22

578 pose de tubage 3 jrs Jeu 13/05/21 Mar 18/05/21 pose de tubage éléctrique
éléctrique

579 Tirage filerie 2 jrs Mer 20/10/21 Ven 22/10/21

580 Pose appareillage 4 jrs Mar 03/05/22 Lun 09/05/22


et lustrerie

581 1er étage 223 jrs Ven 28/05/21 Lun 16/05/22

582 pose de tubage 3 jrs Ven 28/05/21 Mer 02/06/21 pose de tubage éléctrique
éléctrique

583 Tirage filerie 2 jrs Ven 22/10/21 Mar 26/10/21

584 Pose appareillage 4 jrs Mar 10/05/22 Lun 16/05/22


et lustrerie

585 2eme étage 217 jrs Lun 14/06/21 Ven 20/05/22

586 pose de tubage 3 jrs Lun 14/06/21 Ven 18/06/21 pose de tubage éléctrique
éléctrique

587 Tirage filerie 2 jrs Mar 26/10/21 Jeu 28/10/21

588 Pose appareillage 4 jrs Lun 16/05/22 Ven 20/05/22


et lustrerie

589 3eme étage 211 jrs Mer 30/06/21 Ven 27/05/22

590 pose de tubage 3 jrs Mer 30/06/21 Lun 05/07/21 pose de tubage éléctrique
éléctrique

591 Tirage filerie 2 jrs Jeu 28/10/21 Lun 01/11/21

592 Pose appareillage 4 jrs Lun 23/05/22 Ven 27/05/22


et lustrerie

593 IMM A 259 jrs Mar 01/06/21 Jeu 14/07/22

594 RDC 247 jrs Mar 01/06/21 Ven 24/06/22

595 pose de tubage 3 jrs Mar 01/06/21 Lun 07/06/21 pose de tubage éléctrique
éléctrique

596 Tirage filerie 2 jrs Mar 02/11/21 Jeu 04/11/21

597 Pose appareillage 4 jrs Lun 20/06/22 Ven 24/06/22


et lustrerie

598 1er étage 241 jrs Jeu 17/06/21 Ven 01/07/22

599 pose de tubage 3 jrs Jeu 17/06/21 Mar 22/06/21 pose de tubage éléctrique
éléctrique

600 Tirage filerie 2 jrs Jeu 04/11/21 Lun 08/11/21

601 Pose appareillage 4 jrs Ven 24/06/22 Ven 01/07/22


et lustrerie

602 2eme étage 235 jrs Ven 02/07/21 Jeu 07/07/22

603 pose de tubage 3 jrs Ven 02/07/21 Mer 07/07/21 pose de tubage éléctrique
éléctrique

604 Tirage filerie 2 jrs Lun 08/11/21 Mer 10/11/21

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 17
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
605 Pose appareillage 4 jrs Ven 01/07/22 Jeu 07/07/22
et lustrerie

606 3eme étage 229 jrs Lun 19/07/21 Jeu 14/07/22

607 pose de tubage 3 jrs Lun 19/07/21 Jeu 22/07/21 pose de tubage éléctrique
éléctrique

608 Tirage filerie 2 jrs Mer 10/11/21 Ven 12/11/21

609 Pose appareillage 4 jrs Jeu 07/07/22 Jeu 14/07/22


et lustrerie

610 FAUX PLAFOND 148 jrs Mar 20/04/21 Mer 08/12/21

611 ZONE 3 108 jrs Mar 20/04/21 Mer 06/10/21

612 IMM K 28 jrs Mar 20/04/21 Mer 02/06/21

613 RDC 7 jrs Mar 20/04/21 Ven 30/04/21 RDC


614 1 ér étage 7 jrs Ven 30/04/21 Mer 12/05/21 1 ér étage
615 2 ème étage 7 jrs Mer 12/05/21 Lun 24/05/21 2 ème étage
616 3 ème étage 7 jrs Lun 24/05/21 Mer 02/06/21 3 ème étage
617 IMM J 28 jrs Jeu 03/06/21 Ven 16/07/21

618 RDC 7 jrs Jeu 03/06/21 Lun 14/06/21 RDC


619 1 ér étage 7 jrs Lun 14/06/21 Jeu 24/06/21 1 ér étage
620 2 ème étage 7 jrs Jeu 24/06/21 Mar 06/07/21 2 ème étage
621 3 ème étage 7 jrs Mar 06/07/21 Ven 16/07/21 3 ème étage
622 IMM I 24 jrs Ven 16/07/21 Mar 24/08/21

623 RDC 6 jrs Ven 16/07/21 Mar 27/07/21 RDC


624 1 ér étage 6 jrs Mar 27/07/21 Mer 04/08/21 1 ér étage
625 2 ème étage 6 jrs Jeu 05/08/21 Ven 13/08/21 2 ème étage
626 3 ème étage 6 jrs Ven 13/08/21 Mar 24/08/21 3 ème étage
627 IMM H 28 jrs Mar 24/08/21 Mer 06/10/21

628 RDC 7 jrs Mar 24/08/21 Ven 03/09/21 RDC


629 1 ér étage 7 jrs Ven 03/09/21 Mer 15/09/21 1 ér étage
630 2 ème étage 7 jrs Mer 15/09/21 Lun 27/09/21 2 ème éta
631 3 ème étage 7 jrs Lun 27/09/21 Mer 06/10/21

632 ZONE 3 72 jrs Ven 23/07/21 Ven 12/11/21

633 IMM G 28 jrs Ven 23/07/21 Lun 06/09/21

634 RDC 7 jrs Ven 23/07/21 Mar 03/08/21 RDC


635 1 ér étage 7 jrs Mar 03/08/21 Ven 13/08/21 1 ér étage
636 2 ème étage 7 jrs Ven 13/08/21 Mer 25/08/21 2 ème étage
637 3 ème étage 7 jrs Mer 25/08/21 Lun 06/09/21 3 ème étage
638 IMM F 24 jrs Lun 06/09/21 Mer 13/10/21

639 RDC 6 jrs Lun 06/09/21 Mer 15/09/21 RDC


640 1 ér étage 6 jrs Mer 15/09/21 Jeu 23/09/21 1 ér étage
641 2 ème étage 6 jrs Ven 24/09/21 Lun 04/10/21

642 3 ème étage 6 jrs Lun 04/10/21 Mer 13/10/21

643 IMM E 20 jrs Mer 13/10/21 Ven 12/11/21

644 RDC 5 jrs Mer 13/10/21 Jeu 21/10/21

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 18
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
645 1 ér étage 5 jrs Jeu 21/10/21 Jeu 28/10/21

646 2 ème étage 5 jrs Jeu 28/10/21 Ven 05/11/21

647 3 ème étage 5 jrs Ven 05/11/21 Ven 12/11/21

648 ZONE 3 108 jrs Mar 22/06/21 Mer 08/12/21

649 IMM D 28 jrs Mar 22/06/21 Mer 04/08/21

650 RDC 7 jrs Mar 22/06/21 Ven 02/07/21 RDC


651 1 ér étage 7 jrs Ven 02/07/21 Mer 14/07/21 1 ér étage
652 2 ème étage 7 jrs Mer 14/07/21 Lun 26/07/21 2 ème étage
653 3 ème étage 7 jrs Lun 26/07/21 Mer 04/08/21 3 ème étage
654 IMM C 28 jrs Jeu 05/08/21 Ven 17/09/21

655 RDC 7 jrs Jeu 05/08/21 Lun 16/08/21 RDC


656 1 ér étage 7 jrs Lun 16/08/21 Jeu 26/08/21 1 ér étage
657 2 ème étage 7 jrs Jeu 26/08/21 Mar 07/09/21 2 ème étage
658 3 ème étage 7 jrs Mar 07/09/21 Ven 17/09/21 3 ème étag
659 IMM B 28 jrs Ven 17/09/21 Lun 01/11/21

660 RDC 7 jrs Ven 17/09/21 Mer 29/09/21

661 1 ér étage 7 jrs Mer 29/09/21 Lun 11/10/21

662 2 ème étage 7 jrs Lun 11/10/21 Jeu 21/10/21

663 3 ème étage 7 jrs Jeu 21/10/21 Lun 01/11/21

664 IMM A 24 jrs Mar 02/11/21 Mer 08/12/21

665 RDC 6 jrs Mar 02/11/21 Mer 10/11/21

666 1 ér étage 6 jrs Mer 10/11/21 Ven 19/11/21

667 2 ème étage 6 jrs Ven 19/11/21 Mar 30/11/21

668 3 ème étage 6 jrs Mar 30/11/21 Mer 08/12/21

669 ETANCHIETE 165 jrs Ven 26/03/21 Lun 13/12/21

670 ZONE 1 104 jrs Ven 26/03/21 Mar 07/09/21

671 IMM K 80 jrs Ven 26/03/21 Ven 30/07/21

672 étanchieté des sdb 8 jrs Lun 19/07/21 Ven 30/07/21 étanchieté des sdb
673 étanchieté du 11 jrs Ven 26/03/21 Mar 13/04/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
674 IMM J 77 jrs Mer 14/04/21 Jeu 12/08/21

675 étanchieté des sdb 8 jrs Ven 30/07/21 Jeu 12/08/21 étanchieté des sdb
676 étanchieté du 11 jrs Mer 14/04/21 Ven 30/04/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
677 IMM I 74 jrs Ven 30/04/21 Mer 25/08/21

678 étanchieté des sdb 8 jrs Jeu 12/08/21 Mer 25/08/21 étanchieté des sdb
679 étanchieté du 11 jrs Ven 30/04/21 Mar 18/05/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
680 IMM H 71 jrs Mar 18/05/21 Mar 07/09/21

681 étanchieté des sdb 8 jrs Mer 25/08/21 Mar 07/09/21 étanchieté des sd
682 étanchieté du 11 jrs Mar 18/05/21 Ven 04/06/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
683 ZONE 2 148 jrs Ven 26/03/21 Mar 16/11/21

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 19
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
684 IMM G 132 jrs Ven 26/03/21 Jeu 21/10/21

685 étanchieté des sdb 8 jrs Ven 08/10/21 Jeu 21/10/21

686 étanchieté du 11 jrs Ven 26/03/21 Mar 13/04/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
687 IMM F 129 jrs Mer 14/04/21 Mer 03/11/21

688 étanchieté des sdb 8 jrs Jeu 21/10/21 Mer 03/11/21

689 étanchieté du 11 jrs Mer 14/04/21 Ven 30/04/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
690 IMM E 126 jrs Ven 30/04/21 Mar 16/11/21

691 étanchieté des sdb 8 jrs Mer 03/11/21 Mar 16/11/21

692 étanchieté du 11 jrs Ven 30/04/21 Mar 18/05/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
693 ZONE 3 125 jrs Ven 28/05/21 Lun 13/12/21

694 IMM D 101 jrs Ven 28/05/21 Jeu 04/11/21

695 étanchieté des sdb 8 jrs Ven 22/10/21 Jeu 04/11/21

696 étanchieté du 11 jrs Ven 28/05/21 Mar 15/06/21 étanchieté du terrasse + protection mécanique
terrasse + protection
mécanique
697 IMM C 98 jrs Mer 16/06/21 Mer 17/11/21

698 étanchieté des sdb 8 jrs Jeu 04/11/21 Mer 17/11/21

699 étanchieté du 11 jrs Mer 16/06/21 Ven 02/07/21 étanchieté du terrasse + protection mécaniqu
terrasse + protection
mécanique
700 IMM B 95 jrs Ven 02/07/21 Mar 30/11/21

701 étanchieté des sdb 8 jrs Mer 17/11/21 Mar 30/11/21

702 étanchieté du 11 jrs Ven 02/07/21 Mar 20/07/21 étanchieté du terrasse + protection m
terrasse + protection
mécanique
703 IMM A 92 jrs Mar 20/07/21 Lun 13/12/21

704 étanchieté des sdb 8 jrs Mar 30/11/21 Lun 13/12/21

705 étanchieté du 11 jrs Mar 20/07/21 Ven 06/08/21 étanchieté du terrasse + protec
terrasse + protection
mécanique
706 REVETEMENT 206 jrs Mar 08/06/21 Jeu 28/04/22

707 POSE DE CARRELAGE ET MARBRE


180 jrs Lun 19/07/21 Jeu 28/04/22

708 ZONE 1 119 jrs Lun 19/07/21 Ven 21/01/22

709 IMM K 30 jrs Lun 19/07/21 Ven 03/09/21 IMM K


710 IMM J 30 jrs Ven 03/09/21 Jeu 21/10/21

711 IMM I 29 jrs Jeu 21/10/21 Lun 06/12/21

712 IMM H 30 jrs Lun 06/12/21 Ven 21/01/22

713 ZONE 2 83 jrs Ven 08/10/21 Mer 16/02/22

714 IMM G 30 jrs Ven 08/10/21 Mer 24/11/21

715 IMM F 29 jrs Mer 24/11/21 Lun 10/01/22

716 IMM E 24 jrs Lun 10/01/22 Mer 16/02/22

717 ZONE 3 119 jrs Ven 22/10/21 Jeu 28/04/22

718 IMM D 30 jrs Ven 22/10/21 Mer 08/12/21

719 IMM C 29 jrs Jeu 09/12/21 Lun 24/01/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 20
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
720 IMM B 30 jrs Lun 24/01/22 Ven 11/03/22

721 IMM A 30 jrs Ven 11/03/22 Jeu 28/04/22

722 REVETEMENT DES FACADES 113 jrs Mar 08/06/21 Jeu 02/12/21

723 ZONE 1 69 jrs Jeu 10/06/21 Mar 28/09/21

724 IMM K 15 jrs Jeu 10/06/21 Lun 05/07/21 IMM K


725 IMM J 14 jrs Mar 13/07/21 Mar 03/08/21 IMM J
726 IMM I 12 jrs Jeu 05/08/21 Mar 24/08/21 IMM I
727 IMM H 14 jrs Lun 06/09/21 Mar 28/09/21 IMM H
728 ZONE 2 44 jrs Mar 08/06/21 Lun 16/08/21

729 IMM G 12 jrs Mar 08/06/21 Ven 25/06/21 IMM G


730 IMM F 10 jrs Ven 02/07/21 Lun 19/07/21 IMM F
731 IMM E 12 jrs Mer 28/07/21 Lun 16/08/21 IMM E
732 ZONE 3 71 jrs Jeu 12/08/21 Jeu 02/12/21

733 IMM D 14 jrs Jeu 12/08/21 Ven 03/09/21 IMM D


734 IMM C 12 jrs Mar 07/09/21 Lun 27/09/21 IMM C
735 IMM B 14 jrs Ven 08/10/21 Ven 29/10/21

736 IMM A 15 jrs Mar 09/11/21 Jeu 02/12/21

737 MENUISERIE ALUMINIUM 160 jrs Mar 14/09/21 Mar 24/05/22

738 ZONE 1 99 jrs Mar 14/09/21 Mer 16/02/22

739 IMM K 10 jrs Mar 14/09/21 Mer 29/09/21

740 IMM J 10 jrs Ven 29/10/21 Mar 16/11/21

741 IMM I 10 jrs Mer 15/12/21 Jeu 30/12/21

742 IMM H 10 jrs Mar 01/02/22 Mer 16/02/22

743 ZONE 2 63 jrs Ven 03/12/21 Lun 14/03/22

744 IMM G 10 jrs Ven 03/12/21 Lun 20/12/21

745 IMM F 10 jrs Mer 19/01/22 Jeu 03/02/22

746 IMM E 10 jrs Ven 25/02/22 Lun 14/03/22

747 ZONE 3 99 jrs Ven 17/12/21 Mar 24/05/22

748 IMM D 10 jrs Ven 17/12/21 Lun 03/01/22

749 IMM C 10 jrs Mer 02/02/22 Jeu 17/02/22

750 IMM B 10 jrs Mar 22/03/22 Mer 06/04/22

751 IMM A 10 jrs Ven 06/05/22 Mar 24/05/22

752 MENUISERIE BOIS 158 jrs Mar 14/09/21 Jeu 19/05/22

753 POSE DES PORTES 158 jrs Mar 14/09/21 Jeu 19/05/22
BOIS+PLACARDS
754 ZONE 1 97 jrs Mar 14/09/21 Lun 14/02/22

755 IMM K 8 jrs Mar 14/09/21 Lun 27/09/21 IMM K


756 IMM J 8 jrs Ven 29/10/21 Jeu 11/11/21

757 IMM I 8 jrs Mer 15/12/21 Mar 28/12/21

758 IMM H 8 jrs Mar 01/02/22 Lun 14/02/22

759 ZONE 2 61 jrs Ven 03/12/21 Jeu 10/03/22

760 IMM G 8 jrs Ven 03/12/21 Jeu 16/12/21

761 IMM F 8 jrs Mer 19/01/22 Mar 01/02/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 21
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
762 IMM E 8 jrs Ven 25/02/22 Jeu 10/03/22

763 ZONE 3 97 jrs Ven 17/12/21 Jeu 19/05/22

764 IMM D 8 jrs Ven 17/12/21 Jeu 30/12/21

765 IMM C 8 jrs Mer 02/02/22 Mar 15/02/22

766 IMM B 8 jrs Mar 22/03/22 Lun 04/04/22

767 IMM A 8 jrs Ven 06/05/22 Jeu 19/05/22

768 PEINTURE 178 jrs Jeu 16/09/21 Jeu 23/06/22

769 ZONE 1 116 jrs Jeu 16/09/21 Jeu 17/03/22

770 IMM K 28 jrs Jeu 16/09/21 Ven 29/10/21

771 IMM J 28 jrs Mer 03/11/21 Jeu 16/12/21

772 IMM I 27 jrs Ven 17/12/21 Lun 31/01/22

773 IMM H 27 jrs Jeu 03/02/22 Jeu 17/03/22

774 ZONE 2 77 jrs Mar 07/12/21 Jeu 07/04/22

775 IMM G 28 jrs Mar 07/12/21 Jeu 20/01/22

776 IMM F 27 jrs Ven 21/01/22 Ven 04/03/22

777 IMM E 24 jrs Mar 01/03/22 Jeu 07/04/22

778 ZONE 3 117 jrs Mer 22/12/21 Jeu 23/06/22

779 IMM D 27 jrs Mer 22/12/21 Mer 02/02/22

780 IMM C 27 jrs Ven 04/02/22 Ven 18/03/22

781 IMM B 28 jrs Jeu 24/03/22 Ven 06/05/22

782 IMM A 28 jrs Mer 11/05/22 Jeu 23/06/22

783 CUISINE 166 jrs Mar 14/09/21 Mer 01/06/22

784 ZONE 1 105 jrs Mar 14/09/21 Ven 25/02/22

785 IMM K 16 jrs Mar 14/09/21 Ven 08/10/21

786 IMM J 16 jrs Ven 29/10/21 Mer 24/11/21

787 IMM I 16 jrs Mer 15/12/21 Lun 10/01/22

788 IMM H 16 jrs Mar 01/02/22 Ven 25/02/22

789 ZONE 2 69 jrs Ven 03/12/21 Mer 23/03/22

790 IMM G 16 jrs Ven 03/12/21 Mer 29/12/21

791 IMM F 16 jrs Mer 19/01/22 Lun 14/02/22

792 IMM E 16 jrs Ven 25/02/22 Mer 23/03/22

793 ZONE 3 105 jrs Ven 17/12/21 Mer 01/06/22

794 IMM D 16 jrs Ven 17/12/21 Mer 12/01/22

795 IMM C 16 jrs Mer 02/02/22 Lun 28/02/22

796 IMM B 16 jrs Mar 22/03/22 Ven 15/04/22

797 IMM A 16 jrs Ven 06/05/22 Mer 01/06/22

798 LES ASCENSEURS 141 jrs Mar 14/09/21 Ven 22/04/22

799 IMM K 20 jrs Mar 14/09/21 Jeu 14/10/21

800 IMM J 20 jrs Jeu 14/10/21 Mar 16/11/21

801 IMM I 20 jrs Mar 16/11/21 Jeu 16/12/21

802 IMM H 20 jrs Jeu 16/12/21 Mar 18/01/22

803 IMM G 20 jrs Ven 03/12/21 Mer 05/01/22

804 IMM F 20 jrs Mer 05/01/22 Ven 04/02/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 22
N° Mode Task Name Durée Début Fin Semestre 2, 2020 Semestre 1, 2021 Semestre 2, 2021
Tâche A S O N D J F M A M J J A S
805 IMM E 20 jrs Ven 04/02/22 Mer 09/03/22

806 IMM D 20 jrs Ven 17/12/21 Mer 19/01/22

807 IMM C 20 jrs Mer 19/01/22 Ven 18/02/22

808 IMM B 20 jrs Ven 18/02/22 Mer 23/03/22

809 IMM A 20 jrs Mer 23/03/22 Ven 22/04/22

Fractionnement critique Project Summary Inactive Summary Start-only Critique


Task External Tasks Manual Task Finish-only
Project: msproj11
Date: Sam 29/05/21 Split External Milestone Duration-only Deadline
Milestone Inactive Task Manual Summary Rollup Progress
Summary Inactive Milestone Manual Summary Progression manuelle

Page 23

Vous aimerez peut-être aussi