PROJET X GO 31

ELECTRICIEN 1
9/13/2021
DEBUT FIN DEBUT DEBUT FIN
tache ACTON AVANCEMENT Délais prevu prevu PREVU 2 FIN PREVU 2 REEL REEL Retard Remarque
Administration
Fondations X 100% 15J 12/8/2014 12/25/2014 Sep-14 Nov-14
Superstructures X 85% 15 j 12/26/2014 1/12/2014 1/12/2015
Maçonnerie X 60% 7j 2/28/2015 4J RENFORCEMENT DES EQUIPES
Enduit X 0% 4j 2/28/2015 3/16/2015 2/28/2015
Electrcité X 0% 4j 1/28/2015 2/1/2015
Evacuation Plomberie X 0% 1j 2/4/2015 2/5/2015
Etanchéité X 0% 15 j 2/7/2015 2/22/2015 3/7/2015 3/23/2015 3/4/2015 16 +2J ABSENCE ST D ETANCHEITE
Revetement X 0% 10 j 2/12/2015 2/22/2015
Mensuierie ALU et BOIS X 0% 15 j 2/10/2015 2/25/2015
Peinture X 0% 6j 2/20/2015 2/26/2015
Sanitaire X 0% 1j 2/25/2015 2/26/2015
Salle de classe
Fondations X 100% 12 j 12/8/2014 12/20/2014 Nov-15 Nov-15
Plancher Haut RDC X 85% 10 j 12/21/2014 1/1/2015 1/20/2015
Plancher Haut 1 Etage X 80% 10 j 2/18/2015 7J ABSENCE DES EQUIPES SUFF
Acrotère X 0% 6j 1/13/2015 1/19/2015
Maçonnerie X 0% 14 j 2/24/2015 3/10/2015 2/28/2015 3/14/2015 2/28/2015 4J MANQUE D EFFECTIF
Enduit X 0% 7j 3/4/2015 3/18/2015 3/14/2015 3/21/2015 10J MANQUE D EFFECTIF
Electrcité X 0% 14 j 2/11/2015 2/25/2015
Evacuation Plomberie X 0% 1j 2/1/2015 2/2/2015
Etanchéité X 0% 7j 2/20/2015 2/27/2015
Revetement X 0% 10 j 2/28/2015 3/8/2015
Mensuierie ALU et BOIS X 0% 15 j 2/10/2015 2/25/2015
Peinture X 0% 6j 2/20/2015 2/26/2015
Salle Scientifique
Fondations X 100% 14 j 12/16/2014 12/30/2014 Nov-14 1311/2014 14J
Plancher Haut RDC X 100% 10 j 1/1/2015 1/10/2015 1/15/2015 1/24/2015 14J
Plancher Haut 1 Etage X 80% 10 j 1/11/2015 1/21/2015 1/25/2015 2/4/2015 14J
Maçonnerie X 0% 14 j 2/18/2015 3/8/2015 2/26/2015 3/12/2015 2/26/2015 5J ABSENCE DES EQUIPES SUFF
Enduit X 0% 7j 2/7/2015 2/14/2015
Electrcité X 0% 6j 2/2/2015 2/8/2015
Evacuation Plomberie X 0% 1j 2/3/2015 2/4/2015
Etanchéité X 0% 6j 2/7/2015 2/13/2015
Revetement X 0% 15 j 2/21/2015 3/6/2015
Mensuierie ALU et BOIS X 0% 14 j 2/10/2015 2/25/2015
Peinture X 0% 5j 2/26/2015 3/1/2015
SANITAIRE
Fondations X 80% 14 j 12/8/2014 12/22/2014 Nov-14 38J
Superstructures X 0% 10 j 2/23/2015 1/2/2015 2/28/2015 3/13/2015 2/19/2015 30J
Maçonnerie X 0% 10 j 1/3/2015 1/13/2015 3/20/2015 3/30/2015 17J
Enduit Extérieur X 0% 6j 1/14/2015 1/20/2015 12J
Electrcité X 0% 3j 1/10/2015 1/13/2015 12J
Evacuation Plomberie X 0% 1j 1/12/2015 1/13/2015 12J
Etanchéité X 0% 7j 1/14/2015 1/21/2015 10J
Enduit Intérieur X 0% 6j 1/15/2015 1/21/2015 10J
Revetement X 0% 15 j 1/22/2015 2/7/2015
Mensuierie ALU et BOIS X 0% 15 j 2/10/2015 2/25/2015
Peinture X 0% 6j 2/26/2015 3/2/2015
Sanitaire X 0% 3j 1/30/2015 3/2/2015