TABLEAU RECAPTULATIF DE TRAITEMENT DES PLANS CDP TRANCHE 2 - SAN PEDRO

Date de Date de
Date de transmission Date réception de Dans le circuit de
Sites Designation Liste des plans transmission Plans validé transmission des Avis
prévue l'avis du BCT validation
effective corrections
GBAPET (Base 2)
02. Fiche technique systeme
modulaire
09000.100A-Fiche technique du materiau fabrique'
15/12/2023 x
modulaire

04. Structural Drawings


TG-B2-A- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-B- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-C-Foundation Plan&Details R0 (10mm@150mm ) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-D- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-E- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-G- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-HI- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-J- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
TG-B2-K- Foundation Plan Details R0-(10mm@150mm) 15/12/2023 04/01/2024 x AVIS SUSPENDU
05. note de calcul beton
Concrete Calculation Notes R1.2- 80 kpa. C25
15/12/2023 x
(ENGLISH)
06. Electrical drawings
GBABET-PLAN ECLAIRAGE INTERIEUR EXTERIEUR 15/12/2023 29/12/2023 x AVIS SUSPENDU
GBABET-PLAN PRISE DE COURANT 15/12/2023 29/12/2023 x AVIS SUSPENDU
GBABET-PLAN REGARDS ET TRANCHEES 15/12/2023 29/12/2023 x AVIS SUSPENDU
GBAPET- PLAN CHEMINEMENT DES CABLES 15/12/2023 29/12/2023 x AVIS SUSPENDU
GBAPET-PLAN DE MISE A LA TERRE 15/12/2023 29/12/2023 x AVIS SUSPENDU
GBAPET-PLAN DISPOSITION DE LA PRISE DE
15/12/2023 29/12/2023 x AVIS SUSPENDU
DONNÉES
GBAPET-SCHEME UNIFILIARE 15/12/2023 29/12/2023 x AVIS SUSPENDU
07. water supply
schools project water supply typical base 2-WS 15/12/2023 20/12/2023 x 04/01/2024 AVIS SUSPENDU
08. drainage eau usee eau vanne
Schools Project B2 Type KOBLEKRO-DR 15/12/2023 20/12/2023 x 04/01/2024 AVIS SUSPENDU
09. terrassement
ACAD-SDP GBAPET FINAL-Model_R2 15/12/2023 20/12/2023 x AVIS SUSPENDU
10. topographie
RAW FILE TOPO GBAPET 15/12/2023 x
11. finishing
09100.212A-BASE 02-CALENDRIER DES FINITIONS 15/12/2023 x
09100.215A-BASE 2-FINITION DES SOL 15/12/2023 x
12. mobilier
09100.216A-BASE 2-PLAN DU MOBILIER 15/12/2023 x
13. lutte contre incendie
15000.200A-BASE 2 -LUTTE CONTRE L INCENDIE.. 15/12/2023 OUI 29/12/2023 x
14. faux plafond
09100.217A-BASE 2-FAUX PLAFOND 15/12/2023 x
15. calendrier des portes et
fenetres
08000.002A-BASE 2 -CALENDRIER DES PORTES ET
15/12/2023 x
FENETRES
16. evacuation eau pluviale
PLAN D'EVACUATION D'EAU PLUVIAL typique Base 2
15/12/2023 20/12/2023 x 04/01/2024 AVIS SUSPENDU
et base 4
17.note de calcul
Note de calculs n° 15000.801A indice 00 : BASE 2-
04/01/2024 OUI 05/01/2024
NOTES DE CALCUL DE L EAU USEE EAU VANNE
HANNIE (Base 4)
02. Fiche technique systeme modulaire
'09000.100A-Fiche technique du mate'riau fabrique'
15/12/2023 x
modulaire
04. Structural Drawings
TG-B4-A- Foundation Plan Details (HANNIE) C25 -R0 15/12/2023 x
TG-B4-B- Foundation&Details (HANNIE)- C25 R0 15/12/2023 x
TG-B4-C-Foundation Plan &Details(HANNIE) C25 R0 15/12/2023 x
TG-B4-D-Foundation Plan&Details (HANNIE) C25 R0 15/12/2023 x
TG-B4-E-Foundation Plan&Details (HANNIE) C25- R0 15/12/2023 x
TG-B4-F-Foundation Plan& Details (HANNIE) C25-R0 15/12/2023 x
TG-B4-G-Foundation Plan&Details(HANNIE) C25-R0 15/12/2023 x
TG-B4-HI-Foundation Plan&Details (HANNIE) C25-R0 15/12/2023 x
TG-B4-J- Foundation Plan&Details (HANNIE) C25-R0 15/12/2023 x
TG-B4-K- Foundation Plan&Details (HANNIE) C25 R0 15/12/2023 x
TG-B4-L- Foundation Plan&Details (HANNIE) C25-R0 15/12/2023 x
TG-B4-M- Foundation Plan&Details (HANNIE) C25-R0 15/12/2023 x
05. note de calcul beton
Concrete Calculation Notes R1.2- 80 kpa. C25
15/12/2023 x
(ENGLISH)
06. Electrical drawings
HANNIE PLAN -PLAN DE MISE A LA TERRE 15/12/2023 29/12/2023 x AVIS SUSPENDU
HANNIE PLAN CHEMINEMENT DES CABLES 15/12/2023 29/12/2023 x AVIS SUSPENDU
HANNIE PLAN DISPOSITION DE LA PRISE DE
15/12/2023 29/12/2023 x AVIS SUSPENDU
DONNÉES
HANNIE PLAN ECLAIRAGE INTERIEUR EXTERIEUR 15/12/2023 29/12/2023 x AVIS SUSPENDU
HANNIE PLAN PRISE DE COURANT 15/12/2023 29/12/2023 x AVIS SUSPENDU
HANNIE-PLAN REGARD ET TRANCHÉES 15/12/2023 29/12/2023 x AVIS SUSPENDU
SCHEME UNIFILIAIR HANNIE 15/12/2023 29/12/2023 x AVIS SUSPENDU
07. water supply
schools project water supply typical base 4 15/12/2023 20/12/2023 x 04/01/2024 AVIS SUSPENDU
08. drainage eau usee eau vanne
15000.603A-BASE 4-PLAN DE DRAINAGE DES EAUX
15/12/2023 20/12/2023 x 04/01/2024 AVIS SUSPENDU
USEES-HANNIE..
09. terrassement
ACAD-SDP Hannié FINAL-Model_R2 15/12/2023 20/12/2023 x AVIS SUSPENDU
10. topographie
RAW FILE TOPO HANNIE 15/12/2023 x
11. finishing
09100.215A-BASE 04-CALENDRIER DES FINITIONS 15/12/2023 x
09100.216A-BASE 04-FINITIONS DES SOLS 15/12/2023 x
12. mobilier
09100.212B-BASE 04-PLAN DU MOBILIER typique 15/12/2023 x
13. lutte contre incendie
15000.201A-BASE 4 -LUTTE CONTRE L’INCENDIE
15/12/2023 OUI 29/12/2023 x
typique
14. faux plafond
09000.217A-BASE 4-FAUX PLAFOND 15/12/2023 x
15. calendrier des portes et fenetres
08000.001B-BASE 04-CALENDRIER DES PORTES ET
15/12/2023 x
FENETRES
16. evacuation eau pluviale
PLAN D'EVACUATION D'EAU PLUVIAL typique Base 2
15/12/2023 20/12/2023 x 04/01/2024 AVIS SUSPENDU
et base 4
17.note de calcul
Note de calculs n° 15000.802A indice 00 : BASE 4-
04/01/2024 OUI 05/01/2024
NOTES DE CALCUL DE L EAU USEE EAU VANNE
Note de calculs n° 15000.803A indice 00 : BASE 4-
04/01/2024 OUI 05/01/2024
NOTES DE CALCUL DE L'EAU PLUVIALE
MAHINO (Base 4)
02. Fiche technique systeme modulaire
'09000.100A-Fiche technique du mate'riau fabrique'
15/12/2023 x
modulaire
04. Structural Drawings
TG-B4-A- Foundation Plan Details (MAHINO) C25 -R0 15/12/2023 x
TG-B4-B- Foundation&Details (MAHINO)- C25 R0 15/12/2023 x
TG-B4-C-Foundation Plan &Details(MAHINO) C25 R0 15/12/2023 x
TG-B4-D-Foundation Plan&Details (MAHINO) C25 R0 15/12/2023 x
TG-B4-E-Foundation Plan&Details (MAHINO) C25- R0 15/12/2023 x
TG-B4-F-Foundation Plan& Details (MAHINO) C25-R0 15/12/2023 x
TG-B4-G-Foundation Plan&Details(MAHINO) C25-R0 15/12/2023 x
TG-B4-HI-Foundation Plan&Details (MAHINO) C25-R0 15/12/2023 x
TG-B4-J- Foundation Plan&Details (MAHINO) C25-R0 15/12/2023 x
TG-B4-K- Foundation Plan&Details (MAHINO) C25 R0 15/12/2023 x
TG-B4-L- Foundation Plan&Details (MAHINO C25-R0 15/12/2023 x
TG-B4-M- Foundation Plan&Details (MAHINO) C25-R0 15/12/2023 x
05. note de calcul beton
Concrete Calculation Notes R1.2- 80 kpa. C25
15/12/2023 x
(ENGLISH)
06. Electrical drawings
MAHINO PLAN -CHEMINEMENT DES CABLES 15/12/2023 29/12/2023 x AVIS SUSPENDU
MAHINO PLAN -PLAN DE MISE A LA TERRE 15/12/2023 29/12/2023 x AVIS SUSPENDU
MAHINO PLAN -PLAN REGARD ET TRANCHÉES 15/12/2023 29/12/2023 x AVIS SUSPENDU
MAHINO PLAN -PRISE DE COURANT 15/12/2023 29/12/2023 x AVIS SUSPENDU
MAHINO PLAN DISPOSITION DE LA PRISE DE
15/12/2023 29/12/2023 x AVIS SUSPENDU
DONNÉES -
MAHINO PLAN ECLAIRAGE INTERIEUR EXTERIEUR - 15/12/2023 29/12/2023 x AVIS SUSPENDU
SCHEME UNIFILIAIR MAHINO 15/12/2023 29/12/2023 x AVIS SUSPENDU
07. water supply
schools project water supply typical base 4 15/12/2023 21/12/2023 x 04/01/2024 AVIS SUSPENDU
08. drainage eau usee eau vanne
schools project water supply typical base 4 15/12/2023 21/12/2023 x 04/01/2024 AVIS SUSPENDU
09. terrassement
ACAD-SDP MAHINO FINAL-Model_R2 15/12/2023 21/12/2023 x AVIS SUSPENDU
10. topographie
RAW FILES TOPO MAHINO 15/12/2023 x
11. finishing
09100.215A-BASE 04-CALENDRIER DES FINITIONS 15/12/2023 x
09100.216A-BASE 04-FINITIONS DES SOLS 15/12/2023 x
12. mobilier
09100.212B-BASE 04-PLAN DU MOBILIER typique 15/12/2023 x
13. lutte contre incendie
15000.201A-BASE 4 -LUTTE CONTRE L’INCENDIE
15/12/2023 OUI 29/12/2023 x
typique
14. faux plafond
09000.217A-BASE 4-FAUX PLAFOND 15/12/2023 x
15. calendrier des portes et fenetres
08000.001B-BASE 04-CALENDRIER DES PORTES ET
15/12/2023 x
FENETRES
16. evacuation eau pluviale
PLAN D'EVACUATION D'EAU PLUVIAL typique Base 2
15/12/2023 21/12/2023 x 04/01/2024 AVIS SUSPENDU
et base 4
17.note de calcul
Note de calculs n° 15000.802A indice 00 : BASE 4-
04/01/2024 OUI 05/01/2024
NOTES DE CALCUL DE L EAU USEE EAU VANNE
Note de calculs n° 15000.803A indice 00 : BASE 4-
04/01/2024 OUI 05/01/2024
NOTES DE CALCUL DE L'EAU PLUVIALE
PARA (Base 4)
02. Fiche technique systeme modulaire
'09000.100A-Fiche technique du mate'riau fabrique'
15/12/2023 x
modulaire
04. Structural Drawings
TG-B4-A- Foundation Plan Details (PARA) C25 -R0 15/12/2023 x
TG-B4-B- Foundation&Details (PARA)- C25 R0 15/12/2023 x
TG-B4-C-Foundation Plan &Details(PARA) C25 R0 15/12/2023 x
TG-B4-D-Foundation Plan&Details (PARA) C25 R0 15/12/2023 x
TG-B4-E-Foundation Plan&Details (PARA) C25- R0 15/12/2023 x
TG-B4-F-Foundation Plan& Details (PARA) C25-R0 15/12/2023 x
TG-B4-G-Foundation Plan&Details(PARA) C25-R0 15/12/2023 x
TG-B4-HI-Foundation Plan&Details (PARA) C25-R0 15/12/2023 x
TG-B4-J- Foundation Plan&Details (PARA) C25-R0 15/12/2023 x
TG-B4-K- Foundation Plan&Details (PARA) C25 R0 15/12/2023 x
TG-B4-L- Foundation Plan&Details (PARA) C25-R0 15/12/2023 x
TG-B4-M- Foundation Plan&Details (PARA) C25-R0 15/12/2023 x
05. note de calcul beton
Concrete Calculation Notes R1.2- 80 kpa. C25
15/12/2023 x
(ENGLISH)
06. Electrical drawings
PARA PLAN -PLAN DE MISE A LA TERRE 15/12/2023 29/12/2023 x AVIS SUSPENDU
PARA PLAN CHEMINEMENT DES CABLES 15/12/2023 29/12/2023 x AVIS SUSPENDU
PARA PLAN DISPOSITION DE LA PRISE DE 15/12/2023 29/12/2023 x AVIS SUSPENDU
PARA PLAN ECLAIRAGE INTERIEUR EXTERIEUR 15/12/2023 29/12/2023 x AVIS SUSPENDU
PARA PLAN PRISE DE COURANT 15/12/2023 29/12/2023 x AVIS SUSPENDU
PARA-PLAN REGARD ET TRANCHÉES 15/12/2023 29/12/2023 x AVIS SUSPENDU
SCHEME UNIFILIAIR PARA 15/12/2023 29/12/2023 x AVIS SUSPENDU
07. water supply
schools project water supply typical base 4 15/12/2023 21/12/2023 x 04/01/2024 AVIS SUSPENDU
08. drainage eau usee eau vanne
15000.604A-BASE 4 -PLAN DE DRAINAGE DES EAUX
15/12/2023 21/12/2023 x 04/01/2024 AVIS SUSPENDU
USEES-PARA..
09. terrassement
ACAD-SDP PARA FINAL-Model 15/12/2023 21/12/2023 x AVIS SUSPENDU
10. topographie
RAW FILE TOPO PARA 15/12/2023 x
11. finishing
09100.215A-BASE 04-CALENDRIER DES FINITIONS 15/12/2023 x
09100.216A-BASE 04-FINITIONS DES SOLS 15/12/2023 x
12. mobilier
09100.212B-BASE 04-PLAN DU MOBILIER typique 15/12/2023 x
13. lutte contre incendie
15000.201A-BASE 4 -LUTTE CONTRE L’INCENDIE
15/12/2023 OUI 29/12/2023 x
typique
14. faux plafond
09000.217A-BASE 4-FAUX PLAFOND 15/12/2023 x
15. calendrier des portes et fenetres
08000.001B-BASE 04-CALENDRIER DES PORTES ET
15/12/2023 x
FENETRES
16. evacuation eau pluviale

PLAN D'EVACUATION D'EAU PLUVIAL typique Base 2


15/12/2023 21/12/2023 x 04/01/2023 AVIS SUSPENDU
et base 4
17.note de calcul
Note de calculs n° 15000.802A indice 00 : BASE 4-
04/01/2024 OUI 05/01/2024
NOTES DE CALCUL DE L EAU USEE EAU VANNE
Note de calculs n° 15000.803A indice 00 : BASE 4-
04/01/2024 OUI 05/01/2024
NOTES DE CALCUL DE L'EAU PLUVIALE