AIR
IRIGASI SAWAH DESA JENGGAWAH
KAB. JEMBER-JAWA TIMUR
Data Dasar 19 - - - - - - - - - - - -
DATA HUJAN HARIAN
Sta…… Pulau : Lintang :
Thn 2005 Elevation : …….. m Bujur :
Tgl Jan Feb Mar Apr Mei Jun Jul Agt Sep Okt Nov Des
1 - 6 - 6 6 - - - - - 14 31
2 - 3 - 3 - - - - - - 9 32
3 - - - - - 28 - - - 24 - 10
4 - - 18 - 34 16 - - 3 - 48 -
5 37 2 6 - 10 - - - - - 96 -
31 11 - - - - - - - - - - -
Total 245,0 356,0 431,0 207,0 167,0 372,0 78,0 31,0 241,0 330,0 319,0 165,0
Rerata 10,9 18,2 23,9 7,2 9,0 15,4 2,8 2,0 8,4 16,3 16,3 8,4
Max 103,0 226,0 335,0 59,0 122,0 227,0 18,0 31,0 112,0 190,0 201,0 103,0
H Hujan 15,0 17,0 16,0 13,0 10,0 10,0 9,0 4,0 10,0 16,0 12,0 15,0
DATA CURAH HUJAN RERATA BULANAN
Curah Hujan Rerata Bulanan
Tahun Total
Jan Feb Mar Apr Mei Jun Jul Ags Sep Okt Nov Des
2004 245,0 356,0 431,0 207,0 167,0 372,0 78,0 31,0 241,0 330,0 319,0 165,0 2.745,0
2005 301,0 430,0 290,0 353,0 3,0 88,0 54,0 22,0 2,0 256,0 406,0 241,0 2.446,0
2006 241,0 324,0 337,0 261,0 285,0 132,0 0,0 0,0 0,0 249,0 556,0 22,0 2.407,0
2007 494,0 179,0 298,0 143,0 26,0 74,0 13,0 0,0 31,0 410,0 224,0 121,0 2.013,0
2008 599,0 432,0 111,0 145,0 61,0 21,0 56,0 15,0 6,0 0,0 206,0 308,0 1.985,0
2009 563,0 344,0 254,0 86,0 179,0 24,0 22,0 0,0 0,0 0,0 0,0 0,0 1.472,0
2010 240,0 329,0 288,0 132,0 116,0 9,0 25,0 5,0 56,0 5,0 160,0 395,0 1.760,0
2011 240,0 329,0 288,0 132,0 116,0 9,0 25,0 5,0 56,0 5,0 160,0 395,0 1.760,0
2012 211,0 173,0 244,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 601,0
2013 48,0 62,0 213,0 38,0 60,0 72,0 0,0 0,0 0,0 0,0 0,0 0,0 493,0
Rerata 318,20 295,80 275,40 149,70 101,30 80,10 27,30 7,80 39,20 125,50 203,10 164,70 1768,20
CURAH HUJAN EFEKTIF
No Prob Jan Feb Mar Apr Mei Jun Jul Ags Sep Okt Nov Des
1 9,1% 599,00 432,00 431,00 353,00 285,00 372,00 78,00 31,00 241,00 410,00 556,00 395,00
2 18,2% 563,00 430,00 337,00 261,00 179,00 132,00 56,00 22,00 56,00 330,00 406,00 395,00
3 27,3% 494,00 356,00 298,00 207,00 167,00 88,00 54,00 15,00 56,00 256,00 319,00 308,00
4 36,4% 301,00 344,00 290,00 145,00 116,00 74,00 25,00 5,00 31,00 249,00 224,00 241,00
5 45,5% 245,00 329,00 288,00 143,00 116,00 72,00 25,00 5,00 6,00 5,00 206,00 165,00
6 54,5% 241,00 329,00 288,00 132,00 61,00 24,00 22,00 0,00 2,00 5,00 160,00 121,00
7 63,6% 240,00 324,00 254,00 132,00 60,00 21,00 13,00 0,00 0,00 0,00 160,00 22,00
8 72,7% 240,00 179,00 244,00 86,00 26,00 9,00 0,00 0,00 0,00 0,00 0,00 0,00
9 81,8% 211,00 173,00 213,00 38,00 3,00 9,00 0,00 0,00 0,00 0,00 0,00 0,00
10 90,9% 48,00 62,00 111,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
R80 80,0% 216,80 174,20 219,20 47,60 7,60 9,00 0,00 0,00 0,00 0,00 0,00 0,00
Reff 15 harian 2,45 2,18 2,47 0,56 0,09 0,11 0,00 0,00 0,00 0,00 0,00 0,00
Reff 4,90 4,36 4,95 1,11 0,17 0,21 0,00 0,00 0,00 0,00 0,00 0,00
Jan Feb Mar Apr Mei Jun Jul Ags Sep Okt Nov Des
Jumlah Hari
31 28 31 30 31 30 31 31 30 31 30 31
DATA KLIMATOLOGI
Temperatur Penyinaran Kelembaban Angin (km/jam)
Tahun
rata-rata max min % rata-rata (%) v terbesar v rata-rata
1 Temperatur Rata-rata t o
C Data 26,256 26,312 26,568 26,694 26,594 26,324 25,398 25,428 26,216 26,442 27,550 26,650
2 Tekanan Uap Air Ea m bar Tabel 34,138 34,252 34,774 35,031 34,827 34,276 32,458 30,582 34,057 32,539 36,777 34,941
3 Kelembaban Relatif Rata-rata RH % Data 83,984 86,202 86,956 75,208 84,586 82,088 85,950 86,830 90,950 86,556 86,232 90,750
4 Tekanan Uap Sebenarnya Ed m bar Ea (RH/100) 28,670 29,526 30,238 26,346 29,459 28,137 27,898 26,554 30,974 28,165 31,714 31,709
5 (Ea-Ed) m bar Hitung 5,468 4,726 4,536 8,685 5,368 6,140 4,560 4,028 3,082 4,375 5,063 3,232
6 Kecepatan Angin U2 Km/hari Data 58,512 76,730 56,000 43,216 49,718 50,868 63,729 64,678 73,848 ###### 32,550 25,530
7 Kecepatan Angin Uday m/det Hitung 0,677 0,888 0,648 0,500 0,575 0,589 0,738 0,749 0,855 5,385 0,377 0,295
8 Fungsi Kecepatan Angin f(u) Km/hari Hitung 0,427 0,476 0,421 0,386 0,404 0,407 0,441 0,444 0,468 1,520 0,357 0,339
9 Interpolasi W - Tabel 0,758 0,758 0,761 0,762 0,761 0,758 0,749 0,749 0,757 0,759 0,771 0,762
10 (1-W) mm/hari Hitung 0,242 0,242 0,239 0,238 0,239 0,242 0,251 0,251 0,243 0,241 0,230 0,239
DATA EVAPOTRASPIRASI
11 Radiasi Ra mm/hari Tabel 16,100 16,100 15,500 14,400 13,100 12,400 12,700 13,700 14,900 15,800 16,000 16,000
12 Penyinaran Matahari n/N % Data 0,297 0,392 0,472 0,552 0,616 0,582 0,635 0,590 0,556 0,496 0,297 0,306
13 (0.25+0.54n/N) - - Hitung 0,410 0,462 0,505 0,548 0,583 0,564 0,593 0,569 0,550 0,518 0,410 0,415
14 Rs = Ra (0.25+0.54n/N) Rs mm/hari Hitung 6,605 7,434 7,825 7,890 7,635 6,997 7,529 7,791 8,200 8,180 6,567 6,643
15 Fungsi Suhu f(t) - Tabel 15,911 15,924 15,982 16,010 15,988 15,927 15,717 15,723 15,902 15,957 16,203 16,000
16 Fungsi Tekanan Uap f(ed) - Hitung 0,104 0,101 0,098 0,114 0,101 0,107 0,108 0,113 0,095 0,106 0,092 0,092
17 Fungsi Penyinaran f(n/N) - Hitung 0,367 0,453 0,525 0,597 0,655 0,624 0,671 0,631 0,601 0,546 0,367 0,375
18 Rn1 = f(t) f(ed) f(n/N) - - Hitung 0,610 0,728 0,822 1,090 1,059 1,059 1,135 1,124 0,908 0,928 0,549 0,554
19 C - - Tabel 1,100 1,100 1,000 1,000 0,950 0,950 1,000 1,000 1,100 1,100 1,150 1,150
20 - mm/hari Hitung 3,857 4,219 4,295 4,476 4,069 3,780 3,884 3,984 4,319 5,554 3,787 3,633
ETo* = W.(0.75Rs - Rn1) + (1-w) f(u) (Ea-Ed)
21 ETo = C*ETo* - mm/hari Hitung 4,243 4,641 4,295 4,476 3,866 3,591 3,884 3,984 4,751 6,110 4,355 4,178
PERSIAPAN LAHAN
Tabel 1 .5 N ila i p e rk o la si p a d a b e rb a g a i te k stu r ta n a h
No. Te k stu r ta n a h N ila i P e rk o la si (m m /h r) TABEL 1. KEBUTUHAN AIR UNTUK PENYIAPAN LAHAN
1. C la y 1 – 1 ,5 Eo + P T (30 hari) T (45 hari)
2. S illty C la y 1 ,5 – 2
3. C la y Lo a m , S ilty C la y 2 – 2 .5 S = 250 S = 300
mm/hr S = 250 mm S = 300 mm
4. Lo a m 2 .5 – 3 mm mm
5. M u d y C la y lo a m 3 – 5
S a n d y Lo a m 5 11,1 12,7 8,4 9,5
Pola Tanam
PADI PADI PALAWIJA
Koefisien Tanaman
:
C1 LP LP 1,30 1,27 1,33 1,30 1,30 0,00 LP LP 1,30 1,27 1,33 1,30 1,30 0,00 LP LP 1,10 1,10 1,05 1,05 0,95 0,00 LP LP
C2 LP LP LP 1,30 1,27 1,33 1,30 1,30 0,00 LP LP 1,30 1,27 1,33 1,30 1,30 0,00 LP LP 1,10 1,10 1,05 1,05 0,95 0,00 LP
C ( rata-rata ) LP LP 1,30 1,29 1,30 1,32 1,30 0,65 LP LP 1,30 1,29 1,30 1,32 1,30 0,65 LP LP 1,10 1,10 1,08 1,05 1,00 0,95 LP LP
Evapotranspirasi
mm/hr 6,11 6,11 4,36 4,36 4,18 4,18 4,24 4,24 4,64 4,64 4,30 4,30 4,48 4,48 3,87 3,87 3,59 3,59 3,88 3,88 3,98 3,98 4,75 4,75 6,11 6,11
( ETo )
Perkolasi ( P ) mm/hr 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00 3,00
Penggunaan
mm/hr LP LP 5,66 5,60 5,43 5,49 5,52 2,76 LP LP 5,58 5,52 5,82 5,89 5,03 2,51 LP LP 4,27 4,27 4,28 4,18 4,75 4,51 LP LP
Konsumtif (ETc) =
k x Eto
Penggantian
mm/hr
Lapisan Air :
WLR1 1,67 1,67 1,67 1,67 1,67 1,67 1,67 1,67
WLR2 1,67 1,67 1,67 1,67 1,67 1,67 1,67 1,67
WLR (rata-rata)
1,67 1,67 1,67 1,67 1,67 1,67 1,67 1,67 1,67 1,67
Kebutuhan Air
mm/hr 14,03 14,03 12,83 12,83 12,68 12,68 7,84 7,84 8,71 8,71 7,83 7,83 11,59 11,59 12,28 12,28 12,06 12,06 12,46 12,46 12,53 12,53 13,14 13,14 14,03 14,03
Bersih
Kebutuhan Air
lt/dt/ha 1,62 1,62 1,49 1,49 1,47 1,47 0,91 0,91 1,01 1,01 0,91 0,91 1,34 1,34 1,42 1,42 1,40 1,40 1,44 1,44 1,45 1,45 1,52 1,52 1,62 1,62
Irigasi
T a b e l 1 .7 . K o e fisie n k e ka sa ra n d a s a r sa lu ra n P e rsa m a a n
S tric kle r
D e b it R e n ca n a ( m 3 / d t ) k ( m 1/3/ d t )
Q > 10 45
5 < Q < 10 4 2 ,5
1 < Q < 5 40
Q < 1 d a n sa lu ra n te rsie r 35
T a b e l 1 .1 0 . P e n e n tu a n T in g g i ja g a a n b e rd a sa rka n
d e b it (Q )
3
Q ( m /dt ) T in g g i Ja g a a n ( m )
< 0 ,5 0 ,4
0 ,5 - 1 ,5 0 ,5
1 ,5 - 5 ,0 0 ,6
5 ,0 - 1 0 ,0 0 ,7 5
1 0 ,0 - 1 5 ,0 0 ,8 5
> 1 5 ,0 1 ,0 0
PERENCANAAN UKURAN DIMENSI
Perhitungan Dimensi Saluran dengan Menggunakan
Metode Strickler
SALURAN
Elevasi Awal
Primer
Saluran = 498
Elevasi Akhir Dicoba
Saluran = 492 B = 0,2 m
(L) Panjang Saluran = 425m H = 0,4 m
(Qkeb) Debit Kebutuhan = 153lt/det/ha m 1
=
Luas Areal yang Akan di
Airi = 102ha
Efesiensi Saluran = 90% A
Koefesien = (b + m x h) x h
Kekasaran = 35 = 0,24m2
P = B + 2H x (m2+1)^1/2
Kemiringan (Elevasi Awal Saluran - Elevasi Akhir Saluran) /
(I) Saluran = Panjang Saluran = 1,33137m
= (56 - 50) / 463 R =A/P
= 0,01296
= 0,18027m
Asumsi B = H V = K x R2/3 x I1/2
0,2 m
Pengambilan Air Debit Rencana / Efesiensi
(DR) di Intake = Saluran CHECk!!
= 0,1656 / 0,9 !
= 0,18407m3/det (DR) Q Okee!!
< hitung !
Perhitungan Dimensi Saluran dengan Menggunakan Metode
PERENCANAAN UKURAN DIMENSI
Strickler
SALURAN
Elevasi Awal
Saluran = 492
Sekunder 1
Elevasi Akhir
Saluran = 483 Dicoba
(L) Panjang Saluran = 1,223m B = 0,1 m
(Qkeb) Debit Kebutuhan = 1,53lt/det/ha H = 0,4 m
Luas Areal yang Akan di m = 1
Airi = 33,7ha
Efesiensi Saluran = 90% A = (b + m x h) x h
Koefesien = 0,2m2
Kekasaran = 35
P = B + 2H x (m2+1)^1/2
A = (b + m x h) x h
Kemiringan (Elevasi Awal Saluran - Elevasi Akhir Saluran) / Panjang = 0,24m2
(I) Saluran = Saluran
(488 - 486) / P = B + 2H x (m2+1)^1/2
= 313 = 1,33137m
= 0,00639 R = A/ P
Asumsi B = H = 0,18027m
V = K x R2/3 x I1/2
Debit Kebutuhan x Luas Areal yang
(Q) Debit Rencana = Akan di Airi = 0,8928m/det 0,4m
= 1,53 x 102 Q = AxV
= 156,06lt/det = 0,21427
0,15606m /det
3
= 0,2 m
Pengambilan Debit Rencana / Efesiensi CHECk!!!
(DR) Air di Intake = Saluran
(DR) < Q hitung Okee!!!
= 0,1560 / 0,8
= 0,19508m3/det