TOTAL HT 26,363,184.10
RECAPITULATION
BLOC (A1) BARRE (16 logements ) EN (R+3)
N° Designation Montant
1 TERRASSEMENT 94,600.00
2 INFRASTRUCTURE 2,939,000.00
3 ASSAINISSEMENT 155,900.00
4 SUPERSTRUCTURE 8,009,955.00
5 MACONNERIE 2,860,320.00
5)1 ENDUIT 2,441,274.50
6 REVETEMENT 2,939,058.00
7 DIVERS 267,776.00
8 ETANCHEITE 992,000.00
9 MENUISERIE EN BOIS 1,766,000.00
10 MENUISERIE METALLIQUE 66,300.00
11 ELECTRICITE 532,952.00
12 PLOMBERIE 1,815,520.00
13 PEINTURE ET VITRERIE 1,482,528.60
TOTAL EN HT 26,363,184.10
TVA 7% 1,845,422.89
TOTAL EN TTC 28,208,606.99
TOTAL HT 19,340,253.60
RECAPITULATION
BLOC (A2) BARRE (12 logements ) EN (R+2)
N° Designation Montant
1 TERRASSEMENT 82,600.00
2 INFRASTRUCTURE 2,608,250.00
3 ASSAINISSEMENT 155,900.00
4 SUPERSTRUCTURE 5,306,180.00
5 MACONNERIE 2,148,312.00
5)1 ENDUIT 1,822,331.00
6 REVETEMENT 2,157,957.00
7 DIVERS 200,616.00
8 ETANCHEITE 992,000.00
9 MENUISERIE EN BOIS 1,326,000.00
10 MENUISERIE METALLIQUE 65,100.00
11 ELECTRICITE 350,564.00
12 PLOMBERIE 1,362,240.00
13 PEINTURE ET VITRERIE 762,203.60
TOTAL EN HT 19,340,253.60
TVA 7% 1,353,817.75
TOTAL EN TTC 20,694,071.35
TOTAL HT 19,388,253.60
RECAPITULATION
BLOC (A3) BARRE (12 logements ) EN (R+2)
N° Designation Montant
1 TERRASSEMENT 82,600.00
2 INFRASTRUCTURE 2,608,250.00
3 ASSAINISSEMENT 155,900.00
4 SUPERSTRUCTURE 5,306,180.00
5 MACONNERIE 2,148,312.00
5)1 ENDUIT 1,857,331.00
6 REVETEMENT 2,157,957.00
7 DIVERS 200,616.00
8 ETANCHEITE 992,000.00
9 MENUISERIE EN BOIS 1,326,000.00
10 MENUISERIE METALLIQUE 65,100.00
11 ELECTRICITE 350,564.00
12 PLOMBERIE 1,362,240.00
13 PEINTURE ET VITRERIE 775,203.60
TOTAL EN HT 19,388,253.60
TVA 7% 1,357,177.75
TOTAL EN TTC 20,745,431.35
Total HT 65,091,691.30
TVA 07% 4,556,418.39
Total TTC 69,648,109.69