N°d DESIGNATIONS U Qté marche Qté Réalisé Qté Prv P.U ( HT) en TOTAL H.T marche TOTAL H.

Prv P.U ( HT) en TOTAL H.T marche TOTAL H.T Réalisé


es chiffres
prix

1 INSTALLATION DE CHANTIER FT 1 0.75 1.00 200,000.000 200,000.00 150,000.00


TERRASSEMENT EN MASSE DEBLAIS OU EN
2 TRANCHEES EN TERRAIN DE TOUTE NATURE Y M3 114123 168,123.30 172,518.82 13.00 1,483,599.00 2,185,602.90
COMPRIS DANS LE ROCHER

3 REMBLAIS M3 79803 88,000.00 89,321.70 16.00 1,276,848.00 1,408,000.00


4 FOURNITURE TRANSPORT ET POSE DES BUSES ML 479 535.70 685.60 1,100.00 526,900.00 589,270.00
EN CAO DE DIAMETRE Ø1000

FOURNITURE TRANSPORT ET POSE DES BUSES


5 EN CAO DE DIAMETRE Ø800 ML 285 164.18 244.18 950.00 270,750.00 155,971.00

6 FOURNITURE TRANSPORT ET POSE DES BUSES ML 280 56.94 284.44 600.00 168,000.00 34,164.00
EN CAO DE DIAMETRE Ø600

7 BETON POUR BETON ARME B25 (B2) m3 969 320.00 843.80 900.00 872,100.00 288,000.00
8 BETON POUR BETON DE PROPRETE B15 (B5) m3 171 68.234 141.393 600.00 102,600.00 40,940.40

9 ACIER A HAUTE ADHERENCE kg 100815 46,273.83 82,497.00 11.50 1,159,372.50 532,149.05

10 FOSSE BETONNE ML 5154 2,069.00 2,269.00 300.00 1,546,200.00 620,700.00

11 PROTECTION EN GABION M3 3981 5,373.00 5,796.00 300.00 1,194,300.00 1,611,900.00

12 COUCHE ANTICONTAMINANTE M3 10666 10,016.00 10,016.00 45.00 479,970.00 450,720.00

13 COUCHE DE FONDATION EN GNF2 M3 36234 36,842.50 36,842.50 55.00 1,992,870.00 2,026,337.50


14 COUCHE DE BASE EN T.V 0/31,5 TYPE M3 18838 19,047.00 19,047.00 70.00 1,318,660.00 1,333,290.00
GNB
15 COUCHE DE MATERIAUX SELECTIONNES POUR M3 10668 10,242.00 10,242.00 60.00 640,080.00 614,520.00
ACCOTEMENTS TYPE MS1

16 MISE EN OUVRE COUCHE D’IMPREGNATION M2 106191 102,236.00 102,236.00 2.00 212,382.00 204,472.00

17 FOURNITURE DU LIANT POUR IMPREGNATION T 159 153.35 153.35 4,900.00 779,100.00 751,434.60
EN EMULSION 55
MISE EN OUVRE REVETEMENT SUPERFICIEL
18 BICOUCHE NON COMPRIS FOURNITURE DU M2 106191 102,236.00 102,236.00 3.00 318,573.00 306,708.00
LIANT

FOURNITURE DU LIANT POUR REVETEMENT


19 SUPERFICIEL BICOUCHE (BITUME FLUIDIFIER T 287 276.04 276.04 5,100.00 1,463,700.00 1,407,789.72
800/1400)

DEPLACEMENT DES POTEAUX ELECTRIQUES


17 U 7 0.00 0.00 5,000.00 35,000.00 0.00

18 PANNEAUX D'INDICATION U 6 0.00 6.00 4,000.00 24,000.00 0.00

19 PANNEAUX DE PRESCRIPTION U 2 0.00 2.00 5,000.00 10,000.00 0.00


TOTAL H T 16,075,004.50 14,711,969.17
TVA 20% 3,215,000.90 2,942,393.83
TOTAL T T C 19,290,005.40 17,654,363.00
TOTAL H.T Prv Poucentage %
dépassement prevu

200,000.00

2,242,744.66

1,429,147.20
754,160.00

231,971.00

170,664.00

759,420.00
84,835.80

948,715.50

680,700.00

1,738,800.00

450,720.00

2,026,337.50
1,333,290.00

614,520.00

204,472.00

751,415.00

306,708.00

1,407,804.00

0.00

24,000.00

10,000.00
16,370,431.80
3,274,086.36
19,644,518.16 -1.84