Vous êtes sur la page 1sur 10

1525

Design and construction coordination problems


and planning for design–build project new users
Andrew S. Chang, Fang-Ying Shen, and William Ibbs

Abstract: Design–build (DB) is adopted as a project delivery method in hopes to improve performance. Previous studies
focus on upstream issues such as conditions for adoption and contractor selection, but few address the design and construc-
tion coordination issues that are very likely to be encountered in execution by new users. This paper investigates coordina-
tion problems arising from design and construction concurrence and solutions by studying five ongoing DB projects and
interviewing nine major contract parties. Inconsistent application of the design and construction process and infrequent
feedback are two major problems found to have high influence on DB execution. A work unit planning process with five
steps is presented in this paper to help better manage the design and construction coordination of a DB project.
Key words: design–build, design and construction concurrence coordination, project delivery method, constructability feed-
back, work unit planning.
Résumé : La conception-construction est utilisée comme méthode de livraison de projet en espérant améliorer le rende-
ment. Des études antérieures ont porté sur les questions en amont, telles que les conditions pour l’adoption et la sélection
des entrepreneurs, mais peu traitent des questions de coordination de la conception et de la construction qui seront proba-
blement rencontrées lors de l’exécution par de nouveaux utilisateurs. Le présent article traite des questions de coordination
découlant de la convergence de la conception et de la construction et des solutions en étudiant cinq projets de conception-
construction en cours et en interviewant neuf grands entrepreneurs. Une utilisation irrégulière du processus de conception-
construction et le peu de rétroaction sont deux problèmes principaux ayant une grande influence sur l’exécution de la mé-
thode de conception-construction. Un processus de planification par unités de travail comportant cinq étapes est présenté
dans cet article afin d’aider à mieux coordonner le processus de conception-construction d’un projet.
Mots-clés : conception construction, coordination de la convergence conception-construction, méthode de livraison de pro-
jet, rétroaction sur la constructibilité, planification par unités de travail.
[Traduit par la Rédaction]

Introduction large amounts of planning, communication, and experience.


Peña-Mora and Li (2001) stated that the advantages associ-
The design–build (DB) method brings many benefits to a ated with DB are not easy to realize with only ad hoc plan-
project, including singular responsibility, cost and time sav- ning. These authors also noted that the problems of planning
ings, quality improvement, and reduction in change orders and executing DB projects are not well understood, espe-
(BFC 1995; DBIA 1997). Studies have examined the use of cially for new users.
DB and its influence on projects (Ndekugri and Turner Under DB, the coordination and transfer of project infor-
1994; Yates 1995) and surveyed the industry to identify DB mation occurs earlier and with less definition than in tradi-
adoption and design-builder selection criteria (Songer et al. tional design–bid–build (DBB) projects. Project participants,
1996; Palaneeswaran and Kumaraswamy 2000). Other stud- especially new DB users, could not cooperate with each
ies have concluded that DB projects produced better per- other well owing to the lack of experience. The problems
formance (Konchar and Sanvido 1998; Ernzen and may also arise from the design and construction (DC) con-
Schexnayder 2000). currence that will not occur in DBB projects such as incom-
However, the DB project delivery system requires careful plete design information, unfamiliarity with DB process, and
planning and professional execution to be successful (DBIA lack of collaboration between the designer and constructor
1997). Williams (1995) stated that fast-track projects require (Terwiesch et al. 2002; Cheng and Tsai 2008).
Received 30 April 2009. Revision accepted 28 July 2010. Published on the NRC Research Press Web site at cjce.nrc.ca on 5 October
2010.
A.S. Chang and F.-Y. Shen.1 Department of Civil Engineering, National Cheng Kung University, No. 1, University Road, Tainan City
701, Taiwan (R.O.C.).
W. Ibbs. Department of Civil and Environmental Engineering, University of California at Berkeley, 213 McLaughlin Hall, UC Berkeley,
Berkeley, CA 94720, USA.
Written discussion of this article is welcomed and will be received by the Editor until 30 April 2011.
1Corresponding author (e-mail: sfangying@yahoo.com.tw).

Can. J. Civ. Eng. 37: 1525–1534 (2010) doi:10.1139/L10-090 Published by NRC Research Press
1526 Can. J. Civ. Eng. Vol. 37, 2010

Some research focused on knowledge management and for the designers and constructors to get along with each
information technologies to improve information processing other.
between participants (Abduh and Skibniewski 2003). For ex- The DB projects come from the Kaohsiung Mass Rapid
ample, a multicriteria decision system could help the selec- Transit (KMRT) BOT Program in Taiwan. The total KMRT
tion of an effective alternative on construction design and program budget is about $5.3 billion and divided into 15
management, such as architectural design, contractor, and major civil and architecture projects with stations and tun-
project managers (Zavadskas et al. 2008; Šarka et al. 2008; nels as well as 10 core electrical and mechanical (E&M)
Turskis et al. 2009). A knowledge management system ena- projects such as trackwork, signaling, and communications.
bles knowledge transfer and better communication among The DB is used for the detailed design and construction of
stakeholders and enhances value engineering practices all 15 civil and architecture projects including the five case
(Dave and Koskela 2009; Zhang et al. 2009). But for DB projects.
projects, design and construction are often done by different The KMRT program organization is shown in Fig. 1. The
companies, and they may not be willing to store and retrieve KMRT Department (KMRTD) is the government owner, and
information through the same management system (Chi- Kaohsiung Rapid Transit Corporation (KRTC) is the BOT
nowsky and Rojas 2003). concessionaire. The KMRTD hired a quality and safety con-
There is also the issue of increased project intensity sultant to inspect KRTC’s work. The KRTC hired four ma-
(amount of work at any given time) that necessarily stems jor consultants individually for conceptual design,
from design and construction being done concurrently. Adler construction project management, core E&M integration, as
(1995) indicated that the relationship between design and well as operation and maintenance evaluations. Each of the
manufacturing becomes an important variable when time to 15 civil and architecture design-builders signed, as a single
market is compressed. Terwiesch et al. (2002) pointed out entity, a DB contract with KRTC and they are also named
that tasks being completed in parallel by relying on prelimi- constructors in this paper. The design was about 50% com-
nary information from other tasks frequently cause rework. plete at the time that the design-builders were hired.
Project participants with different experiences, concepts,
goals, and practices contribute to more inconsistencies Research methodology
(Peña-Mora and Tamaki 2001). The case study method was used to understand and ana-
Because few studies address the DC concurrence prob- lyze coordination problems of DC concurrence of five on-
lems of DB projects and because these problems are gener- going DB projects. Although five may seem like a small
ally coordination issues, this paper aims to investigate DB number of case studies for research purposes, when investi-
project coordination problems arising from design and con- gated deeply they are enough to describe the phenomena
struction concurrence, analyze the degree of influence each and build theories (Eisenhardt 1989). External validation
problem has, and propose a work unit planning method as a can still be assured by convergent answers and comparisons
solution to help new users avoid the preventable problems. with the major interviews with the design-builders as well as
Coordination has been considered as a major factor for the remaining auxiliary interviews to support the studied
achieving success (Pocock et al. 1996; Thomas et al. 1998; subject contexts (Yin 2003). The problems identified later
Chua et al. 1999). Understanding and targeting coordination in this paper are mainly resulted from the DB system and
problems provide a foundation for better DB project execu- inexperienced users, not from the differences of the studied
tion. projects or companies. Therefore, the number of cases is ac-
ceptable.
Background of studied DB projects The DB literature was first reviewed, relevant project
documents were collected and read, and interviews were
This research studied five ongoing civil and architecture conducted with the project participants. The documents in-
DB projects as cases (see Table 1). These five subway proj- clude contracts, correspondence, meeting minutes, construc-
ects include detailed design and construction of station, tun- tion plans, and monthly reports. Since the DB projects under
nel (boring or cut-and-cover), and overpass. The contract the KMRT program are complex and many parties are in-
lump-sum prices of DB projects are between $143 million volved, 23 interviews were conducted at two stages to gain
and $267 million and durations between 49 and 59 months. complete perspectives. With two or three interviewees par-
These durations are shorter than similar Taipei DBB projects ticipating, each interview took about 1.5 h and notes were
completed earlier. The five DB projects were essentially on taken. The interviewees are senior managers of relevant par-
schedule, with 80% of design and 20% of construction com- ties and project (deputy) managers of the design-builders
pleted when interviewed at the early stage; they progressed with experience of more than 20 years.
with 100% of design and more than 80% of construction At the early stage in February 2003, the first five inter-
completed at the latter interview. They bypassed competitive views were conducted with the management parties of
bidding, with five design-builders selected by the private KRTC, KMRTD, and three consultants, because they were
owner. The five design-builders are large constructors (but involved in contract awarding and understood the conditions
were inexperienced in DB projects, as revealed during inter- of the studied DB projects. The interviews explored the de-
views). They are mostly joint ventures by Taiwanese and sign and construction performances, conflicts between con-
Japanese construction companies, and all hired major Taiwa- ceptual and detailed design, management methods of the
nese engineering consulting firms for design. In the begin- design-builders, and different perspectives of the designers
ning, the DB projects did not go smoothly and it took time and constructors.

Published by NRC Research Press


Chang et al. 1527

Table 1. Background of five studied DB projects.

Progress (%)
Early stage Later stage
Project $ (million) Duration (months) Design Construction Construction Construction work Design-builders
A 143 50 84 23 91 Station and tunnel Japan and Taiwan
B 223 50 81 22 91 Station and tunnel Taiwan and Malaysia
C 216 49 79 19 83 Station and tunnel Japan, Taiwan, and Taiwan
D 181 50 81 20 85 Station and overpass Taiwan
E 267 59 80 18 82 Station and tunnel Taiwan and Japan

Fig. 1. Organization of the case projects.

After answers from these parties were reviewed and situa- the number of questions was minimized and basically the
tions clarified, two sets of questions were prepared to inter- same for designers and constructors. Sub-questions were
view the execution parties: the design-builders (see added for the designers, since their role in DB projects is
Appendix). In December 2003, nine interviews were con- quite different from that in traditional DBB projects. The
ducted with design-builders, first five designers and then first question asks about conceptual design that is the input
four constructors. After the nine interviews, it was found to and influential on the DC process. Questions 2 and 3 con-
that their answers to design and construction concurrence cern the DC interaction consistency and feedback, which are
problems were similar and converged. Also, because the important functions in DB projects. Question 4 probes the
fourth and fifth constructors came from the same company, DC difficulty and the time and cost impact on the project.
the interview with the fifth constructor was skipped. Question 5 seeks information about design changes and con-
In January 2004, KMRTD, KRTC, and the three consul- flicts, because previous studies claim that DB minimizes
tants were interviewed again to confirm or clarify the results such.
from the design-builder interviews. Information collected The views about DC coordination of the five designers
from these interviews was compiled, analyzed, and com- and four constructors are summarized in Tables 2 and 3, re-
pared. Since these DB projects were executed by a BOT spectively. Coordination problems are seen as arising from
program, some of the observations may have been caused inadequate planning and execution. The former includes a
by the BOT mechanism, not just the DB delivery system, high level of conceptual design completion. The latter in-
and are noted below. cludes inconsistent DC amounts, a long review process, and
At the later stage, a five-step work unit planning method, little feedback between designer and constructor. Moreover,
helping divide the project work into smaller units systemati- the consequence of inadequate DC coordination includes
cally to enhance coordination between design and construc- time and cost increase as well as design change and con-
tion, was proposed to address the identified DC concurrence flicts. They are explained below. More detailed information
problems. In September 2006, the four design-builders were is cited from the interview records throughout the remainder
interviewed again. They were asked to evaluate the five of this paper.
steps and effects of the planning method on DC problems
and whether similar steps (could) have been adopted in their High conceptual design completion
DB project execution. Both designers and constructors believed that conceptual
design was overly completed on these projects when de-
tailed design was started. On projects A and D (Question 1
Problem analyses and results
in Table 2), 50% of all design was finished before the de-
The interview questions in the Appendix are related to co- tailed design package was awarded. The designer for project
ordination and information transfer. To make them simple, D stated that the amount of detailed design work would

Published by NRC Research Press


1528 Can. J. Civ. Eng. Vol. 37, 2010

Table 2. Designer views about DC coordination.

Questions Project A Project B Project C


1.1 Conceptual design level 40% for cut and cover, 60% Adequate conceptual design
for tunneling level
1.2 Influence of conceptual Higher completion makes Hard to deal with when conceptual Should incorporate design-
design detailed design simpler design does not conform to builder’s needs
design criteria
2.1 How to plan design Follow construction schedule Meet construction needs Follow construction plan
and schedule
2.2 Design amount match Design chases construction Yes Almost
construction amount
3.1 Design review process Too many reviews Review frequent,
review process long
3.2 Feedback between design Constructor gives opinions Constructor asks for design revi- Feedback to each other
and construction to designer sion if feasible and cost allows
4.1 Difficulty for DC concur- Feasible Need more engineers in the be- Design fragmented
rence ginning
4.2 Time, cost, quality affected Time increased by 30–40%, cost Time increased, hard to control Time and cost increased
increased 10–20%, quality is quality significantly
the same
5.1 Reasons for design changes Design drawings not consistent Construction demands Owner change,
with construction such as improved layout
5.2 Dealing with design Many conflicts, design changed Few conflicts,
construction conflicts for construction construction is the first priority

Table 3. Constructor views about DC coordination.

Questions Project A Project B


1. Influence of conceptual design level 40% complete Design should be finished
Detailed design will be easier if 60% done Some factors are not considered
Basic problems should be solved
2. DC concurrence difficulty Not easy Difficult
Design chases construction progress Hard to control schedule
3. Feedback to designer Not much Not much
4. Time, cost, quality affected Hard to estimate Hard to estimate

5. Dealing with DC conflicts Not clear Solved by coordination meeting

have been the same no matter how much of the conceptual Inconsistent DC amounts
design was completed. On the other hand, the designer and The second question addresses how to plan design activ-
constructor for project A (Table 3) stated that detailed de- ities to match construction. All the interviewed designers
sign was simpler when there was a higher level of concep- voiced the belief that design should comply with construc-
tual design completion at the time of the detailed design tion and follow the construction schedule, which seems ob-
contract’s award, but they hoped to avoid conflicts between vious (Table 2). However, in some cases, design was chased
the two designs. by construction progress. For example, one constructor, after
Before KRTC awarded the DB contracts, KMRTD di- finishing the station foundation, was awaiting the detailed
rected conceptual design for 16 months and therefore its design of walls. This observation is not too surprising, since
completion level was quite high. The intention was to save the designers were subcontractors to the design-builders.
time in subsequent detailed design. However, the result was On the other hand, the contractors believed that the design
problematic. Most notably, extra analysis and design on amount rarely matched the construction needs (Question 2 in
quality and safety standards of functions and operations Table 3). One explanation for this may be that the inter-
were required. These extra conceptual designs reduced de- views were conducted early in construction, when not
tailed design flexibility and eventually hindered construc- enough design was finished and DC cooperation was not
tion. This higher level of conceptual design was mainly functioning well. In some situations, construction was de-
caused by the BOT mechanism. layed because designers did not know the onsite schedules
Lower levels of conceptual design at time of detailed de- of suppliers. Either the contractor did not manage the ven-
sign award allow greater flexibility and optimization in de- dors properly or did not provide schedule information to the
tailed design, as well as minimize the conflicts and changes design subconsultant. Because it is the constructor’s respon-
between the two designs (DBIA 1997; Molenaar et al. sibility to inform the designer of such construction needs, an
1999). American Consulting Engineers Council (1994) and effective DC concurrence planning and execution mecha-
Fredrickson (1998) suggest 35% design completion or less nism is needed. These needs come out of the DB delivery
at award. mechanism.

Published by NRC Research Press


Chang et al. 1529

Project D Project E Summary


40–50% Level high, should be reduced Level of conceptual design is too high

Should be minimized because of the Different conceptual and detailed design Functional requirements and external
same amount of detailed design work concepts add extra work constraints should be clearer

Attach to construction time Comply with construction process Design should comply with construction

Hard to match in the beginning Exceed construction Design can match construction

Review process is too long Review process is too long

Constructor gives ideas to designer Designer gives idea to constructor Feedback exists, but informal and ad hoc

No problem Hard to control time Difficulty exists but can be overcome

Time increased 25%, cost 10%, Negative on time, cost, and quality Time increased more, cost increased,
quality the same quality not affected

Owner’s or constructor’s demand Construction mistakes or condition change Design changes according to construction

Design complies with construction No conflict Conflicts exist

Project C Project D Summary


Completeness is too high Detail design follows conceptual design Level of conceptual design is too high
Constant conflicts between conceptual No right to change design Conceptual design problems should be solved
design specs and construction specs
Not easy OK DC concurrence difficult
Construction stops when design not finished Design amount hard to match construction
Yes, provide construction methods Yes, provide construction ideas Little and ad hoc feedback
Time increased by 20% Time no difference Time and cost increased little
Cost increased by 20% Cost increased by 3–5% Quality the same
Quality remains the same Quality no difference
A few conflicts No conflicts Few conflicts, but can be resolved

Long review process The owners should have communicated earlier with design-
All designers complained about the long review process ers about the review procedure in terms of design task divi-
requested by KRTC. To feed construction’s needs, the de- sion, reviewers in charge, and responsibilities. Immediate
tailed design work was divided into many smaller units or and informal communication and trust between participants
work packages but some of which were not approved or ap- are essential rather than formal and step-by-step submitted
proved conditionally owing to integration consideration. Re- instructions (Williams 1995).
view was conducted for each of these units, and some
reviews took as long as 2.5 months. Overall, it took 18 Little feedback between designer and constructor
months to complete the design work, whereas these design- Feedback between the detailed designers and contractors
ers estimated that it would normally take about 15 months. existed but it was informal, ad hoc, and in numerous cases
In addition, problems that occurred in the review proce- insufficient according to both the designers and constructors
dure and with the reviewers also lengthened the review (Tables 2 and 3). Designers of projects A, B, D, and E indi-
process. The project design manual stipulated for review of cated that they only received one-way instructions from the
the design documents, by whom, and in what sequence. But constructors. The feedback process was further complicated
KRTC sent many documents to many departments and con- by the fact that the designers and constructors were located
sultants for review. The conceptual designer also played a and worked in two different cities.
strict gatekeeper role for the owner KRTC. Many comments The interaction between designers and constructors was
were given to designers, but some of them were inappropri- infrequent. The routine was that the designer finished and
ate for DB projects. sent certain drawings to the constructor for review, approval,
Because it was the first time for participants to execute and construction. Designers generally only inquired about
such a large BOT program and because there were so many review status when they could see that the constructor had
DB projects underway at the same time, KRTC exercised problems with construction or supplier materials. Only a
extra caution in the reviews, which lengthened the process. few constructors provided construction ideas to their design-

Published by NRC Research Press


1530 Can. J. Civ. Eng. Vol. 37, 2010

ers, and when they did so, it was informal, which was diffi- (Ibbs et al. 2003). Peña-Mora and Tamaki (2001) character-
cult for the designers. Many detailed design considerations ize these as ‘‘underground’’ change orders, for instance.
were not consistent.
The advantages of DB projects cannot be fully exploited Practical implications
if the information feedback loop is not working well be-
tween the designer and constructor. The situation is aggra- The analyses in the previous section indicate that some dif-
vated if the designer is not experienced with ficulty or problems come from the inexperience of design-
constructability and the constructor just meekly follows the builders in DB practice or the influence of BOT, and not
design drawings. The DB delivery system should provide a so much from the DB process itself. Upon further investi-
mechanism for mutual feedback and collaboration (Cheng gation, we found that the constructors planned construction
and Tsai 2008). work and prepared Critical Path Method (CPM) schedules
while the designers focused on their own detailed design.
Increased time and cost The design and construction were executed separately with-
out close cooperation. This phenomenon is really a prob-
All the designers stated that individual design time and lem for new users of DB methods.
cost were increased but quality was not affected (Question
As summarized in Table 2 (Question 4), the five design-
4 in Table 2). Two apparent reasons are the design adjust-
ers in this study indicate that difficulties with DC concur-
ment based on construction and the long review process.
rence existed but could be overcome. The contractors
Design activities had to be adjusted to respond to construc-
agreed that DC concurrence was not easy and that it is diffi-
tion needs, and these adjustments resulted in additional time
cult to match design amount with construction (Table 3).
and cost. The contractors repeatedly held the designers to a
This DC concurrence problem deserves a systematic solu-
high standard of using economical materials or methods,
tion.
which created time pressures and complicated the designers’
efforts to innovate and optimize design or improve quality The problems discussed are summarized and solutions are
(Williams 1995). suggested in Table 4. Among these six problems, the incon-
sistent DC amounts and little feedback have the highest
As shown in Table 3, the constructors thought time and
level of influence for DB projects, as analyzed in the prior
cost increased slightly, but quality was not affected. Under
section. The inconsistent DC amounts generally will not
intense project schedule pressures, the constructors could
happen in traditional DBB projects because designers fre-
not allow the designers to spend much time in optimizing
quently dominate the project contractually. The construc-
design. When they did allot more design phase time for
tion-oriented design or constructability imposed by the DB
such optimization, they would increase equipment or work-
method places designers in more of a subordinate role, and
force to accelerate construction phase duration.
this makes it more difficult to stick to their original design.
Incomplete or unoptimized design information increases
On the other hand, feedback is not provided in traditional
cost (Terwiesch et al. 2002). However, these constructors
DBB, but the separation in time between the design and
were generally in the position to control design work devel-
construction phases may allow the parties sufficient time to
opment and the designers, so only some cost increase re-
deal with it. Conversely, it is harder for the DB method to
sulted. Under strict supervision of the KMRTD-hired safety
deal with this feedback issue on account of the reduced
and quality consultant, construction quality was controlled in
amount of project duration and the concurrency of design
the traditional way and was not notably influenced.
and construction.
The above individual design and construction cost in-
To overcome these two problems, formal and systematic
creases are consistent with findings by Ibbs et al. (2003).
planning and execution guidelines are needed. Work unit
The design times for these projects had small time increases
planning is helpful in this regard, as proposed and discussed
compared to the overall total DC time. Quality of both the
in the next section.
design and the construction work on these DB projects was
considered to be consistent with other DBB projects. Ibbs et al. (2003) argue that project management expertise
and experience of design-builders may have a great impact
Design change and conflicts on DB performance. Lam et al. (2008) indicated that effec-
tive project management action including planning, commu-
The designers knew that DC conflicts existed but yielded nication, control, and organization structure is a critical
to construction because construction was the first priority. In success factor for DB projects. Good general management
the view of the designers (Table 2), design changed accord- expertise may be enough to solve the less-serious problems.
ing to construction because of owner’s demand, condition For example, the owner follows the principle of not letting
change, or inconsistency. For example, the size of ventilation conceptual design get too far ahead of detailed design (what
shaft was decreased owing to KRTC’s space consideration; we call the ‘‘low design principle’’), perhaps by hiring a
drawings were modified on account of construction condi- consultant to manage this interface. The result is improved
tions or mistakes. On the other hand, the constructors felt cooperation between designer and constructor, and the par-
that conflicts were few and resolvable if existed (Table 3). ties gain their own experience in DC concurrence.
These results indicate the following. (1) Design changes
still exist, and in many cases the designer absorbs them at
his own cost rather than request a change order. (2) The con- Work unit planning as a solution
structor is in a better position to deal with conflicts. Under To solve the above DC coordination problems, this study
proper circumstances, such conflicts can be managed by the further developed a work unit (WU) planning method and
constructor to reduce change and its impact to the designer interviewed four design-builders to validate its effects. It is

Published by NRC Research Press


Chang et al. 1531

Table 4. Problems with and solutions for DC coordination.

Problems Degree of influence Solutions


High conceptual design completion Low Management expertise
Inconsistent DC amounts High Planning and execution guidelines
Long review process Low Management expertise
Little feedback between designer and constructor High Planning and execution guidelines
Individual time and cost increase Low Management expertise
Design change and conflicts Medium Management expertise

Fig. 2. Work unit planning steps.

derived from task order planning for on-call contracting were not involved in planning. The result is that the design
projects (Chang and Ibbs 1998). The WU planning consists work was catching up to construction most of the time. The
of five steps as shown in Fig. 2: (1) divide the overall work; problems of inconsistent DC amounts can be reduced if the
(2) group tasks into WUs; (3) design the WU(i), where i design and construction work is jointly planned and the next
represents task number; (4) review and issue the WU(i); execution steps are followed.
and (5) construct and feedback. The five steps iterate until
all WUs are constructed. Table 5 shows how the five steps Group tasks into work units
of WU planning target the problems and the design-builders’ After work is divided into tasks, the tasks need to be
views on the effects of WU planning. They are explained grouped into WUs or work packages for design and con-
below. struction. Designers and constructors should work together
to define the scope of WUs. This joint planning is helpful
Divide overall work to reduce the problems of inconsistent DC amounts. The
The first step in WU planning is to divide the overall scope of WUs is then smaller and easier to manage than the
work into smaller, clearly identified tasks and determine du- whole DB project. This step is performed continually.
rations, resource needs, and relationships. The work break- Grouping WUs should consider the constructor’s workload
down structure (WBS) and master CPM schedule are then and the nature of the design–construction interface to derive
produced. The overall CPM schedule covering all project adequate design and construction amounts. The supply of re-
tasks is a very important and useful foundation for WU sources such as workers and machines can be stabilized ac-
planning. cordingly.
Design and construction work should be planned by both Since the design-builder knows his/her own needs, he/she
designers and constructors of the DB team. Joint planning should take the lead in determining WU packages. The con-
helps delineate clear work contents and sequence. Most in- structor’s management considerations should be supple-
terviewed design-builders agreed that joint planning could mented by the designer’s technical knowledge and
improve inconsistent DC amounts and reduce project time experience, such as the relationships among design and con-
(Step 1 in Table 5); however, it was not implemented be- struction tasks.
cause of tight schedules and different opinions from design-
ers. The constructor should take the lead in this regard Design work unit
because construction schedule is key, while design schedule This step further designs tasks within the WU and deter-
is usually more flexible. In the five DB case projects, sched- mines more detailed durations and resource needs. It is basi-
ule was determined by the constructors (design-builders); the cally like Step 1 except the scope is smaller and the analysis
designers were only performing design work, and generally more detailed. Since WUs are already small compared with

Published by NRC Research Press


1532 Can. J. Civ. Eng. Vol. 37, 2010

Table 5. Work unit planning targeting DC coordination problems and design-builder views.

Steps of WU planning Targeted problems Project A Project B


1. Divide overall work Inconsistent DC amounts Joint planning can solve the problem Joint planning is helpful to the pro-
Time and cost increase and reduce time blem, but its impact is not obvious
Schedule too tight to do it
2. Group tasks into WUs Inconsistent DC amounts Joint planning can solve the problem Joint planning is helpful to the problem

3. Design WU(i) Design change and con- Assign design reviewers Confirm design continually
flicts Check all drawings Change is not allowed after design
to a certain point
4. Review and issue WU(i) Long review process Clear definition of work packages can Discussion with KRTC and detailed
improve, but not used design consultant
5. Construct and feedback Little feedback Designer and constructor discussion Design-builder takes lead in design
Assign design reviewers

the whole project, they can be better designed so the subse- it will be easier to review and issue WUs. The designer will
quent change or conflict is reduced. be able to follow a streamlined and balanced workflow with-
Project design freezing is an action taken to reduce out awaiting approval every time from the design-builder.
changes and change impacts during design. After planning
the project to a certain point, the scope is then frozen to al- Construct and feedback
low detailed design to progress with less inefficiency and re- After the design of the WUs is finished, the designs are
work. This results in a shorter design time and maybe reviewed and issued for construction. This last step also col-
shorter overall project duration. Design freezing is suggested lects and analyzes construction information and feedback to
as a way to manage DC coordination while the WU plan- the subsequent WUs, so that they can take advantage of les-
ning has features similar to project design freezing (Chang sons learned. Construction experience or constructability
and Ibbs 1998). Design freezing is usually harder than it ap- brings construction knowledge into design, which results in
pears. For controlling design change and conflicts, most de- improved DC coordination and reduces the DC concurrence
sign-builders agreed that it is helpful not to change after problem.
designing to a certain point, like design freezing (Step 3 in To improve the problem of little feedback, it is indicated
Table 5). Besides, projects A and D assigned reviewers and in Table 5 that the designer and constructor should have in-
checked design drawings. ternal discussions and the constructor should provide con-
Designers should be proactive in this step and help by struction sequence to the designer before design. The
providing input from the design perspective. One advantage designer may have opinions that are different from the con-
for the design-builder is that WU mechanism brings in a de- structor, which is helpful to the DC coordination.
sign manager for the original design work. But bringing in a By way of the feedback mechanism, the executability of
design manager does not imply that the designer does extra individual WUs is continually transmitted to the whole
work since he/she should plan for his/her design work any- project, which in turn helps shorten execution time and
way. In addition, the designer gains more influence, perhaps raise productivity and project success. For example, after
control over the planning process. the prior WU is constructed, the design-builder may find
that certain construction means and methods save time or
Review and issue work unit cost. That information can then be incorporated into subse-
Once the WU design is completed, it goes into Step 4, quent WUs. Since the whole DB project is executed under
review and issue for construction. Since the scope of the sequential WUs, each WU’s execution results are fed back
WU is smaller and design is more complete, design review to the project for evaluation, which can help avoid
is easier, and therefore a long review process can be mistakes and improve the performance of future WUs.
avoided. In Table 5, the design-builders agreed that work The designers and constructors are continually learning
units should be clearly defined (to shorten design review during the WU execution process through this feedback
time). mechanism.
With individual WUs finished one by one, the design- Overall, the work unit planning method is helpful to solv-
builder has time to review the design process and deliver- ing DC coordination problems. Although not completely va-
ables for the preceding WUs, and think of better ways to lidated, the steps to plan and execute DB projects are
issue the subsequent WUs for construction. This is also accepted by the interviewed design-builders. The design-
helpful to design review. Work interface is a consideration builders actually indicated that some steps such as ‘‘divide
for the design-builder when reviewing and issuing WUs. overall work’’ and ‘‘construct and feedback’’ were used on
This means, for instance, that the ease or difficulty of meet- their projects but to a lesser degree. For example, the overall
ing to discuss WUs will influence the size of the WUs. If work was divided into smaller tasks but without being iden-
large distances separate the designer and constructor, the tified clearly, and designers did not join the planning. Feed-
WUs might be larger than otherwise recommended. back between designers and constructors had been more
If a project’s overall plan or schedule has been accepted than with traditional DBB projects, but its frequency could
in the beginning and kept updated and approved regularly, be increased.

Published by NRC Research Press


Chang et al. 1533

Project C Project D Summary


Joint planning can solve the problem and Joint planning could solve the problem and Joint planning could solve the problem and
good for the project reduce time reduce project time
Designers do not agree
Joint planning can solve the problem and Joint planning could solve the problem Joint planning could solve the problem
good for the project
Change is not allowed after design to a Change is not allowed after design Change is not allowed after design
certain point to a certain point to a certain point
Its effect is not obvious
Hold review meetings and limit attendants Clear definition of work packages is good Work units should be clearly defined
for the project
Provide construction sequence Construction feedback, designers might not Designer and constructor discussion
Judge design based on experience accept it Provide construction sequence to designer

Conclusions DB. Participants of DB projects must have the capability


and experience in design and construction coordination.
Adoption of the DB project delivery method has increased Although the cases used in this study are from subway proj-
in recent years. Many studies address the upstream issues of ects, the investigated DC concurrence problems and pro-
this method such as identifying advantages, conditions for posed WU planning method are the same for other types of
adoption, and design-builder selection. However, DC con- large DB projects. Therefore, the findings are generally ap-
currence will be the core in execution after the DB contract plicable to all types of construction projects, with some dif-
is awarded. We know from the manufacturing industry of ference in application complexity.
concurrent engineering that if information is not transmitted
effectively between designer and constructor, advantages of References
the DB will not be realized.
This research studied DC coordination problems on five Abduh, M., and Skibniewski, M.J. 2003. Utility assessment of elec-
DB projects, and proposed a work unit planning method to tronic networking technologies for design-build projects. Auto-
guide the coordination. By analyzing these projects, coordi- mation in Construction, 12(2): 167–183. doi:10.1016/S0926-
5805(02)00042-0.
nation problems were found to arise from inadequate plan-
Adler, P.S. 1995. Interdepartmental interdependence and coordina-
ning and execution. The former includes a high level of
tion: the case of the design/ manufacturing interface. Organiza-
conceptual design completion. The latter includes inconsis- tion Science, 6(2): 147–167. doi:10.1287/orsc.6.2.147.
tent DC amounts, a long review process, and little feedback American Consulting Engineers Council. 1994. Design/build posi-
between designer and constructor. Moreover, the conse- tion statement. ACEC, Washington, D.C.
quence of inadequate DC coordination includes time and BFC. 1995. Report on design-build as an alternative construction
cost increase as well as design change and conflicts. Two delivery method for public owners. Building Futures Council,
problems have a major influence on DB execution. The first Georgetown, Md.
is inconsistent DC amounts. It is difficult, yet important, for Chang, A.S., and Ibbs, C.W. 1998. On-call contracting strategy and
the design amount to match construction progress (a paced management. Journal of Management in Engineering, 14(4): 35–
issue). The second problem is little feedback. Typically, 44. doi:10.1061/(ASCE)0742-597X(1998)14:4(35).
feedback between the designers and constructors is little, in- Cheng, M.Y., and Tsai, M.H. 2008. Cross-organization process in-
formal, and ad hoc. tegration in design-build team. Automation in Construction,
Generally, these problems are not as pronounced on tradi- 17(2): 151–162. doi:10.1016/j.autcon.2006.12.002.
tional DBB projects because of separate design and con- Chinowsky, P.S., and Rojas, E.M. 2003. Virtual teams: guide to suc-
struction. Although they occurred in the DB projects cessful implementation. Journal of Management in Engineering,
studied in this research, the degree of their influence on DC 19(3): 98–106. doi:10.1061/(ASCE)0742-597X(2003)19:3(98).
execution varied. Formal planning and execution guidelines Chua, D.K.H., Kog, Y.C., and Loh, P.K. 1999. Critical success fac-
as well as good management expertise are needed to solve tors for different project objectives. Journal of Construction En-
or minimize the problems. gineering and Management, 125(3): 142–150. doi:10.1061/
(ASCE)0733-9364(1999)125:3(142).
The WU planning method is proposed as a way to handle
Dave, B., and Koskela, L. 2009. Collaborative knowledge manage-
the identified problems. It consists of five steps: divide over-
ment — a construction case study. Automation in Construction,
all work; group tasks into WUs; design; review and issue; 18(7): 894–902. doi:10.1016/j.autcon.2009.03.015.
and construct and feedback. How the five steps of WU plan- DBIA. 1997. Design-build process for civil infrastructure projects.
ning reduce the individual problems are explained. The WU Design-Build Institute of America, Washington, D.C.
planning is a systematic way to minimize DC coordination Eisenhardt, K.M. 1989. Building theories from case study research.
problems, particularly those of inconsistent design and con- Academy of Management Review, 14(4): 532–550. doi:10.2307/
struction amounts and design change and conflicts. 258557.
Although only five case projects were available to study, Ernzen, J.J., and Schexnayder, C. 2000. One company’s experience
these problems are very likely to be encountered by new with design/build: labor cost risk and profit potential. Journal of
users of other DB projects. Not resolving these problems Construction Engineering and Management, 126(1): 10–14.
will undercut management’s efforts to reap the benefits of doi:10.1061/(ASCE)0733-9364(2000)126:1(10).

Published by NRC Research Press


1534 Can. J. Civ. Eng. Vol. 37, 2010

Fredrickson, K. 1998. Design guidelines for design-build projects. Turskis, Z., Zavadskas, E.K., and Peldschus, F. 2009. Multi-criteria
Journal of Management in Engineering, 14(1): 77–80. doi:10. optimization system for decision making in construction design
1061/(ASCE)0742-597X(1998)14:1(77). and management. The Engineering Economist, 1(61): 7–17
Ibbs, C.W., Kwak, Y.H., Ng, T., and Odabasi, A.M. 2003. Project Williams, G.V. 1995. Fast track pros and cons: consideration for
delivery systems and project change: quantitative analysis. Jour- industrial projects. Journal of Management in Engineering,
nal of Construction Engineering and Management, 129(4): 382– 11(5): 24–32. doi:10.1061/(ASCE)0742-597X(1995)11:5(24).
387. doi:10.1061/(ASCE)0733-9364(2003)129:4(382). Yates, J.K. 1995. Use of design/build in E/C Industry. Journal of
Konchar, M., and Sanvido, V. 1998. Comparison of U.S. project Management in Engineering, 11(6): 33–38. doi:10.1061/(ASCE)
delivery systems. Journal of Construction Engineering and Man- 0742-597X(1995)11:6(33).
agement, 124(6): 435–444. doi:10.1061/(ASCE)0733- Yin, R.K. 2003. Case study research: design and methods. Sage,
9364(1998)124:6(435). London.
Lam, E.W.M., Chan, A.P.C., and Chan, D.W.M. 2008. Determi- Zavadskas, E.K., Turskis, Z., Tamosaitiene, J., and Marina, V.
nants of successful design-build projects. Journal of Construc- 2008. Multicriteria selection of project managers by applying
tion Engineering and Management, 134(5): 333–341. doi:10. grey criteria. Technological and Economic Development of
1061/(ASCE)0733-9364(2008)134:5(333). Economy, 14(4): 462–477. doi:10.3846/1392-8619.2008.14.462-
Molenaar, K.R., Songer, A.D., and Barash, M. 1999. Public-sector 477.
design/build evolution and performance. Journal of Management Zhang, X., Mao, X., and Abourizk, S.M. 2009. Developing a
in Engineering, 15(2): 54–62. doi:10.1061/(ASCE)0742- knowledge management system for improved value engineering
597X(1999)15:2(54). practices in the construction industry. Automation in Construc-
Ndekugri, I., and Turner, A. 1994. Building procurement by design tion, 18(6): 777–789. doi:10.1016/j.autcon.2009.03.004.
and build approach. Journal of Construction Engineering and
Management, 120(2): 243–256. doi:10.1061/(ASCE)0733-
9364(1994)120:2(243).
Appendix. Interview questions
Palaneeswaran, E., and Kumaraswamy, M.M. 2000. Contractor se-
lection for design/build projects. Journal of Construction Engi- For the designers
neering and Management, 126(5): 331–339. doi:10.1061/ 1. What is the level of conceptual design completion?
(ASCE)0733-9364(2000)126:5(331). How will the completion of conceptual design influence de-
Peña-Mora, F., and Li, M. 2001. Dynamic planning and control tailed design?
methodology for design/build fast-track construction projects.
2. How do you plan and arrange design work to match
Journal of Construction Engineering and Management, 127(1):
construction needs? Is the designed amount in tune with
1–17. doi:10.1061/(ASCE)0733-9364(2001)127:1(1).
Peña-Mora, F., and Tamaki, T. 2001. Effect of delivery systems on
construction needs?
collaborative negotiations for large-scale infrastructure projects. 3. How is the design review process executed? How are
Journal of Management in Engineering, 17(2): 105–121. doi:10. design lessons fed back to the constructor?
1061/(ASCE)0742-597X(2001)17:2(105). 4. What are the difficulties for the design and construction
Pocock, J.B., Hyun, C.T., Liu, L.Y., and Kim, M.K. 1996. Rela- concurrence? How does design cost, time, or quality af-
tionship between project interaction and performance indicators. fected compare with traditional design projects?
Journal of Construction Engineering and Management, 122(2): 5. What are the reasons for design changes? How do you
165–176. doi:10.1061/(ASCE)0733-9364(1996)122:2(165). deal with design and construction conflicts?
Šarka, V., Zavadskas, E.K., Ustinovičius, L., Šarkiene, E., and
Ignatavičius, C. 2008. System of project multicriteria decision For the constructors
synthesis in construction. Technological and Economic Develop- 1. How will the completion of conceptual design influ-
ment of Economy, 14(4): 546–565. doi:10.3846/1392-8619. ence construction?
2008.14.546-565.
2. What are the difficulties for the design and construction
Songer, A., Molenaar, K., and Robinson, G. 1996. Selection factors
concurrence?
and success criteria for design-build in the U.S., and U.K. Jour-
nal of Construction Procurement, 2(2): 69–82. 3. How are construction lessons fed back to the designer?
Terwiesch, C., Loch, C.H., and Meyer, A.D. 2002. Exchanging pre- 4. How is construction cost, time, or quality affected by
liminary information in concurrent engineering: alternative coor- design construction concurrence compared with traditional
dination strategies. Organization Science, 13(4): 402–419. construction projects?
doi:10.1287/orsc.13.4.402.2948. 5. How do you deal with the design and construction con-
Thomas, S.R., Tucker, R.L., and Kelly, W.R. 1998. Critical com- flicts?
munications variables. Journal of Construction Engineering and
Management, 124(1): 58–66. doi:10.1061/(ASCE)0733-
9364(1998)124:1(58).

Published by NRC Research Press

Vous aimerez peut-être aussi