PLANNING D'EXECUTION DES TRAVAUX GROS ŒUVRE IMMEUBLE R+1 AVEC TERRASSE POOL HOUSE

MOIS 9 MOIS 10
MOIS 1 MOIS 2 MOIS 3 MOIS 4 MOIS 5 MOIS 6 MOIS 7 MOIS 8
(JANVIER (FEVRIER
DESIGNATION DES TRAVAUX (MAI) (JUIN) (JUILLET) (AOUT) (SEPT.) (OCT.) (NOV.) (DEC.)
) )
S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3 S4 S1 S2 S3

LOT 0 - GENERALITE
1 - INSTALLATION CHANTIER
2 - DEMOLITION DE BETON EN
FONDATION
LOT 1 - TERRASSEMENT
1 - FOUILLE
2 - REMBLAIS
LOT 2 - GROS ŒUVRE
I - INFRASTRUCTURE (FONDATION)

II - SUPERSTRUCTURE (RDC)
1 - MACONNERIE
2 - BETON ARME
3 - COFFRAGE
4 - ENDUITS
III - SUPERSTRUCTURE (ETAGE 1)
1 - MACONNERIE
2 - BETON ARME
3 - COFFRAGE
4 - ENDUITS
IV - SUPERSTRUCTURE (ETAGE 2)
1 - MACONNERIE
2 - BETON ARME
3 - COFFRAGE
4 - ENDUITS
10
IER

S4
PLANNING D'EXECUTION DES TRAVAUX U.I.G.B
AMENAGEMENT BUREAU DU PRESIDENT

SEMAINE 1 SEMAINE 2
DESIGNATION DES TRAVAUX
j1 j2 j3 j4 j5 j6 j7 j8 j9 j10 j11 j12 j13 j14 j15
- Installation du chantier
- Dépose faux plafond en c/p
- Démolition d'un mur en agglo
- F/P de faux plafond staff
- Dépose de fenêtre existante
- Reprise tableau au mortier
- F/P d'aluminium coulissante
- Dépose et repose de P.C
- Dépose et repose de P.I
- Dépose et repose de P.T
- Cloison en c/p secrétariat
- F/P de porte blindée de 35 mm
- F/P de porte blindée de 40 mm
- Automatisme porte
- Enduit sur mur
- Application de peinture
- F/P de store jalouette
- F/P de revêtements durs
- Nettoyage et livraison chantier