REKAPITULASI JANGKA WAKTU PELAKSANAAN PEKERJAAN (BARCHART dan KURVA-S )

PEKERJAAN Peningkatan Dermaga Sungai Gampa Kabupaten Barito Kuala Tahap II (dua) (Lelang Tidak Mengikat)
LOKASI Dermaga Sungai Gampa Kabupaten Barito Kuala
TAHUN ANGGARAN 2022

MASA PELAKSANAAN 330 HARI KALENDER

TOTAL BIAYA BOBOT M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37 M38 M39 M40 M41 M42 M43 M44 M45 M46 M47 M48
NO. URAIAN PEKERJAAN 3 Feb-9 10 Feb-16 17 Feb-23 24 Feb-2 3 Mar-9 10 Mar-16 17 Mar-23 24 Mar-30 31 Mar-6 7 Apr-13 14 Apr-20 21 Apr-27 28 Apr-4 5 Mei-11 12 Mei-18 19 Mei-25 26 Mei-1 02 Jun-08 09 Jun-15 16 Jun-22 23 Jun-29 30 Jun-06 07 Jul-13 14 Jul-20 21 Jul-27 28 Jul-3 4 Agt-10 11 Agt-17 18 Agt-24 25 Agt-31 1 Sep-7 8 Sep-14 15 Sep-21 22 Sep-28 29 Sep-5 6 Okt-12 13 Okt-19 20 Okt-26 27 Okt-2 3 Nov-9 10 Nov-16 17 Nov-23 24 Nov-30 1 Des-7 8 Des-14 15 Des-21 22 Des-28
29 Des
Feb Feb Feb Mar Mar Mar Mar Mar Apr Apr Apr Apr Mei Mei Mei Mei Jun Jun Jun Jun Jun Jul Jul Jul Jul Agt Agt Agt Agt Agt Sep Sep Sep Sep Okt Okt Okt Okt Nov Nov Nov Nov Nov Des Des Des Des

( Rp ) (%) 7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 119 126 133 140 147 154 161 168 175 182 189 196 203 210 217 224 231 238 245 252 259 266 273 280 287 294 301 308 315 322 329 330

99.852 100.00
I. PEKERJAAN PERSIAPAN Rp 724,178,211.64 6.899 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146
94.48
0.146
96.27 0.146
98.062 0.021
92.69
90.01 90.90
87.52 87.86 88.21 89.11
86.83 87.18
84.34 85.59 M
II. PEKERJAAN DERMAGA Rp 9,291,452,198.00 81.85 83.10
79.41 A
3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 3.934 76.98
A PEK. TIANG PIPA BAJA Ø457.2 mm T = 12 mm Rp 6,193,217,412.69 59.003 74.54 S
72.11
69.67 A
67.24
64.80
62.37
2.2886 2.2886 2.2886 2.2886 2.2886 2.2886 2.2886 2.2886
B PEK. BETON K275 Rp 1,921,764,176.14 18.309 P
58.29
54.21 E
50.13 M
C PEK. RAMDOR MANUAL Rp 461,720,240.00 4.399 46.05 1.100 1.100 1.100 1.100
E
41.97
37.89 L
33.81 0.197 0.197 0.197 0.197 I
D PEK. CATWALK Rp 82,750,369.18 0.788 29.73 H
25.65
A
21.57
E PEK. LAIN-LAIN Rp 632,000,000.00 6.021 17.49 0.753 0.753 0.753 0.753 0.753 0.753 0.753 0.753 R
13.41 A
9.33 A
5.25 0.891 0.891 0.891 0.891 0.891 0.127 N
III. PEKERJAAN SISI DARAT Rp 480,750,000.00 4.580 0.88 1.02 1.17
0.15 0.29 0.44 0.59 0.73

180
JUMLAH Rp 10,496,380,409.65 100 HA
RI
SCHEDULE PEKERJAAN PER - MINGGU 0.146 0.146 0.146 0.146 0.146 0.146 0.146 0.146 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 4.080 2.435 2.435 2.435 2.435 2.435 2.435 2.435 2.435 1.246 1.246 1.246 1.246 0.343 0.343 0.343 0.343 0.899 0.899 0.899 1.790 1.790 1.790 1.790 1.790 0.148
JUMLAH KOMULATIF RENCANA 0.15 0.29 0.44 0.59 0.73 0.88 1.02 1.17 5.25 9.33 13.41 17.49 21.57 25.65 29.73 33.81 37.89 41.97 46.05 50.13 54.21 58.29 62.37 64.80 67.24 69.67 72.11 74.54 76.98 79.41 81.85 83.10 84.34 85.59 86.83 87.18 87.52 87.86 88.21 89.11 90.01 90.90 92.69 94.48 96.27 98.062 99.852 100.00
JUMLAH BOBOT KOMULATIF AKTUAL S/D MINGGU INI - - - - - - - - - - - - - - - 10.93 -
JUMLAH KOMULATIF REALISASI - - - - - - - - - - - - - - - 10.93 10.93
DEVIASI ( +/-) -0.146 -0.293 -0.439 -0.585 -0.732 -0.878 -1.024 -1.171 -5.251 -9.331 -13.411 -17.49 -21.57 -25.65 -29.73 -22.88 -26.96

Gampa, 02 Juni 2022


Diketahui Oleh: Disetujui Oleh: Dibuat oleh:
Pejabat Pembuat Komitmen Konsultan Pengawas Kontraktor Pelaksana
(PPK) CV. CAHAYA NUSANTARA

INDRA YANTO K.Y, S.E. BAKIR MULYADI, S.T. TIMBUL MANALU, S.T.

NIP : 19831205 2OO9O3 1 OO3 Direktur Site Manager