CAPEP TRAVAUX
Marché N° 13/2022/DAH
1. VIDANGE DE FOND :
TRAVAUX AVANCEMENT(%)
CREUSEMENT 65,53 %
SOUTENEMENT 63,17 %
REVETEMENT 0,00 %
AVANCEMENT TOTALE 53.82 %
2. PRISE AEP 3 :
TRAVAUX AVANCEMENT(%)
CREUSEMENT 100 %
SOUTENEMENT 100 %
REVETEMENT 92.31 %
AVANCEMENT TOTALE 98.72 %
3. PRISE AEP 2 :
TRAVAUX AVANCEMENT(%)
CREUSEMENT 39.70 %
SOUTENEMENT 0.00 %
REVETEMENT 0.00 %
AVANCEMENT TOTALE 19.85 %
4. PRISE AEP 1 :
TRAVAUX AVANCEMENT(%)
CREUSEMENT 0.00 %
SOUTENEMENT 0.00 %
REVETEMENT 0.00 %
AVANCEMENT TOTALE 0.00 %
TRAVAUX AVANCEMENT(%)
CREUSEMENT 0.00 %
SOUTENEMENT 0.00 %
REVETEMENT 0.00 %
AVANCEMENT TOTALE 0.00 %
6. DERIVATION PROVISOIRE :
TRAVAUX AVANCEMENT(%)
CREUSEMENT 100 %
SOUTENEMENT 100 %
REVETEMENT 96.90 %
AVANCEMENT TOTALE 99.48 %
7. PUITS DE VANNAGE :
TRAVAUX AVANCEMENT(%)
CREUSEMENT 16.43 %
SOUTENEMENT 16.43%
REVETEMENT 0.00 %
AVANCEMENT TOTALE 13.69 %
8. GALERIE D’INJECTION :
TRAVAUX AVANCEMENT(%)
CREUSEMENT 100 %
SOUTENEMENT 100%
REVETEMENT 100 %
AVANCEMENT TOTALE 100 %
9. EVACUATEUR DE CRUE :
Demi-plot
- - - - -
SEUIL 1b droit
COURSIER - - - - - -
CUILLERE - - - - - -