Vous êtes sur la page 1sur 6

PROJECT

AZITO PHASE IV PROJECT


COMBINED CYCLE POWER PLANT EXPANSION PROJECT
(CÔTE D’IVOIRE)

ANNEX

ESSAIS DES PARATONERRES 225 kV

DOCUMENT NUMBER

AZ-0014-PRO-AEE-0004

REVISION 00
DOCUMENT ISSUED FOR: REVIEW
DATE 11/03/2021

VLT-AEE POWER YEB-AEE POWER JIV-AEE POWER

Issued by: Revised by: Approved by:

THIS DOCUMENT CONTAINS PROPRIETARY INFORMATION AND CAN NOT BE DUPLICATED, MODIFIED OR DISCLOSED TO
THIRD PARTIES FOR ANY USE OTHER THAN THIS PROJECT AND THE PURPOSE FOR WHICH IT IS INTENDED FOR, WITHOUT
THE WRITTEN CONSENT OF COBRA.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page
PROTOCOLE DES ESSAIS A REALISER SUR LES
PARATONNERRES 225 KV 1 de 5

LISTE D’ESSAIS ET VERIFICATIONS

1. INSPECTION VISUELLE APPLICABLE  NON APPLICABLE 

2. RESISTANCE D’ISOLEMENT (AU MEGGER) APPLICABLE  NON APPLICABLE 

3. FACTEUR DE PUISSANCE APPLICABLE  NON APPLICABLE 

INFORMATION GÉNÉRALE

LOCALISATION : POSTE 225 kV AZITO

MODULE : D14 AUTOTRANSFORMATEUR TRAVEE

FABRICANT : TRIDELTA TENSION ASSIGNÉE : 228 kV

TYPE : SBKC 228/SH-II PHASE L1: 315054

DATE DE FABRICATION : 2020 NUMÉRO DE SÉRIE PHASE L2: 315055

COURANT NOMINAL DE DÉCHARGE: 20 KA PHASE L3: 315056

FRÉQUENCE NOMINALE : 50Hz CLASSE DE DÉCHARGE DE LIGNE: 4

1. INSPECTION VISUELLE

ELÉMENT PHASE R PHASE S PHASE T


 Bon état  Bon état  Bon état
État de la porcelaine
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
État des connexions.
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
État des isolateurs de support
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
État de la mise à une terre
 Mauvais état  Mauvais état  Mauvais état

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page
PROTOCOLE DES ESSAIS A REALISER SUR LES
PARATONNERRES 225 KV 2 de 5

2. RÉSISTANCE D'ISOLEMENT
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÈLE – SÉRIE DATE DE CALIBRAGE

2.1 HAUTE - TERRE (Mesure dans GΩ, Injectée de 10000 VDC*1 minute).
PHASE MESURE OBTENUE TEMPERATURE (ºC) HUMIDITE (%)
L1
L2
L3

3. FACTEUR DE PUISSANCE
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÈLE – SÉRIE DATE DE CALIBRAGE

3.1 HAUTE TENSION - TERRE (Mesure en % facteur de puissance, tip-up, tension injectée de 2 - 10 kV.)
TENSION CAPACITANCIA TEMP. HUMiD.
PHASE COURANT (mA) Fréquence (Hz) F.P. (%)
INJECTÉE (kV) (pF) (ºC) (%)
L1
L2
L3
RAPPORT D’ESSAIS ÉMIS PAR ÉQUIPEMENT ________________

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page
PROTOCOLE DES ESSAIS A REALISER SUR LES
PARATONNERRES 225 KV 3 de 5

OBSERVATIONS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page
PROTOCOLE DES ESSAIS A REALISER SUR LES
PARATONNERRES 225 KV 4 de 5

PHOTOS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page
PROTOCOLE DES ESSAIS A REALISER SUR LES
PARATONNERRES 225 KV 5 de 5

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.