PROJECT

AZITO PHASE IV PROJECT


COMBINED CYCLE POWER PLANT EXPANSION PROJECT
(CÔTE D’IVOIRE)

ANNEX

ESSAIS DES SECTIONNEURS 225 kV

DOCUMENT NUMBER

AZ-0014-PRO-AEE-0004

REVISION 00
DOCUMENT ISSUED FOR: REVIEW
DATE 11/03/2021

VLT-AEE POWER YEB-AEE POWER JIV-AEE POWER

Issued by: Revised by: Approved by:

THIS DOCUMENT CONTAINS PROPRIETARY INFORMATION AND CAN NOT BE DUPLICATED, MODIFIED OR DISCLOSED TO
THIRD PARTIES FOR ANY USE OTHER THAN THIS PROJECT AND THE PURPOSE FOR WHICH IT IS INTENDED FOR, WITHOUT
THE WRITTEN CONSENT OF COBRA.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEUR TRIPOLAIRE 225 kV 1 de 5

LISTE D’ESSAIS ET VERIFICATIONS

1. INSPECTION VISUELLE APPLICABLE  NON APPLICABLE 

2. RESISTANCE D’ISOLEMENT (AU MEGGER) APPLICABLE  NON APPLICABLE 

3. RESISTANCE DE CONTACT APPLICABLE  NON APPLICABLE 

4. TEMPS DE FONCTIONNEMENT - SIMULTANEITE APPLICABLE  NON APPLICABLE 

5. COURANT DE MOTEUR APPLICABLE  NON APPLICABLE 

INFORMATION GÉNÉRALE

LOCALISATION : POSTE 225 kV AZITO

MODULE : D14 AUTOTRANSFORMATEUR TRAVEE

FABRICANT : GENERAL ELECTRIC TENSION ASSIGNÉE : 245 kV

TYPE : S2DAT COURANT NOMINAL : 2.000 A

DATE DE FABRICATION : 2020 COURANT DE COURT CIRCUIT : 50 KA, 3 s

NUMÉRO DE SÉRIE : : A299688 020 001 FRÉQUENCE NOMINALE : 50Hz

1. INSPECTION VISUELLE

ÉLEMENT PHASE L1 PHASE L2 PHASE L3


 Bon état  Bon état  Bon état
L'État des isolateurs
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
Calibrage des contacts principaux
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
Mise à une terre
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
L'État de la boîte de commandement
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
État des connexions secondaires
 Mauvais état  Mauvais état  Mauvais état

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEUR TRIPOLAIRE 225 kV 2 de 5

2. RÉSISTANCE D'ISOLEMENT
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODELE – SÉRIE DATE DE CALIBRAGE

3.1 HAUTE - TERRE (Mesure dans GΩ, Injectée de 10000 VDC*1 minute).

PHASE MESURE OBTENUE TEMPERATURE (ºC) HUMIDITE (%)


L1
L2
L3
CONDITIONS DU CLIMAT :

3. RÉSISTANCE DE CONTACT
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÉLE – SÉRIE DATE DE CALIBRAGE

3.1 SECTIONNEUR FERMÉ (Mesure en , Courant injecté de 100 A. DC.)


PHASE MESURE OBTENUE OBSERVATIONS
L1
L2
L3
RAPPORT D’ESSAIS

4. TEMPS DE FONCTIONNEMENT -SIMULTANÉITÉ


TEMPS D'OUVERTURE: sec
TEMPS DE FERMETURE: sec
SIMULTANÉITÉ: sec

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEUR TRIPOLAIRE 225 kV 3 de 5

5. COURANT DE MOTEUR
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÉLE – SÉRIE DATE DE CALIBRAGE

COURANT MAXIMAL DE FERMETURE: A


COURANT MAXIMAL D’OUVERTURE: A

OBSERVATIONS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEUR TRIPOLAIRE 225 kV 4 de 5

PHOTOS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 1 de 4

LISTE D’ESSAIS ET VERIFICATIONS

1. INSPECTION VISUELLE APPLICABLE  NON APPLICABLE 

2. RESISTANCE D’ISOLEMENT (AU MEGGER) APPLICABLE  NON APPLICABLE 

3. RESISTANCE DE CONTACT APPLICABLE  NON APPLICABLE 

4. TEMPS DE FONCTIONNEMENT - SIMULTANEITE APPLICABLE  NON APPLICABLE 

5. COURANT DE MOTEUR APPLICABLE  NON APPLICABLE 

INFORMATION GÉNÉRALE

LOCALISATION : POSTE 225 kV AZITO

MODULE : D14 AUTOTRANSFORMATEUR TRAVEE

FABRICANT : GENERAL ELECTRIC TENSION ASSIGNÉE : 245 kV

TYPE : S2DA COURANT NOMINAL : 2.000 A

DATE DE FABRICATION : 2020 COURANT DE COURT CIRCUIT : 50 KA, 3 s

NUMÉRO DE SÉRIE : : A299688 010 0012 FRÉQUENCE NOMINALE : 50Hz

1. INSPECTION VISUELLE

ÉLEMENT PHASE L1 PHASE L2 PHASE L3


 Bon état  Bon état  Bon état
L'État des isolateurs
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
Calibrage des contacts principaux
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
Mise à une terre
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
L'État de la boîte de commandement
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
État des connexions secondaires
 Mauvais état  Mauvais état  Mauvais état

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 2 de 4

2. RÉSISTANCE D'ISOLEMENT
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODELE – SÉRIE DATE DE CALIBRAGE

3.1 HAUTE - TERRE (Mesure dans GΩ, Injectée de 10000 VDC*1 minute).

PHASE MESURE OBTENUE TEMPERATURE (ºC) HUMIDITE (%)


L1
L2
L3
CONDITIONS DU CLIMAT :

3. RÉSISTANCE DE CONTACT
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÉLE – SÉRIE DATE DE CALIBRAGE

3.1 SECTIONNEUR FERMÉ (Mesure en , Courant injecté de 100 A. DC.)


PHASE MESURE OBTENUE OBSERVATIONS
L1
L2
L3
RAPPORT D’ESSAIS

4. TEMPS DE FONCTIONNEMENT -SIMULTANÉITÉ


TEMPS D'OUVERTURE: sec
TEMPS DE FERMETURE: sec
SIMULTANÉITÉ: sec

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 3 de 4

5. COURANT DE MOTEUR
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÉLE – SÉRIE DATE DE CALIBRAGE

COURANT MAXIMAL DE FERMETURE: A


COURANT MAXIMAL D’OUVERTURE: A

OBSERVATIONS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 4 de 4

PHOTOS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 1 de 4

LISTE D’ESSAIS ET VERIFICATIONS

1. INSPECTION VISUELLE APPLICABLE  NON APPLICABLE 

2. RESISTANCE D’ISOLEMENT (AU MEGGER) APPLICABLE  NON APPLICABLE 

3. RESISTANCE DE CONTACT APPLICABLE  NON APPLICABLE 

4. TEMPS DE FONCTIONNEMENT - SIMULTANEITE APPLICABLE  NON APPLICABLE 

5. COURANT DE MOTEUR APPLICABLE  NON APPLICABLE 

INFORMATION GÉNÉRALE

LOCALISATION : POSTE 225 kV AZITO

MODULE : D01 COUPLAGE TRAVEE

FABRICANT : GENERAL ELECTRIC TENSION ASSIGNÉE : 245 kV

TYPE : S2DA COURANT NOMINAL : 3.150 A

DATE DE FABRICATION : 2020 COURANT DE COURT CIRCUIT : 50 KA, 3 s

NUMÉRO DE SÉRIE : : A299688 030 005 FRÉQUENCE NOMINALE : 50Hz

1. INSPECTION VISUELLE

ÉLEMENT PHASE L1 PHASE L2 PHASE L3


 Bon état  Bon état  Bon état
L'État des isolateurs
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
Calibrage des contacts principaux
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
Mise à une terre
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
L'État de la boîte de commandement
 Mauvais état  Mauvais état  Mauvais état
 Bon état  Bon état  Bon état
État des connexions secondaires
 Mauvais état  Mauvais état  Mauvais état

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 2 de 4

2. RÉSISTANCE D'ISOLEMENT
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODELE – SÉRIE DATE DE CALIBRAGE

3.1 HAUTE - TERRE (Mesure dans GΩ, Injectée de 10000 VDC*1 minute).

PHASE MESURE OBTENUE TEMPERATURE (ºC) HUMIDITE (%)


L1
L2
L3
CONDITIONS DU CLIMAT :

3. RÉSISTANCE DE CONTACT
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÉLE – SÉRIE DATE DE CALIBRAGE

3.1 SECTIONNEUR FERMÉ (Mesure en , Courant injecté de 100 A. DC.)


PHASE MESURE OBTENUE OBSERVATIONS
L1
L2
L3
RAPPORT D’ESSAIS

4. TEMPS DE FONCTIONNEMENT -SIMULTANÉITÉ


TEMPS D'OUVERTURE: sec
TEMPS DE FERMETURE: sec
SIMULTANÉITÉ: sec

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 3 de 4

5. COURANT DE MOTEUR
ÉQUIPEMENT UTILISÉ POUR CET ESSAI
DESCRIPTION FABRICANT MODÉLE – SÉRIE DATE DE CALIBRAGE

COURANT MAXIMAL DE FERMETURE: A


COURANT MAXIMAL D’OUVERTURE: A

OBSERVATIONS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.
NOM DU AZITO PHASE IV PROJECT
PROJET COMBINED CYCLE POWER PLANT EXPANSION PROJECT

CLIENT

Page

PROTOCOLE D’ESSAIS DES SECTIONNEURS UNIPOLAIRES 225 kV 4 de 4

PHOTOS :

AEE POWER COBRA AZITO ENERGIE CIE


Nom: Nom:
Nom: Nom:

Signature : Signature : Signature : Signature :

Date: Date:
Date: Date:
Préparé par Autorisé par Autorisé par Autorisé par
F-GC-001 Rev.0 CE DOCUMENT EST PROPRIÉTÉ DE AEE POWER, INTERDIT DE RÉPRODUIRE SANS AUTORISATION.